Judge: Daniel S. Murphy, Case: 22STCV14536, Date: 2023-08-18 Tentative Ruling
Case Number: 22STCV14536 Hearing Date: August 18, 2023 Dept: 32
|
AZAD STEEL, INC., Plaintiff, v. RENAISSANCE CONSTRUCTION GROUP, et al., Defendants.
|
Case No.: 22STCV14536 Hearing Date: August 18, 2023 [TENTATIVE]
order RE: defendants’ motion for summary judgment
or adjudication |
|
|
|
BACKGROUND
On May 2, 2022, Plaintiff Azad
Steel, Inc. (Plaintiff) filed this action against Defendants Renaissance Construction
Group (RCG) and Youssef Mikhail (Mikhail), asserting causes of action for (1)
breach of contract, (2) quantum meruit, (3) account stated, and (4) open book
account.
Plaintiff was the subcontractor on a
construction project in which RCG was the primary contractor. Plaintiff and RCG
entered into a written agreement whereby Plaintiff would complete a portion of
the project relating to the fabrication and installation of structural steel.
RCG also allegedly ordered additional work from Plaintiff and promised to pay
for it. Mikhail is allegedly RCG’s alter ego. Plaintiff filed this action to
recover unpaid compensation.
On June 2, 2023, Defendants filed
the instant motion for summary judgment or adjudication in the alternative.
Plaintiff filed its opposition on August 4, 2023. Defendants replied on August
11, 2023
LEGAL STANDARD
The function of a motion for summary
judgment or adjudication is to allow a determination as to whether an opposing
party cannot show evidentiary support for a pleading or claim and to enable an
order of summary dismissal without the need for trial. (Aguilar v. Atlantic
Richfield Co. (2001) 25 Cal.4th 826, 843.) Code of Civil Procedure section
437c, subdivision (c) “requires the trial judge to grant summary judgment if
all the evidence submitted, and ‘all inferences reasonably deducible from the evidence’
and uncontradicted by other inferences or evidence, show that there is no
triable issue as to any material fact and that the moving party is entitled to judgment
as a matter of law.” (Adler v. Manor Healthcare Corp. (1992) 7 Cal.App.4th
1110, 1119.) “The function of the pleadings in a motion for summary judgment is
to delimit the scope of the issues; the function of the affidavits or declarations
is to disclose whether there is any triable issue of fact within the issues
delimited by the pleadings.” (Juge v. County of Sacramento (1993) 12 Cal.App.4th
59, 67, citing FPI Development, Inc. v. Nakashima (1991) 231 Cal. App.
3d 367, 381-382.)
As to each claim as framed by the
complaint, the defendant moving for summary judgment must satisfy the initial burden
of proof by presenting facts to negate an essential element, or to establish a
defense. (Code Civ. Proc., § 437c, subd. (p)(2); Scalf v. D. B. Log Homes,
Inc. (2005) 128 Cal.App.4th 1510, 1520.) Once the defendant has met that burden,
the burden shifts to the plaintiff to show that a triable issue of one or more
material facts exists as to that cause of action or a defense thereto. To establish
a triable issue of material fact, the party opposing the motion must produce substantial
responsive evidence. (Sangster v. Paetkau (1998) 68 Cal.App.4th 151,
166.) Courts “liberally construe the evidence in support of the party opposing
summary judgment and resolve doubts concerning the evidence in favor of that
party.” (Dore v. Arnold Worldwide, Inc. (2006) 39 Cal.4th 384, 389.)
DISCUSSION
I.
Attorneys’ Fees
“Except as attorney’s fees are
specifically provided for by statute, the measure and mode of compensation of
attorneys and counselors at law is left to the agreement, express or implied,
of the parties . . . .” (Code Civ. Proc., § 1021.) Thus, a plaintiff must set
forth a statutory or contractual basis for attorney’s fees in order to recover such
fees.
It is undisputed that the contract
between the parties does not contain an attorneys’ fees provision. (Def.’s
Stmnt. of Undisputed Facts (UF) 4.) However, Plaintiff seeks attorneys’ fees on
a statutory basis, specifically the prompt payment statute embodied in Business
and Professions Code section 7108.5.
Section 7108.5 provides: “A prime
contractor or subcontractor shall pay to any subcontractor, not later than
seven days after receipt of each progress payment, unless otherwise agreed to
in writing, the respective amounts allowed the contractor on account of the
work performed by the subcontractors, to the extent of each subcontractor’s
interest therein.” (Bus. & Prof. Code, § 7108.5(a).) “Any violation of this
section shall constitute a cause for disciplinary action and shall subject the
licensee to a penalty, payable to the subcontractor, of 2 percent of the amount
due per month for every month that payment is not made.” (Id., subd. (b).)
“In any action for the collection of funds wrongfully withheld, the prevailing
party shall be entitled to his or her attorney’s fees and costs.” (Id.,
subd. (c).)
Defendants argue that this section
does not apply because it only applies to progress payments, and Plaintiff has
no evidence that Defendants received progress payments. Defendants also argue
that Plaintiff is not claiming a progress payment as damages but is instead
seeking a lump sum owed under the contract, or a final payment. (See Murray’s
Iron Works, Inc. v. Boyce (2008) 158 Cal.App.4th 1279, 1299.) Defendants
point to the allegations that “Plaintiff has performed each and every
obligation on its part to be performed under the Contract except those
obligations excused by the action or inaction of RENAISSANCE” and that
Plaintiff seeks “the balance due under the Contract.” (Compl. ¶¶ 14, 16.)
As discussed in the Court’s order denying
Defendants’ motion to strike attorneys’ fees, those allegations are not
dispositive on whether Plaintiff seeks progress payments or one final payment.
(Nov. 7, 2022 Order re Mtn. to Strike 3:23-4:10.) The Court held that this is a
factual dispute to be resolved through evidence. (Id. at 4:11-12.)
Defendants do not present any
evidence to satisfy their initial burden on summary judgment. Instead,
Defendants attempt to prematurely shift the burden to Plaintiff, arguing that “at
no point has Plaintiff shown that the owner of the Property ever paid Defendants
a progress payment which included payment for work performed by the Plaintiff,
triggering a duty to pay Plaintiff.” (Mtn. 3:23-25.) Plaintiff is not required
to make any showing until Defendants do so first. (See Consumer Cause, Inc.
v. Smilecare (2001) 91 Cal.App.4th 454, 468-69.) Defendants have no
evidence that RCG was not paid any progress payments by the owner,
thereby leaving open a triable issue. Defendants claim that the declaration of
Mikhail shows RCG never received a progress payment from the owner. Mikhail’s
declaration shows no such thing.
Mikhail’s declaration only avers
that the contract did not provide for RCG to receive progress payments from the
owner. (UF 2.) However, as Defendants acknowledge, Section 7108.5 is “not triggered
by whether the general contractor ‘should have’ received a payment from
the owner. Rather, they begin to run upon the general contractor actually
receiving a progress payment.” (Mtn. 3:25-28, quoting Tesco Controls,
Inc. v. Monterey Mech. Co. (2004) 124 Cal.App.4th 780, 803-04.) Whether the
contract required progress payments only addresses whether RCG “should have”
received a progress payment. But the statute depends on whether RCG “actually
received” a progress payment. The fact that the contract did not require
progress payments does not mean it prohibited progress payments. The contract
does not preclude the possibility that the owner paid RCG progress payments. Defendants
have not presented evidence that RCG never received progress payments. Therefore,
Defendants have not satisfied their initial burden on summary judgment.
II.
Payment to Plaintiff
Defendants argue that “[t]he undisputed
facts show that Plaintiff was paid for all services it performed on the
Project.” (Mtn. 5:3-4.) For support, Defendants rely on Mikhail’s declaration,
averring that “[a]fter terminating Plaintiff, I fully paid Plaintiff for all
the work it performed on the Project. There is no outstanding balance due
Plaintiff for work or services it completed on the Project.” (Mikhail Decl. ¶
5.) However, Plaintiff avers that it is owed $81,489.50 for unpaid fabrication
and installation, plus $8,800 for shop drawings. (Ghadimian Decl. ¶ 22, Ex. G.)
Additionally, Mikhail himself admitted in a text message that Plaintiff was
owed $95,000. (Id., Ex. A.) This conflicting evidence raises a triable
issue and precludes summary judgment.
Defendants argue that Plaintiff’s supporting
documentation is insufficient to justify Plaintiff’s calculation of the amount
owed. Defendants also argue that it is unclear what the text about $95,000 was
referring to. However, this goes to the weight of the evidence, which is a
matter for the jury.
III.
Mikhail as a Defendant
Lastly, Defendants argue that “Mikhail
should be dismissed from this action. The Subcontract was between two parties: Plaintiff
and Defendant Renaissance.” (Mtn. 5:14-15.) Defendants again place the burden
on Plaintiff instead of satisfying their own initial burden. Defendants cite no
evidence supporting their contention that the subcontract was only between
Plaintiff and RCG. Additionally, Plaintiff alleges that Mikhail is the alter
ego of RCG. (Compl. ¶ 8.) Defendants cite no evidence precluding an alter ego
theory against Mikhail. Therefore, there is a triable issue over whether Mikhail
is liable to Plaintiff.
Defendants argue that the alter ego theory
was not properly pleaded in the first place, claiming that Plaintiff merely
alleges in conclusory fashion that RCG is a mere shell. However, the complaint
alleges more than that, including that Mikhail used RCG assets for personal
use, transferred RCG funds to himself without adequate consideration, solely
controls RCG without any director or shareholder meetings, did not maintain records
of corporate meetings, and entered into transactions with RCG without director
or shareholder approval. (Compl. ¶ 8.) These facts are sufficient to infer
alter ego liability. On summary judgment, it is Defendants’ burden to negate
the allegations with evidence, which Defendants have not done.
CONCLUSION
Defendants’ motion for summary
judgment or adjudication is DENIED. Plaintiff’s request for a continuance under
Code of Civil Procedure section 437c(h) is denied as moot because the motion
fails on the merits based on existing evidence.