Judge: David Sotelo, Case: 19STCV27360, Date: 2022-10-19 Tentative Ruling



Case Number: 19STCV27360    Hearing Date: October 19, 2022    Dept: 40

MOVING PARTY:               Defendant/Cross-Complainant Dollar Shave Club, Inc. (Motion for Summary Adjudication);

 

Plaintiff/Cross-Defendant Afshin Moghavem, Inc. (Motion to Compel Deposition of Michael Dubin).

 

 

Defendant Dollar Shave Club, Inc. (“DSC”), which specializes in direct-to-consumer subscription (shaving) razor blade services, entered into a Consulting Agreement with Plaintiff Afshin Moghavem, Inc. (“AMI”) for the claimed purpose of assisting in the building proprietary razor manufacturing capabilities to phase-out DSC’s third-party supplier—Dorco—and bring DSC’s blade production in-house.

 

Afshin Moghavem is the principal of AMI.

 

Michael Dubin was DSC’s CEO at all relevant times.

 

The Consulting Agreement eventually led to the creation of Project Quantum (“PQ”), through which AMI would operate a Facility in Israel to manufacture DSC blades (“Israel Factory”). On summary adjudication, the parties disagree as to whether Project Quantum specifically involved the production of two-blade, four-blade, and six-blade blade products in the Israel Factory or instead involved only the general construction of the Factory without particulars as to blades created there (hereafter referred to as the “scope of Project Quantum”).

 

On February 3, 2016, DSC’s Board of Directors approved “an investment amount for a manufacturing facility to manufacture razors for DSC.” That same day, Michael Dubin sent an email to AMI stating: “Great work today guys. We got the green light. Here we go!” While the parties agree on summary adjudication that the “green light” referred to Project Quantum, the parties disagree on whether Dubin’s or DSC’s Board’s statements or decisions entailed the building of a razor manufacturing facility with two-blade, four-blade, and six-blade output.

 

In or about July 2016, Plaintiff and DSC began negotiating an Amended and Restated Consulting Agreement (“ARCA”) that was drafted on July 8, 2016 and executed on or around July 15 or 16, 2016. This ARCA extended the term of AMI’s consultancy through July 8, 2019. Afshin Moghavem signed the ARCA on behalf of AMI. Michael Dubin signed the ARCA on behalf of DSC.

 

The parties agree on summary adjudication that the ARCA is a valid, enforceable, and unambiguous contract (despite disputes regarding Section 5). Plaintiff’s compensation under the ARCA was governed by Section 5. The first cash equivalent awards associated with the stock options grants specified in Sections 5.b(i) and 5.b(ii) of the ARCA were paid to Plaintiff. Section 5.b(iii) of the ARCA (most relevant here) provided that:

 

101,553 shares subject to the Additional Option Grant [would] vest upon the milestone (the achievement of which shall be reasonably determined by the [DSC] Board) of Company’s [i.e., DSC’s] first commercial shipment of proprietary razors manufactured in the factory for which Consultant’s [i.e., AMI’s] Services have been engaged under [the ARCA] on or before September 30, 2018, provided this milestone shall be achieved if Company [DSC] at any time decides to not fully fund the factory as already approved by the [DSC] Board for a reason other than one related to Consultant’s [i.e., AMI’s] performance, the ability of Consultant [AMI] to deliver a satisfactory razor manufacturing facility by the milestone date or the quality of razors produced by the factory.

 

The parties disagree on summary adjudication as to whether, at the time the ARCA was entered, Plaintiff understood that it was possible the factory would not begin making commercial shipments by September 30, 2018 (the “Milestone Date”).

 

The parties agree, however, that prior to the execution of the ARCA, Dubin put pressure on AMI to close the ARCA deal quickly—going so far as to send AMI an email stating “it is imperative we finalize this [ARCA deal] tomorrow [by July 15, 2016]”—and that DSC failed to disclose that Unilever—a multinational consumer goods company—was acquiring DSC within several days of the ARCA’s execution.

 

DSC argues on summary adjudication that this information was confidential, that AMI had no right to know of this information and that AMI netted millions of dollars from the ARCA deal, which would not have been possible after the Unilever acquisition. AMI argues that failing to disclose the Unilever acquisition materially affected AMI’s position because AMI could have made different decisions regarding whether to enter the ARCA, particularly because AMI had previously worked with Unilever and understood that Unilever’s way of doing business would require redrafting the plans for the Israel Factory that would push back the operational date for the Factory.

 

AMI further argues that DSC was embroiled in a patent infringement litigation with razor company Gillette at that time, and that this information was not disclosed to AMI, and that it should have done so.

 

Several days later, on July 18, 2016, after the execution of the ARCA, DSC was acquired by Unilever, Inc. (Plaintiff learned of DSC’s impending acquisition of Unilever at some point between the execution of the ARCA and the execution of the Unilever acquisition.) As a result of DSC’s acquisition by Unilever, Inc., any vested stock options grants under Section 5(b) of the ARCA were converted to cash equivalent awards, e.g., the Milestone Award was cashed into a $3,081,259.14 option payment. Further, DSC’s Board was replaced by Unilever executives.

 

AMI was ultimately unable to meet the Milestone Date of September 30, 2018, i.e., AMI failed to effect its first commercial shipment of proprietary razors manufactured in the Israel Factory until 2019. (The Court has previously found in another summary adjudication motion in this action that DSC fully funded the Israel Factory.)

 

AMI argues on summary adjudication that it was willing and able to so ship viable four and six-blade razor products as of the Milestone Date but was unable to do so because DSC engaged in a series of activities to prevent AMI from reaching the Milestone Date after the ARCA’s execution, including:  Requiring the (“perfunctory”) approval of Unilever for any expenses of $100,000 or more; Asking that the plans for Project Quantum be reproposed to DSC, leading to reapproval in December 2016; Instituting a hiring freeze at AMI from August 2016 to December 2016; Demanding new conditions on the Factory’s lease after prior negotiation on this topic between the parties; Requiring that AMI redesign the six-blade and four-blade razor designs in April 2017; Requiring that AMI redesign the dispensers for the four-blade and six-blade razor products in August 2017, causing an additional delay of four to six months; Failing to ensure the timely design, development, and production of the handles to be attached to the AMI-produced razors (DSC’s responsibility under the ARCA), resulting in further delays; instructing AMI to follow procedures that were not the most advantageous for the production of blades designed at the Israel Factory, resulting in further delays; and Delaying the shipment of AMI-produced blades from December 2018 (after the Milestone Date) to sometime in 2019 in lieu of pending litigation with Gillette, which concluded sometime in 2019 and before the date of the first AMI shipment from the Israel Factory.

 

DSC argues on summary adjudication that most of the evidence provided to support these arguments is inadmissible.

 

Based on the above, Plaintiff AMI brought this action, alleging (1) Breach of Contract, (2) Breach of Implied Covenant of Good Faith and Fair Dealing, (3) Intentional Misrepresentation, (4) Concealment, and (5) Negligent Misrepresentation against DSC. (Plaintiff’s operative pleading is its Second Amended Complaint, or “SAC”.)

 

DSC filed a Cross-Complaint alleging (1) Declaratory Judgment regarding the Consulting Fees; (2) Declaratory Judgment regarding the Milestone Option Payment; and (3) Declaratory Judgment regarding AMI’s misrepresentation and concealment claims.

 

On September 3, 2021, AMI made a Motion for Summary Adjudication against First Cause of Action for Breach of Contract, claiming damages based on DSC’s nonpayment of AMI’s consulting fees and the Milestone Award contemplated by the ARCA. The Court “GRANTED [summary adjudication] in favor of Plaintiff AMI in the [SAC’s] First cause of action [Breach of Contract] for the monthly consulting cash compensation which appears to total approximately $226,209.65” but DENIED summary adjudication as to the Breach of Contract claim, as supported by damages related to the Milestone Award, because “[t]here [was] no evidence showing a triable issue of material fact was submitted to establish the conditions in paragraph 5, subdivision (b) of the ARCA were ever triggered.”

 

DSC now brings its own opposed Motion for Summary Adjudication, seeking resolution in its favor as to the Four remaining causes of action in AMI’s Second Amended Complaint and the three Declaratory Relief claims alleged by DSC in its Cross-Complaint.

 

Evidentiary Objections

 

Plaintiff AMI’s Objection

           

ALL OVERRULED.

 

Defendant DSC’s Objections

 

ALL SUSTAINED

 

Application to Seal: GRANTED

 

Motion to Seal – Moving Papers: “A party requesting that a record be filed under seal must file a motion or an application for an order sealing the record. The motion or application must be accompanied by a memorandum and a declaration containing facts sufficient to justify the sealing.” (Cal. Rules of Court, Rule 2.551, subd. (b)(1).) Plaintiff AMI met this requirement on June 10, 2022 through the submission of this application explaining that the parties have stipulated to the sealing of either portions or the entirety of confidential business record in the record. (Application to Seal, pp. 1-3.)

 

Motion to Seal – Service: “A copy of the motion or application must be served on all parties that have appeared in the case. Unless the court orders otherwise, any party that already possesses copies of the records to be placed under seal must be served with a complete, unredacted version of all papers as well as a redacted version.” (Cal. Rules of Court, rule 2.551, subd. (b)(2).) Here, Plaintiff AMI served copies of the application DSC’s Counsel on June 10, 2022 via mail.

 

Motion to Seal – Lodging: Unless good cause exists, a record to be filed under seal must be put in an envelope or other appropriate container labeled ‘CONDITIONALLY UNDER SEAL,’ have a cover sheet affixed thereto with an appropriate caption page stating the envelope contains a motion to file a record under seal and be lodged in the sealed envelope with the Court. (Cal. Rules of Court, rule 2.551, subds. (b)(4), (d)(2), (d)(4).) Here, the Court has received unredacted copies of the documents to be wholly or partially sealed that meet these requirements.

 

Motion to Seal – Redacted and Unredacted Versions: If necessary to prevent disclosure, any motion to seal and any supporting documents must be filed in a public redacted version and lodged in a complete, unredacted version conditionally under seal. The cover of the redacted version must identify it as “Public-Redacts materials from conditionally sealed record” while the cover of the unredacted version must identify it as “May Not Be Examined Without Court Order-Contains material from conditionally sealed record.” (Cal. Rules of Court, rule 2.551, subd. (b)(5).) Here, the Court has received copies of the sealed record (redacted and unredacted) and the Court’s online docket system reflects that copies of the documents to be sealed—Exhibits 2-11, 15, 18, 20-21, 23-24, 27, 30 attached to the Doniger Declaration submitted in support of the AMI Opposition to summary adjudication—appear in the public record.

 

Motion to Seal – Findings: “The public has a First Amendment right of access to civil litigation documents filed in court and used at trial or submitted as a basis for adjudication.” (Savaglio v. Wal-Mart Stores, Inc. (2007) 149 Cal.App.4th 588, 596 [citing NBC Subsidiary (KNBC-TV), Inc. v. Superior Court (1999) 20 Cal.4th 1178, 1208-1209, fn. 25].) Therefore, before a trial court orders a record sealed, it must hold a hearing and make express findings set forth in California Rules of Court, Rule 2.550, subdivision (d): (1) there exists an overriding interest that overcomes the right of public access to the record; (2) the overriding interest supports sealing the record; (3) a substantial probability exists that the overriding interest will be prejudiced if the record is not sealed; (4) the proposed sealing is narrowly tailored; and (5) no less restrictive means exist to achieve the overriding interest. (Id.; Cal. Rules of Court, rule 2.550, subd. (d).)

 

Here, the Court finds that: (1) there exists an overriding interest to protect the information to be redacted from the Doniger Declaration at Exhibits 2 to 11, 15, 18, 20, 21, 23, 24, 27, and 30 because this information involves confidential information springing from a business transaction between two companies; (2) the interest in protecting the confidentiality of this business transaction overrides the right of public access to this record, particularly in light of the skewed importance of confidentiality in this business transaction in comparison to the public’s interest in the same information; (3) the interest in confidentiality in the documents to be sealed would be prejudiced if the record is not sealed because the Court cannot retract this information from the public record easily once it has been published and is accessible for duplication; (4) the proposed sealing is narrowly tailored given that the parties—per the Court’s wishes—have minimized the amount of redactions in the record to compartmentalize any sealing of the record to confidential business transactions between DSC and AMI; and (5) no less restrictive means of achieving this interest exist because the evidence at issue is being submitted into the record and plays a part in the disposition of the issues at bar, and thus, to fail to seal the partial or whole redactions requested by Plaintiff AMI would result in this information’s full disclosure—Exhibits 2 to 11, 15, 18, 20, 21, 23, 24, 27, and 30 of the Doniger Declaration on Opposition—to the prejudice of the overriding interest in the confidentiality of the parties’ business records.

 

Motion for Summary Adjudication: GRANTED, in Part; Denied in Part

 

Legal Standard: A motion for summary judgment shall be granted if all the papers submitted show that there is no triable issue as to any material fact and that the moving party is entitled to a judgment as a matter of law. (Code of Civ. Proc., § 437c, subd. (c).) A party may also seek summary adjudication of an entire a cause of action or, under certain circumstances, parts thereof, which may be made by a standalone motion or as an alternative to a motion for summary judgment and proceeds in all procedural respects as a motion for summary judgment. (Code Civ. Proc., § 437c, subds. (f)(1)-(2), (t); see Lilienthal & Fowler v. Superior Court (1993) 12 Cal.App.4th 1848, 1854-55; see also Public Utilities Com. v. Superior Court (2010) 181 Cal.App.4th 364, 380.) The moving party bears the initial burden of production to make prima facie showing no triable material fact issues. (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 850.) This burden on summary judgment “is more properly one of persuasion rather than proof, since he must persuade the court that there is no material fact for a reasonable trier of fact to find, and not to prove any such fact to the satisfaction of the court itself as though it were sitting as the trier of fact.” (Id. at p. 850, fn.11.) If the moving party meets this burden, the burden shifts to the opposing party to make converse prima facie showing that a triable issue of material fact exists. (Ibid.) The evidence of the moving party is strictly construed, and the evidence of the opposing party liberally construed. (Crouse v. Brobeck, Phleger & Harrison (1988) 67 Cal.App.4th 1509, 1524.) Doubts as to the propriety of granting the motion must be resolved in favor of the party resisting the motion. (Stationers Corp. v. Dun & Bradstreet, Inc. (1965) 62 Cal.2d 412, 417.)

 

I.

 

First Cause of Action [Breach of Contract]: GRANTED.

 

Defendant argues that Plaintiff’s Breach of Contract claim fails on summary adjudication because the Court has already determined questions of fact as to this cause of action the January 4, 2022 Minute Order. (MSA, 5:18-24.) This is not correct.

 

The Court’s January 4, 2022 Order Granted Plaintiff summary adjudication for Breach of Contract only as supported by DSC’s nonpayment of the Consulting Fees contemplated by Section 5.b of the ARCA. (See Jan. 4, 2022 Minute Order, pp. 3-4; Mot., Beffa Decl., Ex. Z, pp. 3-4.) That same Order Denied Plaintiff summary adjudication as to the SAC’s First cause of action for Breach of Contract insofar as the claim was supported by allegations that DSC wrongfully withheld payment of the Milestone Award from AMI. (See Jan. 4, 2022 Minute Order, pp. 3-4; Mot., Beffa Decl., Ex. Z, pp. 3-4.) California case law holds that “[a]n order denying [a] motion [for summary judgment or adjudication] simply establishes the existence of a triable issue of fact[;] [i]t does not decide the issue.” (Transport Ins. Co. v. TIG Ins. Co. (2012) 202 Cal.App.4th 984, 1009.) Based on this instruction, the Court’s January 4, 2022 Order did not dispose of the First cause of action insofar as this claim is premised on DSC’s nonpayment of the separate so-called Milestone Award to AMI.

The Court finds that a reasonable factfinder could not conclude the evidence underlying the Court’s January 4, 2022 Order shows triable issues of fact exist as to whether AMI is entitled to the Milestone Award: In fact, the evidence shows that the conditions precedent to such an award were never triggered. (See Jan. 4, 2022 Minute Order, pp. 3-4; Mot., Beffa Decl., Ex. Z, pp. 3-4.)

 

Plaintiff AMI altogether fails to address the SAC’s First Cause of Action in its Opposition (MSA Opp’n, 6:14-20:22) and thus fails to meet its burden on summary adjudication.

 

II.

 

Second Cause of Action [Breach of Implied Covenant of Good Faith and Fair Dealing]: DENIED.

 

This Second Cause of Action seeks damages equal to the Milestone Award ($3,081,259.14) based on alleged actions taken by DSC to delay or foreclose AMI’s ability to meet the Milestone Date, constituting a Breach of Implied Covenant of Good Faith and Fair Dealing implicit in the parties’ ARCA. (SAC, ¶¶ 46-49.)

 

“There is an implied covenant of good faith and fair dealing in every contract that neither party will do anything which will injure the right of the other to receive the benefits of the agreement.” (Comunale v. Traders & General Ins. Co. (1958) 50 Cal.2d 654, 658 [citation omitted].) “The covenant of good faith finds particular application in situations where one party is invested with a discretionary power affecting the rights of another” where “[s]uch power must be exercised in good faith.” (Carma Developers (Cal.), Inc. v. Marathon Development California, Inc. (1992) 2 Cal.4th 342, 371-72 [citations omitted].)

 

DSC argues this cause of action fails because (1) Plaintiff seeks to impermissibly recover the Milestone Award through an implied recovery theory when this court has already concluded that the express terms of the ARCA’s Milestone Award were never triggered (something DSC paints as attempting to “trump” the express terms in the contract); (2) any delay caused to AMI’s ability to ship out its first shipment of commercial proprietary razors, even if caused by DSC, was within the contemplation of the parties; and (3) Plaintiff cannot recover the Milestone Award where Section 5.b(iii) of the ARCA is the only trigger for such an award. (MSA, 5:25-9:2.)

 

The Court finds none of these positions—nor any evidence in support them—availing on summary adjudication.

 

The Court is unconvinced that a reasonable factfinder could determine Plaintiff is attempting to recover the Milestone Award in the second Cause of Action. This cause of action seeks to recover an amount equal to the Milestone Award based on a series of delays caused by DSC that impeded Plaintiff’s ability to in fact ship a commercial shipment of proprietary razors by September 30, 2018 (the Milestone Date). (SAC, ¶¶ 46-49.) Stated otherwise, this Second cause of action seeks to recover the $3,081,259.14 AMI would have been paid by DSC if AMI had met the Milestone Date in the absence of DSC’s interference. (See SAC, ¶¶ 46-49; see also Reply, Separate Statement, UMF Nos. 131-152.)

 

DSC’s remaining arguments (MSA, 5:27-6:14, 6:24-9:2) are unavailing, insofar as DSC attacks the Second cause of action for attempting to recover the Milestone Award but fails to recognize the Second cause of action technically seeks not the Milestone Award itself, but rather, seeks an award in the same amount because the Milestone Award is equal to the amount of damages suffered by Plaintiff as a result of DSC’s alleged interference with AMI’s ability to make its first commercial shipment of proprietary razors by September 30, 2018.

 

Second, the Court is not convinced that a reasonable factfinder could determine that no triable issues of fact exist as to whether DSC, in bad faith, took actions to delay or frustrate AMI’s ability to meet the Milestone Date. Despite DSC’s best assertions (MSA, 6:15-23), the facts presented on summary adjudication could be viewed in two ways: DSC made business decisions that were best for DSC without contemplating the resulting effects on AMI (see Reply, 3:21-4:2), or DSC, through inferential evidence that simple business decisions incrementally but surely deprived AMI of its ability to meet the Milestone Date. (See SAC, ¶¶ 46-49; see, e.g., Reply, Separate Statement, UMF Nos. 131-152; Doniger Decl., Exs. 6, 7, 16.)

 

Summary adjudication of the SAC’s Second cause of action is therefore DENIED.

 

III.

 

Third and Fifth Causes of Action [Intentional Misrepresentation; Negligent Misrepresentation]: GRANTED

 

The SAC’s Third and Fifth causes of action—Intentional Misrepresentation and Negligent Misrepresentation—are premised on one theory: when then-DSC CEO Michael Dubin stated to AMI, “Great work today guys[;] We got the green light[;] Here we go!”, Dubin either misrepresented or concealed the fact that the DSC Board had not approved the production of six-, four-, and two-blade razor products in addition to the construction of the Israel Factory, thus causing unspecified damages to Plaintiff AMI. (SAC, ¶¶ 5-12, 51-52, 71-72.)

In relevant part, Defendant DSC argues on summary adjudication that the Third and Fifth Causes of Action fail because, “[u]nder the most generous interpretation of Plaintiff’s claim, Plaintiff would be entitled to nothing more than what the contract would have awarded him if DSC’s Board had approved the … non-funding details of the factory in February 2016” and, even then, “Plaintiff would still not be entitled to the milestone payment because, as the Court has already determined, the milestone was triggered off of funding approved by the Board, not any other non-funding details.” (MSA, 12:20-22.)

 

The Court finds that this argument carries DSC’s burden on summary adjudication as to the Third and Fifth causes of action. A claim for intentional or negligent misrepresentation must allege and prove damages relating to the misrepresentation(s) at issue. (Service by Medallion, Inc. v. Clorox Co. (1996) 44 Cal.App.4th 1807, 1816 [intentional misrepresentation]; B.L.M. v. Sabo & Deitsch (1997) 55 Cal.App.4th 823, 834 [negligent misrepresentation].) In its Opposition, AMI argues that “[a]s a result of entering into the ARCA and the Milestone Date provision based on DSC’s misrepresentations, AMI was deprived of, inter alia, the $3,081,259.14 third Option Payment.” (MSA Opp’n, 16:12-13.)

 

However, the Court has found on summary adjudication that AMI is not entitled to the Milestone Award. Further, as discussed ante about the SAC’s Second cause of action, the pertinent evidence supporting infringement of AMI’s ability to obtain the Milestone Award relates to actions taken by DSC after the ARCA was executed in July 2016—at least five months after Dubin made his February 2016 “green light statement.” The Court is thus persuaded that a reasonable factfinder could determine that Dubin’s words were not causally connected to the only damages presented by AMI on summary adjudication as to the Third and Fifth causes of action: the loss of the Milestone Award itself. (See Opp’n, 16:12-13.)

 

The Court also finds that Plaintiff cannot carry its burden on summary adjudication as to the Third and Fifth causes of action based on the same logic: AMI claims only the loss of the Milestone Award (rather than an award for damages in the same amount of the Milestone Award, as contemplated in the Second cause of action), and these damages have been adjudicated in favor of DSC in this Order. (Second Amended Complaint, First Cause of Action discussion supra.) Further, AMI presents no other evidence of damages for these claims. (See Opp’n, 16:10-27.) Last, the SAC does not allege nor does AMI argue or show on summary adjudication that DSC never intended to pay out the Milestone Award, either as of February 2016 (when the Factory was first “green lit” and possibly before the Milestone Award was even contemplated as part of the ARCA—the evidence is unclear either way) or July 2016 (when the ARCA with the Milestone Award was executed, and after Mr. Dubin’s alleged misrepresentations).

 

The Court briefly notes that while it “previously held that AMI plausibly alleged DSC’s liability for misrepresentation” (MSA Opp’n, 1:3-4), the Court notes that sufficiency of pleading is a lower bar than sufficiency of evidence, and here, AMI presented insufficient evidence of damages to support the Third and Fifth Causes of Action on summary adjudication.

 

The Court thus GRANTS summary adjudication as to the SAC’s Third and Fifth causes of action.

 

IV.

 

Fourth Cause of Action [Concealment]: GRANTED.

 

This cause of action is based on three “concealments”: (1) AMI’s concealment of the fact that it had never approved Project Quantum with respect to two-blade, four-blade, and six-blade assembly; (2) DSC’s concealment as to the Unilever acquisition; and (3) DSC’s concealment as to the Gillette litigation. (SAC, ¶¶ 61.)

 

The Court finds similar logic to that employed in the discussion of Third and Fifth causes of action is applicable to all three concealment grounds: the only damages at issue in the Fourth Cause of Action on summary adjudication are Plaintiff’s entitlement to the Milestone Award and nothing else, and the Court has adjudicated the Milestone Award in favor of in favor of DSC in this same Order, for which reason Defendant DSC carries its burden on summary adjudication as against the SAC’s Concealment claim and Plaintiff cannot make a rebuttal showing as to survive summary adjudication. (See MSA Opp’n, 20:15-22 [arguing on Opposition that the only damages that AMI suffered as a result of DSC’s alleged misrepresentation in relation to the scope of Project Quantum, the Unilever Acquisition, and the Gillette Litigation were the deprivation of the Milestone Award itself]; see also Second Amended Complaint, First Cause of Action discussion supra [summary adjudication in favor of DSC on the SAC’s Breach of Contract claim as supported by DSC’s nonpayment of the Milestone Award to AMI].)

 

V.

 

Cross-Complaint, First to Third Cause of Action [Declaratory Relief re: (1) Consulting Fees, (2) Milestone Award, (3) Misrepresentations]: GRANTED.

 

Defendant DSC argues that the Court should grant summary adjudication as to the Cross-Complaint’s three causes of action because (1) the Court’s summary adjudication as to the SAC’s Breach of Contract claim disposed of the first cause of action in the Cross-Complaint (regarding declaratory relief establishing the consulting fees) (MSA, 5:18-24) and (2) its other arguments on summary adjudication dispose of the remaining claims in the Cross-Complaint. (MSA, 17:10-14.) The Opposition fails to address these points altogether. (See Opp’n, 6:14-20:22.)

 

The Court finds that its January 4, 2022 Order, as well as the Second Amended Complaint, First Cause of Action discussion ante, estops discussion of issues related to the Cross-Complaint’s First and Second Causes of Action as a matter of law because (1) the claims ask that the Court resolve a controversy between AMI and DSC regarding the consulting fees and Milestone Award contemplated by Section 5 of the ARCA (See Aug. 26, 2021 Cross-Complaint, ¶¶ 29, 33) and (2) the Court’s January 4, 2022 Order and discussion herein show that a final adjudication as to the same issues was actually litigated and necessarily decided as between AMI and DSC. (Jan 4. 2022 Order, pp. 3-4; MSA, Beffa Decl., Ex Z, pp. 3-4; Second Amended Complaint, First Cause of Action discussion supra; see also KN Holdings LLC v. Faerber (2015) 61 Cal.4th 813, 825 [Issue preclusion applies “(1) after final adjudication (2) of an identical issue (3) actually litigated and necessarily decided in the first suit and (4) asserted against one who was a party in the first suit or one in privity with that party”].)

 

Similarly, the Cross-Complaint’s third claim for Declaratory Relief asks that the Court resolve AMI’s misrepresentation and concealment claims against DSC (Complaint, ¶¶ 37-38) and these issues have been litigated and necessarily decided as between AMI and DSC, as adjudged in this Order. (See Second Amended Complaint, Third and Fifth causes of action discussion & Second Amended Complaint, Fifth cause of action discussion supra; see also KN Holdings LLC, supra, 61 Cal.4th at p. 825.)

 

Motion to Compel Deposition: MOOT

 

Plaintiff AMI’s Motion to Compel Deposition of Michael Dubin is MOOT because the Motion “requests that this Court issue an Order compelling Dubin to appear for deposition on AMI’s fraud claims, or alternatively precluding Dubin from testifying at trial to anything related to AMI’s fraud claims” (Compel Mot., 8:5-7) and this Court has adjudicated such claims in favor of DSC, mooting any need for further discovery on these SAC’s fraud claims.

Conclusion

 

Plaintiff Afshin Moghavem, Inc.’s Application to Seal is GRANTED because an overriding interest exists in the protecting of a confidential information related to the AMI and DSC’s business transactions exists, which overrides the public interest in the same information, and where the non-sealing of this information would prejudice AMI and DSC through its public disclosure and no less restrictive means exist to protect this narrowly tailored request.

 

Defendant/Cross-Complainant Dollar Shave Club, Inc.’s Motion for Summary Adjudication is:

 

GRANTED as to the First cause of action because AMI met its burden on summary adjudication as to AMI’s non-entitlement to the Milestone Award and AMI failed to make a rebuttal showing by failing to address this issue altogether;

 

DENIED as to the Second cause of action because Defendant DSC failed to carry its burden on summary adjudication; and

 

GRANTED as to the Third through Fifth causes of action because Defendant DSC carries its burden on lack of damages to AMI on these claims and Plaintiff AMI failed to make a converse showing; and

 

GRANTED as to the First through Third causes of action because these issues at the heart of these claims have been resolved by this Court’s orders here and on January 4, 2022.

 

Plaintiff Afshin Moghavem, Inc.’s Motion to Compel Deposition of Michael Dubin is MOOT because it seeks to compel the deposition of Michael Dubin as to the fraud claims alleged in the Second Amended Complaint and these claims have been adjudicated as against Plaintiff AMI in this Order.