Judge: Cherol J. Nellon, Case: 20STCV36066, Date: 2023-10-13 Tentative Ruling
Case Number: 20STCV36066 Hearing Date: March 11, 2024 Dept: 14
Setoyan vs Pashyan
Case Background
Plaintiff alleges that Defendant
failed to pay them for work done on Defendant’s house. Defendant alleges that
Plaintiff, along with several other contractors, failed to do adequate work.
Defendant also alleges that the contractor he hired to fix Plaintiff’s work actually
compounded the original errors, leaving the whole project stalled.
Complaint
On September
21, 2020, Plaintiff Mkrtich Setoyan dba MK Construction Co. filed their Complaint
for (1) Foreclosure of Mechanic’s Lien, (2) Breach of Written Contract, and (3)
Quantum Meruit against Defendants Hovanes Pashyan aka Hovhannes Pashyan (“Hovanes”)
and DOES 1-25.
On December 24, 2020, Defendant Hovanes
filed his Answer.
On January 3, 2024, Plaintiff
voluntarily dismissed Defendant DOES 1-25, without prejudice.
Pashyan Cross-Complaint
On May 4,
2022, Defendant Hovanes and Armine Pashyan (“Armine”) (collectively “Pashyans”)
filed their Third Amended Cross-Complaint for (1) Breach of Contract; (2)-(4)
Negligence, (5) Breach of Implied Warranty; and (6) Enforcement of Claim on License
Bond against Plaintiff and Cross-Defendants ARPA Technology Group (“ARPA”), MCR
Construction, Inc. (“MCR”), Hudson Insurance Company (“Hudson”), J&S
Electrical Services, Inc. (“J&S”), Majestic Blue Pools, Inc. (“Majestic”),
Magic Brush Painting, Inc. (“Magic”), Glendale Fire Protection, Inc. (“Glendale”),
Danny’s Crane, Inc. (“Danny’s”), Darling Plastering, Inc. (“Darling”), JMB
Stainless Steel, Inc. (“JMB”), Giniani Corp. dba Los Angeles Cast Stone (“Giniani”),
GV Roofing, Inc. (“GV”), SIS Air, Inc. (“SIS”), C&C Concrete Works (“C&C”),
and ROES 1-50.
On February 2, 2021, Plaintiff had filed
its Answer to the original Cross-Complaint.
On December 3, 2021, Cross-Defendant
Hudson had filed its Answer to the first amended Cross-Complaint.
On February 16, 2022,
Cross-Defendant ARPA had filed its Answer to the second amended Cross-Complaint.
On February 25, 2022,
Cross-Defendant ARPA filed a Notice of Settlement between it and Cross-Complainant
Hovanes.
On May 26, 2022, Cross-Complainant
Pashyans voluntarily dismissed Cross-Defendant ARPA, with prejudice.
On June 7, 2022, Cross-Defendant
MCR filed its Answer.
On July 11, 2022, Cross-Defendant
Darling filed its Answer.
On July 14, 2022, Cross-Complainant
Pashyans filed an “Amendment to Complaint” substituting Cross-Defendant SureTec
Insurance Company (“SureTec”) in lieu of ROE 1.
On July 20, 2022, Cross-Defendants
J&S and Glendale filed their respective Answers.
Also on July 20, 2022, the defaults
of Cross-Defendants Majestic, Danny’s, and SIS were entered.
On July 22, 2022, Cross-Defendant
Giniani filed its Answer.
On July 29, 2022, Cross-Complainant
Pashyans voluntarily dismissed the 1st-5th causes of
action as asserted against Cross-Defendant SureTec, without prejudice.
On September 27, 2022,
Cross-Defendant SureTec filed its Answer.
On March 29, 2023, Cross-Defendant
Glendale filed a Notice of Settlement between it and Cross-Complainant
Pashyans.
On April 25, 2023, Cross-Defendant
Pashyans voluntarily dismissed their claims against Cross-Defendant Danny’s,
with prejudice.
On May 15, 2023, Cross-Defendant
Pashyans voluntarily dismissed their claims against Cross-Defendant J&S,
with prejudice.
On May 31, 2023, Cross-Defendant
Pashyans voluntarily dismissed their claims against Cross-Defendant Glendale,
with prejudice.
On September 7, 2023, Cross-Complainant
Pashyans filed an “Amendment to Complaint” substituting Cross-Defendant California
Construction Group, Inc. (“California Construction”) in lieu of ROE 2. Proof of
service was filed on September 29, 2023, indicating service on September 20,
2023.
On October 31, 2023, Cross-Defendant
Pashyans voluntarily dismissed their claims against Cross-Defendants JMB and
ROES 3-50, without prejudice.
On November 8, 2023, Cross-Defendant
Pashyans voluntarily dismissed their claims against Cross-Defendant SureTec,
with prejudice.
On the same date, the default of
Defendant California Construction was entered.
On January 12, 2024, the defaults
of Defendants Magic, GV, and C&C were entered.
All parties remaining on this
cross-complaint have either answered or been defaulted. Those who have answered
are: Plaintiff/Cross-Defendant, MCR, Hudson, Darling, and Giniani. Those in
default are: Majestic, Magic, GV, SIS, C&C, and California Construction
ARPA Cross-Complaint
On February
24, 2021, Cross-Defendant ARPA filed its Cross-Complaint for (1) Breach of
Contract — Express Indemnification; (2) Breach of Contract — Duty to Defend; (3)
Declaratory Relief — Indemnification (4) Declaratory Relief — Duty of Defend; (5)
Declaratory Relief; (6) Equitable Indemnity; (7) Contribution/Apportionment of
Fault; and (8) Declaratory Relief against Plaintiff and Cross-Defendants
Ecumena Design Studio dba Gary Akopian (“Ecumena”) and DOES 1-75.
On March 29, 2021, Plaintiff/Cross-Defendant
filed his Answer.
On September 10, 2021, Cross-Complainant
ARPA voluntarily dismissed Defendant Ecumena, without prejudice.
On August 8,
2021, Cross-Complainant ARPA filed an “Amendment to Complaint” substituting
Cross-Defendant MCR in lieu of DOE 2.
On June 6,
2022, Cross-Complainant ARPA voluntarily dismissed its entire Cross-Complaint,
without prejudice.
MCR Cross-Complaint
On February
14, 2022, Cross-Defendant MCR filed its Cross-Complaint for (1) Breach of
Contract, (2) Fraud, (3) Negligent Misrepresentation, and (4) Declaratory
Relief against Cross-Defendant Pashyan, Ara Amyan dba ArtDesign USA (“Amyan”),
and DOES 1-50.
On March
11, 2022, Cross-Defendant Pashyan filed his Answer.
On February
21, 2024, Cross-Defendant Amyan filed his Answer.
Glendale Cross-Complaint
On July 20,
2022, Cross-Defendant Glendale filed its Cross-Complaint for (1) Implied and
Equitable Indemnity, (2) Contribution and Apportionment, and (3) Declaratory
Relief against MOES 1-20.
SureTec Cross-Complaint
On
September 27, 2022, Cross-Defendant SureTec filed its Cross-Complaint for (1)
Express Indemnity, (2) Implied Indemnity, (3) Statutory Reimbursement, and (4)
Contribution against Cross-Defendants MCR, Mark Rolph (“Rolph”) and MOES 1-50.
On January
17, 2023, Cross-Defendants MCR and Rolph filed their joint Answer.
Trial Date
Jury trial
is currently set for March 11, 2024.
Instant Motion
Plaintiff/Cross-Defendant
now moves this court for an order continuing trial by six months, with
discovery deadlines to track the new date.
Decision
The motion
is GRANTED. Trial is continued to September 23, 2024, at 9:00 am. Final Status
Conference is set for September 12, 2024, at 10:00 am. All counsel are to
appear IN PERSON at the Final Status Conference. All discovery-related
deadlines will track the new date, as well as the deadlines for motions in
limine and the preparation of trial documents.
Discussion
California
Rules of Court Rule 3.1332(a) provides that trial dates are to be treated as
firm. However, Rule 3.1332(c) provides that, although continuances are “disfavored,”
requests should be considered on an individual basis. That subsection also
includes a non-exhaustive list of possible grounds for a continuance.
Defendants base
their motion on Rule 3.1332(c)(5), which provides for a continuance if a new
party has been added to the case. That subdivision applies here.
Cross-Defendant
Amyan joined this case by filing an answer to the MCR Cross-Complaint less than
three weeks before the present trial date. He is entitled to conduct discovery
and prepare his defense.
The court
currently has 5 other trials scheduled for March 11, another case trailing pending
long cause submission, and still another trailing to March 18. Of those, three
are older than this case. Therefore, the court’s calendar also compels a
continuance.
Finally,
counsel should note that this case will be four years old in September of this
year. It has now been continued on two separate occasions because a new party
has been added on a cross-complaint immediately prior to trial. Counsel should
be advised that the court has no present intention of giving another
continuance. If a new party should once again be added on a cross-complaint,
the court’s inclination will be to sever that cross-complaint and proceed with
the remainder of the case.
Conclusion
Because a
new party has recently been brought into the case and because the court’s own
calendar is impacted, the motion for a continuance is GRANTED. Trial is
continued to September 23, 2024, at 9:00 am. Final Status Conference is set for
September 12, 2024, at 10:00 am. All counsel are to appear IN PERSON at the Final
Status Conference. All discovery-related deadlines will track the new date, as
well as the deadlines for motions in limine and the preparation of trial
documents.