Judge: H. Jay Ford, III, Case: 22SMCV00834, Date: 2023-02-02 Tentative Ruling
Case Number: 22SMCV00834 Hearing Date: February 2, 2023 Dept: O
Case Name:
Advanced Framing Structures, Inc. v. United El Segundo, Inc.
|
Case No.: 22SMCV00834 |
Complaint Filed: 6-6-22 |
|
Hearing Date: 2-2-23 |
Discovery C/O: None |
|
Calendar No.: 9 |
Discover Motion C/O: None |
|
POS: OK |
Trial Date: None |
SUBJECT: DEMURRER WITHOUT MOTION TO
STRIKE TO Cross-COMPLAINT
MOVING
PARTY: Plaintiff/Cross-Defendant
Advanced Framing Structures, Inc.
RESP.
PARTY: Cross-Complainants United
El Segundo, Inc., City Constructors, Inc. d/b/a Reaume Richardson and Rapid
Gas, Inc.
TENTATIVE
RULING
Plaintiff/Cross-Defendant
Advanced Framing Structures, Inc.’s Demurrer to Cross-Complaint of City
Constructors, Inc. d/b/a Reaume Richardson is SUSTAINED WITHOUT LEAVE TO AMEND to
the 2nd cause of action for equitable indemnification and OVERRULED
as to the 1st cause of action for breach of contract, 3rd
cause of action for express indemnification and 4th cause of action
for negligence.
1st
cause of action for breach of contract—OVERRULE. Advanced demurs to the 1st cause
of action for breach of written contract on grounds that the terms of the
contract are not pled in hace verba or by material intendment and effect. The terms of the agreement, Advanced’s breach
of the agreement, City Constructors, Inc.’s performance and City Constructors,
Inc.’s damges are sufficiently alleged at ¶¶7-17.
2nd
cause of action for equitable indemnification—SUSTAIN WITHOUT LEAVE TO AMEND. Advanced demurs to the 2nd cause
of action for equitable indemnity on grounds that City Constructors, Inc. fails
to allege that Advanced is a joint tortfeasor to a third party. City Constructors, Inc. alleges that Advanced
performed wood framing work on a work of improvement owned by United El
Segundo, Inc. pursuant to a subcontract and it performed the work on United El
Segundo, Inc.’s work of improvement negligently. See Cross-Complaint, ¶¶7-21.
However, an essential element of
implied equitable indemnity is the indemnitee’s potential to liability to a
third party as a result of the indemnitor’s negligence. CACI 3801 (implied equitably indemnity
requires that (1) indemnitee “may be” required to pay liability to third party
and (2) that indemnitor’s conduct be a substantial factor in causing
third-party plaintiff’s harm); see also Yamaha Motor Corp. v. Paseman
(1990) 219 Cal.App.3d 958, 964 ("Unless the prospective indemnitor and
indemnitee are jointly and severally liable to the plaintiff there is no basis
for indemnity.") Indemnification is
generally understood to apply to third party liability and not direct
liability, the exception being in cases of express contractual indemnification
where the provision could be reasonably be interpreted to include direct liability
to the plaintiff. See Hot Rods, LLC
v. Northrop Grumman Systems Corp. (2015) 242 Cal.App.4th 1166, 1179.
Here, City Constructors, Inc. only
alleges that it was forced to hire separate subcontractors to complete and
correct Advanced’s scope of work. See
Cross-Complaint, ¶20. City Constructors,
Inc. does not allege that it is potentially liable to United El Segundo, Inc.
or any other third party due to Advanced’s negligence on the work of
improvement. There is also no allegation
that there is a pending legal action by United El Segundo, Inc. or any other
third against City Constructors for negligence in connection with the work of
improvement. As such, City Constructors fail
to allege a cause of action for equitable indemnification.
Finally,
City Constructor does not make any showing or claim that it can allege
existence of a potential third-party claim against it that would support an
equitable indemnification claim. The burden is on Plaintiff to establish that the defect is reasonably
capable of cure with leave to amend. See Hendy v. Losse (1991) 54 Cal.3d 723, 742.
3rd
cause of action for express contractual indemnification—OVERRULE. As with the 2nd cause of
action for equitable indemnification, Advanced demurs to the 3rd cause
of action for express contractual indemnity on grounds that indemnification
requires that City Constructors allege a third-party claim against it. However, express contractual indemnification does
not necessarily require a third party claim. “Although indemnity generally
relates to third party claims, this general rule does not apply if the parties
to a contract use the term ‘indemnity’ to include direct liability as well as
third party liability. Each indemnity
agreement is interpreted according to the language and contents of the contract
as well as the intention of the parties as indicated by the contract. When indemnity is expressly provided by
contract, the extent of the duty to indemnify must be determined from the
contract itself.” Hot Rods, LLC v.
Northrop Grumman Systems Corp. (2015) 242 Cal.App.4th 1166, 1179.
Depending on the parties’ intent
and the language of the express indemnification provision, an indemnity clause
can reasonably be interpreted to encompass first party claims. Id. at 1179-1180 (parties’ express
indemnification provision obligated indemnitee to pay for both first party (indemnitee)
and third party claims). An express
indemnification provision was interpreted as covering direct, first party
claims by the indemnitee where (1) the indemnification provision failed to
specify that only third party claims were covered; (2) the express
indemnification provision covered “any claims, demands, fees, fines,
liability, damages, costs, losses, or other expenses” was deemed broad enough
to encompass first party claims; (3) “claims” was defined as “any claim or
demand by any Person for any alleged liabilities”; and (4) “person” was defined
as “any person, employee, individual, corporation….” Id. at 1181-1182.
Advanced fails to establish that
the express indemnification cannot reasonably interpreted to cover first party,
direct claims by City Constructor for its own damages due to Advanced’s
negligence. The portion of the express
indemnification provision pled in the complaint requires Advanced to
“indemnify, defend, hold harmless” City Constructor “from any
loss…damage or liability for…damage or destruction to any property, arising out
of or in connection with any actual or alleged act or omission of”
Advanced. See Cross-Complaint,
¶23.
Based on the alleged excerpt, City
Constructor’s interpretation of the clause as encompassing direct, first party
claims is reasonable and must be accepted on demurrer. See Rutherford Holdings, LLC v. Plaza Del
Rey (2014) 223 Cal.App.4th 221, 229 (plaintiff who failed to allege its own
“reasonable interpretation” should be given opportunity to amend complaint to
do so); Aragon-Haas v. Family Security Ins. Services, Inc. (1991) 231
Cal.App.3d 232, 239 (general demurrer to complaint admits not only contents of
the instrument but also any pleaded meaning to which the instrument is
reasonably susceptible and “[s]o long as the pleading does not place a clearly
erroneous construction upon the provisions of the contract, in passing upon the
sufficiency of the complaint, we must accept as correct plaintiff's allegations
as to the meaning of the agreement.”)
However, Advanced is not precluded
from challenging the reasonableness of this interpretation later based on the
full agreement and evidence of the parties’ intent. For now, at the demurrer stage, City
Constructor has pled a claim for express equitable indemnification.
City Constructor also sufficiently
alleges the terms of the agreement by material intended and effect. The text of the relevant clause is alleged at
¶23 and City Constructor alleges it is part of the Advanced Subcontract. The terms of the Advanced Subcontract is
alleged at ¶¶7-8.
4th cause of action
for negligence—OVERRULE. Advanced
argues the negligence claim fails to sufficiently identify the negligent
conduct, i.e. what work was deficient, how the work was deficient and what
property damage did the deficient work cause.
“Ordinarily, negligence may be alleged in general terms, without specific
facts showing how the injury occurred, but there are limits to the generality
with which a plaintiff is permitted to state his cause of action, and the
plaintiff must indicate the acts or omissions which are said to have been
negligently performed. He may not recover upon the bare statement that the
defendant's negligence has caused him injury.”
Berkley v. Dowds (2007) 152 Cal.App.4th 518, 527.
The negligence claim is
sufficiently pleaded. City Constructor
alleges more than a bare statement that Advanced’s negligence caused it
injury. City Constructor alleges that
Advanced provided wood framing services on the project, the services were
performed without reasonable care, the negligently performed wood framing
caused damage to the areas of the Project outside of Advanced’s scope of
work. See Cross-Complaint, ¶¶8-10,
29-31. As a result of Advanced’s
negligence, City Constructor was forced to hire other subcontractors to replace
and repair the damage done by Advanced’s work.
Id. at ¶¶25, 27.