Judge: Daniel S. Murphy, Case: 20STCV49781, Date: 2023-08-04 Tentative Ruling
Case Number: 20STCV49781 Hearing Date: August 4, 2023 Dept: 32
|
HARRIDGE DEVELOPMENT GROUP, LLC, et al., Plaintiffs, v. VARDE PARTNERS, INC.,
et al., Defendants.
|
Case No.: 20STCV49781 Hearing Date: August 4, 2023 [TENTATIVE]
order RE: defendants’ motion for summary judgment |
|
|
|
BACKGROUND
This action was initially filed on December
30, 2020. The operative First Amended Complaint was filed on March 1, 2023. The
FAC is brought by Plaintiffs Harridge Development Group, LLC, Met East Holdco,
LLC, Inglewood Partners, LLC, and 3240 Wilshire Associates, LLC (collectively,
Harridge) against Defendants Varde Partners, Inc., Mountain Real Estate
Capital, LLC, VP Met LLC, VP Inglewood, LLC, VP Wilshire, LLC, and MRECV Blake
Street, LLC (collectively, Varde and MREC).
Harridge is a real estate
development company who partnered with investors Varde and MREC on numerous
projects. Some of the projects sold at a profit and others sold at a loss. As a
safety net for Varde and MREC to recoup their investments in the event of a
loss, the parties agreed to reserve a portion of proceeds from the projects to pay
for Varde and MREC’s capital contributions and minimum preferred returns. These
funds are referred to by the parties as the “Withheld Promote” or “Designated
Reserve.” This lawsuit involves two disputes, both concerning funds which Varde
and MREC seek to withhold to cover project losses but which Harridge claims it
is entitled to as profits. Harridge alleges that Varde and MREC have improperly
withheld Harridge’s rightful profits. Accordingly, the FAC asserts causes of
action for breach of contract, bad faith, conversion, declaratory relief,
unjust enrichment, and money had and received.
The first dispute concerns $3.4 million
of Designated Reserve funds that Varde argues must be used to recoup losses
from the Blake Street Project. Harridge claims that the parties agreed to
transfer the funds from the Blake Street Project to the Met Project such that
the funds only secured the Met Project and no other project. According to
Harridge, the parties agreed that once Varde recouped its losses from the Met
Project, the remainder would go to Harridge. Since the Met Project sold at a
profit and Varde did not need to tap into the reserve, Harridge claims it is
entitled to the entire $3.4 million.
The second dispute concerns $730,000
of Withheld Promote funds from the profitable Inglewood Project which Varde seeks
to use to cover losses from the Koreatown Project. It is undisputed that a
portion of Inglewood profits were cross-collateralized to cover Koreatown
losses. However, Harridge contends that Varde is not entitled to the funds
because it was Varde’s own bad faith actions that caused the Koreatown Project to
sell at a loss.
On June 2, 2023, Varde filed the
instant motion for summary judgment. MREC stipulated to cease defending the
action in its own name and agreed to abide by any judgment entered in the
action. (See May 26, 2023 Stipulation.) Harridge filed its opposition on July
12, 2023. Varde replied on July 26, 2023.
LEGAL STANDARD
The
function of a motion for summary judgment or adjudication is to allow a determination
as to whether an opposing party cannot show evidentiary support for a pleading
or claim and to enable an order of summary dismissal without the need for trial.
(Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843.) Code of
Civil Procedure section 437c, subdivision (c) “requires the trial judge to
grant summary judgment if all the evidence submitted, and ‘all inferences reasonably
deducible from the evidence’ and uncontradicted by other inferences or
evidence, show that there is no triable issue as to any material fact and that the
moving party is entitled to judgment as a matter of law.” (Adler v. Manor
Healthcare Corp. (1992) 7 Cal.App.4th 1110, 1119.) “The function of the
pleadings in a motion for summary judgment is to delimit the scope of the
issues; the function of the affidavits or declarations is to disclose whether
there is any triable issue of fact within the issues delimited by the pleadings.”
(Juge v. County of Sacramento (1993) 12 Cal.App.4th 59, 67, citing FPI
Development, Inc. v. Nakashima (1991) 231 Cal. App. 3d 367, 381-382.)
As to each claim as framed by the
complaint, the defendant moving for summary judgment must satisfy the initial burden
of proof by presenting facts to negate an essential element, or to establish a
defense. (Code Civ. Proc., § 437c, subd. (p)(2); Scalf v. D. B. Log Homes,
Inc. (2005) 128 Cal.App.4th 1510, 1520.) Once the defendant has met that burden,
the burden shifts to the plaintiff to show that a triable issue of one or more
material facts exists as to that cause of action or a defense thereto. To establish
a triable issue of material fact, the party opposing the motion must produce substantial
responsive evidence. (Sangster v. Paetkau (1998) 68 Cal.App.4th 151,
166.) Courts “liberally construe the evidence in support of the party opposing
summary judgment and resolve doubts concerning the evidence in favor of that
party.” (Dore v. Arnold Worldwide, Inc. (2006) 39 Cal.4th 384, 389.)
DISCUSSION
I.
Choice of Law
Each Operating Agreement associated
with the pertinent projects contains a choice of law provision selecting Delaware
law to govern disputes. (Defendant’s Statement of Facts (UF) 13.) Courts favor
freedom of contract and therefore apply a “strong policy favoring enforcement
of [choice of law] provisions.” (Nedlloyd Lines B.V. v. Superior Court
(1992) 3 Cal.4th 459, 465.) A choice of law provision will be enforced “unless
either (a) the chosen state has no substantial relationship to the parties or
the transaction and there is no other reasonable basis for the parties choice,
or (b) application of the law of the chosen state would be contrary to a
fundamental policy of a state which has a materially greater interest than the
chosen state in the determination of the particular issue.” (Ibid.)
All of the parties involved in this
action are Delaware companies. This demonstrates a sufficient connection to
Delaware. “A party's incorporation in a state is a contact sufficient to allow
the parties to choose that state's law to govern their contract.” (Nedlloyd,
supra, 3 Cal.4th at p. 467.) Moreover, Harridge has “identified no
fundamental policy of our state at issue in its essentially contractual dispute
with” Varde. (See id. at p. 468.) Therefore, there is no fundamental
policy in conflict and no reason why California has a greater interest in this
dispute. Therefore, the analysis will proceed under Delaware law in accordance
with the parties’ choice of law provision.
II.
Dispute 1 (Blake Street Project/Met Project)
It is undisputed that $3.4 million of
Promote Proceeds were withheld from the Silver Lake, Pinecrest, and Tramonto Projects
in order to secure the Blake Street Project. (UF 19.) This is the Designated
Reserve at issue. (UF 20.) Varde contends that the funds were properly
calculated and withheld under the applicable Operating Agreements. (UF 22-23.)
Harridge contends that the funds were initially properly withheld, until the
Designated Reserve was transferred from the Blake Street Project to the Met
Project in March 2018. (Plntf.’s Resp. to UF 22-23.) In other words, but for
the purported transfer in March 2018, the funds would be properly withheld
under the Operating Agreements. Therefore, the issue is whether such a transfer
occurred.
To that end, Harridge relies on phone
calls and a Term Sheet between the parties, which purportedly demonstrate the
parties’ intent to transfer the $3.4 million security from the Blake Street Project
to the Met Project. (Plntf.’s Additional Facts (AF) 76, 82, 84, 88.) Varde’s managing
director, Brendan Bosman, supposedly told Harridge’s CEO, David Schwartzman,
that Varde needed more cross-collateralization for the Met Project and proposed
that the Withheld Promote securing the Blake Street Project be transferred to
the Met Project. (AF 76.) Furthermore, the parties executed a Term Sheet providing
that “Harridge has agreed to provide certain promote reserves . . . amounting
to approximately $3.4mm, as additional security for the return of Värde
Member’s capital contributions and Preferred Return on the [Met] Project.” (UF
29.) The Term Sheet further provides that if the Met Project results in a loss,
“the Reserves will be distributed first to Värde until it has achieved such
Preferred Return and return of capital, with any remainder then being
distributed to Harridge.” (Ibid.)
However, the Term Sheet served merely as a
letter of intent that was by its own terms nonbinding. (UF 32.) Harridge
acknowledges that the Term Sheet is nonbinding and confirms that it is not
suing on the Term Sheet. (UF 33; Opp. at p. 12, fn. 7.) In any case, the Term Sheet
does not state that the reserve funds from the Blake Street Project would be
transferred to the Met Project. Furthermore, the Operating Agreements for the
pertinent projects contain integration clauses and prohibit modifications
without written consent. (UF 17.) In other words, neither the oral
conversations between Bosman and Schwartzman, nor the nonbinding Term Sheet, could
modify any of the Operating Agreements. (See Kanno v. Marwit Capital
Partners II, L.P. (2017) 18 Cal.App.5th 987, 1002.) And Harridge does not
contend that either the oral conversations or the Term Sheet are themselves
contracts. Therefore, the Operating Agreements are the only contracts that Varde
could have breached.
A plaintiff alleging breach of contract
must prove (1) the existence of a contractual obligation, (2) breach of that
obligation, and (3) damages resulting from the breach. (VLIW Tech., LLC v.
Hewlett-Packard Co. (Del. 2003) 840 A.2d 606, 612.) Here, none of the
Operating Agreements contains a term providing for the transfer of reserve
funds from the Blake Street Project to the Met Project. In fact, the Operating
Agreements indisputably provide, to this day, that the Designated Reserve funds
are available to secure Varde and MREC’s return of capital contributions and preferred
returns on the Blake Street Project. (UF 23.) Even if the parties initially
intended to modify the Operating Agreements to effectuate the transfer that
Harridge advocates for, it is undisputed that they ultimately did not amend the
Operating Agreements to that effect. Therefore, Varde and MREC did not breach
any contract term by withholding the $3.4 million to cover their Blake Street
losses.
“The implied
covenant of good faith and fair dealing inheres in every contract and requires
‘a party in a contractual relationship to refrain from arbitrary or unreasonable
conduct which has the effect of preventing the other party to the contract from
receiving the fruits’ of the bargain.” (Kuroda v. SPJS Holdings, L.L.C. (Del.Ch.
2009) 971 A.2d 872, 888.) Varde
and MREC also could not have acted in bad faith. The Blake Street Project sold
at a loss through no fault of either party (FAC ¶ 19), and Varde/MREC merely withheld
funds that they were contractually entitled to under such circumstances. (See
Glaxo
Grp. Ltd. v. Drit LP
(Del. 2021) 248 A.3d 911, 920 [“One generally cannot base a claim for breach of
the implied covenant on conduct authorized by the terms of the agreement”].) Therefore,
Varde and MREC cannot be liable under the first and second causes of action as
a matter of law.
III.
Dispute 2 (Inglewood Project/Koreatown Project)
As with above, it is undisputed that
the pertinent Operating Agreements provided for the cross-collateralization of
project proceeds to cover shortfalls. (UF 46-47.) Specifically, the Inglewood
Withheld Promote was contractually dedicated to making up the Koreatown
shortfall. (UF 67.) Varde exited the Koreatown Project, as it was entitled to
under the Operating Agreement. (UF 51-52.) Harridge wished to remain as the
developer on the Koreatown Project and assisted in the efforts to find a buyer
for Varde’s interest. (UF 54.)
In March 2020, as a deal was approaching
to sell Varde’s interest, Harridge requested additional capital from Varde to
fund debt service for Koreatown. (UF 59, 63.) Varde declined to provide
additional capital, purportedly because it was about to exit the project. (UF
60.) However, Harridge and Varde entered into a Letter Agreement, whereby
Harridge and its new capital partner would service the debt, but Harridge would
be reimbursed for the payments. (UF 61.) There was no default on the debt, and Varde
reimbursed Harridge for the debt payments. (UF 62.)
The Koreatown Project was sold in July
2020. (UF 58.) The sale resulted in a deficiency that did not provide Varde
with its full preferred return. (UF 65-66.) The Inglewood Project was sold at a
profit, and Varde withheld approximately $730,000 to cover the Koreatown
shortfall. (UF 68.) This is the Withheld Promote that is the subject of this second
dispute.
While Harridge does not dispute that the
pertinent Operating Agreements cross-collateralized the Inglewood proceeds to
cover Koreatown, Harridge argues that Varde cannot create the conditions that
cause the shortfall and then force Harridge to pay for its mistake. Specifically,
Harridge contends that Varde forced a distressed sale of Koreatown by exiting
when it lacked capital to continue the investment and making Harridge find a buyer
as quickly as possible, which resulted in a purchase price that was lower than
what would otherwise have been obtained. (FAC ¶¶ 24-25; Plntf.’s Resp. to UF
51.) In essence, Harridge argues that Varde breached the implied covenant of
good faith and fair dealing.
“The implied
covenant [of good faith and fair dealing] seeks to enforce the parties' contractual
bargain by implying only those terms that the parties would have agreed to during
their original negotiations if they had thought to address them.” (Gerber v.
Enter. Prods. Holdings, LLC (Del. 2013) 67 A.3d 400, 418.) “Express contractual
provisions always supersede the implied covenant, but even the most carefully
drafted agreement will harbor residual nooks and crannies for the implied
covenant to fill.” (Id. at p. 419.) While parties are expected to
exercise contractually-granted discretion in good faith, the implied covenant “should
not be used to imply terms that modify or negate an unrestricted contractual
right authorized by an agreement.” (Glaxo, supra, 248 A.3d at p. 920.)
Here,
it is undisputed that the Koreatown Operating Agreement gave Varde the “absolute
and unconditional right to sell or require the sale of the project at any time.”
(UF 52.) Because the contract gave Varde an unrestricted contractual right to
withdraw from Koreatown, that right cannot be altered by the implied covenant.
(See Glaxo,
supra, 248
A.3d at p. 920.) To imply a term into the contract whereby Varde cannot recoup
its losses from Koreatown if its withdrawal causes a shortfall would contradict
the express terms of the contract by restricting Varde’s right to withdraw. In
sum, Varde did not breach the implied covenant of good faith and fair dealing because
there can be no implied term restricting its right to withdraw from Koreatown.
Varde also did not breach any
express contract term because the right to unilaterally withdraw, and to
withhold the Inglewood Promote to cover shortfalls, is indisputably expressly
allowed by the Operating Agreements. Therefore, both the fifth and sixth causes
of action fail.
IV. Declaratory
Relief
Four
elements are required to consider a controversy suitable for declaratory judgment:
(1) the controversy must involve a claim of right or other legal interest of
the party seeking declaratory relief; (2) the claim of right or other legal
interest must be asserted against one who has an interest in contesting the
claim; (3) the conflicting interests must be real and adverse; and (4) the
issue must be ripe for judicial determination. (Weiner v. Selective Way Ins.
Co. (Del. Super. Ct. 2002) 793 A.2d 434, 439.)
Varde
argues that there is no actual controversy regarding the parties’ rights and
duties with respect to the Designated Reserve and Withheld Promote. As
demonstrated above, Varde/MREC properly withheld the funds as a matter of law
as their contractual right. Accordingly, the fourth and eighth causes of action
fail.
V. Conversion,
Unjust Enrichment, Money Had and Received
“Conversion
is an act of dominion wrongfully exerted over the property of another, in
denial of his right, or inconsistent with it.” (Arnold v. Society for Sav.
Bancorp, Inc. (Del. 1996) 678 A.2d 533, 536.) Unjust enrichment occurs when
a defendant receives a benefit and unjustly retains the benefit to the loss of
another. (Kuroda,
supra, 971
A.2d at p. 891.) “Whenever one person
has in his hands money equitably belonging to another, that other person may
recover it by assumpsit for money had and received.” (Mass. Mut. Life Ins.
Co. v. Certain Underwriters at Lloyd's of London (Ch. Sep. 24, 2010, No.
4791-VCL) 2010 Del. Ch. LEXIS 198, at *12.)
It
is undisputed that the Designated Reserve has been maintained in a segregated
account at Harridge’s request and that the Withheld Promote continues to be
held in the Inglewood joint venture entity. (UF 72-73.) This prevents wrongful
distribution of the money while the dispute is pending. Therefore, Defendants
have not wrongfully taken any money for purposes of conversion, unjust
enrichment, and money had and received. Additionally, as discussed above, Varde
and MREC properly withheld the funds under the applicable contracts. The third,
seventh, ninth, and tenth causes of action fail as a matter of law.
CONCLUSION
Defendants’
motion for summary judgment is GRANTED.