Judge: Gary I. Micon, Case: 23CHCV00718, Date: 2024-03-05 Tentative Ruling
Case Number: 23CHCV00718 Hearing Date: March 5, 2024 Dept: F43
Dept. F43
Date: 3-5-24
Case # 23CHCV00718, Castaic Truck Stop, Inc. vs. David
Simon, et al.
Trial Date: N/A
DEMURRER
MOVING PARTY: Defendants David Simon dba ShanCor and
Virachai Pummarachai
RESPONDING PARTY: Plaintiff Village Fuel Stop, Inc., dba Castaic
Truck Stop
RELIEF REQUESTED
Demurrer to the Complaint
·
1st Cause of Action for Breach of
Contract
·
2nd Cause of Action for Negligence
·
3rd Cause of Action for Professional
Negligence
RULING: Sustained in part and overruled in part
SUMMARY OF ACTION
In September 2021, Defendant David Simon dba ShanCor
(ShanCor) entered into a contract with “Village Fuel Shop,” which was owned by
Vazgen Khirmian, to repair some fuel tanks for Village Fuel Shop. Khirmian and
Peter Pummarachai, the project manager for ShanCor, signed the contract. Defendants
represented to Plaintiff that the work was completed. Plaintiff filed this action
after discovering that the work performed by ShanCor on the property was allegedly
incomplete and unsatisfactory.
On August 1, 2023, Plaintiff filed its First Amended
Complaint (FAC) with three causes of action: breach of contract, negligence,
and professional negligence.
Defendants filed their demurer on October 18, 2023. Plaintiff
filed its opposition on February 21, 2024. Defendants filed their reply on February
27, 2024.
ANALYSIS
Defendants demur to the First Cause of Action for Breach of
Contract on the basis that Plaintiff is not the party to the contract, nor is
Defendant Pummarachai. Next, Defendants demur to the Second Cause of Action for
Negligence on the basis that tort remedies for negligence are not permitted for
a breach of contract outside of certain circumstances, and on the basis that
Defendant Pummarachai owes no duties to Plaintiff. Finally, Defendants demur to
the Third Cause of Action for Professional Negligence on the basis that tort
remedies for professional negligence are not permitted for a breach of contract
outside certain circumstances; there is no allegations that the claims are
based on the work of a design professional; and the contract does provide for
engineering services within its defined scope of work.
A demurrer is an objection to a pleading, the grounds for
which are apparent from either the face of the complaint or a matter of which
the court may take judicial notice. (CCP § 430.30(a); see also Blank v. Kirwan (1985) 39 Cal.3d 311,
318.) The purpose of a demurrer is to challenge the sufficiency of a pleading
“by raising questions of law.” (Postley
v. Harvey (1984) 153 Cal.App.3d 280, 286.) “In the construction of a
pleading, for the purpose of determining its effect, its allegations must be
liberally construed, with a view to substantial justice between the parties.” (CCP
§ 452.) The court “ ‘ “treat[s] the demurrer as admitting all material facts
properly pleaded, but not contentions, deductions or conclusions of fact or law…”
’ ” (Berkley v. Dowds (2007) 152
Cal.App.4th 518, 525.) In applying these standards, the court liberally
construes the complaint to determine whether a cause of action has been stated.
(Picton v. Anderson Union High School
Dist. (1996) 50 Cal.App.4th 726, 733.)
For the First Cause of Action, Defendants argue that
Plaintiff is not a real party in interest to the contract. Defendants argue
that this is because Khirmian signed the contract. However, on the face of the
contract, it appears that Khirmian was signing the contract as the owner/agent
for Village Fuel Shop. Village Fuel Shop, which appears to be a fictitious name
for Plaintiff, was the party to the contract, not Khirmian as owner.
Furthermore, the FAC identifies Village Fuel Stop, dba Castaic Truck Stop as
the Plaintiff.
Next, Defendants argue that Pummarachai was not a party to
the contract and therefore does not owe duties under the contract. Pummarachai
was signing the contract as the project manager/agent of ShanCor. There are no
facts pled in the FAC that Pummarachai was personally a party to the contract.
Defendants’ demurrer to the First Cause of Action is
sustained for Defendant Pummarachai only, and overruled for ShanCor. Plaintiff
is given leave to amend.
For the Second and Third Causes of Action for Negligence and
Professional Negligence, tort remedies for negligence are not permitted for a
breach of contract outside of certain circumstances. (See Erlich v. Menezes
(1999) 21 Cal.4th 543.) Plaintiff argues in its opposition that it may maintain
a negligence cause of action where there has been negligence in addition to a
breach of contract. However, Plaintiff does not cite any authority to support
this idea. The case Plaintiff does cite, Erlich, appears to stand for
the opposite.
“‘Contract damages are generally limited to those within the
contemplation of the parties when the contract was entered into or at least
reasonably foreseeable by them at that time; consequential damages beyond the
expectation of the parties are not recoverable. [Citations.] This limitation on
available damages serves to encourage contractual relations and commercial
activity by enabling parties to estimate in advance the financial risks of
their enterprise.’” (Erlich, supra, at 550, citing Applied
Equipment Corp. v. Litton Saudi Arabia Ltd. (1994) 7 Cal.4th 503, 515.) A
mere negligent breach of contract is not sufficient to allow for a separate negligence
cause of action. (Id. at 552.)
Plaintiff cannot maintain separate causes of action for
negligence against Defendant ShanCor where Plaintiff has alleged a breach of
contract against ShanCor, unless Plaintiff can plead that an exception would
apply. Theoretically, Plaintiff could have negligence causes of action against
Defendant Pummarachai since he was not a party to the contract, but Plaintiff’s
FAC does not have any facts indicating what specific actions that Pummarachai
himself took as an individual that may have been negligent. Though since he
would have been acting in his capacity as an agent of ShanCor, it is unlikely
that he would have been individually negligent.
The Court sustains Defendants’ demurrer to Plaintiff’s
Second and Third Causes of Action with leave to amend.
Defendants’
demurrer is sustained to Plaintiff’s First Cause of Action for Defendant
Pummarachai only, and is sustained for Plaintiff’s Second and Third Causes of
Action for both Defendants. The demurrer to the First Cause of Action is
overruled for Defendant ShanCor.
Moving party to give notice.