Judge: Daniel S. Murphy, Case: 23STCV06015, Date: 2025-03-14 Tentative Ruling
Case Number: 23STCV06015 Hearing Date: March 14, 2025 Dept: 32
|
ACCUCON CORPORATION, Plaintiff, v.
P.T. ENTERPRISES, LLC,
et al., Defendants.
|
Case No.: 23STCV06015 Hearing Date: March 14, 2025 [TENTATIVE]
order RE: defendant p.t. enterprises, llc’s motion
for summary judgment |
|
|
|
BACKGROUND
On March 17, 2023, Plaintiff Accucon
Corporation filed this action against Defendants P.T. Enterprises, LLC and
Autobuilders General Contracting Services, Inc., asserting causes of action for
(1) breach of contract, (2) good sold and delivered, (3) open book account, (4)
account stated, (5) foreclosure of mechanics lien, and (6) recovery of
statutory penalties. Plaintiff filed the operative First Amended Complaint on
June 29, 2023.
Defendant Autobuilders was the
contractor on a certain project owned by Defendant P.T. Enterprises. Plaintiff
contracted with Autobuilders to be the subcontractor on the project. This
lawsuit arises from an alleged unpaid balance of over $500,000 owed to
Plaintiff.
On October 10, 2024, Defendant P.T.
Enterprises filed the instant motion for summary judgment. Plaintiff filed its
opposition on February 14, 2025. Defendant filed its reply on February 24,
2025.
LEGAL STANDARD
The function of a motion for summary
judgment or adjudication is to allow a determination as to whether an opposing
party cannot show evidentiary support for a pleading or claim and to enable an
order of summary dismissal without the need for trial. (Aguilar v. Atlantic
Richfield Co. (2001) 25 Cal.4th 826, 843.) Code of Civil Procedure section
437c, subdivision (c) “requires the trial judge to grant summary judgment if
all the evidence submitted, and ‘all inferences reasonably deducible from the
evidence’ and uncontradicted by other inferences or evidence, show that there
is no triable issue as to any material fact and that the moving party is
entitled to judgment as a matter of law.” (Adler v. Manor Healthcare Corp.
(1992) 7 Cal.App.4th 1110, 1119.) “The function of the pleadings in a motion
for summary judgment is to delimit the scope of the issues; the function of the
affidavits or declarations is to disclose whether there is any triable issue of
fact within the issues delimited by the pleadings.” (Juge v. County of
Sacramento (1993) 12 Cal.App.4th 59, 67, citing FPI Development, Inc. v.
Nakashima (1991) 231 Cal. App. 3d 367, 381-382.)
As to each claim as framed by the
complaint, the defendant moving for summary judgment must satisfy the initial
burden of proof by presenting facts to negate an essential element, or to
establish a defense. (Code Civ. Proc., § 437c, subd. (p)(2); Scalf v. D. B.
Log Homes, Inc. (2005) 128 Cal.App.4th 1510, 1520.) Once the defendant has
met that burden, the burden shifts to the plaintiff to show that a triable
issue of one or more material facts exists as to that cause of action or a
defense thereto. To establish a triable issue of material fact, the party
opposing the motion must produce substantial responsive evidence. (Sangster
v. Paetkau (1998) 68 Cal.App.4th 151, 166.) Courts “liberally construe the
evidence in support of the party opposing summary judgment and resolve doubts
concerning the evidence in favor of that party.” (Dore v. Arnold Worldwide,
Inc. (2006) 39 Cal.4th 384, 389.)
REQUEST FOR
JUDICIAL NOTICE
Defendant’s request for judicial
notice of Exhibits 1-4 is granted.
EVIDENTIARY
OBJECTIONS
Plaintiff’s
Objections
Defendant’s
Objections
DISCUSSION
I.
Statutory Framework
Defendant P.T. Enterprises moves for
summary judgment on the sole cause of action asserted against it—the fifth
cause of action for foreclosure of mechanics lien. Specifically, Defendant
argues that Plaintiff failed to timely record the mechanics lien.
The governing statute provides as follows:
“A claimant other
than a direct contractor may not enforce a lien unless the claimant records a
claim of lien within the following times:
(a) After the
claimant ceases to provide work.
(b) Before
the earlier of the following times:
(1) Ninety
days after completion of the work of improvement.
(2) Thirty
days after the owner records a notice of completion or cessation.”
(Civ.
Code, § 8414.)
“Completion of a work of improvement” is
defined as any one of the following:
(1) Actual
completion of the work of improvement.
(2) Occupation or
use by the owner accompanied by cessation of labor.
(3) Cessation of
labor for a continuous period of 60 days.
(4) Recordation of
a notice of cessation after cessation of labor for a continuous period of 30
days.
(Civ.
Code, § 8180(a).)
Alternatively, “[n]otwithstanding
subdivision (a), if a work of improvement is subject to acceptance by a public
entity, completion occurs on acceptance.” (Civ. Code, § 8180(b).)
II.
Acceptance by a Public Entity
Here, the City of Industry executed a
Certificate of Completion, recorded on February 7, 2022, attesting that “the
construction of the Improvements on the Project Site has been satisfactorily
performed and completed.” (Def.’s RJN, Ex. 1.) By its own terms, the
Certificate of Completion is “a conclusive determination of satisfactory
completion of the construction of Improvements required with respect to the
Project Site.” (Ibid.)
Defendant argues that this constitutes
“acceptance by a public entity,” which in turn constitutes completion under
Civil Code section 8180(b). Thus, according to Defendant, completion occurred
on February 7, 2022. The mechanics lien attached to the complaint shows that it
was recorded on December 15, 2022, more than ninety days past the purported
date of completion. (See FAC, Ex. B; Civ. Code, § 8414(b)(1).) Therefore,
Defendant argues that the claim is untimely as a matter of law.
However, Civil Code section 8180(b) only
applies “if a work of improvement is subject to acceptance by a public entity.”
According to Defendant’s cited authority, “the phrase ‘subject to acceptance’ .
. . must find its base in some legislative enactment by the public authority.”
(Sundt Corp. v. Dynamic Finance Corp. (In re El Dorado Improvement Corp.)
(9th Cir. 2003) 335 F.3d 835, 839, quoting Howard A. Deason & Co. v.
Costa Tierra, Ltd. (1969) 2 Cal.App.3d 742, 751.) This is “applicable only
to a limited class of projects,” such as “public works, i.e., those built under
contract with a public entity” or “civic improvements such as roads, sidewalks,
gutters or sewers built under private contract in connection with otherwise
private construction projects.” (Id. at p. 838.) Additionally, “the
existence of some civic elements does not make the work of improvement as
a whole subject to acceptance.” (Id. at p. 842, emphasis in
original.) “State cases applying the public acceptance requirement have
typically involved subdivision developments where the entire work of
improvement was subject to public acceptance, not merely some portion of it.” (Ibid.)
Here, the Certificate of Completion concerns
“certain improvements defined [in the lease] as the Improvements on the Project
Site.” (Def.’s RJN, Ex. 1, § C.) The term “Improvements” is not defined in the
Certificate itself, and Defendant provides no other evidence of its meaning,
such as the lease. There is no evidence that “the Improvements” referenced in
the Certificate fall within the “limited class of projects” subject to
acceptance by a public agency. (See Sundt Corp., supra, 335 F.3d at p.
838.) The mere fact that the City issued the Certificate is not sufficient, as
a certificate of completion was also issued in Sundt Corp., yet the
court concluded the “work of improvement was not subject to public
acceptance.” (Id. at pp. 842-43.) There is also no evidence that “the
Improvements” refers to the entire project or includes work that Plaintiff
performed.
As a result, the Certificate does not
indisputably establish that completion occurred on February 7, 2022. This
leaves open a triable issue that work on the project continued to a later date,
possibly within 90 days of the mechanics lien.
III.
Evidence of Continued Work within 90 Days of Plaintiff’s Lien
Defendant cites to certain
inspection approvals and certificates of occupancy to show that work on the
project stopped more than 90 days before the lien. (See Schlager Decl., Ex.
5-10.) While this evidence supports an inference that the work was completed,
it does not preclude a triable issue.
Plaintiff’s opposing evidence suggests
that work on the project continued past the dates of the inspection cards and
certificates of occupancy. For example, Plaintiff “was called back to the
Project site on February 25, 2022 to perform concrete work on the light pole
foundation,” which is a type of work normally performed “early in
construction.” (Karimi Decl. ¶¶ 7-8.) Plaintiff further avers that work on a
project can proceed despite a certificate of occupancy and final inspection. (Id.,
¶ 10.) Plaintiff denies ever being informed by Autobuilders (the general
contractor) that work on the project had been completed. (Id., ¶ 12.) In
fact, as recently as March 2023, Plaintiff received a notice from Autobuilders
listing certain work that remained incomplete on the project. (Id., ¶
14, Ex. 3.)
When interpreted in the light most
favorable to Plaintiff, the evidence supports a triable issue that work on the
project has not been completed, or was not completed until sometime within 90
days before Plaintiff recorded the mechanics lien. Therefore, it cannot be
determined as a matter of law that the fifth cause of action is time-barred.
CONCLUSION