Judge: James C. Chalfant, Case: 21STCP01969, Date: 2023-05-25 Tentative Ruling
Case Number: 21STCP01969 Hearing Date: May 25, 2023 Dept: 85
NASA Services, Inc., et al. vs. City of
Montebello, et al., 21STCP01969
Tentative decision on petition
for writ of mandate: denied
Petitioners
NASA Services and 1701 Gage Road, LLC (collectively, “NASA”) seeks a writ of
mandate compelling Respondents City of Montebello (“City”) and City Council of
the City of Montebello (“City Council”) (collectively, “City”) to grant NASA’s
conditional use permit (“CUP”) application.
The
City opposes. Intervenors Gage Avenue Investment, LLC, Mater Montebello, 1717
Gage Road, LLC, Hermark 25, LLC, Hermark Investment Company, 901 Union Street,
LLC, R/G/G/L Corp., Peter Bacci, in Trust as Trustee of the Bacci Living Trust,
P.B. Industrial Holdings, LLC, and Greenwood Ave Properties, LLC separately
oppose in a joint opposition.
The
court has read and considered the moving papers, oppositions, and reply, and renders
the following tentative decision.
A. Statement of
the Case
1. The Petition
Petitioners
commenced this action on June 21, 2021, alleging causes of action for (1)
traditional and administrative mandamus, (2) denial of substantive due process,
(3) denial of equal protection, and (4) declaratory relief. The verified Petition alleges in pertinent
part as follows.
NASA’s
operation is located at 1701 Gage Road, Montebello, California (“Project
site”). The Project site is located in
the City’s M-2 (Heavy Manufacturing) Zone with a General Plan land use
designation of Industrial. The Project
Site is comprised of approximately 1.07 acres or 45,746 square feet (“sf”). The property is currently improved with an
1,856 sf wood frame and stucco office building, a 3,500 sf metal building, 240 sf
of paved parking/drive aisles, and approximately 6,000 sf of landscaping.
On May 9, 1994, the City’s Planning Commission (“Planning
Commission”) approved CUP 2-94 to allow for the establishment of a glass
recycling plant at the Project site. NASA
currently uses the Project site as a collection truck and roll-off container
storage yard. Approximately 30
collection trucks and 60 roll-off bins can be stored on the site at any
time. The facility operates between 3:00
a.m. – 5:00 p.m., Monday through Sunday, and is typically staffed by one to two
employees.
On
October 26, 2020, NASA applied to the City for a CUP to allow the operation of
a solid waste transfer station on the Project site. NASA seeks a solid waste transfer station to process
and transfer of up to 750 tons per day of municipal solid waste. Pursuant to the Project, the existing
structures will be demolished and a 26,940 sf building will be erected in its
place.
NASA’s
CUP application is considered a project under CEQA. City staff recommended a CEQA initial study
to consider the Project’s potential impacts on the environment. The initial study concluded that the Project
would have less than significant effects on the environment. A negative declaration was prepared which
analyzed the potential environmental impacts and found that the Project does
not have the potential to result in any significant environmental impacts.
At
the January 5, 2021 Planning Commission hearing on the CUP application and the
negative declaration, City staff presented the staff report with a
recommendation of approval and adopt the negative declaration. The staff report provided a thorough review
of the Project’s impacts, and the Project’s compliance with the applicable provisions
of the City’s code and general plan. The
Planning Commission disregarded the evidence presented by the staff and denied the
CUP application.
On
January 13, 2021, NASA timely filed an appeal pursuant to Montebello Municipal
Code (“MMC”) section 17.78.070. NASA sought
the City Council’s review to overturn the Planning Commission’s denial. On February 24, 2021, the City Council
conducted a public hearing and received oral and written presentations from
NASA and others. The City’s staff again recommended
approval of the Project, citing the lack of any significant environmental
impacts and the Project’s compliance with the MMC.
The
City Council denied the appeal and directed City staff and the City Attorney to
prepare a resolution denying NASA’s request and upholding the Planning Commission’s
decision (the “Resolution”). The Resolution
includes unsupported determinations that the Project (1) is not consistent with
the City’s General Plan; (2) fails to meet the findings required by MMC
sections 17.70.070 and 17.70.130; and (3) the initial study fails to properly
and adequately study, analyze, and address the Project’s significant
environmental impacts. In adopting the
Resolution, the City Council disregarded the evidence and the incontestable
determination of MMC compliance provided by the City staff.
2.
The Complaint-in-Intervention
On
October 4, 2022, Intervenors filed a Complaint-in-Intervention alleging in
pertinent part as follows.
The
Project site is in an M-2 (Heavy Manufacturing) Zone. The Project calls for demolition of an
existing structure on the Project site and erection of (1) a 25,250 sf solid
waste transfer station building that can process and transfer 1,500 tons per
day, (2) 1,530 sf of offices, and (3) a 160 sf house. The City’s initial study found that the
Project would have less than significant impacts on the environment, and a
negative declaration was prepared.
At
the Planning Commission’s hearing on January 5, 2021, Intervenors and other
neighboring property owners testified against the Project. They expressed concern that the Project would
have adverse impacts on adjacent properties and that the negative declaration
was insufficient under CEQA. The Planning
Commission voted to deny the requested entitlements for the Project.
NASA
appealed the denial. At the City Council
hearing on February 24, 2021, Intervenors and other neighboring property owners
again testified against the land use entitlements for the Project. After full consideration of the appeal, the
City Council directed staff and the City Attorney to prepare the Resolution
which the City Council then adopted. Intervenors
request that the court deny NASA’s Petition.
3. Course of Proceedings
On
June 22, 2021, Petitioners served the City with the Petition and Summons.
On
August 31, 2021, the City filed an Answer.
On
September 28, 2021, the court ordered all damages claims stayed.
On
September 15, 2022, the court granted Intervenors’ motion to intervene. Intervenors filed their Complaint-in-Intervention
and Answer on October 4, 2022.
B. Standard of Review
A party may seek to set aside an agency decision by
petitioning for either a writ of administrative mandamus (CCP §1094.5) or
traditional mandamus (CCP §1085). A
petition for traditional mandamus is appropriate in all actions “to compel the
performance of an act which the law specially enjoins as a duty resulting from
an office, trust, or station....” CCP
§1085. CCP section 1094.5 is the
administrative mandamus provision which structures the procedure for judicial
review of adjudicatory decisions rendered by administrative agencies. Topanga Ass’n for a Scenic Community v.
County of Los Angeles, (“Topanga”) (1974) 11 Cal.3d 506, 514-15. The decision on issuance of a CUP is a quasi-judicial,
administrative decision governed by CCP section 1094.5. See Jacobson v. County of Los
Angeles, (1977) 69 Cal. App. 3d 374, 391.
CCP section 1094.5 does not on its face specify which cases
are subject to independent review, leaving that issue to the courts. Fukuda v. City of Angels, (1999) 20
Cal.4th 805, 811. Instead, that issue
was left to the courts. In cases other
than those requiring the court to exercise its independent judgment, the
substantial evidence test applies. CCP
§1094.5(c). Land use decisions do not
typically involve vested rights requiring independent review. See PMI Mortgage Insurance Co. v.
City of Pacific Grove, (1981) 128 Cal.App.3d 724, 729. The granting of a permit or variance does not
infringe on the fundamental vested rights of adjoining property owners. Bakman v. Dept. of Transportation,
(1979) 99 Cal.App.3d 665, 689-90. There
is no vested right in the enforcement of a zoning ordinance. Hermosa Beach Stop Oil Coalition v. City
of Hermosa Beach, (2001) 86 Cal.App.4th 534, 552. Therefore, the court’s review in this case is
for substantial evidence.
“Substantial evidence” is relevant evidence that a
reasonable mind might accept as adequate to support a conclusion (California
Youth Authority v. State Personnel Board, (“California Youth Authority”)
(2002) 104 Cal.App.4th 575, 585) or evidence of ponderable legal significance,
which is reasonable in nature, credible and of solid value. Mohilef v. Janovici, (1996) 51
Cal.App.4th 267, 305, n.28. An
agency’s reliance “upon the opinion of its staff in reaching decisions … has
been recognized as constituting substantial evidence.” Browning-Ferris Industries v. City Council,
(1986) 181 Cal.App.3d 852, 866.)
Substantial evidence may include statements of neighbors “if they are
based on relevant personal observations or involve ‘nontechnical’ issues.” Bowman v. City of Berkeley, (“Bowman”)
(2004) 122 Cal.App.4th 572, 583; see also McCoy v. Gustafson,
(2009) 180 Cal.App.4th 56, 100 (applying Bowman’s lay opinion standard for a nuisance claim).
The trial court considers all evidence in the administrative
record, including evidence that detracts from evidence supporting the agency’s
decision. California Youth Authority,
supra, 104 Cal.App.4th at 585. “‘[T]he
test of substantiality must be measured on the basis of the entire
record, rather than by simply isolating evidence which supports the board and
ignoring other relevant facts of record which rebut or explain that evidence.’
[Citations.]” Martori Brothers
Distributors v. Agricultural Labor Relations Bd., (1981) 29 Cal.3d 721, 727
(italics added.)”; Gerawan Farming,
Inc. v. Agric. Labor Relations Bd., (2018) 23 Cal.App.5th 1129, 1162. The standard is met if there is relevant
evidence in the record which a reasonable mind might accept in support of the
findings. Id. (citation
omitted). If there is a plausible basis
for the decision, the fact that contrary findings may be equally reasonable, or
even more so, is of no moment. Id.
The agency’s decision must be based on the evidence
presented at the hearing. Board of
Medical Quality Assurance v. Superior Court, (1977) 73 Cal.App.3d 860,
862. The hearing officer is only
required to issue findings that give enough explanation so that parties may
determine whether, and upon what basis, to review the decision. Topanga, supra, 11 Cal.3d at
514-15. Implicit in CCP section 1094.5
is a requirement that the agency set forth findings to bridge the analytic gap
between the raw evidence and ultimate decision or order. Topanga, 11 Cal.3d at 515.
An agency is presumed to have regularly performed its
official duties (Evid. Code §664), and the petitioner therefore has the burden
of proof. Steele v. Los Angeles
County Civil Service Commission, (1958) 166 Cal.App.2d 129, 137. “[T]he burden of proof falls upon the party
attacking the administrative decision to demonstrate wherein the proceedings
were unfair, in excess of jurisdiction or showed prejudicial abuse of
discretion.” Afford v. Pierno,
(1972) 27 Cal.App.3d 682, 691. The
petitioner has the burden of demonstrating that the agency’s findings are not
supported by substantial evidence in light of the whole record. Young v. Gannon, (2002) 97 Cal.App.4th
209, 225.
C. Governing Law
1.
Govt. Code
The legislative body of
a city or county may, by ordinance, create and establish either a board of
zoning adjustment, or the office of zoning administrator, or both. Government Code (“Govt. Code”) §65900. It may also, by ordinance, create and
establish a board of appeals. Govt. Code
§65900.
If a city or county
establishes a board of zoning adjustment, that board shall hear and decide
applications for conditional uses or other permits when the zoning ordinance
provides therefor and establishes criteria for determining those matters, and
applications for variances from the terms of the zoning ordinance. Govt. Code §65901(a). In the event that neither a board of zoning
adjustment or the office of a zoning administrator has been created and established,
the planning commission shall exercise all of the functions and duties of said
board or said administrator. Govt. Code
§65902.
A board of appeals, if
one has been created and established by local ordinance, shall hear and
determine appeals from the decisions of the board of zoning adjustment or the
zoning administrator, as the case may be. Govt. Code §65903. Procedures for such appeals shall be as
provided by local ordinance. Govt. Code
§65903. Such board may reverse or
affirm, wholly or partly, or may modify the order, requirement, decision or
determination appealed from, and may make such order, requirement, decision, or
determination as should be made, and such action shall
be final. Govt. Code §65903.
2. Montebello Municipal Code
For zoning purposes, the
terms “abut,” “adjoining,” or “contiguous” means two or more lots or parcels of
land sharing a common boundary line. MMC
§17.08.010. “Adjacent” means lots or
objects which are located in close proximity to each other, separated only by
an alley, street, highway, or recorded easement. MMC §17.08.030.
The Planning Commission
shall have the authority to grant a CUP subject to the MMC’s procedures. MMC §17.70.020. Before any CUP shall be granted, all of the
following findings must be made: (1) the site for the proposed use is adequate
in size and shape; (2) the site has sufficient access to streets and highways,
and is adequate in width and pavement type to carry the quantity and quality of
traffic generated by the proposed use; (3) the proposed use will not have an
adverse effect upon adjacent or abutting properties; and (4) the proposed use
is consistent with the objectives of the community redevelopment project area
in which the site is located. MMC
§17.70.070.
Any condition imposed
upon the granting of a CUP may
be modified or eliminated, or new conditions may be added, provided that the
granting body shall first conduct a public hearing in the same manner as
required for the granting of the original permit. MMC §17.70.130. No modification shall be made unless the Planning
Commission or City Council finds that such modification is necessary to protect
the public interest and/or adjacent or abutting properties or, in case of
deletion of an existing condition, that such action is necessary to permit
reasonable operation and use under the conditional use permit. MMC §17.70.130.
The decision of the Planning
Commission in granting or denying a CUP shall go into effect in 20 days, or
upon the day following the first regular City Council meeting after its decision,
whichever shall occur first, unless within such period an appeal in writing is
filed by the applicant or an opponent with the city clerk. MMC §17.78.070. At the same time as the filing of an appeal,
the appealing party shall pay a filing and processing fee in a sum to be set by
resolution of the City Council. MMC
§17.78.070.
Upon receipt of the
appeal, the City Council shall set the matter for hearing before itself within 30
days from the receipt of the appeal. MMC
§17.78.080. Notice of the hearing shall
be given in accordance with the MMC. MMC
§17.78.080. At such hearing, the City Council
shall make the same findings and consider the same criteria as required of the Planning
Commission. MMC §17.78.080. Any action by the City Council on such
matters shall be final. MMC §17.78.100.
D. Statement of Facts
1.
Background
On
May 9, 1994, the Planning Commission approved CUP 2-94 to allow for the
establishment of a recycling plant at the Project site, which was in the M-2 (Heavy
Manufacturing) zone. AR 22, 1446-49. As a condition of approval, all active use
areas, including containment bins, had to be fully enclosed. AR 30, 712.
Condition 6.d also disallowed garbage and food waste processing and
required removal of any incidental amounts within 48 hours. AR 712.
Sometime
afterwards, NASA converted the Project site to a collection truck and roll-off
container storage yard that is not open to the public. AR 1468.
The site has a maximum capacity of 30 collection trucks and 60 roll-off
bins. AR 1468. The yard is open seven days a week from 3:00
a.m. to 5:00 p.m. and typically has one or two employees on duty. AR 1468.
2.
The Project
On
October 26, 2020, NASA filed the CUP application for the Project site. AR 1. The
application sought to modify the existing CUP to allow the Project site to
receive up to 1,500 tons per day of municipal solid waste. AR 18, 79.
NASA explained that it planned to build a solid waste transfer facility. AR 3. Collection
and transfer trucks would enter from Union Street and exit onto Gage Road, in a
circulation pattern that minimizes cross traffic. AR 3.
The 25,250 sf transfer station building would allow multiple vehicles on
the tipping floor, inbound and outbound scales, adequate room for vehicle
circulation and maneuvering, administrative offices, parking, and landscaping. AR 3.
All
tipping, sorting, processing, and loading activities would occur inside the
enclosed transfer station building. AR
18. Whereas the truck and roll-off bin
storage yard on the Project site currently has 104 vehicle trips per day, the
Project would generate 426 additional vehicle trips when operating at full
capacity. AR 18.
a.
The Initial Study
City
staff recommended a CEQA initial study of environmental impacts. See AR 626. The initial study prepared by Clements Environmental
(“Clements”) and dated October 2020 explains in the project description that the
25,250 sf transfer station building would be about 40 feet tall. AR 628.
It would incorporate a variety of building materials, including decorative
blocks and metal and translucent panels on the upper portions. AR 628.
The building would be setback ten feet from the front property line and
15 feet from the side property line. AR
628. NASA would direct all onsite truck
traffic one-way to simplify traffic control and enhance site safety. AR 628.
The
initial study asserted that most categories of environmental impact would not
occur at all and that the level of some types of impact would be less than
significant. AR 730-748. The Project Site is in an M-2 (Heavy
Manufacturing) zone, which is reserved for the heaviest industrial uses in the
City. AR 1486. The four adjacent properties are also zoned
M-2; all four are warehouses with two of them doubling as manufacturing
facilities. AR 1471. The Project would not conflict with any land
use plan, policy, or regulation of an agency with jurisdiction. AR 1486.
For
air quality, the initial study stated that there would be a less than significant
impact on odors adversely affecting a substantial number of people. AR 732.
The Project would mitigate odors by processing and loading waste inside
the building, which would have negative air pressure and an overhead misting
system with neutralizing agents. AR
733. The initial study did not address odor
emissions from the garbage trucks. See
AR 733. The trucks are required to
comply with the California Air Resources Board’s rule adopted in 2004 and eventually
all collection trucks will operate with compressed natural gas (“CNG”). AR 732.
Hazardous
waste would not be accepted. AR
739. If some incidental hazardous waste is
onsite, the facility would comply with all requirements of the Solid Waste Facility
Permit and Department of Toxic Substance Control. AR 739.
The initial study concluded there would be a less than significant impact
related to the release of hazardous materials.
AR 739.
As
for water quality, any impact from a violation of water quality standards or
waste discharge requirements would be less than significant. AR 739.
The Project would not impact surface or groundwater because all industrial
material storage, handling, and activity would be indoors. AR 740.
The facility is completely paved and there will be no significant change
in drainage pattern. AR 740. The Project also would not substantially
increase the amount of surface runoff or contribute to runoff which would
exceed the capacity of the existing or planned stormwater drainage system. AR 740.
The facility would comply with all requirements of the Industrial
Stormwater General Permit Order. AR
740.
For
noise, demolition of the existing buildings and construction of a new building
could result in a substantial temporary increase in ambient noise levels. AR 646.
Because construction would follow all local general plans, noise
ordinances, and applicable standards, this impact would be less than
significant. AR 646. Upon completion of construction, all Project
activities except for truck traffic would occur inside the building, and noise
levels not expected to exceed standards of the General Plan or noise ordinance. AR 646.
The
initial study concluded that the Project would not have a significant effect on
the environment and Clements prepared a negative declaration. AR 1474.
3.
December 1, 2020 Planning Commission Meeting
The
Planning Commission heard the CUP application on December 1, 2020. AR 44-47, 78.
At
the December 1, 2020 meeting, Assistant Planner Saara Chaudry (“Chaudry”) explained
that Planning staff had recommended an initial study to assess the
environmental impacts for the Project under CEQA. AR 78, 80.
The initial study revealed that the Project would have less than significant
impacts on the environment, and a negative declaration was prepared to that
effect. AR 80.
In
a written comment, 901 Union opposed the Project as a nuisance and detriment to
its property. The City should not allow
a use that would negatively impact the City in an area that has become an
economic engine. AR 81, 116.
Another written comment asserted that an environmental
impact report (“EIR”) was necessary under CEQA for any trash-related business. AR 81, 115.
Another
commenter, Robert Glushon, Esq. (“Glushon”), alleged that there were several
Brown Act issues with the notice of the hearing. AR 82, 107.
That notice said that the Project was substantially similar to the
previously approved glass recycling use but the Project site is currently a
truck storage facility, and in any case glass recycling is different from solid
waste management. AR 83. The initial study did not evaluate several of
the potential impacts that are always evaluated with solid waste transfer
stations. AR 83. One finding for the proposed use must be that
it cannot have any adverse effect on the adjacent properties, but the City needed
to evaluate these impacts further before it could make that finding. AR 83.
Representatives
from Clements responded to Glushon’s comment.
AR 84. Clements had reviewed all
the impacts listed in Glushon’s letter, including air quality, odor, health,
runoff, noise, and traffic, and determined that all of them were less than
significant. AR 84. Clements has done a lot of work with similar
facilities, so it understood the potential impacts and how to address
them. AR 84. The Project would be a state-of-the-art solid
waste transfer station with all uses contained inside a building. AR 85.
NASA’s vehicles use CNG to further minimize air impacts. AR 85.
The Project would have various mitigation measures and an aesthetically
compatible design with the surrounding neighborhood that conceals what is
occurring on the Project site. AR
85. The regulatory environment in place
would reduce most potential impacts to insignificant levels. AR 85.
The
Planning Commission voted to postpone the decision to December 15, 2020 and issued
new notices for that date. AR 90, 118-21.
4.
The December 15, 2020 Planning Commission Meeting
Glushon
submitted a December 1, 2020 letter to the Planning Commission which explained
that most proposed solid waste transfer station uses require either an EIR or
mitigated negative declaration because of certain potential significant impacts
including odor, health, water runoff, traffic, noise, air emissions and
quality, storm water quality, vectors like rodents and scavenging birds,
litter, and public safety and resources.
AR 257.
Glushon
further explained that the properties adjacent to the Project site included
food processing, food and beverage, storage, fashion design and apparel,
offices, and other uses incompatible with the proposed facility. AR 257.
Water runoff from the Project site already runs behind and under some of
those buildings and runoff from a solid waste facility would have a significant
impact on those properties. AR 257.
The
Planning Commission voted to skip the agenda item and adjourn until January 5,
2021. AR 303.
5.
The Agenda Packet for the January 5, 2021 Planning Commission Meeting
a.
Staff Report
The
staff report recommended adoption of a resolution approving the CUP. AR 318.
The report explained that the Project facility would transfer waste from
smaller hauling trucks onto larger hauling trucks. AR 319. This would allow for consolidated operations and
a more efficient system of waste transportation. AR 319.
The
Project is consistent with two goals of the City’s General Plan. AR 1007.
Goal #1 is to formulate a plan which is responsive to the needs of the
community and permits the orderly arrangement of land uses, while permitting
sufficient areas for reasonable development.
AR 1007. Goal #4 is to provide
for growth and development of an industrial area in a manner compatible with
other uses. AR 1007. The Project also is compatible with Policy #4
to preserve frontage along Santa Ana Freeway for industrial and compatible
commercial uses. AR 1007.
The
Project meets all four requirements under MMC section 17.70.070. AR 320-22.
The Project site (1) is adequate in size and shape, (2) has sufficient
access to streets and highways, adequate in width and pavement type to carry
the quantity and quality of traffic generated by the proposed use, (3) would
not have an adverse effect upon adjacent or abutting properties, and (4) conforms
with the goals, policies, and objectives of the General Plan, the MMC, and any
applicable specific plan. AR 320-22.
For
the first requirement, the 1.07-acre lot is big enough for the facility to meet
all setback requirements, height requirements, and floor area to lot size
requirements. AR 1007. The proposed footprint is 26,940 sf with a
building height of 40 feet. AR 1007. The Project would provide 27 off-street
parking spaces, which is sufficient to meet MMC requirements. AR 1007.
All proposed development meets development standards for the M-2
zone. AR 1007. The Project site is therefore adequate in
size and shape. AR 1007.
For
the second requirement, the streets and highways that serve the Project site are
designed to accommodate the heavy industrial vehicles NASA would use. AR 1007.
The site is located in an industrial area zoned M-2 (Heavy
Manufacturing), with frontage on Union Street and Gage Road. AR 1007.
Two major roads, Greenwood Avenue and Telegraph Road, provide access to
Union and Gage, respectively. AR
1008. The truck traffic would mostly
consist of collection vehicles, which themselves are maneuverable and
accessible to standard residential and commercial neighborhoods. AR 1008.
Access to the I-5 Freeway is therefore available via streets adequate in
width, pavement type, and classification to accommodate a proposed transfer
station. AR 1008.
For
the third requirement, the Project is in the M-2 area and bordered by
industrial development in all directions.
AR 1008. It is designed to
minimize the potential adverse effects on adjacent and abutting properties by
conducting all waste material processing inside the transfer station
building. AR 1008. The building will be equipped with a negative
air pressure system and overhead misting system to control dust and odors. AR 1007.
It will provide a safe and efficient traffic circulation system that
will employ spotters to further minimize traffic impacts on adjacent properties
and businesses. AR 1008. The Project would be an asset to the area
because its aesthetically pleasing design would contribute to the surrounding
properties. AR 1008.
For
the fourth requirement, the Project is consistent with Goal #1. AR 1008.
The facility would provide a vital service to the local community. AR 1008.
It would facilitate efficient transfer of solid waste from residential,
commercial, and industrial land uses to the local landfills. AR 321.
The prime location for such a facility is close to the communities it
serves but with adequate distance from sensitive receptors such as residential
communities and schools. AR
321-322. The Project site is the most
ideal site for this transfer facility.
AR 322.
MCC
section 17.70.130 allows the imposition, modification, or elimination of a
condition on a CUP only if the Planning Commission finds that such modification
is necessary to protect the public interest and/or adjacent or abutting
properties. AR 322. The staff report found that the proposed
modification would provide an essential service to the community by
facilitating efficient transfer of solid waste to local landfills. AR 322.
The Project will protect the public interest because the new facility
would provide adequate community infrastructure to support and service City
residents. AR 322.
b.
Clements Memo
Clements
prepared a December 10, 2020 memorandum to clarify and expand on the proposed Project’s
operations. AR 436. The memorandum explained that, although the existing
CUP allows NASA to operate a glass recycling operation on the Project site, it
has not done so for years. AR 436. NASA uses the property as a truck yard for
solid waste collection vehicles and empty roll-off containers. AR 436.
The
Project would provide a transfer station to consolidate waste from multiple
collection vehicles into larger, high-volume transfer trucks for efficient and
economical shipment to disposal sites.
AR 436. Such stations increase
the efficiency of collection trucks because they reduce driving times and
travel distances, which in turn reduce vehicle emissions and overall vehicle
miles. AR 437. All tipping and loading activities would
occur entirely inside the building to minimize litter, odors, and vectors. AR 437.
The
Clements memorandum included pictures of large garbage collection vehicles and
the interior of a typical transfer station.
AR 438-39.
c.
Comment Letters
(1).
Samantha Millman
Samantha
Millman (“Samantha”) submitted a comment letter as manager of three properties
adjacent to the Project site: Hermark 25, Hermark Investment, and 1717 Gage Rd. AR 449-450, 581. She explained that the Project site is quiet because
NASA has not acted on its existing CUP to recycle glass. AR 449, 581.
The businesses that operate on Gage Road are quiet office, hospitality,
warehousing, distribution, and food processing facilities. AR 449.
A hotel is just “a few doors down” from the Project site. AR 449.
The property across the street from the site is an apparel company with
predominantly office and showroom space.
AR 450. Samantha’s tenant at 1717
Gage Road, directly adjacent to the Project site, distributes food products and
sundries. AR 450.
These
businesses will be significantly harmed if a solid waste transfer station that
processes up to 1,500 tons of solid waste per day opens next door. AR 450. Such a facility will cause increased odor,
noise, and traffic. AR 450. They are always dirty, produce odor, increase
traffic and emissions, and attract vermin.
AR 450. The City should also
study drainage from the Project site, which runs behind the building at 1717
Gage Road, under the building at 1725 Gage Road, and through the parking lot of
the hotel at the end of Gage Road. AR
450.
(2). Angela Wong
Angela
Wong (“Wong”) is the CEO of Quality Inn and Suites, which operates a hotel
close to the Project site. AR 452, 1224. Because of its close proximity to the hotel,
the Project would negatively affect the hotel’s business and the area as a
whole. AR 452. The 420 additional vehicle trips during
business hours, most of which would be collection and transfer trucks, would significantly
increase the area’s traffic. AR
452. Both the stigma of a waste
processing plant in the area and the environmental issues like truck and
operational noise, odor, and vermin would have a negative impact on the
neighborhood. AR 452, 1224. The reputation of the area would suffer. AR 452.
(3).
Doron Kadosh
Doron
Kadosh (“Kadosh”) is the owner of 2253 Apparel, which operates a design
showroom, warehouse, and offices at 1708 Gage Road. AR 454.
Her company chose this location because it is a quiet street and
area. AR 454. A CUP would result in over 400 daily vehicle
trips past the business, most of which would be large garbage trucks. AR 454.
The noise and emissions from those trucks, along with the odors of the
Project facility and vermin it would attract, are intolerable to 2253 Apparel. AR 454.
(4).
Michael Roski
Michael
Roski (“Roski”) is the managing partner of Gage Ave, which owns property 250
feet south of the Project site. AR
456. Gage Ave’s tenant is a food
manufacturing company that has expressed concern that it does not want to be
next to a “dump station.” AR 456. The Project is a more intensive use of the
Project site than its current use. AR
456. It would impact the immediate
surrounding area with high volume trash truck traffic, smells, odors, rodents,
and other unwanted affects. AR 456.
There
is no EIR for the Project, and any EIR would disfavor it. AR 456.
The surface water from the Project site runs directly under Roski’s
building and onto the neighboring hotel property. AR 456.
Roski has not heard of any water treatment plans to address the concerns
of adjacent property owners that the run-off water would be contaminated. AR 456.
(5).
John Huang
CJ
Distribution CEO John Huang (“Huang”) engages in wholesale distribution of
foods and restaurant supplies a few buildings away from the Project site. AR 461.
His business thrives because of the clean streets, quiet surroundings,
light traffic, and orderly environment.
AR 461. The Project site is only
a few buildings away from his and would introduce heavy traffic, unpleasant
odors, pest infestation, and health hazards.
AR 461.
(6).
Bacci
Peter
Bacci (“Bacci”) is an industrial real estate broker. AR 478.
He asserted that the Project would cause a significant negative impact
to the property owners and tenants around the Project site because it would
diminish property values and hinder the ability to attract investors and
tenants due the uncertainty of the environment, the stigma of the use, and the
risk of contamination. AR 478.
(7). Shahen Hairapetian
Attorney
Shahen Hairapetian (“Hairapetian”) asserted that the criticism of the CUP
Application is primarily anecdotal and failed to address the applicable law and
requirements. AR 470.
6. The January 5, 2021 Planning
Commission Meeting
Planning
staff made a presentation to the Planning Commission at the January 5, 2021
meeting. AR 419. Staff explained that the main function of the
Project is to reduce the milage of City vehicles by providing a place to
transfer waste from smaller to larger hauling trucks. AR 424.
Clements’ representative explained
that it prepared a negative declaration for the Project because the initial
study revealed no areas of impact that would require additional mitigation
measures. AR 512.
a. Public Comment
(1). Kenneth Millman
Kenneth Millman (“Kenneth”) stated
that he is a principal owner of properties adjacent to the Project site. AR 513.
He noted that the CUP for recycling clean glass, which was operated for
a short time, was subject to stringent restrictions on the daily amount of
glass to import and the number of trucks that could come to the site. AR 513.
The Project would materially change
the nature of the Project site’s use. AR
513. It would generate 530 daily trips
in and out of the site, 500 of which would be trash trucks with about 1,500
tons of solid waste. AR 513. The federal Environmental Protection Agency
(“EPA”) has documented that transportation generally results in environmental
issues such as traffic, noise, orders, emissions, vector, and litter. AR 513.
Conducting all operations indoors does not mitigate the concerns because
that many truck trips will mean that the doors either open and close 500 times
a day or stay open. AR 513-14. Odors, vectors, and noise can escape each
time they open. AR 514. Kenneth was extremely concerned about the
impact of a solid waste transfer station on property values and the ability to
attract tenants. AR 514.
(2). Samantha
Samantha stated that the proposed
CUP is a profound intensification of use.
AR 515. The uses surrounding the
Project site are not heavy industrial uses; they are quiet small business
owners. AR 515. These longstanding businesses would suffer if
next to a solid waste transfer station.
AR 515. The Project would also impair
the City’s ability to attract other high-quality businesses to that
location. AR 515.
(3). Glushon
Glushon stated that he has never
seen such a blatant CEQA violation in 40 years of practice. AR 517.
The Project would change the Project site from a truck storage yard with
very little traffic impact to a solid waste transfer station. AR 517.
Other transfer stations have required an EIR or mitigated negative
declaration. AR 517.
The adjacent businesses are
incompatible with a solid waste transfer station, and water runoff flows from
the Project site behind his client’s building at 1717 Gage and under the
building at 1725 Gage, as well as to other properties. AR 517.
The question is not whether runoff exists, but how impactful it will be. AR 517.
An environmental review enables the identification of such issues, and
similar sites in other cities required such review. AR 517.
The Planning Commission cannot approve the CUP application unless it
finds that the proposed use will not possibly have an adverse impact on
adjacent properties, but it will. AR
517.
(4). Brian Vanriper
Brian Vanriper (“Vanriper”) of 2253
Apparel, directly across the street from the Project site, explained that his
business has buyers like Bloomingdales, Nordstrom, Macys, and Guess Jeans. AR 518.
It brings a lot of buyers and other producers through and has therefore
invested a lot in property improvements.
AR 518. In the time it has
operated, the street has been quiet. AR
518. 2253 Apparel cannot operate the way
it has been if this changes due to the volume of truck traffic the Project
would bring. AR 518-19.
b. The Planning Commission’s Decision
Planning Commissioner Marlene Ramirez
(“Ramirez”) noted that the Project poses a lot of extreme concerns that NASA had
not addressed. AR 520. She was concerned about the impact on
adjacent businesses and the increase of storm water runoff onto the other
properties. AR 520.
Planning Commission Vice-Chair Alexandra
Briseno (“Briseno”) disagreed with the initial study’s findings that the
Project’s proposed use is substantially similar to the current use. AR 521.
The Project is likely to cause significant adverse impacts to the
surrounding business and to the community.
AR 521.
Commissioner Cuevas (“Cuevas”)
agreed that the Project would harm a lot of the current businesses because of
rodents, traffic, and truck queuing for dumping and leaving the facility. AR 521.
Hotels and food-related businesses are particularly vulnerable. AR 521.
Planning Commissioner Berj Aliksanian
(“Aliksanian”) asked what modifications to the CUP, if any, address the public
concerns about rodents and environmental impact. AR 478, 521.
A Clements representative explained that many different agencies highly
regulate transfer station facilities like the Project. These local enforcement agencies are
concerned with the same issues as those raised in the January 5, 2021 meeting,
including vector control. AR 521. These agencies enforce standard practices
that minimize the potential risks. AR
521. These include a monthly inspection
by a third party subject to more frequent inspections after complaints to a
health department. AR 521-22.
Another Clements representative
added that bait trap inspections and general maintenance of a clean food
facility usually address most of the vector and odor problems. AR 522.
The negative air pressure system and state-of-the-art facility also include
standard operating procedures to address any concerns. AR 522.
Because the Project would also be under the regulatory umbrella for odor
and dust emissions, regulations forbid movement of air in the facility. AR 522. The trucks would use CNG to reduce
emissions. AR 522. As for runoff water, the building would be
enclosed, have storm water infiltration and would capture all runoff onsite
through biofilters with the groundwater.
AR 522. The point of the Project
and its design is to mitigate the impacts typical of these facilities. AR 522.
Commissioner Aliksanian asked
whether the modification to the CUP would bring additional revenue to the
City. AR 522. City staff stated that it had not evaluated
this issue. AR 522.
Commissioner Briseno replied that
the City should know the environmental impacts of the Project before approving
it just like the other transfer stations to which Glushon referred. AR 523.
Commissioner Ramirez responded that she
did not see how the Project could address the impact on surrounding businesses
and she did not agree that it should move forward. AR 523.
The Planning Commission denied the CUP
application on a 3-1 vote with one abstention.
AR 523-24.
7. The Appeal
NASA filed a timely appeal from the
Planning Commission’s decision pursuant to MMC section 17.78.070. AR 542.
In its appeal letter, NASA contended that the denial was based on
unsubstantiated findings that the Project is not compatible with the
surrounding industrial uses. AR 1822.
The City set the appeal hearing for
February 10, 2021, published notice of the public hearing in the Whittier Daily
News, and mailed notice to all property owners within 300 feet of the Project site. AR 542, 551, 570-71.
a. The Staff Report
The staff report for the appeal noted
that the Planning Commission expressed concern regarding unknown potential
environmental impacts to the surrounding properties. AR 551-52. The staff report asserted that the Project
would enable NASA to provide for efficient transfer of solid waste, an
essential service to the community. AR
555. It would provide adequate community
infrastructure to support and service City residents. AR 555.
This meant that it would facilitate the public good and protect the
public interest. AR 555. The Project site is a prime location for an
industrial use that facilitates waste transfer because it is both close to the
communities it serves and distant enough from sensitive receptors. AR 555.
The
report stated that the Project meets all four requirements under MMC section 17.70.070. AR 868-70.
AR 555-56. Staff recommended that
the City Council conduct a public hearing and either uphold the Planning
Commission’s denial of the CUP application or adopt the negative declaration
and overturn the Planning Commission decision. AR 558.
The City Council continued the
appeal hearing to February 24, 2021. AR
865. For the February 24, 2021 hearing, City
staff issued a new staff report with the same recommendations. AR 865.
Staff also submitted a proposed resolution for overturning the Planning
Commission’s denial. AR 874.
b. Written Comments
Some
of the written comments received by the City Council are set forth as follows.
(1). Montebello Concerned Citizens
An
association called Montebello Concerned Citizens asserted that water runoff
from the proposed solid waste transfer station would have a significant impact
on neighboring properties. AR 1175. Other inevitable consequences include heavy
traffic, unpleasant odors, pest infestation, and health hazards. AR 1175.
The Project involves a significant change of use from a truck storage
yard to a waste transfer station and such stations always require an EIR. AR 1175.
(2).
Danny Cota
Danny
Cota (“Cota”) is the Operations Manager of Landsberg Orora (“Landsberg”), which
owns property less than a quarter mile from the Project site. AR 1195.
Landsberg is a packaging solutions provider, and some clients are food
and medical companies. AR 1195.
Traffic
on Union Street is already very heavy. AR
1195. Increased heavy truck traffic from
the Project would only exacerbate the problem.
AR 1195. It would also further
the deterioration of the road, which is not well-maintained. AR 1195.
8.
NASA’s Voluntary Reduction
On
the February 24, 2021 day of the continued hearing, NASA sent the City Council
a letter modifying its CUP application.
AR 1824. While the initial study found
that the Project had no significant environmental impact, NASA decided to
reduce the impact further by halving the tonnage of waste it is requesting to
transport and process. AR 1824. This reduced the daily amount of waste from
1,500 to 750 tons, the number of new vehicle trips from 426 to 274, the
operational air emissions of criteria pollutants by 88%, and greenhouse gas
emissions by 36%. AR 1824.
9.
The February 24, 2021 City Council Appeal Hearing
On
February 24, 2021, the City Council heard NASA’s appeal. AR 1267.
Pertinent testimony is as follows.
a.
Cota[1]
Landsberg
has been doing business at its current location for nearly 49 years. AR 1281.
It is one of the top 25 tax revenue companies in the City. AR 1281.
His
organization is concerned about the Project’s traffic impact. AR 1281.
Traffic congestion on Greenwood Avenue has caused drivers to use Union
Street to get to the 5 Freeway south. AR
1281. This has dramatically increased
traffic on Union Street, a road that is not well-maintained. AR 1281.
Because
the Project would introduce additional traffic to an already congested route,
it poses safety concerns. AR 1281. If the City Council approves the CUP
application, it will increase the heavy traffic on Union Street and have a
severe impact on it. AR 1281. Landsberg drivers already find it difficult
to enter and exit the property. AR
1281. Some have experienced hits
resulting in injuries and close calls, while others experience delays when
trying to back into docks as vehicles pass by.
AR 1281. The most experienced
Class A drivers would find the necessary maneuvers difficult. AR 1281-82.
A
solid waste transfer station also creates potential for odor and rodent
issues. AR 1282. This is particularly problematic for Landsberg
customers in the food and medical industry.
AR 1282.
b.
Bacci[2]
The
Project’s impact on the value of nearby properties would be horrific. AR 1291.
The nearby Bluff Road is already hard to drive on, and the Project would
have 33,000 pound trucks drive on it. AR
1291. Traffic coming off Union, with
trucks lining up to get to the transfer station on Gage Road, would be a
terrible idea. AR 1292.
c.
Kenneth
Kenneth
has been an active property owner in the City for 50 years. AR 1295.
He questions why the City would want a garbage transfer station when
there is no financial incentive for it.
AR 1296.
The
Project would increase traffic. AR
1296. While the Project description
originally said it would add another 400 trips by truck, NASA now asserts it
will only add 200. AR 1296. This still means that one truck enters and
leaves the facility every three to four minutes. AR 1296.
Kenneth
compared the one-acre Project site to other transfer stations. AR 1296.
He drove to transfer stations that were on 14, seven, and three
acres. AR 1296-97. These sites have room for trucks to que on
site. AR 1297. Without this room, NASA trucks would stack up
on Union Street in front of other properties.
AR 1297.
The
Project would have a negative effect on adjacent property values and the
ability to keep existing tenants and attract new ones. AR 1297.
d.
Wong
Wong’s
Quality Inn Hotel and Suites is on Gage and Telegraph. AR 1303.
The hotel has over 50 employees and 150 rooms. AR 1303.
Traffic from the Project would start at 3:00 or 4:00 a.m. and serve as a
major disruption for hotel guests, even if cut in half as NASA recently
suggested. AR 1303.
Those
trucks would pass by a popular City bus stop for Wong’s employees. AR 1304.
The traffic at Gage Road and Telegraph Road, right off the 5 Freeway, is
already horrific right where the hotel is.
AR 1304. The trucks would both
add to this and cause additional wear and tear on the roads. AR 1304.
Wong
also has concerns as to odors, air quality, vermin in the air and ground,
noise, and water runoff. AR 1304. The hotel already has runoff from the Project
site. AR 1304.
e.
Samantha
Even
if NASA cuts the Project’s daily garbage intake in half, it still would bring
1.5 million pounds of garbage to the Project site per day for export within 48
hours. AR 1306. That is millions of pounds of garbage per day
going in and out of the site. AR 1307.
There
is a hotel four doors down from the Project site. AR 1307.
The tenant at 1708 Gage Road directly across the street is an apparel
company with offices and showrooms. AR
1307. Her tenant at 1717 Gage Road
adjacent to the site warehouses and distributes food. AR 1307.
A
waste station in Sun Valley is on 19 acres and next to a landfill, high-voltage
power lines, manufacturing, and rock quarry.
AR 1307. Another Los Angeles site
is over nine acres, with two and a half acres of parking lot “to accommodate
sewing”. AR 1307-08. By comparison, the Project Site is
ill-equipped for this kind of work. AR
1307. Although it is in an M-2 zone, the
surrounding businesses do not involve heavy manufacturing. AR 1307.
The Project site is at the intersection of two small streets, Gage and
Union. AR 1307.
f.
NASA
The
facilities Samantha highlighted are for material recovery, which is a different
operation than the Project for transfer of solid waste. AR 1309.
g.
Clements
The
Project is for a transfer facility which does not process solid waste. AR 1310.
It only transfers (tips) solid waste from small trucks to larger
ones. AR 1310.
Because
NASA owns the trucks that would visit the Project facility, it can coordinate
their delivery times to off-peak hours and avoid queuing on the street. AR 1310.
Clements has designed and received approval for similar facilities on
parcels of lands similar in size to the Project site. AR 1310.
The
facility would be subject to various regulatory agencies including the Los
Angeles County Health Department and the local South Coast Air Quality
Management District (“SCQAMD”). AR 1310-11. The Project would have negative air pressure
systems to mitigate odors. AR 1310-11. The State and cities are all striving for
recycling and more efficient transfer of solid waste and this facility would
accomplish that. AR 1311. Centralized facilities reduce traffic and
allow the waste to be handled where it is generated. AR 1311.
Odors are mitigated by SCAQMD Rule 410, which requires a
negative air pressure system. AR
1311. The Project would comply with the
Regional Water Quality Control Board’s wastewater standards. AR 1311.
It would use Clarifiers and bioswales which would minimize to very low
any potential for stormwater runoff to leave the site. AR 1311.
The traffic numbers fall below the a.m./p.m. peak hour thresholds for
traffic impact. AR 1311. CNG fuel minimizes the impact on air
quality. AR 1311-2. Pest control companies would provide weekly
or monthly monitoring to address vectors.
AR 1312. Because all the
regulatory requirements of agencies that have oversight authority address any
environmental impact, Clements prepared a negative declaration. AR 1311.
Solid
waste transfer is a conditionally permitted use within the M2 zone and Clement
based the environmental impact analysis on the existing use of truck storage,
not the recycling facility use in CUP No. 2-94 as a baseline. AR 1312.
Facilities
such as that proposed are an essential service to the community and the State’s
goal of zero waste. AR 1313. The Project is appropriate for a heavy
industrial zone, Planning staff has recommended its approval, and it is
designed to be an asset to the community as a state-of-the-art facility with
all necessary environmental controls. AR
1313.
h.
Joseph Palombi
City
Planning Director Joseph Palombi (“Palombi”) explained that the City staff based
its recommendation on the zoning of the immediate area and the proposed
use. AR 1338. Staff analyzed what the zone calls for, what
are the allowed uses therein, and what the existing use on the Project site is. AR 1338.
The
Project would reduce the regional traffic trips by streamlining the process of
going to the landfill -- three trucks could offload to a larger truck, which
then would go to the landfill. AR 1339.
Staff
has been very challenged by this particular zone. AR 1340.
This is a heavy industry zone that has not been updated since 1973 and
there are different uses there today. AR
1340. There are refineries (Chevron) and
other heavy intensive uses. AR
1340-41. Staff had to look at the zone
and uses and that is where its recommendation came from. AR 1341.
i.
Larry Miner
Larry
Miner (“Miner”) conducted the traffic analysis for the Project. AR 1339.
His analysis considered that garbage haulers are already picking up
trash to take to the nearest facility.
AR 1339. Because they are already
moving around the region, the Project does not increase the level of
traffic. AR 1340.
There is also a reduction in air emissions. AR 1340.
The Project uses CNG vehicles, and NASA is moving towards electrified
vehicles. AR 1340. This reduces emissions, and the decrease in
miles trucks must travel because of the Project would decrease emissions
further. AR 1340.
10.
The City Council’s Decision
Councilmember
Melendez (“Melendez”) stated that the Project site is in an M-2 heavy
manufacturing zone and is surrounded by industrial development. AR 1316.
The City Council only heard from business owners and not residents. AR 1316. The Project is consistent with the General
Plan and there is no standing to claim a public nuisance. AR 1317.
Mayor
Pro Temp Torres (“Torres”) explained that the City is currently revising the General
Plan to determine what it should look like for the next 10-15 years. AR 1319.
A decision authorizing an intensive use for the Project site like a
solid waste transfer facility will determine the future of the surrounding
area. AR 1319-20. The City Council now has the opportunity to
imagine what to do with the area. AR
1320. The area consists of grocers that
need to be sanitary and food safe, apparel companies with high-quality
customers who visit, and a hotel that would feel an impact from multiple trucks
driving past with garbage at 3:00 to 4:00 a.m.
AR 1320. The building doors
cannot mitigate the odors, noise, or vectors as well if they constantly have to
open for 40-foot-long trucks to come in and out. AR 1320-21.
Other facilities never close their doors because of the constant
vehicular flow. AR 1321.
Councilmember
Jimenez emphasized that while the City will update its General Plan at some
point, for now the area is zoned for heavy manufacturing. AR 1332.
The Project is the specific type of business intended for those
areas. AR 1332-33.
The
City Council voted 3-2 to direct City staff to prepare a resolution of findings
that upheld the Planning Commission’s denial of the CUP application. AR 1348-49.
The City Attorney noted that, per this this motion, the City Council
would consider the new resolution at its next meeting on March 24, 2021. AR 1348-49.
11.
The City Council Meeting Minutes
The
meeting minutes stated Councilmember Melendez observed that the Project
conforms with the City's General Plan and land use element, is compatible with
the surrounding land uses, and supports the existing goals and policies
developed for that area. AR 1228. Councilmember Torres mentioned the City’s plan
to update the General Plan and argued that the decision on this appeal would
determine the future of the surrounding area.
AR 1229. Councilmember Peralta
stated that the City Council should consider the public comments and echoed
that the General Plan had not been updated since 1973 and that land use
acceptable then may not be acceptable today.
AR 1229. Councilmember Jimenez
asked for clarification of staff’s recommendation. Palombi explained that staff recommended
approval based on conformance with the General Plan, underlying zone, and
existing CUP. AR 1229.
12.
The Resolution
Before
the March 24, 2021 City Council meeting, the City staff prepared a report and
attached the draft resolution. AR 1414, 1418.
The report noted that projects that a
public agency’s rejection of a project is not subject to CEQA per Public Resources
Code section 21080(b)(5). AR 1418.
On
March 24, 2021, the City Council adopted Resolution 21-11 (the
“Resolution”). AR 1465. On May 17, 2021, the City clerk mailed NASA
notice of the Resolution. AR 1829.
The Resolution finds as follows.
a.
General Plan
The Project is consistent with the General
Plan. AR 1462. However, it is not compatible with surrounding
land uses and does not support the existing goals and policies for proper
industrial growth and development. AR 1462. Goal #4 is to provide for growth and
development of an industrial area in a manner compatible with other uses. AR 1420.
The Project would have a significant adverse impact on the adjacent
businesses and other operations and land uses in the surrounding area. AR 1420.
Four
adjacent property owners testified that the creation of a solid waste transfer
station at the Project site would create various environmental and health
impacts. AR 1421. These in turn would diminish the value of
property in the vicinity. AR 1421. In addition, 20 adjacent property owners or
residents asserted that the requested modification to the CUP is not the best
interest of or compatible with existing industrial uses of the area. AR 1421.
The significant increase in the transportation of solid waste from
surrounding areas to the Project site creates an imposition of processing waste
not generated by City residents or businesses and has a negative effect on the
existing industrial uses. AR 1421.
b.
MMC Section 17.70.070 Analysis
A
CUP cannot be approved unless it the City makes four findings in its
favor. AR 1463.
The
first required finding is that the Project site is adequate in size and shape. AR 1463.
The proposed building would be 26,940 sf. AR 1463.
The Project site for this building is the same 1.07-acre lot as the
current 5,356 sf building. AR 1463. The intensification of use from a glass
recycling facility to a solid waste transfer station exceeds the appropriate
use for a property of this size and shape. AR 1463.
The Project site is not adequate in size or shape for the proposed
use. AR 1463.
The
second required finding is that the site has sufficient access to streets and
highways and is adequate in width and pavement type to carry the quantity and
quality of traffic generated by the proposed use. AR 1463.
The streets and highways that serve the Project site are designed for
the heavy industrial vehicles that the Project would use. AR 1463.
However, the daily number of inbound and outbound truck trips would
increase from 104 to 530, five times the current truck volume. AR 1464.
This would have a detrimental impact upon traffic in the surrounding
area. AR 1464. Additionally, the intensified use does not
have sufficient access to streets or highways leading to the Project site, and
the increased truck traffic impact would have a detrimental effect on the roads
and general infrastructure. AR 1464.
The
third required finding is that the proposed use will not have an adverse effect
on adjacent or abutting properties. AR
1464. The Project site is in an M-2
(Heavy Manufacturing) zone, and the bordering development is all heavy
manufacturing. AR 1464. Numerous business and property owners,
residents, and interested “property” (sic.) have testified that the
Project would have numerous adverse impacts on adjacent and abutting properties
and businesses. AR 1464. The City Council agrees. AR 1464.
The
fourth required finding is that the proposed use is in conformance with the
goals, policies, and objectives of the General Plan and the purpose and intent
of the MMC and any applicable specific plan.
AR 1464. The Project is
inconsistent with Goal #4 of the General Plan to provide for growth and
development of an industrial area in a manner compatible with other uses. AR 1464.
The intensified use is not compatible with the adjacent industrial area
because of the increased truck traffic, solid waste disposal and processing,
noise, odors, potential rodent infestation, and related impacts. AR 1464.
c.
Modification to CUP Analysis
Under
MMC section 17.70.130, a condition imposed upon granting a CUP can be modified
or eliminated if the granting body first conducts a public hearing in the same
manner as required for the original CUP.
AR 1465. The City Council must
also find that the modification is necessary to protect the public interest and/or
adjacent or abutting properties. AR 1465. The requested modification to CUP 02-94 is
not in the public interest and does not benefit adjacent or abutting
properties. AR 1465.
d.
CEQA
The
negative declaration does not adequately address the Project’s environmental
impacts. AR 1423. Unlike the negative declaration, the City
Council finds that the cumulative effects of the Project can have significant
impact on the area’s traffic, noise, air quality, greenhouse gas emissions,
hazardous materials, and water quality.
AR 1465. Additional environmental
analysis via an EIR or mitigated negative declaration should have been required. AR 1465.
e.
Conclusion
The
CUP application is denied because the underlying Project is not consistent with
the City’s General Plan, does not meet the findings required under MMC section 17.70.070
or 17.70.130, and lacks the required CEQA analysis of significant environmental
impacts. AR 1465.
E.
Analysis
MMC section 17.70.070 lists the four affirmative
findings the City must make prior to granting a CUP:
(1) the site for
the proposed use is adequate in size and shape;
(2) the site has
sufficient access to streets and highways, and is adequate in width and
pavement type to carry the quantity and quality of traffic generated by the
proposed use;
(3) the proposed
use will not have an adverse effect upon adjacent or abutting properties; and
(4) that the
project is in conformance with the goals, policies, and objectives of the
General Plan and the purpose and intent of this code and any applicable
specific plan.
The applicant’s
failure to meet any one of those requirements will result in the proper denial
of a CUP. Saad v. City of Berkeley,
(1994) 24 Cal.App.4th 1206, 1213-14 (italics original). So long as the decisionmaker made a finding
that any one of the necessary elements was lacking, and this finding is itself
supported by substantial evidence, the denial of the application must be
upheld. Id. at 1214 (citing Desmond
v. County of Contra Costa, (1993) 21 Cal.App.4th 330, 336-37).
As a result, the City need only have substantial
evidence for one of the City Council’s four MMC section17.70.070 findings. The City also need only have
substantial evidence to support the City Council’s finding that the requested modification
to CUP 02-94 is not in the public interest and/or it does not benefit adjacent
or abutting properties under MMC section 17.70.130.
1. Preliminary Issues
a. The
Nature of the Dispute
NASA argues that City staff demonstrated before both
the Planning Commission and the City Council that the Project meets all four of
the affirmative findings MMC section 17.70.070. The City
repeatedly ignored City staff’s objective showing, relying on the conclusory
assertions presented by Project opponents to deny the CUP. These criticisms were primarily anecdotal and
failed to address the applicable law and requirements. AR 470. This improper reliance resulted in the City
Council’s unsupported negative conclusions on each of the four required
findings. Pet. Op. Br. at 8.
Intervenors respond
that the comments and opinions of city staff do not bind decisionmakers. Environmental Council v. Board of
Supervisors, 1982)
135 Cal.App.3d 428, 437–38 (the decision-maker has the
power to change the findings prepared by its staff); La Costa Beach Homeowners Ass’n. v. South Coast
Regional Comm’n, (1979) 89 Cal. App. 3d 327, 331 (staff
recommendation “does not mean that the same result would necessarily follow a
public hearing by the full commission”).
Int. Opp. at 2.
While Intervenors are
correct, they misunderstand NASA’s point, which is that the City staff’s
opinions qualify substantial evidence.
This point is distinct from the fact that the City Council is not bound
by its staff’s conclusions. Staff
reports and opinions may constitute substantial evidence to support a
decision. See Young
v. City of Coronado, (2017)
10 Cal.App.5th 408, 432 (use of staff report to support a city’s decision); Browning-Ferris
Industries v. City Council, (1986) 181 Cal.App.3d 852, 866.
There
is little doubt that, if the City Council had decided to approve the CUP, the
staff report, coupled with NASA’s expert opinions, would be substantial
evidence supporting that decision. The
Project is zoned M-2 (Heavy Manufacturing) and is consistent with the General
Plan. The Project would reduce the
regional traffic trips by streamlining the process of going to the landfill;
three trucks could offload to a larger truck which then would travel to the
landfill. AR 1339. The staff report
asserted that the Project would enable NASA to provide for efficient transfer
of solid waste, an essential service to the community. AR 555.
It would provide adequate community infrastructure to support and
service City residents and would facilitate the public good and protect the
public interest. AR 555. The Project site also is a prime location for
an industrial use that facilitates waste transfer because it is both close to
the communities it serves and distant enough from sensitive receptors. AR 555.
The issue, however, is not whether
the Project is supported by substantial evidence but whether the City Council’s
decision to disapprove the CUP is supported by substantial evidence. All the evidence in opposition to the Project
came from neighboring property owners.[3] Layperson
opinions may constitute substantial evidence if the statements are based on
relevant personal observations or non-technical issues. Bowman, supra,
122 Cal.App.4th at 583. NASA
contends that the comments and testimony of neighboring property owners
consists of unsupported conclusions that are not substantial evidence. Reply at 5.
The issue before the court is whether this lay opposition is substantial
evidence.
b. The Adequacy
of NASA’s Opening Brief
The City argues
that NASA’s opening brief fails to set forth all material evidence considered
by the City Council. NASA argues at
length about its supporting evidence while dismissing the testimony of the property
owners as “conclusory assertions”. NASA fails
to describe these specific concerns that were raised about a large Project with
significantly increased heavy truck traffic and unanswered questions about
potential environmental and financial impacts. In ignoring this evidence, NASA has waived its
contention that the City Council’s findings are not supported by substantial
evidence. City Opp. at 6.
When a petitioner challenges an administrative
decision as unsupported by substantial evidence in light of the record as a
whole, it is the petitioner’s burden to demonstrate that the administrative
record does not contain sufficient evidence to support the agency’s decision. State Water Resources Control Board Cases,
(2006) 136 Cal.App.4th 674, 749. The petitioner is obligated to lay out the
evidence favorable to the other side and show why it is lacking. The
"[f]ailure to do so is fatal" to any substantial evidence challenge
and "is deemed a concession that the evidence supports the
findings." Defend the Bay v.
City of Irvine, (2004) 11928 Cal.App.4th 1261, 1266. A recitation of only the part of the evidence
that supports the petitioner’s position is not the demonstration contemplated
by this rule. According, if a petitioner
contends that some issue of fact is not sustained, and he does not lay out all
the material evidence on the point, the error is deemed to be waived. Foreman & Clark Corp. v. Fallon,
(1971) 3 Cal.3d 875, 881.
NASA replies that its opening brief did not
fail to discuss credible evidence presented by the other
side because there was no such evidence to discuss. NASA did discuss the “evidence” relied upon
by the City Council, but it consisted of no more than inflammatory conclusions
and accusations. NASA’s opening brief
references and
cites both the City’s findings and the evidence it relied upon for its
determination. See Pet. Op. Br. at 6, 9, 11, 12, 16. Nowhere in its opposition does the City cite
any specific evidence that NASA failed to discuss. Reply at 4.
A review of NASA’s opening brief shows that NASA
blanket cited to the comment letters and City Council testimony of property
owners. Pet. Op. Br. at 9 (citing AR
1168-225 (comment letters to the City Council), 1234-1403 (City Council hearing
transcript). NASA also pin cited some
specific comments about impact on adjacent properties. Pet. Op. Br. at 11-12 (citing to AR 1175 (email
to City Council from Montebello Concerned Citizens); AR 450 (Samanta letter to
Planning Commission), 456 (letter to City Council from Roski); AR 1291 (Bocci
comment at City Council hearing). NASA
further pin cited property owner comments about: (a) traffic impacts. Pet. Op. Br. at 16 (citing AR 1175 (email to
City Council from Montebello Concerned Citizens; AR 1195 (letter to City
Council from Landsberg); (b) noise impacts.
Pet. Op. Br. at 17 (citing AR 1304 (Wong comment at City Council
hearing), 1224 (Glushon letter to Planning Commission); and (c) air quality and
water runoff impacts. Pet. Op. Br. at 17
(citing AR 454 (2253 Apparel comment to Planning Commission), and 1175 (email
to City Council from Montebello Concerned Citizens).
NASA did not list all property owner
comments or purport to summarize them.
However, NASA did cite opposition comments as examples. While this approach is not fully compliant
with NASA’s burden to demonstrate that the administrative record does not
contain sufficient evidence to support the City Council’s decision, the court
will not find a waiver to deny NASA’s Petition.
The City Council made the
following finding:
“The Property is
located on a 1.07-acre lot with a proposed footprint of a 26,940 square feet of
building footprint. The proposed increased use from a glass recycling facility
to a solid waste transfer station is an intensification of use which exceeds
the appropriate use for a property of this size and shape. The proposed use
would result in a demolition of existing structures to accommodate a new
facility which would increase the current office space and waste processing
uses of the site from approximately 5,356 square feet to a new construction
footprint of 26,940 square feet (over five times the size of the existing site
facilities). All new construction would be placed upon the same 1.07 (46,609
square feet) site as the current use sits. The City Council finds the site is
not adequate in size or shape for the proposed use.” AR 1463.
An agency’s reasoning on an
administrative decision must not be “so conclusory that [it] fail[s] to ‘bridge
the analytic gap between the raw evidence and the ultimate decision or
order.’” Save Livermore Downtown v. City of
Livermore, (2022) 304 Cal.Rptr.3d 103, 108 (quoting Topanga,
supra, 11 Cal.3d at 515); Village
Laguna of Laguna Beach, Inc. v. Board of Supervisors, (“Laguna
Beach”) (1982) 134 Cal.App.3d 1022, 1035 (city did not adequately disclose
its reasons for its administrative decision when all it provided was
“conclusionary, almost boilerplate” language for its findings).
NASA argues that, similar to Laguna
Beach, the City erred in finding that the Project site is “not
adequate in size or shape for the proposed use” by ignoring the objective
determinations and by relying on conclusory, boilerplate language. AR 1421. The evidence demonstrated that the Project site
is adequate for the transfer station.
City staff found that the 1.07-acre Project site is sufficient to
support the transfer station and complies with the necessary setback and
parking requirements. The Project site meets
“development standards for the M-2 zone and … is adequate in size and
shape.” AR
1007. This conclusion is consistent with
the City’s land use element which states that a building size in “industrial
areas may approach 100% lot coverage.” AR 1598.
Pet. Op. Br. at 9.
NASA contends that the public
comments did not present any evidence contradicting the City staff’s
determination that the Project site is of suitable size and shape. To
assuage concerns over the Project size, a project engineer provided examples of
other similar successful projects located on comparably sized sites. AR
1310. Despite this evidence, the City
Council’s Resolution, unguided by any articulated standards or code
requirements, merely recited the square footage of the Project site and the
proposed increase in building size as reasons for its finding. AR
1421. That mere assertion cannot pass
the test of substantial evidence. Pet.
Op. Br. at 9.
The City correctly
states (City Opp. at 7) that the City Council’s written findings are not the
sole means of satisfying Topanga.
“In addition to the findings stated in the council’s resolution, we look
to the transcript of the hearing for statements made by the council members. It
is proper to look for findings in oral remarks made at a public hearing at
which both parties were present, which was recorded and of which a written
transcript could be made.” Lindborg-Dahl
Investors, Inc. v. City of Garden Grove, (1986) 179 Cal. App.
3d. 956, 963.
The City responds that NASA fails to consider the totality of
the evidence. A review of the minutes of
the Planning Commission hearings and the transcript of the City Council hearing
demonstrates that neighboring property owners raised multiple concerns with
respect to the impact on their properties and on the future of south City. A comparison was provided between the waste
transfer facility owned by the City of Los Angeles, which consists of nine
acres along with a two-and-a-half-acre site for parking, as opposed to the
one-acre site for the Project. AR 1307-08. Additionally, the Crown Site in Sun Valley
consists of seven acres, and the Grand Central Recycling and Transfer Station
in the City of Industry consists of three acres, both of which have places for
trucks to queue on site. AR 1296-97.
Accordingly, the City contends that the City Council’s finding
was based on substantial evidence. The
City relies on Harris v. City of Costa Mesa, (“Harris”) (1994) 25
Cal. App. 4th 963, where the court reversed the trial court’s writ of mandate because
the presentations by a neighborhood coalition opposing a project to build a
two-story granny flat on his residential lot were sufficient evidence to
support the city’s denial of a CUP. Harris
relied on Desmond v. County of Contra Costa, (1993) 21 Cal. App. 4th
330, 335, which held that although the city did not articulate any particular
ordinance requirement, the finding that the project is out of character with
the neighborhood may be a summation of several requirements. Id. at 974-75. The Harris project overshadowed the
neighborhood and was detrimental to the welfare and injurious to the immediate
area. Id. at 973-75. The City argues that, like Harris, a
number of neighboring property owners expressed their strong concerns about the
Project. After considering all the
issues and evidence cited, the City Council upheld the Planning Commission’s
denial of the CUP. City Opp. at 8.
The issue is not
whether the City Council made the required finding or whether its finding
satisfies Topanga, but whether it is supported by substantial
evidence. It is not.
Building intensity in industrial
areas may approach 100% lot coverage, less required setback and parking
requirements. AR 1598. As NASA replies (Reply at 5), the City
fails to cite any evidence that the Project site is not of adequate size and
shape for the proposed transfer station.
Aside from the fact that most do not address the size and shape of the
Project site, the comments of neighboring property owners lack expertise to opine
on this issue. The only comments
addressing the size and shape issue were lay comparisons of the Project site to
the size and nature of other waste facilities.
AR
1307-08, 1296-97. However, a NASA representative explained to the
City Council that these facilities were not transfer stations; they are
material recovery facilities which have different operations from a transfer
station. AR 1309. As a result, they are not a good
comparison. NASA’s Project engineer
provided a comparison of the Project site to other similar projects, noting similar
successful projects on “similar sized parcels” at the Universal Waste Systems
transfer station in Santa Fe Springs and in downtown Los Angeles. AR 1310.
NASA is correct that neither the City
nor any Project opponent rebutted the Project engineer with substantial
evidence. Reply at 5-6.
The City Council’s
finding that the Project site is not adequate in size or shape for the proposed
use is not supported by substantial evidence.[4]
3. Whether the Project
Site Has Sufficient Access to the Streets and Highways to Support the Project’s
Traffic
The City Council made the
following finding:
“While the streets and
highways that serve the Project Site are designed to accommodate heavy
industrial vehicles such as those associated with the proposed transfer station
and the surrounding warehouse/distribution and trucking business, the number of
inbound and outbound truck traffic impacts would increase from the current
volume of 104 trips per day to 530 trips per day. This would create five (5)
times more truck traffic volume than currently exists at this location and
would have a detrimental impact upon traffic in the surrounding area. The City
Council finds that the intensified use as proposed by the Applicant does not
have sufficient access to streets or highways of the right of ways leading to
the Project location. In addition, the city Council finds the increased truck
traffic impacts would have a detrimental impact to the pavement and general
infrastructure of the area. AR 1463-64.
NASA argues that the City Council erred
in finding that the proposed transfer station use “does not have sufficient
access to streets or highways of the right of ways leading to the Project
location” and that “the increased truck traffic impacts would have a
detrimental impact to the pavement and general infrastructure of the
area.” AR
1421-22. This finding is unsupported by
any data or standards, contradicted the City staff determinations, disregarded
the City’s traffic guidelines, and ignored NASA’s commitments to mitigate the
Project’s impacts. Pet. Op. Br. at 10.
First, the City Council
contradicted itself and erred in its analysis.
The Resolution found that the streets and highways adjacent to the
Project Site are “designed to accommodate heavy industrial vehicles such as
those associated with the Project,” as well as the vehicles used by the
surrounding warehouse and trucking businesses.
AR 1421. Then, in the same finding, the City
stated that those same trucks “would have a detrimental impact to the pavement
and general infrastructure of the area.”
AR 1464. In fact, NASA’s vehicles are specifically
built for residential neighborhoods and thus are easily suitable for the heavy
industrial roads adjacent to the Project site.
AR 1008. Pet. Op. Br. at 10.
The City Council’s primary concern was the increase in the
quantity of trucks that would use the Project site each day. AR
1463-64. However, the Resolution cited 530
trips per day, which is much greater than the amount of traffic presented for
the Project at the City Council meeting.
In a letter presented to the City Council before its hearing, NASA
voluntarily reduced the Project’s total tonnage by 50%, thus decreasing the
Project’s daily vehicle trips from 530 trips per day to 378. AR
1824. The City Council made its
determination based on inaccurate figures.
Reply at 6-7.
Second, the initial study showed
that the Project’s vehicle trips would be well below the vehicle threshold
established by the City’s Guidelines for Process and Requirements for Traffic
Impact Study Reports. City
staff explained that the Project would reduce the overall vehicle miles
traveled in the City by waste trucks by allowing smaller waste trucks to
efficiently transfer their waste on to larger vehicles. AR 424, 437.
There would be a projected maximum of 32 vehicle trips per hour,
which is 36% lower than the City’s threshold of 50 vehicles for a project. The City Council ignored the fact that the
surrounding infrastructure would adequately support the Project and instead
relied on mere assertions that there would be “heavy traffic”. AR 1175,
1195, 1421. Yet, there was no testimony
evidencing that the Project’s traffic would have a detrimental impact on the
surrounding infrastructure. Pet. Op. Br. at 10.
The City responds that substantial
evidence may include statements of neighbors if they are based on relevant
personal observations or involve non-technical issues. Bowman, supra, 122 Cal. App.
4th at 583. The City Council received a
letter from NASA before the hearing which indicated that new truck trips would
be reduced from 426 to 274. AR 1824.
Pet. Op. Br. at 10, n. 4.[5] Neighboring
property owners indicated that, even with a reduction to 274 trips a day,
trucks would still be entering and leaving the facility every three to four
minutes and would need to queue on the public streets due to the lack of
sufficient parking and turnaround space on the Project site. AR 1296.
Multiple property owners provided testimony that the Project site is
located at the intersection of two small streets (Union and Gage Streets) and
expressed concern that there is insufficient space on those streets for truck
queuing. Testimony was also provided on the current traffic issues in the area
and the problems additional Project traffic to and from the site would cause. AR 1303, 1304, 1308, 1320. City Opp. at 9-10.
The problem with the concern of Project opponents about
parking, queuing, and turnaround space is that it
is unsupported speculation. While the
Project opponents can certainly complain about increased traffic, their opinions
on the technical aspects of traffic design cannot serve as substantial evidence. See Bowman, supra, 122
Cal.App.4th at 583.
NASA’s application states that the Project is designed to allow
for “adequate room for vehicle circulation and maneuvering,” and an “efficient
circulation pattern that minimizes cross traffic” with a one-way traffic flow
throughout the facility. See AR 3. City staff agreed, concluding that the streets
and highways that serve the Project site are designed to accommodate the heavy
industrial vehicles the Project would use.
AR 1007. The site is in an
industrial area zoned M-2 (Heavy Manufacturing), with frontage on Union Street
and Gage Road. AR 1007. Two major roads, Greenwood Avenue and
Telegraph Road, provide access to Union and Gage, respectively. AR 1008.
The truck traffic would mostly consist of collection vehicles, which are
maneuverable and accessible to standard residential and commercial neighborhoods. AR 1008.
Access to the I-5 Freeway is therefore available via streets adequate in
width, pavement type, and classification to accommodate a proposed transfer
station. AR 1008.
The property owner complaints that Gage and Union are too
small and lack sufficient space, are undermined by the facts that the Project
site is located one block from the I-5 Freeway and the General Plan land use
element states that “[f]rontage along Santa Ana Freeway [I-5] should be
preserved for industrial and compatible commercial development.” AR
1598. In any event, to address the concern
about trucks queuing on public roads, NASA’s project engineer explained to the
City Council that NASA would prevent queuing by controlling when their vehicles
access the site, which has been done successfully on similarly-sized
projects. AR 1310.
As NASA argues, neither the City nor any Project opponents presented any
facts or analysis to rebut the Project engineer’s solution. Reply at 7.
There also is no evidence that the Project’s traffic would
have a detrimental impact on the surrounding pavement and infrastructure. The streets and highways that serve the
Project site are designed to accommodate the heavy industrial vehicles NASA
would use. AR 1007. Access to the I-5 Freeway is therefore
available via streets adequate in width, pavement type, and classification to
accommodate a proposed transfer station.
AR 1008.
The City Council’s finding that the proposed transfer station use
does not have sufficient access to streets or highways of the right of ways
leading to the Project location and that the increased truck traffic would have
a detrimental impact to the pavement and general infrastructure of the area is
not supported by substantial evidence.
The
City Council found:
“The proposed use is
located in the M-2 (Heavy Manufacturing) zone, and is bordered by industrial
(Heavy Manufacturing) development in all directions. While the project complies with the M-2
designated land use, it will have an adverse impact on adjacent or abutting
properties….[n]umerous business and property owners, residents, and interested
property (sic.) testified…of the numerous adverse impacts this proposed
use would have both directly and indirectly upon adjacent and abutting
properties and business operations.
After carefully considering the testimony presented, the City Council finds
that the proposed use will have an adverse effect upon adjacent and abutting
properties.” AR 1464.
NASA argues that the City Council improperly
ignored the numerous state-of-the-art minimization measures integrated into the
Project’s design and relied on baseless, inflammatory remarks from Project
opponents. Project opponents presented
no more than a practiced recital of alleged future effects, citing no evidence
or thresholds of significance to indicate that the Project would cause
“traffic, unpleasant odors, pest infestation, health hazards, and more.” AR 450 1175.
These claims assumed a project vastly different in scope, technology, and
mitigation than the actual Project. For
each such alleged impact, NASA designed the Project to render any impact either
non-existent or insignificant. Pet. Op.
Br. at 11.
None of the Project opponents
provided support for their concerns, and they amount to the generalized, vague,
and nonspecific statements from project opponents that cannot amount to
substantial evidence. Lucas
Valley Homeowners Assn. v. County of Marin, (“Lucas Valley”)
(1991) 233 Cal.App.3d 130, 157. For example, nearly all the opponents cited
concerns over odor and vermin that would become “intolerable.” AR 456.
Yet, the evidence demonstrates numerous measures to prevent the
realization of the asserted concerns. To
control vector issues, operations would occur indoors, and NASA would employ
regular vector control. AR 1312.
Any odor and run-off concerns are mitigated by the fact that all
operations would be entirely inside the state-of-the-art building which would
employ a negative air pressure system and onsite stormwater infiltration system
to prevent potential runoff. AR 1310-11.
The Project also is subject to regulatory oversight from numerous
agencies including the Los Angeles County Health Department and the SCAQMD. AR 1310-11.
Intervenors respond that the City Council’s finding is well grounded. The EPA has documented the environmental
impacts of waste transfer stations. AR
513, 515. The existence of poor drainage at the
intersection of Gage Road and Union Avenue has been documented in the City’s
General Plan since 1973. AR 1633. Furthermore, personal
observations of residents on non-technical subjects such as traffic qualify as substantial evidence.
Taxpayers for Accountable School Bond Spending v. San Diego Unified
School Dist., (2013) 215 Cal.App.4th 1013, 1054 (resident testimony regarding traffic congestion and
accidents associated with events at a school stadium constituted substantial
evidence); Keep Our
Mountains Quiet v. County of Santa Clara, (“Keep Our Mountains”)
(2015) 236 Cal.App.4th 714, 735 (traffic conditions raised by
neighbors with personal knowledge of existing hazardous road conditions where
proposed use posed a significant increase in traffic during certain periods of
the day constitute substantial evidence).
The evidence presented by these adjacent and abutting property owners demonstrated
that the Project’s operations would bring impacts including odors, health
concerns, stormwater runoff, traffic, noise, vectors, and litter, and that such
impacts would adversely impact their properties. AR 449-50, 452, 454, 456, 461,
480, 515, 518-19, 588, 593, 612, 614, 1195, 1282, 1303-04, 1436. Int. Opp. at 2-3, 5.
NASA’s own environmental consultants admitted to the existence
of these impacts, stating that “one of the big concerns” posed by the Project
was vector control, and also referred to other impacts of odor, dust, traffic,
noise, stormwater, and air quality. AR
84-85, 521-22. The initial study
documented some of these adverse impacts.
AR 733 (“[t]he project may result in odor emissions resulting from the
solid waste material”); AR 739 (the potential for “incidental hazardous waste” will
be handled by the Department of Toxic Substance Control); AR 646 (acknowledging
noise increase and linking to noise ordinance standards); AR 741 (documenting
the fivefold increase in vehicle traffic).
Int. Opp. at 5.
Intervenors add that the City was not required to treat
these impacts as non-existent simply because NASA’s environmental consultants stated
that the impacts would be minimized by a state-of-the-art facility that will
comply with regulatory permitting requirements, including a negative air pressure
system to minimize odors, will conduct all tipping and loading activities
inside the building, and will employ “regular vector control”. AR 437, 521-22,
1310-12. Minimizing impacts does not
necessarily eliminate them. Despite the
fact that all tipping and loading activities would be conducted inside the
building, the Project’s operations necessarily include the ingress/egress of
full-size garbage trucks at the Project site every three to four minutes, each time
requiring rolling up of the doors to the facility, bringing odors, emissions,
and noise, and allowing vectors to escape while the doors are open. AR 513-14, 1320-21. The noise, traffic, odor
and vector impacts of these outdoor operations alone are adverse impacts on the
adjacent and abutting properties. Int.
Opp. at 5-6.[6]
For these reasons, the City found adverse impacts to the
adjacent and abutting properties. AR
1833 (Resolution); AR 520 (Commissioner Ramirez raising concerns regarding
stormwater runoff); AR 521 (Commissioner Cuevas finding the rodent, traffic and
truck queuing impacts adverse to existing businesses, especially hotel and food
type businesses); AR 1319-21 (Mayor Pro Temp Torres noting that businesses that
handle food and need sanitary conditions, apparel companies and the hotel use
would be particularly impacted by the increase in traffic, vectors, noise and
odors operating as early as 3 a.m.).
Int. Opp. at 4.
Intervenors distinguish Lucas Valley, supra, 233
Cal.App.3d at 130. Unlike Lucas,
the adverse impacts were substantiated.
It is not speculative that full-sized garbage trucks driving past a
hotel, an office, hospitality, or apparel showroom use every three to four
minutes, starting at 3 a.m. and ending at 8 p.m., pose adverse noise, odor, and
transportation impacts. It is also neither vague nor nonspecific that the
vectors attracted to the garbage will adversely impact adjacent business uses,
particularly medical, and food and beverage processing facilities sensitive to
a clean and sanitary environment. Int.
Opp. at 4.
NASA first replies that Intervenors attempt
to move the goalpost beyond the limited scope of “adjacent or abutting
properties.” The term “adjacent” is defined as “lots or
objects which are located in close proximity to each other (separated only by an
alley, street, highway or recorded easement)”.
MMC §§ 17.08.010. The term “abut” is defined as “two or more
lots or parcels of land sharing a common boundary line.” MMC §17.08.030. The City Council understood the limited scope
of this required finding when it stated that the Project “is bordered by
Industrial (Heavy Manufacturing) development in all directions.” AR 1464,
1468 (aerial photograph of the Project site and adjacent and/or abutting
properties). Intervenors try, but fail,
to find substantial evidence of the Project’s harmful impacts to properties
outside the scope of the required finding by mislabeling numerous properties as
adjacent or abutting the Project site, including a hotel nearly a block away. Thus, Intervenors mislabel the following
properties as adjacent or abutting the Project site: 1640 S. Greenwood Ave.,
1725 Gage Road, 1801 Gage Road, and 1550 Gage Road. Reply at
8.
This would be a
good point if it were raised in NASA’s moving papers. NASA was required to criticize the City
Council’s reliance on comments from property owners who are not adjacent to, or
did not abut, the Project site and could not wait until Intervenors also relied
on those property owner comments. NASA’s
suggestion that the City Council understood the limited scope of the
permissible comments by noting that the Project “is bordered by Industrial
(Heavy Manufacturing) development in all directions” is a non-sequitur. It is clear that the City Council accepted
all comments from neighboring owners and businesses. NASA’s failure to raise the issue of the
scope of permissible comments in its moving papers waives this point. Regency Outdoor
Advertising v. Carolina Lances, Inc., (1995) 31 Cal.App.4th 1323, 1333 (New
evidence/issues raised for the first time in a reply brief are not properly
presented to a trial court and may be disregarded). In any event, NASA fails to cite any evidence
demonstrating that the four listed properties are not adjacent to or abut the
Project site.
The impacts of health, vectors, litter, and property values[7] are not sufficiently raised in the comments
of property owners. Therefore, the City
Council’s finding of adverse effects is not supported by those issues. NASA then argues the issues of runoff, odor,
noise, and traffic.
Runoff
Property owners testified that there is drainage and water
runoff from the Project site onto adjacent properties. AR 257, 450, 456, 1175. Intervenors contend that, without any evidence
that compliance with stormwater regulations would address this problem and the
Project’s contribution to it, NASA’s representatives simply claimed that the
Project would comply with regulatory stormwater regulations. AR 522.
Int. Opp. at 3.
NASA argues that the property owners’ concern
about drainage and runoff is unsupported.
Project engineers testified that the Project would ensure that the
potential for stormwater impacts is “very, very low,” by operating completely
indoors, using clarifiers and bioswales (channels to remove pollution from
runoff), testing “all stormwater runoff leaving the site,” and complying with
the Regional Water Quality Control Board industrial wastewater standards. AR
1311. No one answered that evidence in
any fashion. Reply at 9.
The court agrees. The existence of the poor drainage condition at the
intersection of Gage Road and Union Avenue has been documented in the General
Plan since 1973. AR 1629–33. Adjacent
and abutting property owners testified regarding ongoing drainage and water
runoff from the Project site onto adjacent properties. AR 257, 450, 456, 903, 1175. Thus, there is evidence that there is poor
drainage at the Project site and that water runoff on adjacent properties has
occurred. But there is no evidence that
water runoff from the Project would
“inevitably happen.” AR 1175. No engineering or other reports or studies
were relied upon for the inevitability to which the opponent speculated. See Porterville Citizens for Responsible Hillside Development v. City of
Porterville, (2007) 157 Cal.4th 885, 907 (unqualified neighbor’s
concerns over drainage was not substantial evidence). There
is not substantial evidence supporting the City Council’s finding stormwater
runoff from the Project would be an adverse impact on property and business
owners.
Odor
A concern about odor from the Project’s
building and trucks is legitimate. NASA
argues that the concern of property owners that the Project would result in intolerably unpleasant
smells are vague speculations fail to address the air quality mitigation
measures in place at the Project site. AR 454.
The Project’s odor issues were addressed in
the staff report, initial study, and the testimony of Project engineers, all
stating that the Project would neutralize odors by operating completely
indoors, employing a negative air pressure system and an overhead misting
system equipped with neutralizing agents to actively counteract any odorous
particles. AR 1479, 1311, 732. Reply at 9.
NASA is correct that the City and Intervenors
fail to answer NASA’s evidence on the adequacy of its technical,
state-of-the-art odor control system. The
mere suggestion that odors will
escape when the building’s door is opened is unsupported by evidence. AR 513-14, 1320-21. In addition, all NASA
vehicles use CNG fuel to minimize air quality impacts and the Project site is
subject to regulatory oversight from the Los Angeles County Health Department
and the SCAQMD. AR 1310-11. Pet. Op. Br. at 17.
Intervenors point out that odor impacts from the trucks
themselves was not addressed in the initial study. AR 732-33 (air quality analysis). Int. Opp. at 13. True, but that is not substantial evidence of
that property owners will be adversely impacted by odor from the trucks either.
There
is not substantial evidence supporting the City Council’s finding that odor
from the Project’s operation would adversely impact property owners.
Noise
Intervenors point out that the Project initially sought to
bring 1,500 tons of solid waste to the Project site, increasing truck trips
over five times from the existing 104 daily trips to 530 daily trips.[8] AR 18, 1833.
In a last-ditch effort, NASA reduced the Project to bring daily solid
waste of 750 tons, increasing truck vehicle trips to 378 per day, still two and
half times more than the existing 104 trips per day. AR 1824.
For an operation between the hours 3 a.m. and 8 p.m., even 378 trips means
that a truck would enter the Project site every three minutes. These are large
garbage collection vehicles (AR 438-39), each coming to and leaving from the
Project every three to four minutes, bringing odors, emissions, and noise, requiring
the rolling up of the doors to the facility, and allowing vectors to escape while
the doors are open. AR 513-14,
1320-21. Int. Opp. at 3-4.
NASA notes that any
potential noise concerns were addressed by the fact that the Project will be an
entirely indoor operation. AR 1487.
In addition, the Project will be compliant with the applicable noise
ordinances and standards set forth in the General Plan. Ibid. NASA
argues that Project opponents do not provide any details why the indoor Project
would exceed the applicable noise standards in the industrial zone. The General Plan noise element states that noise levels within industrial
zones may be higher than in residential and commercial zones. AR 1567. See Jenson v. City of Santa Rosa,
(2018) 23 Cal.App.5th 877, 894 (noise calculations presented by neighbors were opinions
of non-experts and not substantial evidence).
The opponents’ mere assertion that the Project would result in a
“huge noise disruption” is not substantial evidence. AR 1304,
1224. Pet. Op. Br. at 17; Reply at 9.
The court accepts that the City Council lacks
substantial evidence of noise from the indoor operation. But NASA ignores the fact that the trucks
coming to and from the Project site will make noise. Although the
Project site is in the M-2 (Heavy Manufacturing) zone, the adjacent and
abutting properties to the Project site are office, hospitality, warehousing,
medical, distribution and food and beverage processing facilities, and apparel
showroom space. AR 449, 454, 456, 461, 480, 518, 593, 612, 614, 1195, 1436. The current operations on Gage Road are
described as very quiet. AR 581, 593. The
Quality Inn & Suites also is located a few doors away from the Project
site. AR 449, 452.
The Project’s operations necessarily include the
ingress/egress of garbage trucks driving in and out of the Project site every three
to four minutes between 3 a.m. and 8 p.m. This would be a significant increase from
current operations. Property owners stated
that this number of trucks would cause an undue noise impact on their operations. AR
452, 454, 480, 519, 1136. Property owners can
testify to the existence of disruptive noise even if they cannot scientifically
calculate it. See Jenson, supra,
23 Cal.App.5th at 894. It also is
well-settled that compliance
with a noise ordinance does not foreclose possibility of significant noise
impacts under CEQA (Keep Our
Mountains, supra, 236
Cal.App.4th at 732) and it certainly does not prevent the City
Council from considering noise impacts on adjacent properties. Int. Opp. at 12.
NASA notes that Intervenors cited concerns of
a hotel owner who testified that traffic “starting at 3:00 or 4:00 in the
morning will surely be a huge impact negatively on my hotel.” AR
1304. These concerns ignored the fact
that the current operation at the Project site opens at 3 a.m., six days a
week, with 104 daily vehicle trips. AR 1468.
Yet, the hotel owner previously never stated a concern about the 3 a.m. opening. Notably,
the hotel property is adjacent to Telegraph Road, which is designated as a
truck route, and is across the street from the I-5 freeway. Reply at 10.
This
point does not address the hotel owner’s concern about increase in truck
traffic at 3:00 a.m., nor its or any other property owners’ concerns. There is substantial evidence supporting the
City Council’s finding that noise from the trucks would have an adverse impact
on property and business owners.
Traffic
Property owners testified about
the already congested traffic in the area (AR 1195,
1442, 1281-82) and
that the addition of large amounts of garbage truck traffic (an additional 2.5
times the current traffic level) would further add to the traffic conditions
and adversely impact their businesses and operations. AR 454, 456, 461, 480, 513-14, 1195, 1442,
1444, 1281-82. Property owners testified
that the addition of 2.5 times the current level of garbage truck traffic on
Union (AR 1195, 1442), and from Greenwood to Union (AR 1281-82), plus queuing
at the site, would further add to the traffic conditions and adversely impact
their businesses and operations. AR 454,
456, 461, 480, 513-14, 1195, 1442, 1444, 1281-82.
NASA contends that the property
owners’ assertions about heavy traffic were speculative, without traffic
studies to support them. AR 1421, 1175,
1195. These lay opinions do not
constitute substantial evidence and are directly contradicted by the Project’s
environmental engineers who stated that traffic from the Project would not only
fall well below the City’s peak thresholds for traffic impacts in the
industrial zone but would result in an overall decrease in the number of
vehicle miles traveled by local garbage trucks.
AR 1311, 437. Pet. Op. Br. at 16.
NASA distinguishes Keep Our
Mountains, supra, 236 Cal.App.4th at 7126-27, 735-36, as a
case in which neighboring project opponents in a rural area presented exact
measurements demonstrating that a single-lane mountain road was narrower than
the standard requirements and was missing certain standard safety
requirements. Ibid.
These arguments were also corroborated by an expert traffic
consultant. Ibid.
In contrast, the City staff confirmed that the street adjacent to the
Project site is “designed to accommodate heavy industrial vehicles.” Reply at 10.
The court agrees. Property owners can testify generally to
traffic congestion, but they cannot opine on the Project’s impact on that
traffic congestion without a traffic study.
There also is no evidence of queuing.
As a result, there
is not substantial evidence supporting the City Council’s finding that
increased traffic from the Project would have an adverse impact on property
owners.
5. Whether the Project
Complies With All the Applicable Goals and Polices of the General Plan
The City Council found:
“The
project is not consistent with the goals and policies of the General Plan,
specifically; (sic).
General
Plan Goal #4: “[T]o provide for growth and development of an industrial area in
a manner compatible with other uses”
The
City Council finds the proposed Project is an intensified use that is not compatible
with other adjacent industrial uses. The
increased truck traffic, solid waste disposal and processing, noise, odors,
potential rodent infestation, and related impacts create circumstances which
are incompatible with other surrounding and adjacent uses…..” AR 1464.
The fourth goal of
the General Plan’s land use element is to provide for growth and development of
an industrial area in a manner compatible with other uses. AR 1594-95.
The City’s industrial area should be preserved and maintained. AR 1597.
Frontage along Santa Ana Freeway should be preserved for industrial and
compatible commercial development. AR
1598.
NASA argues that the City Council erred
in finding that the Project is not consistent with the goals and policies of
the General Plan. AR 1422.
A CUP must be consistent with a City’s lawful general plan and zoning
requirements. Neighborhood Action Group v.
County of Calaveras, (1984) 156 Cal.App.3d 1176, 1185. The City staff report stated that the Project
is “consistent with the goals and policies of the General Plan, specifically:
Goal #1: [T]o Formulate a plan which is responsive to the needs of the
community …” and Goal #4: “[T]o provide for growth and development of an
industrial area in a manner compatible with other uses.” AR 1007.
City staff further stated that the Project site is the ideal site to
provide a vital service to the community and “provide adequate community
infrastructure to support and service industrial development across the
City.” Ibid.
This reasoning was consistent with the initial study, which stated that
the Project would be located in the area “reserved for the heaviest industrial uses in the City” and
“would not conflict with any land use plan, policy or regulation.” AR
960. During the City Council meeting,
one Councilmember concluded that the Project is plainly consistent with the
General Plan and that the Project area is zoned “for something specific like
this.” AR
1332. Another stated that the Project is
consistent with the City’s land use element and “bordered by industrial
development in all directions.” AR 1316.
Pet. Op. Br. at 12.
The
court disagrees. As Intervenors argue
(Int. Opp. at 6-7), the City Council found that the Project is not consistent
with General Plan Goal #4 “to provide for growth and development of an
industrial area in a manner compatible with other uses.” AR 1833
(emphasis added). The City Council found
that the Project presented an intensified use not compatible with other
adjacent industrial uses and that the increased truck traffic, solid waste
disposal and processing, noise, odors, potential rodent infestation, and
related impacts would be incompatible with other surrounding and adjacent
uses. AR 1833.
The Project is an intensified
use of garbage trucks on a relatively quiet street with light industry
neighbors consisting of office,
hospitality, warehousing, medical, distribution and food and beverage
processing facilities, and apparel showroom space. AR 449, 454, 456, 461, 480,
518, 593, 612, 614, 1195, 1436. The fact
that the Project site is zoned for M-2 (Heavy Manufacturing) Zone with a
General Plan land use designation of Industrial
does not detract from this fact. Nor
does the fact that some of these impacts -- solid waste disposal and
processing, noise, odors, rodents – are not supported by evidence. There is substantial evidence that the
Project does not meet Goal #4 of a development in a manner compatible with
surrounding uses. A trail of garbage
trucks every three minutes from 3 a.m.
to 8 p.m. is not compatible with the surrounding property uses.
NASA relies on Mitcheltree
v. City of Los Angeles, (“Mitcheltree”) (1971) 17 Cal.App.3d
791, 796-97, n. 4, the court held that a city in the process of developing a
general plan could not rely on it to influence its findings on a CUP. See also J.L. Thomas, Inc. v. County of Los
Angeles, (“J.L.
Thomas”) (1991) 232 Cal.App.3d 916, 927 (irrelevant that the project was
inconsistent with the area’s redevelopment activities when such a finding was
not required for the CUP determination).
NASA contends that the City Council did not simply rely on a not-yet
finalized general plan as in Mitcheltree, it relied on a mere vision
for a future plan, ignoring evidence of the Project’s consistency with the
current General Plan. This reasoning led
the City to the unsupported conclusion that the Project would “create
circumstances which are incompatible with other surrounding and adjacent
uses.” AR
1422. Pet. Op. Br. at 12-13.
During the City Council’s deliberations, Mayor Pro Temp
Torres explained that the City was currently revising the General Plan to
determine what it should look like for the next 10-15 years. AR 1319.
A decision authorizing an intensive use for the Project site like a
solid waste transfer facility will determine the future of the surrounding
area. AR 1319-20. The City Council now has the opportunity to
imagine what to do with the area, including “cleaner uses”. AR 1320, 1323-24. Councilmember Peralta reiterated that the
General Plan has not been updated since 1973 and this area is not the right
area for this Project. AR 1327. Councilmember Jimenez emphasized that while
the City will update its General Plan at some point, for now the area is still
zoned for heavy manufacturing. AR
1332. Councilmember Melendez stated that
the current General Plan allows the Project, and the City Council should not be
telling the business community that it cannot have a project that meets the
zoning standards. AR 1336.
It is unfortunate that two City
Councilmembers referred to how the General Plan might look in the future in
discussing the Project; reliance upon an as-yet unadopted general plan is
unlawful under Mitcheltree and J.L. Thomas. However, the mere
fact that these two Councilmembers suggested that a future General Plan may not
permit such a Project does not mean that they relied on a future plan in their
vote; both Councilmembers set forth other
reasons why they voted to deny the CUP. NASA
fails
to provide any authority that a discussion about potential future City goals is
inappropriate.
The City Council’s finding that the Project
does not comply with all the applicable goals and policies of the General Plan
is supported by substantial evidence.
As an alternative to a new CUP,
NASA sought a CUP modification based on the Project site’s previous approved
use as a glass recycling plant. AR 513, 520.
To approve a CUP modification, the City must find that “such
modification is necessary to protect the public interest and/or adjacent or
abutting properties.” MMC §17.70.130. The City Council found that,
based on all the evidence presented, the Project is “not in the public interest
and does not benefit the existing uses of adjacent or abutting
properties.” AR 1423.
NASA argues that the Resolution parroted
a conclusion that the Project “is not in the public interest and does not
benefit the existing uses of adjacent or abutting properties.” See MMC §17.70.130. This is not sufficient to “bridge
the analytic gap between the raw evidence and the ultimate decision” necessary
to constitute substantial evidence. Topanga,
supra, 11 Cal.3d at 515. Reply at 12.
NASA notes that in Goat
Hill Tavern v. Costa Mesa, (“Goat Hill”) (1992) 6 Cal.App.4th 1519, 1531, the court held that a
city’s administrative determination to deny a CUP renewal based on the adverse
impacts to surrounding neighbors was improper due to a lack of substantial
evidence. The neighboring property owners stated vague
concerns relating to noise and sanitation (id. at 1524) and the court held that these concerns contrasted with
the evidence presented by the project proponent that mitigated these
concerns. Id. at 1531.
NASA argues that, as in Goat
Hill, nearly all the evidence in the instant case contrasts
dramatically with the speculative and vague concerns of the Project
opponents. The evidence confirms that
the Project serves the public interest by providing a necessary public service
within the City. According to the City staff
report, “the modification to the existing conditional use permit will facilitate
the public good and protect the public interest.” AR
555. Staff determined that the Project
will allow NASA to “provide an essential service to the Montebello community”
with “adequate community infrastructure to support and service City
residents.” Ibid.
The Project also will “provide a vital service to the local community by
facilitating efficient transfer of solid waste.” Ibid. Not only is the Project site
a prime location to provide this essential service, it also is carefully
designed to minimize any potential adverse impacts to its neighboring
properties. AR 869-70.
Further, a Project engineer informed the City Council that the
Project would benefit the region by reducing regional pollution through a
decrease in vehicle miles traveled for waste services vehicles. AR
1340. City staff concluded that the
Project would “facilitate the public good and protect the public interest” and
“will be an asset to the area.” AR 321-22.
NASA argues that, instead of
relying on the demonstrable realities of Project design and planning, the City
Council relied on speculative claims that the Project is incompatible with the
surrounding industrial uses, despite the fact that the General Plan’s land use
element states that the “industrial area should be preserved and
maintained.” AR 1567.
There is insufficient evidence to support the City’s conclusory
assertion that the Project is not in the public interest and does not benefit
the surrounding uses. Pet. Op. Br. at
13-14; Reply at 12.
The City responds that the record shows that NASA uses the
Project site as a truck yard and seeks to change this current use to a solid
waste transfer station. “Changes in
operation by businesses…are subject to review by local zoning authorities who
exercise their police power for the welfare of the community.” Breakzone Billiards v. City of Torrance,
(“Breakzone”) (2000) 81 Cal. App. 4th 1205, 1248. “In reaching a decision on an application for
a CUP it is also appropriate for an agency to consider traffic, parking,
safety, noise and nuisance problems; these clearly represent concerns that are
well within the domain of the public interest and public welfare.” Breakzone, supra, 81 Cal. App.
4th at, 1246. City Opp. at 12.
Intervenors and the City argue that
the City Council’s finding that the Project is not in the public
interest and did not benefit the surrounding uses is supported by substantial evidence.
The evidence of the Project’s
incompatibility with, and adverse impacts upon, adjacent and abutting
properties shows that it does protect or benefit them. The property owners’
evidence was neither speculative nor vague and their concerns were
critical in determining that the Project does not serve the public interest. Int. Opp. at 8; City Opp. at 11.
The City staff report indicated
that the Project would enable NASA to provide an essential service to the
community and would thus facilitate the public good and protect the public
interest. AR 555. However, the record
also reflects countervailing evidence that the negative effects of the Project
would substantially exceed whatever benefit it might provide to the City and
its residents. The Resolution
articulates specific evidence that the Project is not compatible with the
surrounding property uses and does not support the goals and policies for
proper industrial growth and development. AR 1831.
City Opp. at 11-12.
The City Council Resolution specified
that: (a) the owners of four adjacent properties provided testimony that the
environmental and health impacts of the Project would diminish property values
in the area; (b) over 20 adjacent property owners or residents expressed their
view that granting the requested modification was not in the best interests of,
or compatible with, the existing industrial uses in the area; and (c) the Project’s
significant increase in solid waste transported primarily from surrounding
communities to the Project site imposes on the City a burden of processing
waste not generated within its borders. AR
1832.[9]
NASA replies that neither the
City nor Intervenors invoke any evidence suggesting that the Project would not
confer important public benefits. The
City simply restates its own findings from the Resolution and fails to provide
specific citations of any of the neighbor opinions. There is insufficient evidence to support the
conclusory assertion that the Project is not in the public interest and does
not benefit the surrounding uses. Reply
at 12-13.
The answer is that the Resolution
relied on all the evidence presented to conclude that the Project is
“not in the public interest and does not benefit the existing uses of adjacent
or abutting properties.” AR 1423. This includes the evidence supporting denial
of the CUP because noise from the trucks would have an adverse impact on
property owners and because the Project does not comply with all the applicable goals
and policies of the General Plan. It
also includes evidence that the Project’s significant increase in solid waste
transported primarily from surrounding communities to the Project site imposes
on the City a burden of processing waste not generated within its borders. There is no doubt that the Project would provide a general
regional benefit, but the City Council was entitled to consider the impact on
its residents, particularly the property owners.
There is substantial evidence to
support the City Council’s conclusion that a modified CUP is not necessary
to protect the public interest of City residents and adjacent or abutting
properties. MMC §17.70.130.[10]
F.
Conclusion
The Petition is denied.
The stayed damages claims are ordered transferred to Department 1 for
assignment to an I/C court.
[3]
For convenience, the court will refer solely to neighboring “property owners” and
not “businesses and property owners”.
[4] Harris
is inapplicable both because the City cannot rely on a summation of ordinance
factors when dealing with a specific required finding and because there is no
supporting evidence for this required finding.
[5]
The new trips of 274 are consistent with the total of 378 discussed by
NASA.
[6] Intervenors
correctly note (Int. Opp. at 5-6) that the arguments of NASA’s environmental
consultants were tailored to an environmental impacts analysis under CEQA. Whether a particular impact meets a threshold
for review or mitigation under CEQA does not control whether the Project will
have an adverse effect on
adjacent and abutting properties under the MMC. The City disagreed
with the CEQA analysis anyway. AR
520-21, 1319-20, 1833.
[7] Property owners testified that the Project would result in
decreased property values. See,
e.g., AR 1291 (broadly stating the Project’s impact on property values
would be “horrific”). A project
opponent’s “general allusions to property values” will only amount to
“speculative, imprecise opinion[s],” not substantial evidence. Lucas
Valley, supra, 233
Cal.App.3d at 157. The property owners
failed to provide facts to support their assertions that the Project would
result in a decrease in property values.
Pet. Op. Br. at 11-12.
Property owners also testified to
the stigma of a waste processing plant in the area. AR 452, 1224.
The stigma created by a solid waste
transfer use would have a negative impact on their business operations and
hinder their availability to attract investors and tenants. AR 452, 478, 515. The reputation of the area would suffer. AR 452. This, too, is an irrelevant generalization too
vague and non-specific to amount to substantial evidence. Lucas Valley, supra, 233 Cal.App.3d at 157.
[8] NASA refers to this increase as 104 to 426,
referring only the change, not the total number of generated trips. AR 18. Int. Opp. at 3, n.1.
[9] Intervenors
argue that NASA’s reliance on Goat Hill is misplaced. Goat Hill presented a set of unique
facts leading the court apply the independent judgment standard of review to the
city’s denial of a CUP renewal because the applicant had established vested
rights to operate Goat Hill Tavern. 6
Cal.App.4th at 1519-30. Goat Hill had little to do with
whether opposing neighbors presented substantial evidence of impacts. In fact, the court found the circumstances
more like the city was revoking a CUP than denying one. Id. at 1529-30. Int. Opp. at 9. NASA explains that its citation of Goat Hill was made to show the kind of evidence that qualifies as
substantial evidence, not to claim any vested rights for the standard of review. Reply at 12-13.
[10] NASA
notes that this is not a CEQA case and
that it addresses the adequacy of the initial study only to argue that the City
Council erred when it refused to adopt the Project’s negative declaration. AR
1465. Pet. Op. Br. at 15. Intervenors point out that CEQA does
not apply to projects which are denied. Pub. Res. Code §21080(b)(5); see
also AR 1418. Thus, the City was not
required to make any CEQA findings. Int.
Opp. at 9.
Given that the court has found
that substantial evidence supports the City Council’s denial of a CUP, and a
modification of the existing CUP, it need not address the adequacy of the City
Council’s CEQA determination. Nor
does the court need to address the parties’ debate about whether the court
lawfully can issue a writ of mandate commanding approval of the CUP application
under CCP section 1094.5(f). Compare City
Opp. at 12-13 and Reply at
14.