Judge: Andrew E. Cooper, Case: 22CHCV00297, Date: 2025-02-28 Tentative Ruling
Counsel wishing to submit on a tentative ruling may inform the clerk or courtroom assisant in North Valley Department F51, 9425 Penfield Ave., Chatsworth, CA 91311, at (818) 407-2251. Please be aware that unless all parties submit, the matter will still be called for hearing and may be argued by any appearing/non-submitting parties. If the matter is submitted on the court's tentative ruling by all parties, counsel for moving party shall give notice of ruling. This may be done by incorporating verbatim the court's tentative ruling. The tentative ruling may be extracted verbatim by copying and specially pasting, as unformatted text, from the Los Angeles Superior Court’s website, http://www.lasuperiorcourt.org. All hearings on law and motion and other calendar matters are generally NOT transcribed by a court reporter unless one is provided by the party(ies).
Case Number: 22CHCV00297 Hearing Date: February 28, 2025 Dept: F51
LOS
ANGELES SUPERIOR COURT
NORTH
VALLEY DISTRICT
DEPARTMENT
F-51
FEBRUARY 27,
2025
DEMURRER WITH
MOTION TO STRIKE
Los Angeles Superior Court Case # 22CHCV00297
¿
Demurrer with Motion to
Strike filed: 10/30/24
¿
MOVING PARTY: Defendants Beitler & Associates,
Inc.; Bayside Domination, LLC; and 11151 Morrison Street LLC (collectively, “Defendants”)
RESPONDING PARTY: Plaintiff
CLC Builders, Inc. (“Plaintiff”)
NOTICE: OK
¿
RELIEF REQUESTED: Defendants
demur against Plaintiff’s entire second amended complaint (“SAC”). Defendants
also move to strike Plaintiff’s references to punitive damages from the SAC.
¿
TENTATIVE RULING: The demurrer is sustained as to Plaintiff’s
second cause of action, with 30 days leave to amend, and overruled as to the
remainder. The motion to strike is denied.
BACKGROUND¿
This is a contract
action in which Plaintiff alleges that in October 2019, it entered into a
written agreement with Defendants in which Plaintiff agreed to provide
construction services to Defendants’ property, located at 5263 N. Cartwright
Avenue, North Hollywood, California 91601. (SAC ¶¶ 10, 24.) “The terms of said
agreement were revised and amended as reflected in a series of documents
wherein Defendants, and each of them, agreed to compensate Plaintiff for the
performance of such services in an amount not less than $2,549,808.80, plus all
additional charges for extras and change orders subsequently ordered.” (Id. at
¶ 24.) Plaintiff alleges that it performed the services as agreed upon, but
Defendants failed to pay Plaintiff. (Id. at ¶¶ 25–28.)
On 4/27/22,
Plaintiff filed its original complaint, alleging against Defendants the
following causes of action: (1) Breach of Contract; and (2) Foreclosure of
Mechanics’ Lien. On 3/2/23, Plaintiff filed its first amended complaint,
alleging against Defendants the following causes of action: (1) Breach of
Contract; (2) Foreclosure of Mechanics’ Lien; (3) Fraud and Deceit; (4) Work,
Labor, and Services (Quantum Meruit); (5) Money Due on an Open Book Account
(Quantum Meruit); (6) Reasonable Value of Services Rendered (Quantum Meruit);
and (7) Unfair Business Practices.
On 6/10/24,
Plaintiff filed its operative SAC, alleging against Defendants the following
causes of action: (1) Breach of Contract; (2) Foreclosure of Mechanics’ Lien;
(3) Fraud and Deceit; (4) Work, Labor, and Services (Quantum Meruit); (5) Money
Due on an Open Book Account (Quantum Meruit); and (6) Reasonable Value of
Services Rendered (Quantum Meruit).
On 10/30/24, Defendants filed the
instant demurrer and motion to strike. On 2/18/25, Plaintiff filed its
opposition. On 2/21/25, Defendants filed their reply.
ANALYSIS
As a general matter, a party may respond to a pleading
against it by demurrer on the basis of any single or combination of eight
enumerated grounds, including that “the pleading does not state facts
sufficient to constitute a cause of action.” (Code Civ. Proc., § 430.10, subd.
(e).) In a demurrer proceeding, the defects must be apparent on the face of the
pleading or via proper judicial notice.¿(Donabedian v. Mercury Ins. Co.
(2004) 116 Cal.App.4th 968, 994.)¿
“A demurrer tests the pleading alone, and not the evidence
or facts alleged.” (E-Fab, Inc. v. Accountants, Inc. Servs.
(2007) 153 Cal.App.4th 1308, 1315.) As such, the court assumes the truth of the
pleading’s properly pleaded or implied factual allegations. (Ibid.) The
only issue a demurrer is concerned with is whether the pleading, as it stands,
states a cause of action. (Hahn v. Mirda (2007) 147 Cal.App.4th
740, 747.)
Here, Defendants
demurs to the entire SAC on the basis that Plaintiff fails¿to allege facts
sufficient to state any cause of action therein.
A. Meet-and-Confer
Defendants’ counsel declares that on the parties met and
conferred by telephone prior to the filing of the instant demurrer and motion
to strike. (Decl. of Mark D. Hurwitz ¶ 2a.) Accordingly, the Court finds that
counsel has satisfied the preliminary meet and confer requirements set forth by
Code of Civil Procedure section 430.31.
B.
Breach of Contract
Plaintiff’s
first cause of action alleges Breach of Contract against Defendants. To state a
cause of action for breach of contract, a plaintiff must be able to establish
“(1) the existence of the contract, (2) plaintiff’s performance or excuse for
nonperformance, (3) defendant’s breach, and (4) the resulting damages to the
plaintiff.” (Oasis West Realty, LLC v. Goldman (2011) 51 Cal.4th 811,
821.) A written contract may be pleaded either verbatim or generally “according
to its legal intendment and effect.” (Construction Protective Services, Inc.
v. TIG Specialty Ins. Co. (2002) 29 Cal.4th 189, 198–199.) “An oral
contract may be pleaded generally as to its effect, because it is rarely
possible to allege the exact words.” (Khoury v. Maly’s of California, Inc.
(1993) 14 Cal.App.4th 612, 616.)
Here,
Plaintiff alleges that “although Plaintiff executed multiple contract documents
at the instance and request of BEITLER, BAYSIDE, 11151 MORRISON, Barry Beitler,
REZAK, and their various agents and employees relating to the 5249 Cartwright
Property, fully executed copies of such documents were never provided by said
Defendants, and each of them, to Plaintiff, and Plaintiff is informed and
believes and based thereon alleges that Defendants, and each of them, remain in
possession thereof.” (SAC ¶ 24.) Instead, Plaintiff attaches to the SAC “true
copies of those contract documents presently in possession of Plaintiff that
evidence and/or constitute incomplete and/or not fully-executed portions of the
final contract between Plaintiff and BEITLER, BAYSIDE, 11151 MORRISON, and DOES
2 to 200.” (Ibid.)
Defendants
argue that “since the Purported Contract is not signed by any of the
Defendants, either the contract claims are patently defective on their face, or
the SAC fails to specify whether the purported contract on which the claims
therein are based is written, is oral, or is implied by conduct.” (Dem. 6:10–13.)
Defendants argue that the “contract attached as Exhibit 1 to the SAC is
incomplete or is not fully executed [SAC, ¶ 24]. Thus, CLC has not alleged the
first and most basic element of a claim for breach of contract, i.e., the
contract itself, much less can it allege that any of the Defendants breached
the contract.” (Id. at 7:10–12.)
The Court disagrees
and finds that while the draft agreement attached to the SAC is admittedly
incomplete/not fully executed, Plaintiff has sufficiently alleged that
Defendants are in exclusive possession of the fully-executed copies of the
subject agreement(s). (SAC ¶ 24.) The Court finds it sufficient at the pleading
stage that Plaintiff has alleged the existence of “a written agreement pursuant
to which Plaintiff agreed to perform certain improvements to and upon the 5249
Cartwright Property, and wherein said Defendants, and each of them, agreed to
compensate Plaintiff for the performance of such services.” (Ibid.; Construction
Protective Services, Inc., 29 Cal.4th at 198–199.)
Defendant
further argues that the draft agreement contains a provision for mediation of
Plaintiff’s claims, and “the SAC does not allege that CLC complied with this
mediation obligation. Thus, even if the Purported Contract were enforceable
(which it is not), CLC cannot plead its performance of its obligations
thereunder.” (Dem. 7:24–26.) However, the Court finds it sufficient that
Plaintiff has alleged that it “has fully performed all conditions, covenants,
and promises required by him [sic] on his [sic] part to be performed in
accordance with the terms and conditions of the 5249 Cartwright Agreement
through the dates of said Defendants’ material breaches thereof.” (SAC ¶ 27.)
Based on
the foregoing, the Court finds that Plaintiff has alleged facts sufficient to
constitute a cause of action for Breach of Contract. Accordingly, the demurrer
is overruled as to Plaintiff’s first cause of action.
C.
Foreclosure of Mechanics’ Lien
Plaintiff’s
second cause of action alleges Foreclosure of Mechanics’ Lien against
Defendants. Here, Defendants argue that “the Lien itself shows that BAI was not
an owner of the Property and CLC did not provide BAI with notice of the Lien.”
(Dem. 8:6–7, citing Ex. 2 to SAC.) In opposition, “Plaintiff acknowledges that
Defendant BEITLER & ASSOCIATES, INC. is not named on the Mechanic’s Lien.”
(Pl.’s Opp. 6:5–6.)
Based on
the foregoing, the Court finds that Plaintiff has failed to allege facts
sufficient to constitute a cause of action for Foreclosure of Mechanics’ Lien
as against defendant Beitler & Associates, Inc. Accordingly, the demurrer
is sustained as to Plaintiff’s second cause of action.
D.
Fraud and Deceit
Plaintiff’s
third cause of action alleges Fraud and Deceit against Defendants. “One who
willfully deceives another with intent to induce him to alter his position to
his injury or risk, is liable for any damage which he thereby suffers.” (Civ.
Code § 1709.) The elements that must be pleaded in a cause of action for fraud
are: (1) a misrepresentation (false representation, concealment or
nondisclosure); (2) knowledge of its falsity (or “scienter”); (3) intent to
defraud (i.e., to induce reliance); (4) justifiable reliance; and (5) resulting
damage. (Philipson & Simon v. Gulsvig (2007) 154 Cal.App.4th 347,
363.)
1.
Particularity
Fairness
requires that allegations of fraud be pled “with particularity” so that the
court can weed out nonmeritorious actions before a defendant is required to
answer. (Small v. Fritz Companies, Inc. (2003) 30 Cal.4th 167, 184.) The
particularity requirement necessitates pleading facts that “show how, when,
where, to whom, and by what means the representations were tendered.” (Lazar
v. Superior Court (1996) 12 Cal.4th 631, 645.)
Here,
Plaintiff alleges that Defendants “falsely promised to execute and return …
signed contract documents to CLC to never actually execute or return such
signed documents to CLC at all, thereby creating a basis upon which to
undermine CLC’s eventual claims against Defendants.” (SAC ¶ 17.) Plaintiff
further alleges that Defendants made misrepresentations to their lenders, and “had
said Defendants disclosed facts suggesting that the reason for such ‘side
agreements’ was to deceive or mislead a financial entity or commit any other
illegal, dishonest or unethical act, Plaintiff would never have agreed to such
an arrangement, or continued to enter into contracts or do business with
BEITLER or any BEITLER-Affiliated Entities at all.” (Id. at ¶¶ 20, 43.)
Defendants
argue that “since CLC has failed to allege how, when, where, to whom, and by
what means Mr. Beitler, Mr. Rezak, or anyone else made the alleged
representations, the demurrer to the Third Cause of Action must be sustained.”
(Dem. 9:10–12.) In opposition, Plaintiff argues that it “has set forth specific
and precise misrepresentations made by Defendants and their principals spanning
multiple commercial construction contracts spanning four lawsuits, which
induced Plaintiff to enter into and perform the Agreement and ultimately
resulted in damages to Plaintiff – exposing CLC unknowingly to BEITLER’s
apparent overall scheme to mislead its own lender. Plaintiff clearly identifies
that the fraudulent representations alleged were made by BEITLER’s owner and
Chief Executive Officer, Barry Beitler, and by its Chief Operations Officer and
de facto in-house counsel, Donald Rezak.” (Pl.’s Opp. 6:17–24, citing SAC ¶¶ 14,
17–20, 40–58.)
Based on
the foregoing, the Court agrees with Plaintiff and finds that Plaintiff has
alleged facts sufficient to meet the heightened pleading standard for a Fraud
and Deceit cause of action.
2.
Economic Loss Doctrine
“In
general, there is no recovery in tort for negligently inflicted ‘purely
economic losses,’ meaning financial harm unaccompanied by physical or property
damage.” (Rattagan v. Uber Technologies, Inc. (2024) 17 Cal.5th 1, 20.) “A
party alleging fraud or deceit in connection with a contract must establish
tortious conduct independent of a breach of the contract itself, that is,
violation of some independent duty arising from tort law.” (Food Safety Net
Servs. v. Eco Safe Sys. USA, Inc. (2012) 209 Cal.App.4th 1118, 1130.)
Here,
Defendants argue that the “fraud claim is effectively a dressed-up version of
the contract claim. Not only are the alleged damages the same, but the
deficiently pleaded representations boil down to statements that CLC’s invoices
would timely be paid.” (Dem. 9:18–20, citing SAC ¶ 41.)
Plaintiff
argues in opposition that it has sufficiently alleged “not only a breach of the
underlying contract, but that Plaintiff was fraudulently induced by Defendants’
multiple misrepresentations to enter into and perform many hundreds of
thousands of dollars of commercial construction work by virtue of the
misrepresentations made by Defendants to the effect that Defendants were and
would remain solvent and able to pay for Plaintiff’s services, when Defendants’
efforts to use Plaintiff to deceive their own lender – a matter independent
from the contract sued upon – clearly establishes the falseness of this
representation.” (Pl.’s Opp. 7:28–8:6.) Plaintiff therefore asserts that it “was
clearly and deliberately lied to and deceived by Defendants in inducing
Plaintiff to enter into and perform the contract in the first place.” (Id. at
8:21–22.)
As the
Court finds that Plaintiff has alleged facts sufficient to constitute a cause
of action for Fraud and Deceit, as outlined above, the Court likewise finds
that this tort is independent from any alleged breach of the underlying contract
itself. Furthermore, Plaintiff has alleged damages resulting from this cause of
action, in addition to the contract damages. (SAC ¶ 58.) Accordingly, the Court
finds that the economic loss rule does not apply to bar Plaintiff’s third cause
of action.
Based on
the foregoing, the demurrer to Plaintiff’s third cause of action is overruled.
E.
Quantum Meruit
Plaintiff’s
fourth, fifth, and sixth causes of action respectively allege (4) Work, Labor,
and Services; (5) Money Due on an Open Book Account; and (6) Reasonable Value
of Services Rendered against Defendants based on Quantum Meruit.
“Quantum meruit refers to the
well-established principle that the law implies a promise to pay for services
performed under circumstances disclosing that they were not gratuitously
rendered. To recover in quantum meruit, a party need not prove the existence of
a contract, but it must show the circumstances were such that the services were
rendered under some understanding or expectation of both parties that
compensation therefor was to be made.” (Chodos
v. Borman (2014) 227 Cal.App.4th 76, 96 [citations and quotation omitted].)
“[I]n order to recover under a quantum meruit theory, a plaintiff must
establish both that he or she was acting pursuant to either an express or
implied request for such services from the defendant and that the services
rendered were intended to and did benefit the defendant.” (Day v. Alta Bates Medical Center (2002) 98 Cal.App.4th 243, 248.)
Here, Defendants argue that since
the Second, Fourth, Fifth and Sixth Causes of Action for quantum meruit all
incorporate the Purported Contract and the allegations with respect thereto …
those claims must fail as well.” (Dem. 7:27–8:1.) In opposition, Plaintiff
argues that “Defendants fail to cite any controlling authority to the effect
that alternatively plead common counts are inherently defeated if a demurrer is
sustained as to a cause of action for breach of contract.” (Pl.’s Opp. 9:1–3.)
As the
Court finds that Plaintiff has alleged facts sufficient to constitute a cause
of action for Breach of Contract, as outlined above, the Court likewise finds
that Plaintiff has alleged facts sufficient to constitute its Quantum Meruit
causes of action. Accordingly, the demurrer to Plaintiff’s fourth, fifth, and
sixth causes of action is overruled.
F.
Motion to Strike
The court
may, upon a motion, or at any time in its discretion, and upon terms it deems
proper, strike any irrelevant, false, or improper matter inserted in any
pleading. (Code Civ. Proc., § 436, subd. (a).) The court may also strike all or
any part of any pleading not drawn or filed in conformity with the laws of this
state, a court rule, or an order of the court. (Id., § 436, subd. (b).)
The grounds for moving to strike must appear on the face of the pleading or by
way of judicial notice. (Id., § 437.)
Punitive
damages may be recovered upon a proper showing of malice, fraud, or oppression
by clear and convincing evidence. (Civ. Code § 3294, subd. (a).) “Malice” is
defined as conduct intended to cause injury to a person or despicable conduct
carried on with a willful and conscious disregard for the rights or safety of
others. (Id. at subd. (c); Turman v. Turning Point of Cent. Cal.,
Inc. (2010) 191 Cal.App.4th 53, 63.) “Oppression” means despicable conduct
subjecting a person to cruel and unjust hardship, in conscious disregard of the
person’s rights. (Ibid.) “Fraud” is an intentional misrepresentation, deceit,
or concealment of a material fact known by defendant, with intent to deprive a
person of property, rights or otherwise cause injury. (Ibid.) Punitive
damages must be supported by factual allegations. Conclusory allegations,
devoid of any factual assertions, are insufficient to support a conclusion that
parties acted with oppression, fraud or malice. (Smith v. Superior Court
(1992) 10 Cal.App.4th 1033, 1042; Anschutz Entertainment Group, Inc. v.
Snepp (2009) 171 Cal.App.4th 598, 643.)
Here,
Defendants argue that “for the reasons set forth in the accompanying Demurrer,
the SAC fails to state a cause of action for fraud, and no other tort claim has
been pled, the allegation and prayer for punitive damages are improper.” (MTS 3:10–12.)
The Court disagrees and reiterates its finding that Plaintiff has sufficiently
alleged a cause of action for Fraud and Deceit against Defendants. Accordingly,
the motion to strike Plaintiff’s prayer for punitive damages is denied.
G.
Leave to Amend
Where a
demurrer is sustained, leave to amend must be allowed where there is a
reasonable possibility of successful amendment. (Goodman v. Kennedy
(1976) 18 Cal.3d 335, 348.) The burden is on the plaintiff to show the court
that a pleading can be amended successfully. (Id.; Lewis v. YouTube,
LLC (2015) 244 Cal.App.4th 118, 226.) However, “[i]f there is any
reasonable possibility that the plaintiff can state a good cause of action, it
is error to sustain a demurrer without leave to amend.” (Youngman v. Nevada
Irrigation Dist. (1969) 70 Cal.2d 240, 245).
Here, the
Court notes that this is the first demurrer and motion to strike brought
against Plaintiffs’ operative pleading, and Plaintiff requests leave to amend
in the event the Court finds merit to any of Defendants’ arguments. (Pl.’s Opp.
9:2124.) Therefore, under the Court’s liberal policy of granting leave to
amend, Plaintiff is granted 30 days leave to amend the complaint to cure the
defects set forth above.
CONCLUSION¿
The demurrer is sustained as to
Plaintiff’s second cause of action, with 30 days leave to amend, and overruled
as to the remainder. The motion to strike is denied.