Judge: Bruce G. Iwasaki, Case: 24STCV08976, Date: 2025-03-19 Tentative Ruling
Case Number: 24STCV08976 Hearing Date: March 19, 2025 Dept: 58
Judge Bruce G. Iwasaki
Hearing
Date: March 19, 2025
Case
Name: Caston, Inc. v. Hamel
Contracting, Inc.
Case
No.: 24STCV08976
Matter: Motion to Compel
Arbitration
Moving Party: Defendants Hamel Contracting, Inc. and Nationwide Mutual
Insurance Company
Responding
Party: None
Tentative
Ruling: The Motion to Compel
Arbitration is granted; the matter is stayed pending resolution of the arbitration.
This action
arises from a dispute between a contractor and its subcontractor over the
performance of construction services on a construction project (Project). Plaintiff
Caston, Inc. (the subcontractor) filed suit against Defendants Hamel Contracting, Inc.
(the contractor for the Project), the City of Pasadena (the owner of
the Project), and Nationwide
Mutual Insurance Company (Hamel’s payment bond surety), alleging causes of action for (1) Breach of
Contract; (2) Common Count – Quantum Meruit; (3) Enforcement of Stop Payment
Notice; and (4) Recovery on Public Works Payment Bond.
On
December 5, 2024, Defendants Hamel Contracting, Inc. and Nationwide Mutual Insurance
Company filed a
motion to compel arbitration pursuant to the parties’ arbitration agreement. No
opposition was filed.
Legal
Standard
Under Code of Civil Procedure
section 1281.2, a court may order arbitration of a controversy if it finds that
the parties have agreed to arbitrate that dispute. Because the obligation to
arbitrate arises from contract, the court may compel arbitration only if the
dispute in question is one in which the parties have agreed to arbitrate. (Weeks
v. Crow (1980) 113 Cal.App.3d 350, 352.) Since arbitration is a favored
method of dispute resolution, arbitration agreements should be liberally
interpreted, and arbitration should be ordered unless the agreement clearly
does not apply to the dispute in question. (Id. at p. 353; Segal v.
Silberstein (2007) 156 Cal.App.4th 627, 633.)
Analysis
Existence of a Valid Agreement
In ruling on
a motion to compel arbitration, a court must determine two threshold matters:
first, whether a valid agreement to arbitrate exists; and second, whether that
agreement encompasses the dispute at issue. (See Code Civ. Proc. § 1281.2.)
By way of
background, Defendant Hamel entered into a contract with the City of Pasadena
to perform construction services as a prime contractor on the Project.
Thereafter, on June 15, 2022, Plaintiff Caston contracted with Defendant Hamel
to provide the drywall and plastering scopes of work on the Project
(Subcontract). (Compl., ¶ 9, Ex. 1.)
General Condition 23 of the
Subcontract states, in relevant part: “… any controversy or claim arising out
of or relating to this subcontract, or the breach thereof, shall be settled by
arbitration administered by the American Arbitration Association under its
construction industry arbitration rules, and judgment on the award rendered by
the arbitrator(s) may be entered in any court having jurisdiction thereof . .
..” (Compl., ¶ 9, Ex. 1, p. 4.)
Notwithstanding
this provision, on April 9, 2024, Plaintiff Caston filed a Complaint against Defendants
Hamel, Swiss Re Corporate Solutions America Insurance Corporation,[1]
and the City, alleging causes of action for: (1) Breach of Contract; (2)
Common Count – Quantum Meruit; (3) Enforcement of Stop Payment Notice; and (4)
Recovery on Public Works Payment Bond.
In support of this motion to compel
arbitration, Defendants Hamel and Nationwide argue that each of Plaintiff Caston’s
causes of action fall within the scope of the arbitration provision in the
Subcontract and must be compelled to arbitration.
This unopposed argument is well
taken. Each cause of action seeks compensation for work allegedly performed by Plaintiff
Caston on the Project, pursuant to the Subcontract. Here, Plaintiff Caston’s
first cause of action against Hamel is for a breach of the Subcontract.
(Compl., ¶¶ 11-17.) Plaintiff Caston’s second cause of action against Hamel
seeks compensation for work, labor, and/or materials provided on the Project . (Compl.,
¶¶ 18-22.) Plaintiff Caston’s third cause of action against Hamel and the City
seeks compensation for work allegedly performed by Plaintiff Caston on the
Project, pursuant to the terms of the Subcontract and at the direction of Defendant
Hamel. (Compl., ¶¶ 23-28.) Finally, Plaintiff Caston’s fourth cause of action
for recovery on public works payment bond against Hamel and Nationwide seek
payment on the bond for work, labor, equipment, and materials provided by
Plaintiff to the Project based on the terms of the Subcontract. (Compl., ¶¶ 29-34.)
As such, each and every of Plaintiff Caston’s causes of action against Defendants
arise out of and relate to the Subcontract. (Compl., ¶¶ 9-34.)
Based on the foregoing,
Defendants have carried their initial burden of demonstrating the existence of a
valid, binding arbitration agreements and that Plaintiff’s claims fall
within the scope of this binding arbitration agreement. In the absence of any
opposition from Plaintiff, Defendants have met their burden on this motion.
CONCLUSION
Accordingly,
the Court grants Defendants’ motion to compel arbitration. The motion to compel
arbitration is granted; the matter is stayed pending the outcome of
arbitration.
[1] Defendant Swiss Re Corporate
Solutions America Insurance Corporation has since been dismissed. Defendant
Nationwide Mutual Insurance Company was added by way of Doe Amendment on August
7, 2024.