Judge: Gail Killefer, Case: 20STCV31276, Date: 2022-10-03 Tentative Ruling



Case Number: 20STCV31276    Hearing Date: October 3, 2022    Dept: 37

HEARING DATE:                 October 3, 2022

CASE NUMBER:                  20STCV31276

CASE NAME:                        Meco Properties, LLC. v. Weather Masters Waterproofing, Inc., et al.

MOVING PARTIES:             Defendants, Weather Masters Waterproofing, Inc., a dissolved corporation, and WMW, Inc.

RESPONDING PARTY:       Plaintiff, Meco Properties, LLC.

TRIAL DATE:                        November 8, 2022

PROOF OF SERVICE:          OK

                                                                                                                                                           

MOTION:                               Defendants’ Motion for Summary Judgment Or, In The Alternative, Summary Adjudication

OPPOSITION:                       September 19, 2022  

REPLY:                                  September 28, 2022

                                                                                                                                                           

RECOMMENDATION:        Defendants’ motion is granted as to the second cause of action and otherwise denied. Defendants are to give notice. 

                                                                                                                                                           

Background

This action arises in connection with the construction of a new house located at 1875 N. Crescent Heights Blvd., Los Angeles, California (“Subject Property”). The owner of Subject Property, Walter Schild (“Schild”), assigned all rights, claims, and causes of action to Meco Properties, LLC (“Plaintiff”). Schild entered into a written contract with Finton Construction (“Finton”) in or about April 2011 for the construction of the Subject Property. On July 15, 2011, Finton, in turn, entered into a subcontract agreement (“Subcontract Agreement”) with Weather Masters Waterproofing, Inc, and its successor entity, Defendant WMW, Inc. (collectively “Defendants”). According to the Complaint, Schild, and Plaintiff as assignee, was a third-party beneficiary of the Subcontract Agreement. Further, Plaintiff alleges the Subcontract Agreement was for the supply and installation of waterproofing at the Subject Property. According to the Complaint, Defendants breached the Subcontract Agreement by failing to construct waterproofing at the Subject Property and, through defective materials and workmanship, caused water intrusion and property damage to the Subject Property.

Plaintiff’s Complaint alleges 3 causes of action as follows: (1) breach of contract, (2) negligence, and (3) breach of implied warranty.

Defendants now move for summary judgment, or, in the alternative, summary adjudication on each cause of action. Plaintiff opposes the motion.

Request for Judicial Notice 

Defendants request judicial notice of the following in support of their motion: 

 

  1. Plaintiff’s Complaint filed in this matter on August 8, 2020. (Exhibit 1)
  2. Defendant Weather Master Water Proofing, Inc’s Answer to the Complaint, filed in this matter on September 24, 2020. (Exhibit 2)
  3. Defendant WMW, Inc.’s Answer to the Complaint, filed in this matter on September 24, 2020. (Exhibit 3)

 

Defendants’ request is granted. The existence and legal significance of this document is a proper matter for judicial notice. (Evidence Code § 452(h).) However, the court may not take judicial notice of the truth of the contents of the documents.  (Herrera v. Deutsche Bank National Trust Co. (2011) 196 Cal.App.4th 1366, 1375.)  Documents are only judicially noticeable to show their existence and what orders were made.  The truth of the facts and findings within the documents are not judicially noticeable.  (Lockley v. Law Office of Cantrell, Green, Pekich, Cruz & McCort (2001) 91 Cal.App.4th 875, 885.)

 

Evidentiary Objections

 

Plaintiff objects to the declaration of Ben Moghaddam:

 

Objection 1-2: Overruled. Declarant, as president for Defendants, does not lack foundation. Not argumentative or vague.

Objection 3: Overruled. Declarant’s description of series of events is not vague or ambiguous.

Objection 4: Overruled. Declarant’s attestations of additional work orders submitted are not irrelevant as they directly relate to the need for repairs or additional work for the Subject Property.

Objection 5-6: Overruled. See objection 1-2.

Objection 7: sustained-in-part, as to “by subsequent contractors or trades,” and “that foot traffic and exposure to the elements,” Declaration lacks foundation and personal knowledge to speak to cause of any damage.

Objection 8-11: Overruled. See objection 4.

Objection 12: Sustained. Hearsay, referenced document lacks authentication.

Objection 13: Sustained, see objection 12.

Objection 14: overruled. Not vague or ambiguous or a misstatement of facts.

 

 

 

Discussion

 

I.                   Legal Authority

 

“The purpose of the law of summary judgment is to provide courts with a mechanism to cut through the parties' pleadings in order to determine whether, despite their allegations, trial is in fact necessary to resolve their dispute.”  (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843.)  CCP § 437c(a) provides:

A party may move for summary judgment in any action or proceeding if it is contended that the action has no merit or that there is no defense to the action or proceeding.  The motion may be made at any time after 60 days have elapsed since the general appearance in the action or proceeding of each party against whom the motion is directed or at any earlier time after the general appearance that the court, with or without notice and upon good cause shown, may direct….  The motion shall be heard no later than 30 days before the date of trial, unless the court for good cause orders otherwise.  The filing of the motion shall not extend the time within which a party must otherwise file a responsive pleading.

A motion for summary judgment may be granted “if all the papers submitted show that there is no triable issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.”  (CCP § 437c(c).) 

“The motion shall be supported by affidavits, declarations, admissions, answers to interrogatories, depositions, and matters of which judicial notice shall or may be taken.  The supporting papers shall include a separate statement setting forth plainly and concisely all material facts that the moving party contends are undisputed.  Each of the material facts stated shall be followed by a reference to the supporting evidence.  The failure to comply with this requirement of a separate statement may in the court’s discretion constitute a sufficient ground for denial of the motion.”  (CCP § 437c(b)(1); see also Cal. Rules of Court, rule 3.1350(c)(2) & (d).) 

In analyzing motions for summary judgment, courts must apply a three-step analysis: “(1) identify the issues framed by the pleadings; (2) determine whether the moving party has negated the opponent's claims; and (3) determine whether the opposition has demonstrated the existence of a triable, material factual issue.”  (Hinesley v. Oakshade Town Center (2005) 135 Cal.App.4th 289, 294 (Hinesley).)  CCP § 437c(p)(2) provides:

A defendant or cross-defendant has met his or her burden of showing that a cause of action has no merit if the party has shown that one or more elements of the cause of action, even if not separately pleaded, cannot be established, or that there is a complete defense to the cause of action.  Once the defendant or cross-defendant has met that burden, the burden shifts to the plaintiff or cross-complainant to show that a triable issue of one or more material facts exists as to the cause of action or a defense thereto.  The plaintiff or cross-complainant shall not rely upon the allegations or denials of its pleadings to show that a triable issue of material fact exists but, instead, shall set forth the specific facts showing that a triable issue of material fact exists as to the cause of action or a defense thereto.

The court must “view the evidence in the light most favorable to the opposing party and accept all inferences reasonably drawn therefrom.”  (Hinesley, 135 Cal.App.4th at p. 294; Dore v. Arnold Worldwide, Inc. (2006) 39 Cal.4th 384, 389 [Courts “liberally construe the evidence in support of the party opposing summary judgment and resolve doubts concerning the evidence in favor of that party.”].)  A motion for summary judgment must be denied where the moving party’s evidence does not prove all material facts, even in the absence of any opposition (Leyva v. Sup. Ct. (1985) 164 Cal.App.3d 462, 475 (Leyva)) or where the opposition is weak (Salasguevara v. Wyeth Labs., Inc. (1990) 222 Cal.App.3d 379, 384, 387). 

II.                Factual Summary

On July 15, 2011, Weather Masters entered into the Subcontract Agreement with Finton for “above and below Grade Waterproofing” at the Subject Property. (MF 2.)

The parties dispute when the waterproofing of the Subject Property was completed. (MF 3.) Defendants contend the waterproofing was originally completed “through mid-2015,” whereas Plaintiff contends Defendants submitted additional work authorization forms well into 2016. (MF 3-4.) Defendants also contend that in 2015, “a water intrusion problem was identified” at the Subject Property “by its owner Walter Schild and/or by the general contractor Finton Construction” and thereafter, “a series of email exchanges, site meetings and written proposals occurred concerning this issue...” (MF 4.) However, Defendants submit only the declaration of its president, Ben Moghaddam, in support of these claims. (Id.) Plaintiff contends it was not put on notice of any intrusion or defect as the “general contractor is not an agent of Plaintiff for purposes of establishing the running of the statute of limitations.” (Id.) Plaintiff also submits the declaration of Walter Schild in dispute of Defendants’ claims, stating he did not identify any water intrusion problems on the Subject Property. (Id.)

Defendants also contend further communications took place with Finton “regarding further waterproofing work to address the water intrusion issues,” but submit no evidence to substantiate the substance of these correspondences beyond work authorization forms. (MF 5-14.) Defendants point to a November 4, 2015 meeting with Finton at the Subject Property as also establishing notice for Plaintiff. (MF 7-8.)

It is also undisputed that James West Roofing and Waterproofing Consultant produced a report (“Report”) dated February 8, 2017, following a January 30, 2017 inspection of the Subject Property. (MF 15.) The Report was sent to Defendants by Schild in April 2018 along with a “Notice of Claim.” (Id.)

III.             Analysis

 

A.     Barring of Plaintiff’s Claims by Applicable Statutes of Limitations

 

Here, Defendants show Plaintiff filed its Complaint on August 18, 2020. (Motion, 4-5.) Defendants correctly point out Plaintiff alleges liability as a breach of a contract and implied warranties, as well under a general theory of negligence. (Id.)

Defendants correctly explain a breach of contract claim is governed by a four-year statute of limitations, pursuant to CCP § 337(a). (Motion, 6.) Defendants contend Plaintiff’s first cause of action is time barred as Plaintiff was put on “actual notice and constructive notice of damage at the [Subject Property] in or about 2015 or earlier, when a water intrusion problem was identified” and “on October 28, 2015,” when Defendants and Finton “had multiple email correspondences regarding waterproofing” of the Subject Property. (Id.) Defendants further contend that on November 5, 2015, Defendants “attended a meeting at [Subject Property] with representatives of Finton and the Property Owner to discuss the water intrusion issues and the exterior decks waterproofing.” (Id.) However, Defendants only introduce evidence of email correspondences between Defendants and Finton, not including any alleged “representatives” of Schild. (MF 8.) Defendants fail to provide sufficient factual evidence to show when any alleged identification of water intrusion problems took place, and fail to provide further evidence of any alleged correspondences between Defendants and Finton, as general contractor of Subject Property.

Defendants contend that since Plaintiff was allegedly put on notice “at least as early as October 28, 2015,” Plaintiff’s first cause of action is time-barred. (Motion, 7.) Defendants fail to point to any supporting authority for the contention that any conversations with a general contractor, here Finton, would necessarily provide constructive notice to Plaintiff, as assignee of Schild.

Next, Defendants contend Plaintiff’s second cause of action for negligence is also time-barred as it is governed by CCP § 338(b). (Motion, 8-9.) Defendants again point to the November 5, 2015 meeting as establishing constructive notice for Schild and his assignee, Plaintiff. (Id.)  Defendants also point to the Report prepared February 8, 2017, to establish the statute of limitations also bars Plaintiff’s negligence claim. (Motion, 9.)

Lastly, Defendants reiterate that any claims regarding a warranty are contract claims in nature, they are also governed by the four-year statute of limitations. (Motion, 9-10.) Therefore, Defendants contend the third cause of action is similarly time-barred as Plaintiff’s first cause of action. (Id.)

 

In opposition, Plaintiff contends “Defendants have failed to provide admissible evidence to support the undisputed accrual date for any cause of action alleged in the complaint.” (Opposition, 2.) Plaintiff also points to the dueling declarations submitted by the parties as necessarily creating triable issues of material fact, which obligate a denial of summary adjudication. (Id.; Opp., 7.) Plaintiff further contends the statute of limitations on any cause of action can only begin to run after a discovery of actual injury, and not the “mere threat of future harm.” (Opp., 5; citing United States Liab. Ins. Co. v. Haidinger–Hayes, Inc. (1970) 1 Cal.3d 586, 597.) Plaintiff thus contends “Defendants offer no admissible evidence concerning the date by which Plaintiff suffered damages because of a defect alleged regarding the waterproofing.” (Opp., 6.) Lastly, Plaintiff argues since the construction and installation on the Subject Property involved “multiple separate structures at issue on the property, and multiple separate assemblies/areas within those structures that Defendants waterproofed,” any time-barring of the statute of limitations for one alleged water intrusion does not “bar as a matter of law to Plaintiff’s claims for damages arising from other waterproofed areas on the Property.” (Opp., 7-8.) However, Plaintiff fails to elaborate or point to supporting authority for the contention that any discovery of alleged harm caused by defective or negligent work product on the Subject Property does not at least create constructive notice as to the entirety of the work done on the Subject Property.

 

In reply, Defendants first correctly point out Schild’s declaration undermines his own claims that he was unaware of any waterproofing issues for “more than 3 years prior to the complaint being filed,” since the Report was prepared and highlighted waterproofing issues over 3 years before the filing of the Complaint. (Reply, 2.) As such, Defendants correctly contend the Report the Report “put Mr. Schild, and thus Plaintiff as his supposed assignee, on actual and constructive notice of the water intrusion issues at the Property” on February 8, 2017, as the Report is dated, “which was more than 3 years prior to the Plaintiff’s Complaint being filed...” (Id.) As such, Defendants contend the second cause of action for negligence is time-barred because of the Report. (Reply, 3.)

 

Defendants further reiterate their contentions regarding the October 28, 2015 correspondences, the November 2015 meeting with Finton, and the April 14, 2016 “Disclaimer of Responsibility” letter as having put Plaintiff on notice and subsequently acting as a time-bar for Plaintiff’s first and third causes of action. (Reply, 3-4.)

 

Here, the undisputed facts show Schild, as owner of Subject Property and assignor of rights to Plaintiff, received a prepared Report dated February 8, 2017, highlighting the defective and/or negligent waterproofing issues of the Subject Property. Since August 18, 2020, is over three years past the date of the prepared Report, as a matter of law, the court finds Plaintiff’s second cause of action for negligence to be barred by the appropriate statute of limitations pursuant to CCP § 338(b).

 

Next, viewing the evidence submitted in the light most favorable to Plaintiff, the court finds that triable issues of material fact exist with regard to the first and third causes of action.

 

Specifically, triable issues of material fact exist as to whether Plaintiff was put on actual or constructive notice done to the Subject Property regarding any waterproofing issues before the lapse of the four-year statute of limitations. While Defendants point to an alleged meeting which took place, and attest to alleged conversations having taken place which provided notice to Plaintiff, competing declarations regarding the sequence of events necessarily ask this court to weight the credibility of evidence present, which this court cannot do at the summary adjudication junction.

 

Interpretation of a contract is a question of law “when it is based on the words of the instrument alone, when there is no conflict in the extrinsic evidence, or when a determination was made based on incompetent evidence.” [citation omitted] (Oakland-Alameda County Coliseum Authority v. Golden State Warriors, LLC (2020) 53 Cal.App.5th 807, 818-819.) However, “if interpreting the contract involves deciding between “conflicting extrinsic evidence concerning the meaning of ... contractual provisions,” or “divergent testimony about what the parties understood certain contractual provisions to mean,” then it is a factual question, not a legal one.” [citation omitted] (Id.)

 

Because interpretation of the Subcontract Agreement, and the notice provided to Plaintiff here of any breach and resulting damages to the Subject Property, also involves conflicting extrinsic evidence in this instance, the court finds several triable issues of material fact exist regarding when Plaintiff was made aware, or could have been made aware with reasonable due diligence, of any breach by Defendants and its resulting damages.

 

For these reasons, Defendants’ motion is denied as to the first and third causes of action.

 

Conclusion

Defendants’ motion is granted as to the second cause of action and otherwise denied. Defendants are to give notice.