Judge: Christopher K. Lui, Case: 23STCV24687, Date: 2025-02-24 Tentative Ruling
Case Number: 23STCV24687 Hearing Date: February 24, 2025 Dept: 76
This is an action for common count
and to foreclose on a mechanic’s lien arising out of labor, services, equipment
and materials for the work of improvement to Defendants’ property performed by
Plaintiff.
Defendants/Cross-Complainants Katan
915 LLC, CRA Dogwood LLC and MTK RE LLC move for judgment on the pleadings as
to the Complaint.
TENTATIVE RULING
Defendants/Cross-Complainants
Katan 915 LLC, CRA Dogwood LLC and MTK RE LLC’s motion for judgment on the
pleadings as to the Complaint is DENIED as to the third cause of action.
ANALYSIS
Motion For
Judgment On The Pleadings
Request For Judicial Notice
Defendants
request that the Court take judicial notice of the following:
Exhibit A Standard Abbreviated Form of
Agreement Between Owner and Contractor;
GRANTED. This was attached to the
Complaint as Exh. A.
Exhibit B Secretary of State Statement
of Information for The Blakerie, LLC under entity number 202109111209;
GRANTED.
The Court may take judicial notice of a business entity’s corporate
status as reflected in the Secretary of State’s records. (Gamet v. Blanchard (2001) 91 Cal.App.4th
1276, 1286; Pedus Bldg. Servs. v. Allen (2002) 96 Cal.App.4th 152, 156 n.2.)
Exhibit C Secretary of State Statement
of Information for The Bakerie, LLC under entity number 202027610740;
GRANTED.
Exhibit D Recommendation on Mechanic’s
Lien Law (Feb. 2008) 37 Cal. Law Revision Com. Rep. (2008);
GRANTED.
The Court may take
judicial notice of legislative history materials relevant to a material issue.
(See Doe v. City of Los Angeles (2007) 42 Cal.4th 531, 544 n.4.)
Exhibit E Sen. Com. on Judiciary, Rep.
on Sen Bill. No. 189 (2009-2010 Reg. Sess.)
GRANTED.
Meet and Confer
The
Declaration of Michael L. Jensen reflects that the meet and confer requirement
set forth in CCP § 439 was satisfied.
Discussion
Defendants/Cross-Complainants Katan
915 LLC, CRA Dogwood LLC and MTK RE LLC move for judgment on the pleadings as
to the Complaint as follows:
1. Third
Cause of Action (Foreclosure of Mechanics Lien).
Defendants
argue that Plaintiff named the wrong hiring party (that is to say, a different
hiring party altogether) in its notice of mechanic’s lien.
Defendants have submitted
judicially noticeable documents which reflect that “The Bakerie LLC” is a
different entity from “The Blakerie LLC,” which is the entity with which
Plaintiff entered into the contract of improvement. (RJN, Exhs. A (contract is
with The Blakerie, LLC), B (The Blakerie, LLC is an Advertising Agency), C (The
Bakerie, LLC is a Retail Dispensary), although they both pertain to the same
parcel of property.
In this regard, the Claim of
Mechanic’s Lien recorded on August 15, 2023
(Complaint, Exh. B) identifies The Bakery LLC, which is not “[t]he name
of the person by whom the claimant was employed or to whom the claimant
furnished work.” (Civil. Code, § 8416(a)(4)[1].)
However, the Claim of Mechanic’s Lien includes the property address and the
names of the property owners, as well as the amount due.
In reference to the second defect
referred to, as to the name of the party to whom the materials were
furnished, the respondent relies on such cases as Madera Flume etc.
Co. v. Kendall, 120 Cal. 182 [52 P. 304, 65 Am. St.
Rep. 177], Hogan v. Bigler, 8 Cal. App. 71
[96 P. 97], and Santa Monica Lumber & Mill Co. v. Hege, 119
Cal. 376 [51 P. 555]. On the other hand, the appellant contends that under
section 1203 of the Code of Civil Procedure, this claim must be held sufficient
in the absence of any showing of injury. In Richman Sanitary
Co. v. Franklin, 122 Cal. App. 229 [9 P.2d 855, 856],
the court said: "Since the enactment of section 1203 of the Code of Civil
Procedure many cases have been decided on the authority of that
section. No one of them has followed the harsh rule stated in the case
of Santa Monica L. & M. Co. v. Hege, supra." In Prince v. Hill, 170
Cal. 192 [149 P. 578, 580], the court said: "The statute does not require
such literal exactness and rigid adherence to precise form as the
appellants contend." In that case the court held that the name
of the person to whom the materials were furnished was sufficiently disclosed
by the allegations of the notice. In Jarvis v. Frey, 175
Cal. 687 [166 P. 997], a notice of lien was held to be sufficient where it
could be reasonably inferred from statements in the notice to whom the
materials were furnished. A somewhat similar rule was followed in
the case of Trout v. Siegel, 202 Cal. 706
[262 P. 320]. In Consolidated Pipe Co. v. Wolski, 211
Cal. 563 [296 P. 277, 278], it is said: "Liens of mechanics or
materialmen will not be held invalid unless they tend to defraud or fail to
impart notice."
(Shafer v. Los Serranos Co.
(1932) 128 Cal.App. 357, 360 [bold emphasis and underlining added].)
Here, the
Claim of Mechanic’s Lien stated that the services were rendered to “The Bakerie
LLC, 915 Venice Boulevard, Los Angeles CA 90015.” (Compliant, Exh. B.) Per the
Statement of Information submitted by Defendants, this is the principal address
of The Blakerie LLC. (RJN, Exh. B.) On
the other hand, the principal address of The Bakerie LLC is stated as 2711 N
Sepulveda Blvd #341—and nowhere is 915 Venice Boulevard identified on The
Bakerie’s Statement of Information. (RJN, Exh. C.) As such, it can be
reasonably inferred from the statements in the recorded notice that the entity
to which Plaintiff furnished labor and materials was The Blakerie. (Shafer,
supra, 128 Cal.App. at 360.) The Court finds that the Notice of Lien was
sufficient and not invalid by virtue of identifying The Bakerie LLC instead of
The Blakerie, LLC.
Defendants also argue that
Plaintiff failed to provide Owner Defendants, who are the owners of the
Property, with a preliminary notice of its intent to record the mechanic’s
lien.
The Complaint alleges at ¶ 13 re:
the third cause of action in pertinent part: “Defendants knew of and welcomed
Plaintiffs contract with Defendant The Bakerie LLC and thus no 20-day
preliminary notice was required.”
Defendants
argue that Plaintiff’s failure to give preliminary notice is fatal to the third
cause of action, based on Civil Code, § 8200, which provides:
(a) Except as otherwise provided
by statute, before recording a lien claim, giving a stop payment notice, or
asserting a claim against a payment bond, a claimant shall give
preliminary notice to the following persons:
(1) The owner or reputed
owner.
(2) The direct contractor or
reputed direct contractor to which the claimant provides work, either directly
or through one or more subcontractors.
(3) The construction lender or
reputed construction lender, if any.
(b) The notice shall comply
with the requirements of Chapter 2 (commencing with Section 8100) of Title 1.
(c) Compliance with this
section is a necessary prerequisite to the validity of a lien claim or stop
payment notice under this title.
(d) Compliance with this section
or with Section 8612 is a necessary prerequisite to the validity of a claim
against a payment bond under this title.
(e) Notwithstanding the
foregoing subdivisions:
(1) A laborer is not required to
give preliminary notice.
(2) A claimant with a direct
contractual relationship with an owner or reputed owner is required
to give preliminary notice only to the construction lender[2] or
reputed construction lender, if any.
(Civ. Code § 8200 [bold emphasis and
underlining added].)
Neither
Civil Code § 8200, nor other sections in the statutory scheme, define “direct
contractual relationship.” However, case law has held that if an owner with
actual knowledge of the improvements being made to the property fails to avail
himself of the mode of exempting his interest from liability, he is deemed to
have a “direct contract with the owner” for purposes of the preliminary notice
exemption—which exists under the current version of Civil Code § 8442:
An owner may be estopped, however,
to assert that a claim is invalid because the claimant failed to give him
the prior notice required by section 1193. Where a noncontracting
owner has actual knowledge of the improvements being made to his property and
fails to avail himself of the mode of exempting his interest from liability for
the work provided by section 1183.1, subdivision (b), 2 he is estopped to deny that the work was done at
his instance and request. ( Halspar, Inc. v. La
Barthe, 238 Cal.App.2d 897 [48 Cal.Rptr. 293], hrg. denied Feb. 16,
1966.) Under such circumstances the claimant has a "direct
contract with the owner" for the purposes of section 1193[3]
and consequently is not required to give the notice prescribed therein.
( Citations [*354] omitted.) "This result is entirely
logical as . . . the owner is already in possession of the type of information
otherwise provided by the prelien notice of section 1193." (Citation
omitted.)
(Scott, Blake & Wynne v. Summit Ridge Estates, Inc. (1967) 251
Cal.App.2d 347, 353-54 [bold emphasis and underlining added].)
Former
section 1183.1 provided as follows regarding a claim of nonresponsiblity:
2 The pertinent portion of
section 1183.1, subdivision (b) provides that every improvement constructed
with the knowledge of the owner shall be held to have been constructed at the
instance of the owner subject to any lien filed in accordance with the
provisions of the mechanic's lien statute unless the owner shall give the
statutory notice of nonresponsibility within 10 days after he has obtained
knowledge of the improvement.
(Scott, Blake & Wynne, supra, 251 Cal.App.2d at 353 n.2.)
The
present-day version of § 1183.1 is found at Civil Code, § 8442:
The following interests in real
property to which a lien attaches are subject to the lien:
(a) The interest of a person that
contracted for the work of improvement.
(b) The interest of a person
that did not contract for the work of improvement, if work for which the
lien is claimed was provided with the knowledge of that person, unless that
person gives notice of nonresponsibility under Section 8444[4].
(Civ. Code § 8442 [bold emphasis added].)
As such,
because the prior statutory language has carried over to the new version, there
is no reason to ignore the case law which interpreted the prior, identical
statutory scheme, especially when Civil Code, § 8200 utilizes the term “direct
contractual relationship with an owner,” without defining that phrase. The
statutory language above has carried over to the current version. Indeed, as
argued in the Opposition, even in the legislative history materials submitted
by Defendants themselves, this construction of a “participating owner” even if
not a directly contracting owner, applies:
Comment. Section 8442 restates the last
part of former Section 3128,
and former Section 3129, without
substantive change. A reference to
“work” is substituted for the former
reference to “commencement of the
work or of the furnishing of the
materials.” See Section 8048 (“work”).
It should be noted that under this
section, the interest of a person that
contracts for a work of improvement
indirectly, for example through a
provision in a lease that requires a
tenant to make the work of
improvement, may be subject to the
lien. Likewise, the interest of a
person that did not contract for a work
of improvement might in some
circumstances be subject to the lien if
the person is a “participating
owner.” See, e.g., Los Banos Gravel Co.
v. Freeman, 58 Cal. App. 3d
785, 130 Cal. Rptr. 180 (1976).
See also Sections 8016 (“know or
knowledge”), 8024 (“lien”), 8032
(“person”), 8050 (“work of
improvement”).
(Defendants’ Request For Judicial
Notice, Ex. E (Recommendation on Mechanic’s Lien Law (Feb. 2008) 37 Cal. Law
Revision Com. Rep. (2008) p. 682.)
The Court finds that for purposes
of this motion for judgment on the pleadings Plaintiff has sufficiently pled
that the 20-day preliminary notice was not required.
Moving
party argues in the Reply that Civ. Code, § 8442 relates to lien interests that
may attached after a lien is validly established, not the requirements for
validity establishing a lien, which requirements are found in § 8200. This
argument is not persuasive, as the statutory scheme contemplates that a lien
has already attached independently of the preliminary notice requirement.
See,
e.g., Civ. Code, § 8410: “A claimant may enforce a lien only if the
claimant has given preliminary notice to the extent required by Chapter 2
(commencing with Section 8200) and made proof of notice.” (Civ. Code § 8410.)
Recordation of the claim of lien establishes enforceability (validity). (See
Civ. Code, § 8412.) As discussed above,
it can be reasonably inferred from the statements in the
recorded notice that the entity to which Plaintiff furnished labor and
materials was The Blakerie. (Shafer, supra, 128 Cal.App. at 360.
Defendants
point to the legislative history of 8200, which states that the provisions of
Civil Code, § 8200 are new or substantively different from former law. (Supplemental
Reply, Page 5:25-1; 2010 Cal. Legis. Serv. Ch. 697, § 107, subd. (b) (S.B. 189).)
However, as noted above, § 8200 retains the substance of the concept of a “claimant
with a direct contractual relationship with an owner” without defining “direct
contractual relationship. (See Civ. Code § 8200(e)(2).) In that regard,
there is no reason to ignore prior case law construing similar language.
Accordingly,
Defendants’ arguments are not persuasive. The motion for judgment on the
pleadings as to the third cause of action is DENIED.
[1] The
legislative history submitted by Defendants itself recognizes: “Comment.
Subdivisions (a)-(e) of Section 8416 restate former Section 3084 without
substantive change.” (Defendants’ Request For Judicial Notice, Ex. E
(Recommendation on Mechanic’s Lien Law (Feb. 2008) 37 Cal. Law Revision Com.
Rep. (2008) p. 676.)
“Construction lender” means either
of the following:
(a) A mortgagee or beneficiary
under a deed of trust lending funds with which the cost of all or part of a
work of improvement is to be paid, or the assignee or successor in interest of
the mortgagee or beneficiary.
(b) An escrow holder or other
person holding funds provided by an owner, lender, or another person as a fund
for with which the cost of all or part of a work of improvement is to be paid.
(Civ. Code
§ 8006.)
[3] As it existed at the time of this
decision, Civ. Proc. Code § 1193 provide as follows:
The pertinent portion of section
1193 provides that "(a) Except one under direct contract with the owner or
one performing actual labor for wages, every person who furnishes labor,
service, equipment or material for which a lien otherwise can be claimed under
this chapter, must, as a necessary prerequisite to the validity of any claim of
lien subsequently filed, cause to be given not later than 15 days prior to the
filing of a claim of lien a written notice as prescribed by this section,
to the owner or reputed owner and to the original contractor."
(Scott, Blake & Wynne v.
Summit Ridge Estates, Inc. (1967) 251 Cal.App.2d 347, 353.)
(a) An owner of real property
or a person claiming an interest in real property on which a work of
improvement is situated that did not contract for the work of improvement may
give notice of nonresponsibility.
(b) A notice of
nonresponsibility shall be signed and verified by the owner.
(c) The notice shall comply
with the requirements of Chapter 2 (commencing with Section 8100) of Title 1.
(d) The notice shall also
include all of the following information:
(1) The nature of the owner’s
title or interest.
(2) The name of a purchaser
under contract, if any, or lessee, if known
.
(3) A statement that the
person giving the notice is not responsible for claims arising from the work of
improvement.
(e) A notice of
nonresponsibility is not effective unless, within 10 days after the person
giving notice has knowledge of the work of improvement, the person both posts
and records the notice.
(Civ. Code § 8444.)