Judge: Elaine Lu, Case: 22STCV10408, Date: 2022-10-12 Tentative Ruling
Case Number: 22STCV10408 Hearing Date: October 12, 2022 Dept: 26
|
PLATFORM HARDEN TRACT III, LLC, Plaintiff, v. REX ENGINEERING GROUP, INC., et al., Defendants. |
Case No.: 22STCV10408 Hearing Date: October 12, 2022 [TENTATIVE] ORDER RE: DEFENDANT’S
DEMURRER TO THE COMPLAINT |
Procedural
Background
On March 25, 2022, Plaintiff Platform Hayden Tract III, LLC
(“Plaintiff”) filed the instant breach of construction contract action against
Defendant REX Engineering Group, Inc. (“Defendant”). The complaint asserts three causes of action
for (1) Negligence, (2) Breach of Contract, and (3) Breach of the Implied
Covenant.
On April 28, 2022, Defendant filed a demurrer to the first and third
causes of action of the complaint. On
September 29, 2022, Plaintiff filed an opposition. On October 5, 2022, Defendant filed a reply.
Allegations
of the Operative Complaint
The complaint alleges that:
“Plaintiff [] is the developer of
Synapse, an approximately 90,000 square foot retail and office building at 8888
Washington Blvd in Culver City, California.”
(Complaint ¶ 9.) In December
2016, Plaintiff hired IED – which merged with another engineering firm to
become Defendant – to provide shell and core interior engineering services for
Synapse including designing Synapse’s generator room. (Id. ¶ 10.)
“The agreement required, among other things, for all work by [Defendant]
to be done in accordance with governing codes.”
(Id. ¶ 11.)
“REX failed to exercise due care,
skill, and diligence in designing the generator room. REX’s design for the
generator room at Synapse provided insufficient airflow. In particular, REX
failed to include an appropriate exhaust system and other needed air flow
features. As a result, the generators would overheat and shut down.” (Id. ¶ 12.)
“In April 2021, the generators failed to pass their start up test due to
overheating caused by REX’s design flaws. The generators and generator room
were not in compliance with Chapter 27 of the California Building Code as a
result.” (Id. ¶ 13.) “To correct these design flaws, an exhaust
fan, additional ducting, and a louvered door had to be installed, among other
things. REX’s design failures also caused a significant delay in obtaining
final electrical and mechanical inspection approvals at Synapse.” (Id. ¶ 14.)
Evidentiary
Objections
In reply, Defendant objects to
portions of the declaration of Colin H. Rolfs.
However, there is no statutory basis for evidentiary objections for a
demurrer. Moreover, these objections are unnecessary because the court,
when reviewing the evidence is presumed to ignore material it knows it
incompetent, irrelevant, or inadmissible. (In re Marriage of Davenport
(2011) 194 Cal. App. 4th 1507, 1526.) Courts are presumed to know and
apply the correct statutory and case law and to be able to distinguish
admissible from inadmissible evidence, relevant from irrelevant facts, and to
recognize those facts which properly may be considered in the judicial
decision-making process. (People v. Coddington (2000) 23 Cal.4th
529, 644.) Accordingly, the court declines to rule on these
objections. However, the court notes
that extrinsic matters outside the pleadings cannot be considered in a
demurrer.
Legal Standard
A demurrer can
be used only to challenge defects that appear on the face of the pleading under
attack; or from matters outside the pleading that are judicially noticeable. (Blank v. Kirwan (1985) 39 Cal 3d 311,
318.) No other extrinsic evidence can be considered (i.e., no “speaking
demurrers”). (Ion Equipment Corp. v. Nelson (1980) 110 Cal.App.3d
868, 881.)
A demurrer for
sufficiency tests whether the complaint states a cause of action. (Hahn v. Mirda (2007) 147 Cal. App. 4th
740, 747.) When considering demurrers,
courts read the allegations liberally and in context. (Taylor
v. City of Los Angeles Dep’t of Water & Power (2006) 144 Cal. App. 4th
1216, 1228.) In a demurrer proceeding,
the defects must be apparent on the face of the pleading or via proper judicial
notice. (Donabedian v. Mercury Ins. Co. (2004) 116 Cal. App. 4th 968,
994.) “A demurrer tests the pleadings
alone and not the evidence or other extrinsic matters. Therefore, it lies only where the defects
appear on the face of the pleading or are judicially noticed.” (SKF Farms v. Superior Ct. (1984) 153
Cal. App. 3d 902, 905.) “The only issue
involved in a demurrer hearing is whether the complaint, as it stands,
unconnected with extraneous matters, states a cause of action.” (Hahn, supra, 147 Cal.App.4th at 747.)
A special demurrer
for uncertainty, Code of Civil Procedure §430.10(f), is disfavored and will
only be sustained where the pleading is so bad that defendant cannot reasonably
respond—i.e., cannot reasonably determine what issues must be admitted or
denied, or what counts or claims are directed against him/her. (Khoury
v. Maly’s of Calif., Inc. (1993) 14 Cal.App.4th 612, 616.) Moreover, even if the pleading is somewhat
vague, “ambiguities can be clarified under modern discovery procedures.” (Ibid.)
Meet and Confer Requirement
Code of Civil
Procedure section 430.41, subdivision (a) requires that “[b]efore filing a
demurrer pursuant to this chapter, the demurring party shall meet and confer¿in
person or by telephone¿with the party who filed the pleading that is subject to
demurrer for the purpose of determining whether an agreement can be reached
that would resolve the objections to be raised in the demurrer.” The parties
are to meet and confer at least five days before the date the responsive
pleading is due and if they are unable to meet the demurring party shall be
granted an automatic 30-day extension. (CCP § 430.41(a)(2).) The
demurring party must also file and serve a declaration detailing the meet and
confer efforts. (Id.¿at
(a)(3).)¿ If an amended pleading is filed, the parties must meet and confer
again before a demurrer may be filed to the amended pleading. (Id.¿at (a).)
Defendant has fulfilled
the meet and confer requirement. (Menjou
Decl. ¶¶ 3-4, Exh. A.)
Discussion
First Cause of Action:
Negligence
Defendant contends that the first cause of action is
barred by the economic loss rule.
Under the economic loss rule, “there is no recovery in
tort for negligently inflicted ‘purely economic losses,’ meaning financial harm
unaccompanied by physical or property damage.”
(Sheen v. Wells Fargo Bank, N.A. (2022) 12 Cal.5th 905, 922.) “‘[T]here is no liability in tort for
economic loss caused by negligence in the performance or negotiation of a
contract between the parties.’ (Rest., § 3.)”
(Id. at p.923.) However, “[n]ot
all tort claims for monetary losses between contractual parties are barred by
the economic loss rule. But such claims are barred when they arise from — or
are not independent of — the parties’ underlying contracts.” (Ibid.) “Tort damages have been permitted in contract
cases where a breach of duty directly causes physical
injury [Citation] for breach of the covenant of good faith and fair
dealing in insurance contracts [Citation]; for wrongful discharge in
violation of fundamental public policy [Citation]; or where the contract
was fraudulently induced. [Citation.] In each of these cases, the duty
that gives rise to tort liability is either completely independent of the
contract or arises from conduct which is both intentional and intended to
harm.” (Erlich v. Menezes (1999)
21 Cal.4th 543, 551–552.)
Here, the complaint alleges that Defendant’s design
provided insufficient airflow which caused the generators to overheat and shut
down. (Complaint ¶ 12.) However, there is no allegation that the
design caused any physical damage to the generators. Nor is there any allegation that the claim
for tort liability is completely independent of the contract.
Relying on Transwestern Pipeline Co. v. Monsanto Co. (1996)
46 Cal.App.4th 50, Plaintiff in opposition contends that the excess heat alone
constitutes physical damage. In Transwestern,
the defendant’s product Turbinol, a lubricant for gas compressors, caused PCB
contamination in gas pipes, and the Court of Appeal concluded that the economic
loss rule was inapplicable as the “PCB contamination constituted property
damage”. (Id. at p.527.) Comparing the situation to asbestos contamination
cases, the Court of Appeal noted that “economic loss occurs when the toxic
substance is merely present but property damage occurs when the toxic substance
actually contaminates the plaintiff's property.” (Ibid.)
Unlike in Transwestern,
the excess heat here is not itself a toxic contaminant like PCB or
asbestos. Nor can it reasonably be
stated that the excess heat contaminates property. Unlike the PCB in Transwestern, which
could not be removed from the gas pipes, heat dissipates on its own. While undoubtably excess heat could lead to
and cause property damage – i.e., damage to the engine from overheating
– Plaintiff has not alleged as such.
Accordingly, the first cause of action is barred by the economic loss
rule.
Therefore,
Defendant’s demurrer to the first cause of action is SUSTAINED.
Third Cause of Action: Breach
of the Implied Covenant
Defendant contends that the third cause of action is
duplicative and merely a restatement of the breach of contract claim.
“The covenant of good faith and fair dealing,
implied by law in every contract, exists merely to prevent one contracting
party from unfairly frustrating the other party's right to receive the benefits
of the agreement actually made.” (Guz v. Bechtel Nat. Inc. (2000) 24 Cal.4th 317, 349.) “It cannot impose substantive duties or
limits on the contracting parties beyond those incorporated in the specific
terms of their agreement.” (Id. at
pp.349–350.) Accordingly,
“[a] breach of the
implied covenant of good faith is
a breach of the contract.”
(Thrifty Payless, Inc. v. The
Americana at Brand, LLC (2013) 218 Cal.App.4th
1230, 1244.) Therefore, “[a] breach of
the covenant of good faith and fair dealing does not give rise to a cause of
action separate from a cause of action for breach of the contract containing
the covenant.” (Smith v. International Brotherhood of Electrical
Workers (2003) 109 Cal.App.4th
1637, 1645, Fn.3.)
Moreover, “[a] ‘breach of the implied covenant of
good faith and fair dealing involves something beyond breach of the contractual
duty itself’ and it has been held that ‘[b]ad faith implies unfair dealing
rather than mistaken judgment....’ [Citations.]” (Careau & Co., supra, 222
Cal.App.3d at p.1394.)
Accordingly, “[i]f the allegations do not go
beyond the statement of a mere contract breach and, relying on the same alleged
acts, simply seek the same damages or other relief already claimed in a
companion contract cause of action, they may be disregarded as superfluous as
no additional claim is actually stated. Thus, absent those limited cases where
a breach of a consensual contract term is not claimed or alleged, the only
justification for asserting a separate cause of action for breach of the
implied covenant is to obtain a tort recovery.”
(Id. at p.1395.) However,
tort recovery for breach of contract, even in bad faith, is limited solely to claims
for breach of an insurance contract. (Freeman
& Mills, Inc. v. Belcher Oil Co. (1995) 11 Cal.4th 85, 87-103; See
also Erlich v. Menezes (1999) 21 Cal.4th 543, 552–553,[“ In holding
that a tort action is available for breach of the [implied covenant of good
faith] in an insurance contract, we have “emphasized the “special
relationship” between insurer and insured, characterized by elements of public
interest, adhesion, and fiduciary responsibility.’”)
Here, the complaint alleges that Defendant breached the
implied covenant of good faith and fair dealing “by failing to deliver designs
for a functional generator room. [Defendant]’s design failed to provide
sufficient airflow to the generators, causing them to overheat.” (Complaint ¶ 26.) While nearly identical to the breach of
contract claim, (See Complaint ¶ 22), the breach of contract claim also
alleges that “[Defendant] further breached the agreement by failing to design
the generator room in accordance with governing codes, including Chapter 27 of the
California Building Code.” (Complaint ¶
23.) For purposes of the first cause of
action, the complaint also expressly alleges that the agreement provided that “[t]he
agreement required, among other things, for all work by [Defendant] to be done
in accordance with governing codes.” (Id.
¶ 11.) These allegations are omitted for
the third cause of action. Accordingly,
the third cause of action reasonably
alleges that Defendant’s design failed to provide sufficient airflow, which
though not in direct violation of an express term of the agreement, violated an
implied term of the agreement, frustrating the purpose of the agreement. Therefore, the third cause of action is not
superfluous of the second cause of action.
Accordingly, Defendant’s demurrer to the third cause of
action is OVERRULED.
Leave to Amend
Leave to amend
must be allowed where there is a reasonable possibility of successful
amendment. (Goodman
v. Kennedy (1976) 18 Cal.3d 335, 348.) The burden is on the plaintiff
to show the court that a pleading can be amended successfully. (Goodman v. Kennedy,
supra, 18 Cal.3d at p. 348; Lewis v. YouTube, LLC (2015) 244
Cal.App.4th 118, 226.)
Here, it seems reasonably possible that Plaintiff may successfully
amend the complaint. Moreover, Plaintiff
has only now been given notice of the legal defects in its causes of action. The
court finds it is proper to allow Plaintiff an opportunity to cure the defects
discussed in this order. (See Goodman v. Kennedy (1976) 18 Cal.3d 335,
349; Kong v. City of Hawaiian Gardens Redevelopment Agency (2002) 108
Cal.App.4th 1028, 1037.)
CONCLUSION AND ORDER
Based on the foregoing, Defendant
REX Engineering Group, Inc.’s demurrer to the complaint is SUSTAINED IN PART
WITH LEAVE TO AMEND as to the first cause of action and otherwise OVERRULED.
Plaintiff is to file an amended
complaint within fifteen (15) days of notice of this order.
The case management conference is
continued to December 12, 2022 at 8:30 am.
Moving Party is to give notice and
file proof of service of such.
DATED: October 12, 2022 _____________________________
Elaine
Lu
Judge
of the Superior Court