Judge: Curtis A. Kin, Case: 23STCV18989, Date: 2024-02-15 Tentative Ruling
Case Number: 23STCV18989 Hearing Date: February 15, 2024 Dept: 82
|
Superior Court of
California County of Los Angeles |
||||
|
SKANSKA USA BUILDING INC., |
Plaintiff, |
Case No. |
23STCV18989 |
|
|
vs. MIK CONSTRUCTION, INC., |
Defendant. |
[TENTATIVE] RULING ON APPLICATION FOR RIGHT TO
ATTACH ORDER Dept. 82 (Hon. Curtis A. Kin) |
|
|
|
|
|
|
|
|
Plaintiff Skanska USA Building Inc. seeks
a writ of attachment against defendant MIK
Construction, Inc. in the amount of $723,810.85. For the reasons that follow, the request is
GRANTED IN PART.
I. Factual Background
Plaintiff Skanska USA Building Inc. (“Skanska”)
was the construction manager of a project to replace the Acute Care Services building
at Hollywood Presbyterian Medical Center (“Project”). (Childress Decl. ¶¶ 2,
3.) Pursuant to a written subcontract agreement dated May 24, 2019, Skanska
engaged defendant MIK Construction, Inc. (“MIK”) to furnish and install the
site concrete, asphalt, hardscape, and related work and services at the
Project. (Childress Decl. ¶¶ 5, 6; Kim Decl. ¶ 8.)
From July 2020 to April 2022, MIK
and Skanska corresponded with respect to changing the type of foam used in the
Project. (Kim Decl. ¶ 9.) On April 19, 2022, Skanska submitted a change order
to the Project owner. (Kim Decl. ¶ 10.) The Project owner rejected Skanska’s
request for change order. (Kim Decl. ¶ 12.)
To
mitigate any potential claims and delays on the Project, on April 30, 2022, Skanska
and MIK executed Change Order No. 3 to MIK in the amount of $1,480,000 with respect
to the changing of foam. (Kim Decl. ¶¶ 12, 14 & Ex. 4; Childress Decl. ¶ 8.)
Change Order No. 3 contains a provision stating, “Subcontractor agrees upon
written demand by Contractor to remit any and all SCO [Subcontractor Change
Order] Advances to Contractors within 10 calendar days of receipt of such
demand.” (Kim Decl. ¶ 14 & Ex. 4 at 1.) Pursuant to Change Order No. 3,
Skanska advanced the sum of $723,810.85 to MIK through two payments. (Childress
Decl. ¶¶ 9, 10 & Exs. B, C.) Pursuant to Skanska’s orders, MIK procured the
desired kind of foam. (Kim Decl. ¶¶ 15, 16.)
On
April 17, 2023, the Project owner terminated its contract with Skanska and
provided notice of its intent to assume the subcontract between Skanska and
MIK. (Kim Decl. ¶ 17.)
On June 21, 2023, with respect to the foam paid for
by Skanska, Gordon Childress, Skanska’s Executive Vice President, purportedly
stated that Skanska would not ask for a credit or refund on the foam, according
to Billy Kim, President of MIK. (Kim Decl. ¶ 21.) Childress denies Kim’s
assertion, stating that he “specifically told Mr. Kim that Skanska expected MIK
to repay these funds now that Skanska was no longer involved with the Project.”
(Supp. Childress Decl. ¶¶ 3, 4.)
MIK
has become general contractor on the Project. (Kim Decl. ¶ 23.) On July 21,
2023, Skanska issued a formal demand to MIK for repayment of the $723,810.85 it
paid pursuant to Change Order No. 3. (Childress Decl. ¶ 13 & Ex. D; Kim
Decl. ¶ 16.) MIK refuses to make repayment. (Childress Decl. ¶¶ 14, 15.)
On July 25, 2023, MIK recorded a mechanic’s lien in
the amount of $381,374.45 for amounts due under the subcontract and for change
orders and extra work ordered by Skanska. (Kim Decl. ¶ 25.)
II. Applicable Law
“Upon
the filing of the complaint or at any time thereafter, the plaintiff may apply
pursuant to this article for a right to attach order and a writ of attachment
by filing an application for the order and writ with the court in which the
action is brought.” (CCP § 484.010.)
The application shall be executed under oath and
must include: (1) a statement showing that the attachment is sought to secure
the recovery on a claim upon which an attachment may be issued; (2) a statement
of the amount to be secured by the attachment; (3) a statement that the
attachment is not sought for a purpose other than the recovery on the claim
upon which the attachment is based; (4) a statement that the applicant has no
information or belief that the claim is discharged or that the prosecution of
the action is stayed in a proceeding under the Bankruptcy Act (11 U.S.C.
section 101 et seq.); and (5) a description of the property to be attached
under the writ of attachment and a statement that the plaintiff is informed and
believes that such property is subject to attachment. (CCP § 484.020.)
The
application for a writ of attachment must be supported “by an affidavit showing
that the plaintiff on the facts presented would be entitled to a judgment on
the claim upon which the attachment is based.” (CCP § 484.030.)
The Court shall consider the showing made by the
parties, as well as the pleadings and other papers in the record. (CCP §
484.090(a), (d).) The Court shall issue a right to attach order if it finds all
of the following:
(1) The claim upon which the attachment is based is
one upon which an attachment may be issued.
(2) The plaintiff has established the probable
validity of the claim upon which the attachment is based.
(3) The attachment is not sought for a purpose
other than the recovery on the claim upon which the attachment is based.
(4) The amount to be secured by the attachment is
greater than zero.
(CCP § 484.090(a)(1-4).)
At
the times prescribed by CCP § 1005(b), the defendant must be served with a copy
of the summons and complaint, notice of application and hearing, and a copy of
the application and supporting affidavits. (CCP § 484.040.)
“The Attachment Law statutes are subject to strict
construction….” (Epstein v. Abrams (1997) 57 Cal.App.4th 1159, 1168.)
III. Analysis
A.
Evidentiary
Matters
All evidentiary objections are
OVERRULED.
B.
Basis
of Attachment
“[A]n
attachment may be issued only in an action on a claim or claims for money, each
of which is based upon a contract, express or implied, where the total amount
of the claim or claims is a fixed or readily ascertainable amount not less than
five hundred dollars ($500) exclusive of costs, interest, and attorney's
fees.” (CCP § 483.010(a).) “An attachment may not be issued on a claim
which is secured by any interest in real property arising from agreement
….” (CCP § 483.010(b).)
Skanska
presents Change Order No. 3, which states:
This
Subcontractor Change Order (SCO) is an Advance on Subcontractor’s issues with
processing changes with the Owner. Subcontractor has asserted it was delayed
and/or impacted due to rejected and lack of negotiated changes in good faith by
the Owner. While the claim with the Owner is pending, Skanska has opted to
advance this SCO to Subcontractor with full reservation of rights.
(Childress Decl. ¶ 8 & Ex. A at 1.) Change
Order No. 3 provides for MIK to provide all labor, material, and equipment on
the portions of the Project specified therein. Change Order No. 3 also provides
explicitly:
Subcontractor
agrees upon written demand by Contractor to remit any and all SCO Advances to
Contractor within 10 calendar days of receipt of such demand.
(Childress Decl. ¶ 8 & Ex. A at 1.)
Change Order No. 3 was executed by Skanska as Contractor and MIK as
Subcontractor.
MIK
objects to Skanska’s presentation of Change Order No. 3 as inadmissible
hearsay. However, MIK presents the same change order in support of its
opposition. (Kim Decl. ¶ 14 & Ex. 4.) MIK does not deny the existence of
the change order.
Pursuant
to Change Order No. 3, Skanska paid $723,810.85 as
an advance on the labor, material, and equipment for the work described in the
change order. (Childress Decl. ¶¶ 8, 9.) MIK does not deny that Skanska paid $723,810.85.
(Opp. at 8:14-17.) Skanska has demanded repayment of $723,810.85 pursuant to
the change order. (Childress Decl. ¶ 13 & Ex. D; Kim Decl. ¶ 24.) The amount
to be secured is readily ascertainable.
Based
on the foregoing, the Court finds that Skanska’s claim for payment of the
amount due under Change Order No. 3 is one upon which attachment may be issued.
C.
Probable
Validity of Plaintiff’s Claims
“A claim has ‘probable validity’ where it is more
likely than not that the plaintiff will obtain a judgment against the defendant
on that claim.” (CCP § 481.190.) “If the defendant opposes the
application, ‘the court must then consider the relative merits of the positions
of the respective parties and make a determination of the probable outcome of
the litigation.’ [Citations.]” (Pech v. Morgan (2021) 61 Cal.App.5th
841, 855.)
Based
on the discussion above, Skanska demonstrates probable validity of its claims. Pursuant
to Change Order No. 3, Skanska and MIK agreed that Skanska would advance money
to MIK and that MIK would repay the money within 10 days of demand by Skanska.
MIK
argues that Skanska has not demonstrated probable validity for several reasons.
Each reason is without merit, as discussed below.
MIK
asserts that Skanska directed it to procure the materials for the work described
in the change order and submitted a claim to the owner for the same work. MIK
also argues that the terms of Skanska’s subcontract with it transferred title
to the work to Skanska at the time of Skanska’s payment. MIK’s arguments ignore
the terms of the change order, a written contract executed by both Skanska and
MIK. MIK agreed to pay Skanska for any advances made on the change order within
10 days of demand. Skanska made the required demand. There are no other
conditions for repayment set forth in Change Order No. 3.
Kim
avers that Childress disclaimed any right to repayment on the materials. (Kim
Decl. ¶ 21.) Not only does Childress deny having disclaimed any refund (Supp.
Childress Decl. ¶¶ 3, 4), Kim’s averment strains credulity. There is no
explanation proffered as to why Childress or Skanska would not enforce its
rights to repayment.
MIK
also argues that Change Order No. 3 violates public policy because it seeks to
waive MIK’s mechanics lien rights. (See Civ. Code § 8122 [“An owner,
direct contractor, or subcontractor may not, by contract or otherwise, waive,
affect, or impair any other claimant’s rights under this part, whether with or
without notice, and any term of a contract that purports to do so is void and
unenforceable unless and until the claimant executes and delivers a waiver and
release under this article”].) The change order does not seek to prevent MIK
from obtaining payment for its work on the Project. MIK has recorded a lien of “$381,374.45
against the property for the Project for amounts due under its Subcontract and
for change orders and extra work that Skanska directed MIK to perform.” (Kim
Decl. ¶ 25.) Any repayment of funds advanced under Change Order No. 3 can be
added to the lien.
MIK
also contends that Change Order No. 3 is unenforceable as a pay-if-paid clause.
“A pay if paid provision makes payment by the owner to the general contractor a
condition precedent to the general contractor’s obligation to pay the
subcontractor for work the subcontractor has performed.” (Wm. R. Clarke
Corp. v. Safeco Ins. Co. (1997) 15 Cal.4th 882, 885.) The California
Supreme Court ruled pay-if-paid clauses unenforceable because “they effect an
impermissible indirect waiver or forfeiture of the subcontractors’
constitutionally protected mechanic's lien rights in the event of nonpayment by
the owner.” (Id. at 886.) Nothing in Change Order No. 3 states that Skanska
will pay MIK only if the Project owner pays Skanska. To the contrary, Skanska advanced funds to
MIK pursuant to Change Order No. 3. Skansak
now seeks the return of the advanced funds pursuant to the explicit terms of
Change Order No. 3. The prohibition
against pay-if-paid clauses has no bearing on Change Order No. 3.
Based on the
foregoing, MIK has not defeated the probable validity of Skanska’s claim
against it.
D.
Purpose
and Amount of Attachment
The
other required findings under CCP § 484.090 are that the “attachment is not
sought for a purpose other than the recovery on the claim upon which the
attachment is based” and that the “amount to be secured by the attachment is
greater than zero.” (CCP § 484.090(a)(3), (a)(4).)
Skanska
declares that attachment is not sought for a purpose other than the recovery on
its claim. (See App. ¶ 4.) MIK argues that Skanska’s application for
right to attach order is sought to harass MIK to dismiss or settle its
Cross-Complaint. There is no evidence for this assertion. Skanska is entitled
to enforce its rights under The Attachment Law, CCP § 482.010, et seq.
Further,
the amount requested by Skanska to be secured is greater than zero.
However, CCP § 483.015(b)(2) provides
that the amount to be secured by an attachment “shall be reduced by…[t]he
amount of any indebtedness of the plaintiff that the defendant has claimed in a
cross-complaint filed in the action if the defendant’s claim is one upon which
an attachment could be issued.” (CCP § 483.015(b)(2).) MIK has filed a
First Amended Cross-Complaint seeking at least $400,000 from Skanska for work
it performed under the subcontract between them. (FAXC ¶¶ 13, 16, 17.) MIK’s
claim for its work is a readily ascertainable amount that is $500 or more. In
its reply, Skanska has not explained how CCP § 483.015(b)(2) is inapplicable. Accordingly,
the amount of attachment is reduced by $400,000 to $323,810.85.
E.
Property
Subject to Attachment
CCP
§ 487.010(a) states that, where the defendant is a corporation, all corporate
property for which a method of levy is provided in CCP § 488.300, et seq.
is subject to attachment. Skanska moves to attach any property of MIK.
F.
Exemptions
MIK
has not filed a claim of exemption.
G.
Undertaking
CCP
§ 489.210 requires the plaintiff to file an undertaking before issuance of a
writ of attachment. CCP § 489.220 provides, with exceptions, for an undertaking
in the amount of $10,000. Neither party addresses the proper amount of an
undertaking. In the absence of any argument by either party, the Court orders
an undertaking in the amount of $10,000.
IV. Conclusion
The
application is GRANTED IN PART. Plaintiff
Skanska USA
Building Inc. is entitled to the issuance of a writ of attachment in the amount
of $323,810.85, subject to plaintiff
first posting an undertaking in the amount of $10,000.
The
Court will with the proposed Right to Attach Order and Order for Issuance of
Writ of Attachment After Hearing (Judicial Council Form AT-120), electronically
received December 13, 2023.
|
Date: February
15, 2024 |
|
|
|
HON.
CURTIS A. KIN |