Judge: Cherol J. Nellon, Case: 23STCV020757, Date: 2025-06-12 Tentative Ruling
Case Number: 23STCV020757 Hearing Date: June 12, 2025 Dept: 14
#7
Case Background
This is an action for breach of contract and common
counts. Plaintiff DMG Corporation (Plaintiff) alleges that in October 2015, it
executed a written credit application with Defendant Techno-Advanced, Inc.
(Techno). In December 2022, Plaintiff provided a quote for materials for use in
a construction project. Techno confirmed the order by issuing a purchase order
to Plaintiff. Techno promised to pay for the materials within 30 days of the
invoice. Despite Plaintiff’s performance under the contract, Techno failed to
pay the sum of $713,644.70.
On August 29, 2023, Plaintiff filed its Complaint
against Techno.
On October 24, 2023, Cross-Complainant Techno filed its
Cross-Complaint against Westport Construction, Inc. (Westport) and 806 West
Adams Property LLC. (806 West Adams), asserting causes of action for (1)
implied indemnity, (2) comparative indemnity, (3) declaratory relief, (4)
comparative indemnity, and (5) contribution.
On April 16, 2024, Techno filed its First Amended
Cross-Complaint (“FACC”) asserting one cause of action for equitable indemnity.
On May 17, 2024, Westport filed a demurrer to the FACC,
arguing that Techno’s equitable indemnity claim was barred by (1) the economic
loss rule, (2) the express indemnity provision in the subcontract, and (3) the
risk-of-loss provision in the subcontract.
On July 11, 2024, the Court sustained Westport’s demurrer
to the FACC with leave to amend.
On August 6, 2024, the Court issued its written ruling
sustaining the FACC demurrer, finding that Techno’s equitable indemnity claim
was barred by the economic loss rule. (July 11, 2024 Minute Order, p. 5.)
Having reached that conclusion, the Court found it unnecessary to discuss the
arguments Westport had raised in its demurrer to the FACC (e.g., that the
risk-of-loss provision in the subcontract barred the equitable indemnity claim).
On July 30, 2024, Techno filed its Second Amended Cross-Complaint
(SACC), asserting one cause of action for breach of oral contract.
On November 12, 2024, the Court sustained Westport’s
demurrer to the SACC without leave to amend because Techno failed to obtain
leave of court to assert a new cause of action for breach of contract and the
Court’s ruling sustaining Westport’s demurrer to the FACC with leave to amend
did not discuss or give Techno the right to do so.
On January 21, 2025, Techno filed a motion for leave to
amend its cross-complaint. Westport opposed the motion.
On April 8, 2025, the Court granted Techno’s motion for
leave to amend and ordered Techno to file its proposed Third Amended
Cross-Complaint (TACC).
After the hearing on April 8, 2025, Techno filed the
operative TACC, asserting causes of action for (1) breach of written contract
and (2) goods sold and delivered against Westport, 806 West Adams, and Roes 1
to 20.
On May 12, 2025, Westport filed the instant demurrer to
the TACC.
On May 22, 2025, Westport filed the instant motion to
continue trial.
On May 30, 2025, Techno filed its opposition to the
demurrer.
On June 5, 2025, Westport filed its reply in support of
the demurrer.
As of June 10, 2025, no opposition to the motion to
continue trial has been filed.
Instant Pleading
Westport demurs Techno’s
first and second causes of action in the TACC.
Decision:
The demurrer to the Third Amended Cross-Complaint is SUSTAINED IN PART and OVERRULED IN PART as follows. The demurrer to the first cause of action for breach of written contract is OVERRULED. The demurrer to the second cause of action for goods sold and delivered is SUSTAINED, with leave to amend. Cross-Complainant Techno-Advanced, Inc. is ordered to file and serve its Fourth Amended Cross-Complaint within 30 days of this ruling.
Demurrer
As an
initial matter, the Court finds that Westport has satisfied the meet and confer
requirement. (Demurrer, Declaration of Geoffrey T. Sawyer, ¶¶ 3, 5.)
Westport
demurs the TACC’s first cause of action for breach of written contract and
second cause of action for goods sold and delivered, arguing: (1) the risk of
loss provision in the “Original Subcontract” precludes the TACC claims; (2) the
alleged “Second Subcontract” essentially lacks consideration and, therefore, it
is not a legally binding contract and cannot support a breach of contract claim;
(3) Techno cannot allege its second cause of action for goods sold and
delivered, which is based on a quasi-contract theory, if Techno is also
alleging there is an enforceable contract between the parties; and (4) Techno
concedes by judicial admission that the parties entered into the Original
Subcontract and, therefore, that concession is conclusive as to the terms of
the Original Subcontract that bar its claims.
In
opposition, Techno argues the following. First, the alleged Second Subcontract
was not in fact a second contract, but a modification of the Original
Subcontract. Second, the risk of loss provision in the Original Subcontract
does not apply to this case because there was no “loss” to the HVAC equipment.
Third, Techno is allowed to plead alternative causes of action and that is why
it asserted a breach of contract claim as well as a good sold and delivered
claim. Finally, Techno argues that its judicial admission does not contradict
the TACC’s allegations.
By way
of background, the TACC alleges the following.
On or
about December 27, 2022, Westport and Techno entered into a written subcontract
agreement for the furnishing of material, labor, equipment, and Techno’s
installation of HVAC equipment in the construction project underlying this case
(this is the “Original Subcontract” that Westport is referring to). (TACC, ¶
5.)
“The
custom in the construction industry is to order and acquire HVAC equipment and materials
when the project commences and the installation of HVAC equipment and materials
are ready to be installed.” (TACC, ¶ 6.)
However,
on or about January 26, 2023, to prevent price increase of the HVAC equipment, Westport
“and plaintiff” (presumably DMG) entered into a written agreement, compromised
of emails, for Techno’s purchase of HVAC equipment earlier than planned (this
is the “Second Subcontract” that Westport is referring to). (TACC, ¶ 8; Exhibit
B – a copy of the emails Techno alleges shows Westport asking for an earlier
purchase of the HVAC equipment, p. 1 – email from Tim Coop of Westport to
Techno’s Alfred Babayans [“Alfred ¶ Get with Geovanni on the submittal for the
LG and other items that we need to get approved quickly and ordered in January
to avoid increases. We can submit these critical items as a separate package to
avoid any hold up from the engineer. Kristen mentioned that you should have the
submittal ready this week”]; p. 2-3 – email from Geovanni Munoz of Westport to
“Techno Advanced team” [“We also will need you to send over the invoices for
the Mechanical Equipment to avoid the price increase, this will be included in
the January billing”].)
“Pursuant
to the written agreement alleged herein, TECHNO purchased the HVAC equipment
and materials from plaintiff prior to commencement of construction of THE
PROJECT.” (TACC, ¶ 9.)
Techno
“has performed all conditions required of it under the written agreement,
except for conditions for which [its] performance was excused.” (TACC, ¶ 10.)
“On or
about May 11, 2023, cross-defendant, WESTPORT CONSTRUCTION,. INC., gave notice
to TECHNO that THE PROJECT had been cancelled. Such cancellation occurred
before construction of THE PROJECT commenced. Plaintiff [DMG] has refused to
accept return of the HVAC equipment and is demanding full payment for
cross-complainant’s purchase of the equipment. Storage fees are being incurred
for the storage of the HVAC equipment.” (TACC, ¶ 11.)
For the
purposes of this demurrer, the Court finds that Westport has failed to show
that the risk-of-loss provision in the Original Subcontract (i.e., Section 4.2
Work Storage in the contract) bars Techno’s claims. “[J]udicial interpretation
is controlled by the clear and explicit meaning of the language of a contract,
interpreted in its ordinary and popular sense, unless the parties intended a
technical sense or a special meaning by usage.” (Pardee Const. Co. v.
Insurance Co. of the West (2000) 77 Cal.App.4th 1340, 1352.) Here, Westport
argues that the risk of loss provision states: “Subcontractor is responsible
for the receipt, delivery, unloading, storage, warehousing, protection ...,
transportation, insurance …, and all risk of loss to its materials, tools, and
equipment, whether stored in a designated or secured area at the Job site or
off the Job site.” (Demurrer, p. 9:11-15 [emphasis removed].) However, nothing
in that language shows that Techno agreed to assume the risk of the cost and
storage fees of the HVAC equipment if the project was cancelled before it
commenced. In addition, Techno argues that “risk of loss” in the context of
construction materials means damage or loss of materials during the
construction process. Since the meaning of the phrase “risk of loss” is
disputed, and Westport has not presented extrinsic evidence to support its
interpretation of that phrase, the Court declines to find on this demurrer that
the risk of loss provision bars Techno’s claims. For those same reasons, the
Court finds Westport’s judicial admission argument unpersuasive.
The
Court also declines to sustain the demurrer on the ground that the alleged “Second
Subcontract” lacks consideration. Indeed, Techno has argued that the alleged
Second Subcontract is merely a modification of the Original Subcontract and not
a second “contract.” In its reply, Westport has neither addressed that argument
nor argued that Techno has failed to state facts sufficient to show
modification. Instead, Westport argues in its reply that Section 3.2 of the
Original Subcontract, which is titled “Early Contract Termination,” precludes
any claims where the job has been cancelled within six months. However,
Westport did not make that argument in its moving papers and, therefore, the
Court declines to consider it.
As for
Westport’s argument that Techno cannot assert both its breach of written
contract claim and goods sold and delivered claim, the Court agrees. “A
plaintiff may not … pursue or recover on a quasi-contract claim if the parties
have an enforceable agreement regarding a particular subject matter.” (Klein
v. Chevron U.S.A., Inc. (2012) 202 Cal.App.4th 1342, 1388.) However, “if a
plaintiff was uncertain as to whether the parties had entered into an
enforceable agreement, the plaintiff would be entitled to plead inconsistent
claims predicated on both the existence and absence of such an agreement.” (Ibid.)
Here, Techno alleges the parties entered into the Original Subcontract and then
a subsequent modification or contract. (TACC, ¶¶ 5, 8.) Since Techno does not
deny the existence or enforceability of those agreements in its second cause of
action for goods sold and delivered, Techno is precluded from asserting that
claim alongside its breach of written contract claim.
Therefore,
the demurrer to the first cause of action for breach of written contract is
overruled, but the demurrer to the second cause of action for goods sold and
delivered is sustained, with leave to amend.
Conclusion
Westport’s demurrer to the Third Amended Cross-Complaint is SUSTAINED IN PART and OVERRULED IN PART as follows. The demurrer to the first cause of action for breach of written contract is OVERRULED. The demurrer to the second cause of action for goods sold and delivered is SUSTAINED, with leave to amend. Cross-Complainant Techno-Advanced, Inc. is ordered to file and serve its Fourth Amended Cross-Complaint within 30 days of this ruling.