Judge: Holly J. Fujie, Case: 22STCV14135, Date: 2023-04-24 Tentative Ruling
Case Number: 22STCV14135 Hearing Date: April 24, 2023 Dept: 56
SUPERIOR
COURT OF THE STATE OF CALIFORNIA
FOR
THE COUNTY OF LOS ANGELES - CENTRAL DISTRICT
|
Plaintiff, vs. CITY OF MONTEREY PARK, et al., Defendants. |
|
[TENTATIVE] ORDER RE: DEMURRER Date:
April 24, 2023 Time: 8:30 a.m. Dept. 56 |
MOVING PARTY: Defendant City of Monterey Park
(“Moving Defendant” or the “City”)
RESPONDING PARTY: Plaintiff
BACKGROUND
This action arises out of a dispute over the
abatement of a public nuisance on real property (the “Property”) owned by
Plaintiff. The currently operative second
amended complaint (the “SAC”) alleges: (1) declaratory relief; (2) breach of
contract – Development Agreement; (3) breach of implied covenant of good faith
and fair dealing – Development Agreement; (4) breach of contract – Settlement
Agreement; (5) breach of implied covenant of good faith and fair dealing-
Settlement Agreement; and (6) declaratory relief regarding ability to foreclose
on deeds of trust.
In relevant part, the SAC alleges: On
December 31, 2015, Moving Defendant as attorney for the People of the State of
California (the “People”) initiated an abatement action in the case styled as The
People of the State of California, ex rel., Mark D. Hensley, City Attorney for
the City of Monterey Park v. Center Int’l Investments, Inc., LASC Case No.
BC605788 (the “Abatement Action”). (SAC
¶ 12.) On April 25, 2017, Plaintiff
and the People entered into a settlement agreement (the “Settlement Agreement”)
to resolve the Abatement Action. (SAC ¶
13, Exhibit A.) The Settlement Agreement
required Plaintiff to take steps to permanently abate the nuisance on the
Property, including slope abatement. (Id.) The Settlement Agreement was subsequently
amended twice to alter its timeline and objectives. (See id.) Under
the Settlement Agreement, permanent slope stabilization efforts could take one
of two possible forms, “Plan A” and “Plan B.”
(SAC ¶ 15.) Plan A required
the construction of residential homes and required approvals (“Entitlements”)
from the City. (SAC ¶ 16.) Plan B did not include the development of
residential homes and was required to be completed in 2022 regardless of the approval
of Plan A. (SAC ¶ 17.)
Plaintiff began submitting applications for the
Entitlements on or around January 13, 2020.
(SAC ¶ 18.) Plaintiff and Moving
Defendant (the “Parties”) thereafter entered into a development agreement (the
“Development Agreement”). (SAC ¶ 19,
Exhibit B.) The City Council authorized Moving
Defendant to enter into the Development Agreement on June 16, 2021. (FAC ¶ 20.)
The Development Agreement became effective July 17, 2021. (SAC ¶ 21.)
The Development Agreement included an indemnification provision that
required Plaintiff to indemnify the City in litigation arising out of the slope
abatement project. (SAC ¶ 24.) The Development Agreement also included a
cooperation clause that required the Parties to cooperate in the defense of any
third-party legal challenge to the Development Agreement. (SAC ¶ 25.)
On or about July 21, 2021, litigation was
filed to challenge Plaintiff’s development of the Property pursuant to the
California Environmental Quality Act (“CEQA”) (the “CEQA Litigation”). (SAC ¶ 26.)
On or around July 21, 2021, the City demanded indemnification for the
CEQA Litigation from Plaintiff pursuant to both the Development and Settlement
Agreements. (See SAC
¶ 27.)
On August 10, 2021, the Parties entered into
a Joint Defense Agreement regarding the CEQA Litigation. (SAC ¶ 28.)
On or around September 20, 2021, the Parties disagreed on the scope of
the CEQA Litigation and Moving Defendant stopped discussing the matter with
Plaintiff. (SAC ¶ 30.) The Parties’ relationship thereafter
deteriorated, which impacted the pace of the CEQA litigation and delayed
Plaintiff’s ability to defend its Entitlements.
(SAC ¶ 31.) On October 13, 2021,
Moving Defendant informed Plaintiff that it would assume control over its
separate settlement negotiations in the CEQA Litigation. (SAC ¶ 32.)
On October 13, 2021, Moving Defendant issued a notice of default (the
“NOD”) pursuant to the Settlement Agreement and assumed control over the
development of the Property. (See SAC
¶ 172.)
Moving Defendant filed a demurrer (the
“Demurrer”) to the FAC on the ground that the FAC fails to state facts
sufficient to constitute a cause of action.
REQUEST FOR JUDICIAL NOTICE
Moving Defendant’s
Request for Judicial Notice is GRANTED.
Plaintiff’s Request for Judicial Notice is GRANTED. While the Court takes judicial notice of the
Parties’ submitted documents, it does not take judicial notice of the truth of all matters stated therein. (See Ragland v. U.S. Bank National Assn. (2012)
209 Cal.App.4th 182, 193-94.)
DISCUSSION
Meet and Confer
The meet and confer requirement has been met.
Legal Standard
A demurrer tests the sufficiency of a
complaint as a matter of law. (Durell v. Sharp Healthcare (2010) 183
Cal.App.4th 1350, 1358.) The court
accepts as true all material factual allegations and affords them a liberal
construction, but it does not consider conclusions of fact or law, opinions,
speculation, or allegations contrary to law or judicially noticed facts. (Shea
Homes Limited Partnership v. County of Alameda (2003) 110 Cal.App.4th 1246,
1254.) With respect to a demurrer, the
complaint must be construed liberally by drawing reasonable inferences from the
facts pleaded. (Rodas v. Spiegel (2001) 87 Cal.App.4th 513, 517.) A demurrer will be sustained without leave to
amend if there exists no reasonable possibility that the defect can be cured by
amendment. (Blank v. Kirwan (1985) 39 Cal.3d 311, 318.)
First and Second Causes of Action
As a preliminary matter, on December 15,
2022, the Court overruled Moving Defendant’s demurrer to the first and second
causes of action alleged in the first amended complaint (the “FAC”). The Court therefore OVERRULES the current Demurrer
to the first and second causes of action alleged in the SAC.
Third Cause of Action
Every contract contains an implied covenant
of good faith and fair dealing providing that no party to the contract will do
anything that would deprive another party of the benefits of the contract. (Wilson v. 21st Century Ins. Co. (2007)
42 Cal.4th 713, 720.) The implied
covenant protects the reasonable expectations of the contracting parties based
on their mutual promises. (Carma Developers (Cal.), Inc. v. Marathon Development
California, Inc. (1992) 2 Cal.4th 342, 373-74.) In essence, the covenant is implied as a
supplement to the express contractual covenants, to prevent a contracting party
from engaging in conduct which (while not technically transgressing the express
covenants) frustrates the other party’s rights to the benefits of the
contract. (Racine & Laramie, Ltd.
v. Department of Parks & Recreation (1992) 11 Cal.App.4th 1026,
1031-32.)
The general rule of exhaustion of
administrative remedies in California is that where an administrative remedy is
provided by statute, relief must be sought from the administrative body and
this remedy exhausted before the courts will act. (Los Globos Corp. v. City of Los Angeles
(2017) 17 Cal.App.5th 627, 632.) There
are three exceptions to the rule of exhaustion: (1) an exception where the
administrative agency does not provide an adequate remedy; (2) the remedy does
not follow the requirements of due process; and (3) where it is futile to
pursue a remedy. (Id. at 633.)
The SAC alleges that Moving Defendant
breached the implied covenant of good faith dealing by failing to issue
Plaintiff a necessary permit and using the permit as the justification for
taking control of the Property. (See SAC
¶¶ 165-66.)
The Court finds that the SAC includes
allegations that the FAC lacked which are sufficient to state the third cause
of action under Mammoth Lakes Land Acquisition, LLC v. Town of
Mammoth Lakes 191 Cal.App.4th 435, 457 (“Mammoth
Lakes”). The Mammoth Lakes court
found that the plaintiff was not required to exhaust its administrative
remedies before filing a civil action because the gravamen of its claims was
the defendant city’s failure to proceed under a development contract, rather
than an administrative decision to deny a building application. (See Mammoth Lakes, supra, 191
Cal.App.4th at 456.) As a result, there
was no administrative process that enabled the plaintiff to seek remedies. (Id.)
The third cause of action arises out of Moving
Defendant’s allegedly bad faith conduct that it used as justification for
denying Plaintiff its rights under the Development Agreement. The failure to issue permits in and of itself
is not the basis for the cause of action. The Court therefore OVERRULES the Demurrer to
the third cause of action.
Fourth through Sixth Causes of Action
The SAC alleges that Moving Defendant
breached the Settlement Agreement by delaying and improperly processing
Plaintiff’s permit applications, subsequently seizing control of the Property,
and failing to implement proper safety measures after it took control of the
Property. (See SAC ¶¶ 71-72.)
The Second Amendment to the
Settlement Agreement includes a provision which states:
“In the event that Plan B is not underway by the deadline
set forth in the Amended Project Schedule, CITY may (1) enter the Property,
abate the Nuisance, and/or complete Plan B, and (2) foreclose on the Liens
recorded in its favor pursuant to Section 2(A)(i) to recover the cost of
completing Plan B. In the event that the actual completion cost is less than
the amounts recovered by CITY through the foreclosure of the Liens, CITY will
return all sums recovered exceeding the actual cost of completion of Plan B to
CII.” (FAC ¶ 169.)
The
SAC sufficiently alleges that Moving Defendant breached the Settlement
Agreement. In addition, the Court is not
persuaded by Moving Defendant’s argument that it is not a party to the
Settlement Agreement. Although the City
Entered into the Settlement Agreement on behalf of the People, the document
separately identifies Moving Defendant and the People and imposes duties
directly on Moving Defendant. Further,
the Settlement Agreement does not preclude Plaintiff from filing a separate
action for breach. The statutory
procedure for enforcing settlement agreements under California Code of Civil
Procedure section 664.6 is not exclusive. It is merely an expeditious,
valid alternative statutorily created. (Nicholson
v. Barab (1991) 233 Cal.App.3d 1671, 1681.) Settlement agreements may also be enforced by
motion for summary judgment, by a separate suit in equity or by amendment of
the pleadings to raise the settlement as an affirmative defense. (Id.)
The Court therefore OVERRULES the Demurrer to the fourth through sixth
causes of action.
Moving Defendant is ordered to
file an answer within 20 days of the date of this order.
Moving
party is ordered to give notice of this ruling.
Parties
who intend to submit on this tentative must send an email to the Court at
SMC_DEPT56@lacourt.org as directed by the instructions provided on the court
website at www.lacourt.org. If the department does not receive an email
and there are no appearances at the hearing, the motion will be placed off calendar.
Dated this 24th day of April 2023
|
|
|
|
|
Hon. Holly J.
Fujie Judge of the
Superior Court |