Judge: James C. Chalfant, Case: 22STCP03172, Date: 2022-09-08 Tentative Ruling
Case Number: 22STCP03172 Hearing Date: September 8, 2022 Dept: 85
Susan Neuhausen v. Laura
Aguilar and Dean Logan, 22STCP03172
Tentative decision on petition
for writ of mandate: granted in part
Petitioner
Susan Neuhausen (“Neuhausen”) petitions for a writ of mandate compelling
Respondents Laura Aguilar (“Aguilar”), in her official capacity as Acting City Clerk
of the City of Sierra Madre (“City Clerk”), and Dean Logan, in his official
capacity as the County of Los Angeles Registrar-Recorder (“Registrar”), to delete
or amend portions of the Argument Against Measure HR (“Argument Against”) for
the November 8, 2022 General Election.
The
court has read and considered the moving papers and opposition (no reply was
permitted) and renders the following tentative decision.
A. Statement of the Case
1. Petition
Petitioner
Neuhausen commenced this proceeding on August 26, 2022, alleging a cause of
action for mandamus, pursuant to Election Code[1]
sections 9295 and 13314. The verified
Petition alleges in pertinent part as follows.
In
March 2020, the City learned of a potential housing development dubbed the
Meadows at Bailey Canyon (“Meadows Project”) on a 17-acre portion of property (“Property”)
owned by The Congregation of the Passion, Mater Dolorosa Community (“Mater
Dolorosa”). The Property is a large
parcel of land in the City that abuts the San Gabriel mountains and is zoned
for “Institutional” use. The Meadows Project
would require a General Plan Amendment and Zone Change.
Measure HR, set for the November ballot, would rezone the Property
for “Hillside/Hillside Management” (“Hillside”), which only would allow
development of single-family residences on lots of at least two acres.
The
Argument Against claims that, when combined with a recent change in state law
in SB 9, Measure HR would permit a developer to build as many as 68 units with
limited design approval. However, SB 9 (1)
requires cities to approve applications to split lots located in single-family
residential zones into no more than two parcels, (2) requires that the
applicant occupy the subject parcel, and (3) prohibits the applicant from
subdividing more than one plot.
In March and April 2022, the City passed an ordinance implementing
SB 9 that also required the applicant to reside on the parcel for three years
prior to the application and prohibits the applicant from applying to split an
adjacent parcel.
These
facts demonstrate that developers cannot take advantage of SB 9’s “urban lot
split”. The only way 68 units could be
constructed as the Argument Against claims would be if every lot owner applied for
an urban lot split, satisfied the criteria to do so, and then built two
separate homes on the new lot. Additionally,
this scenario would require demolition of the Mater Dolorosa Passionist Retreat
Center (“Center”), which will not happen.
The Argument Against gives
voters a false and misleading impression that Measure HR would allow a
developer to build a residential subdivision with virtually no City oversight
and with far more units than is probable.
Neuhausen seeks (1) a writ of mandate compelling Respondents to delete
or amend the false or misleading portions of the Argument Against in the Ballot
Pamphlet for the November 8, 2022 General Election and
(2) attorney’s fees and costs.
2. Course of Proceedings
On
August 29, 2022, Neuhausen filed an ex parte application for order
setting the hearing on the Petition on shortened time. Respontent Registrar took no position on the
merits but asked that the matter be heard by September 9, 2022 in order not to
interfere with the election under section 13314.
On
August 30, 2022, Neuhausen filed a peremptory challenge to Dept. 82 (Hon. Mary
Stroebel) as the Judicial Officer. The
court granted the challenge and the matter was reassigned to this court.
On
August 31, 2022, Dept. 86 (Hon. Mitchell Beckloff) granted the ex parte application
and set the hearing on the Petition on shortened time for the instant
date.
On
September 1, 2022, the court informed the parties that no reply brief would be
permitted for the hearing.
B.
Standard of Review
A
party may seek to set aside an agency decision by petitioning for either a writ
of administrative mandamus (CCP §1094.5) or of traditional mandamus. CCP §1085.
A petition for traditional mandamus is appropriate in all actions “to compel
the performance of an act which the law specially enjoins as a duty resulting
from an office, trust, or station.” Ibid.
A
traditional writ of mandate under CCP section 1085 is the method of compelling
the performance of a legal, ministerial duty. Pomona Police Officers’ Assn.
v. City of Pomona, (1997) 58 Cal.App.4th 578, 583-584. Generally, mandamus
will lie when (1) there is no plain, speedy, and adequate alternative remedy,
(2) the respondent has a duty to perform, and (3) the petitioner has a clear
and beneficial right to performance. Id. at 584. Whether a statute
imposes a ministerial duty for which mandamus is available, or a mere
obligation to perform a discretionary function, is a question of statutory
interpretation. AIDS Healthcare Foundation v. Los Angeles Registrat Dept. of
Public Health, (2011) 197 Cal.App.4th 693, 701.
No
administrative record is required for traditional mandamus to compel
performance of a ministerial duty or as an abuse of discretion.
1.
Elections Code
Any elector may seek a writ of
mandate alleging that an error or omission has occurred, or is about to occur,
in the placing of a name on, or in the printing of, a ballot, county voter
information guide, state voter information guide, or other official matter. §13314(a)(1).
An “elector” is any person who is a United States citizen, is over 18
years old, and is a resident of an election precinct at least 15 days prior to
election. §321. A peremptory writ of mandate shall issue on
proof (1) that the error, omission, or neglect of duty is in violation of the
Elections Code or Constitution and (2) that issuance of the writ will not
substantially interfere with the conduct of the election. §13314(a)(2); see Mann v. Superior Court (1986) 181 Cal.App.3d 372.
The Legislature has expressed its determination that the state has
a strong interest in providing the electorate with accurate information in
voter pamphlets. Washburn v. City of
Berkeley, (1987) 195 Cal.App.3d 578, 585.
The California Supreme Court has long recognized that the essential
purpose of ballot argument provisions is to give the voters information
concerning the measures on the ballot. Patterson
v. Board of Supervisors, (“Patterson”) (1988) 202 Cal.App.3d 22, 29
(citation omitted). The voter’s pamphlet
can have a substantial impact on the equality and fairness of the electoral
process because the arguments set forth therein are likely to carry greater
weight in the minds of the voters than normal campaign literature. Id.
at 30. Restricting the
information in the voter pamphlet to material which is neither false,
misleading nor inconsistent with the purpose of the limited public forum is a
way to foster the integrity of the election process and to aid citizens in
making informed voting choices. Id.
at 30-31.
A peremptory writ of mandate
will be issued only upon clear and convincing evidence that the material in
question is false, misleading, or inconsistent with the requirements of the
Election Code. §9295(b)(2). A ballot designation for a political candidate
is misleading if “there is a substantial likelihood that a reasonably prudent
voter would be misled as to the candidate’s principal profession, vocation or
occupation…The determination shall take into account the plain meaning of the
words constituting the proposed ballot designation and the factual accuracy of
the proposed ballot designation based upon supporting documents or other
evidence submitted by the candidate…” 2
CCR §20716(c).
The ballot pamphlet is a
“limited public forum.” Kaplan v.
County of Los Angeles , (9th Cir. 1990) 894 F.2d 1076,
1080. In determining whether statements
are relevant, courts must be extremely reticent in undertaking the essentially
political task of playing copy editor with one side's wording of a voters’
pamphlet argument. Huntington Beach
City Council v. Superior Court, (“Huntington Beach”) (2002) 94
Cal.App.4th 1417, 1423. In the political
arena, “one person’s relevant argument is another person’s nonsense.” Ibid.
In determining whether statements are false or
misleading, courts look to whether the challenged statement is subject to
verifiability, as distinct from “typical hyperbole and opinionated comments
common to political debate.” Id. at
1432 (statement that a business was the only one in the city that did not pay the
proposed tax was deliberately misleading).
An “outright falsehood” or a statement that is “objectively untrue” may
be stricken. Id. at 1432.
The court will issue a writ of mandate when a petition contains undisputed,
objective untruths calculated to mislead and misinform a reasonable voter. San Francisco Forty-Niners v. Nishioka,
(1999) 75 Cal.App.4th 637, 650. Factual
matters subject to dispute are not the type of untruths that may be deleted or
edited by a court. Id.
The courts will distinguish between fact and opinion in
determining whether a statement is false.
“Almost all, if not all, statements concerning the effect or application
of an initiative can only be the opinion of the interpreter, and the voting
public is generally aware of this.” Chavez
v. Citizens for Fair Farm Labor Law, (“Chavez”) (1978) 84 Cal. App.
3d 77, 82 (emphasis in original) (statement that proposition would deprive
agricultural employers and others of personal property rights was opinion). Opinion statements concerning the potential
benefit or harm from an initiative measure are not subject to proof of their
truth or falsity. Mandicino v.
Maggard, (1989) 210 Cal. App. 3d 1413, 1420 (statements about the measure’s
future effects upon the community were opinion).
Context may show that a statement that in one sense can
be said to be literally true is still materially misleading. Huntington Beach, supra, 94
Cal.App.4th at 1432. A statement that the
owner of an electricity-generating plant “refused to sign a contract for use of
electricity solely in California” was true but misleading where the refusal
only applied to two out of five plants, two others were pledged to the state’s
independent system operator for use in California, and the fifth was reserved
for a staged alert due to a shortage declared by the independent system
operator. Id. at 1435. The court found that the statement implied
that the owner only sells its electricity to out-of-state energy companies,
which was misleading. Ibid.
2. Subdivision Map Act
The Subdivision Map Act (“Map Act”),
Government Code (“Govt. Code”) §66410 et
seq., formerly SB 9, is ‘the primary regulatory control’ governing the
subdivision of real property in California.” Gardner v. County of
Sonoma, (2003) 29 Cal.4th 990, 996 (citation omitted).
The Map Act generally
requires that all subdivisions conform with local general and specific plans
and all conditions of local ordinances. Black Hills Investments, Inc.
v. Albertson’s, Inc., (2007) 146 Cal.App.4th 883, 890. A “subdivision” is the division by a
subdivider of any improved or unimproved land. §66424. To comply
with the Map Act, the landowner must secure local approval and record an
appropriate map. A tentative and final map generally are required for
subdivisions of five or more parcels and a parcel map is required for four or
fewer parcels. Ibid; §66426. A “tentative map” is a map
showing the design and improvement of a proposed subdivision.
§66425.5. A “parcel map” is a subdivision creating five or fewer
lots. The provisions of section 66452 et seq. govern tentative
maps. The procedure for processing the approval of parcel maps shall be
as provided by local ordinance. §66463.
A city or county’s legislative body
shall deny approval of the tentative or parcel map if it finds that (1) the
proposed map is not consistent with applicable general and specific plans (Govt.
Code §66474(a)); (2) the design or improvement of the proposed subdivision is
not consistent with applicable general and specific plans (Govt. Code
§66474(b)), or (3) the design of the subdivision or the proposed improvements are
likely to cause substantial environmental damage or substantially and avoidably
injure fish or wildlife or their habitat (Govt. Code §66474(e)).
Notwithstanding
any other provision of the Map Act and any local law, a local agency shall
ministerially approve a parcel map for an urban lot split only if the split
subdivides an existing parcel to create no more than two new parcels of
approximately equal lot area and the two parcels meet minimum square footage
requirements. Govt. Code §66411.7(a)(1). Neither the owner of the parcel being
subdivided nor any person acting in concert with the owner may have previously
subdivided an adjacent parcel using an urban lot split. Govt. Code §66411.7(a)(3)(G). The local agency shall require the applicant to
sign an affidavit stating that the applicant intends to occupy one of the
housing units as its principal residence for a minimum of three years from the
date of the approval of the urban lot split.
Govt. Code §66411.7(g)(1).
3.
Sierra Madre Municipal Code[2]
a.
Hillside Zoning Regulations
SMMC
Chapter 17.52 lists the regulations for the Hillside zone in the City. Michel Decl., ¶¶ 17-18, Ex. I. Uses allowed in a Hillside zone include (1) any
primary or accessory use permitted in an R-1 one-family residential zone (SMMC
§17.52.070(C)(1)); (2) construction of a detached single-family dwelling unit
on an existing legal lot (SMMC §17.52.070(C)(2)); and (3) land divisions,
whether by parcel map, tract map, or otherwise (SMMC §17.52.070(C)(3)). Michel Decl., ¶¶ 17-18, Ex. I.
Any
permit application must include (1) a flood plan including all
measures, such as elevated building pads or floor plates, necessary to ensure adequate
protection of persons and property (SMMC §17.52.100(A)(4)); (2) a suitability
analysis that clearly delineates Category 4 slopes, riparian areas, drainage
areas, flood plains, vegetation types, prominent ridgelines, and archaeological
and paleontological resources upon director’s request (SMMC §17.52.100(A)(5));
(3) diagrams and photos and, if requested by the director, installation of
three-dimensional story poles that outline the walls, roofs, and other features
that will determine the location, mass, and bulk of the proposed structures
(SMMC §17.52.100(A)(7)); (4) if requested by the director, a three-dimensional
scale model of the subject property and the area 150 feet outside the
boundaries of the subject property (SMMC §17.52.100(A)(8)); and (5) if
requested by the director, a site-specific archaeological, historic and
paleontological report identifying all such resources on a project site,
analyzing potential adverse impacts to such resources, and identifying effective
mitigation measures to reduce potential adverse impacts (SMMC
§17.52.100(A)(9)). Michel Decl., ¶¶
17-18, Ex. I.
Any land divisions in the Hillside zone must result in a
minimum lot width and depth of 150 feet each and lots that are a minimum of two
acres. Michel Decl., ¶¶ 17-18, Ex. I (SMMC
§17.52.140(3)(b), (c), (f)). Grading in
connection from land divisions must also conform with minimum
requirements. Michel Decl., ¶¶ 17-18, Ex.
I (SMMC §17.52.140(4)).
b.
Ordinance No. 1452
In
March and April 2022, the City adopted Ordinance No. 1452 to implement its own
version of the Map Act and establish objective standards and regulations to
govern the subdivision of parcels as authorized therein. Michel Decl., ¶¶ 12-13, Ex. E (SMMC
§16.18.010). The Ordinance limits
urban lot splits to parcels in R-1 One-Family Residential Zones, R-C
Residential Canyon Zones, and Hillside Zones.
Michel Decl., ¶¶ 12-13, Ex. E (SMMC §16.18.020(A)).
The
urban lot split applicant’s parcel cannot (1) have been established through a
prior urban lot split; or (2) be adjacent to another parcel subject to an urban
lot split by either the applicant or another person acting in concert with the
applicant. Michel Decl., ¶¶ 12-13, Ex. E
(SMMC §16.18.020(B)(1)-(2)). The urban
split cannot split more than one parcel or create more than two new
parcels. Michel Decl., ¶¶ 12-13, Ex. E
(SMMC §16.18.050(C)(1)). Both new
parcels must have access to or adjoin the improved public right-of-way,
and the subdivision shall not result in a new parcel with an average width less
than that of the original parcel unless it would preclude the construction of
two units on either of the resulting parcels or result in units less than 800
square feet. Michel Decl., ¶¶ 12-13, Ex. E (SMMC
§16.18.050(C)(3)-(4)). The new parcels
must also be of approximately equal lot area provided that one parcel is not
smaller than 40 percent of the lot area of the original parcel. Michel Decl., ¶¶ 12-13, Ex. E (SMMC §16.18.050(D)(1)).
Upon
issuance of a parcel map by the Director, the applicant shall sign and record a
covenant stating that (1) all resulting parcels will be for residential use (SMMC
§16.18.070(A)(1)); (2) the applicant will occupy one of the housing units
on the subdivided parcels as the occupant’s principal residence for at least
three years from the date of the approval of the urban lot split (SMMC
§16.18.070(A)(5)); and (3) neither the applicant, a successor in
interest, nor any person acting in concert with them may apply for an urban lot
split for an adjacent parcel (SMMC §16.18.070(A)(10)).
D. Statement of Facts
1.
Petitioner Neuhausen’s Evidence[3]
a.
The Property, the Meadows Project, and Measure HR
The
Property is a 45-acre site on the edge of the San Gabriel mountains. Michel Decl., ¶10, Ex. C. Mater Dolorosa uses 35 acres of the Property
for a Center while the remaining 17 acres are undeveloped. Michel Decl., ¶10, Ex. C; Pet. Ex. C.
The
Meadows Project is a proposal to build up to 42 single-family detached
residential units on the Property’s 17 undeveloped acres. Michel Decl., ¶¶ 9-10, Exs. B-C. The Meadows Project would rezone the Property
from Institutional to Single-Family Residential. Michel Decl., ¶9, Ex. B.
On August 25, 2022, the City provided notice that it would conduct
a September 15, 2022 public hearing on the Meadows Project. Michel Decl., ¶9, Ex. B. The draft Specific Plan is pending the City’s
final review and approval. Michel Decl.,
¶10, Ex. C. In response to questions,
the Center announced that it intends to remain on the Property for decades to
come and be the closest neighbor to the homes built on the Property. Michel Decl., ¶11, Ex. D.
In response to the Meadows Project,
on January 25, 2022, three citizens submitted notice of intent to circulate a
petition to change the zoning of the 45-acre Property from Institutional to
Hillside. Michel Decl., ¶8, Ex. A. According to a zoning map attached to the
report, all other large properties adjacent to the San Gabriel Mountains are
zoned either Hillside or Open Space. Ex.
A. As of May 13, 2022, the petition had
1,300 “sufficient” signatures and will be placed on the ballot for the November
8, 2022 election. Michel Decl., ¶8, Ex.
A. The petition became Measure HR.
b. The Terner Center Report
In
a report from July 2021, the Terner Center at the University of California at
Berkeley (“Terner Center”) analyzed whether SB 9 would increase the supply of
new homes. Michel Decl., ¶14, Ex. F. Terner Center noted that some single-family
lots were too small or have other physical conditions that prevent changes to
the existing homes, and that other homeowners may not want to pursue new
development or find it financially infeasible.
Ex. F.
The
report concluded that, while it would enable development of more units on
410,000 single-family parcels (5.4% of all current single-family parcels), only
110,000 single-family parcels realistically could be developed where it had not
previously been financially feasible to do so. Ex. F. For
the majority of single-family properties, the most financially viable outcome would
be not to pursue any development. Michel
Decl., ¶14, Ex. F. The report further
noted that owner occupancy requirements, which SB 9 permits jurisdictions to
impose, will dramatically decrease the number of owners willing to apply to
split the lot. Ex. F.
c.
The March 22, 2022 City Council Meeting
During
a City Council meeting on March 22, 2022, City Attorney Aleks Giragosian (“Giragosian”)
explained that SB 9 sought to prevent private equity developers from purchasing
multiple lots next to each other, splitting the lots, making a profit from the
development that follows, and leaving.
Michel Decl., ¶¶ 2, 4. SB 9
therefore only provides an “urban lot split” option to property owners that
live in the units they want to split.
Michel Decl., ¶3. The City
Attorney further described the requirement that an owner live in one lot for
three years as “intended to prevent private equity firms from coming in and
dividing them up and selling them and leaving.”
Michel Decl., ¶4.
d.
The City Attorney’s 9212 Report
On July 8, 2022, the City Attorney issued a Report
on Measure HR Prepared Pursuant to Elections Code Section 9212 (“9212 Report”). Pet., Ex. C.
The 9212 Report explained that Measure HR’s Hillside zoning would allow
subdivision of the undeveloped 17 acres into eight lots. Ex. C.
Because 10 of the 45 acres on the Property are too steep, the 35 acres
of developable land on the Property could yield a maximum of 17 two-acre lots. Ex. C.
In either scenario, the General Plan only allows one housing unit per
parcel. Pet. at Ex. C.
SB 9, Accessory Dwelling Unit
(“ADU”) law, and Junior Accessory Dwelling Unit (“JADU”) law all preempt local
density limits and would allow development of two units on each lot. Ex. C.
SB 9 allows subdivision of the Property’s 35 acres into 34 lots or the
undeveloped 17 acres into 16 lots. Ex.
C. Through either duplexes or some
combination of single-family homes and ADUs or JADUs, this could lead to either
32 units on the undeveloped 17 acres or 68 units on the 35 acres. Ex. C.
The 9212 Report included a
comparison of (1) the Meadows Project, both with and without an ADU and JADU on
each parcel; (2) development of the undeveloped 17 acres by Hillside standards
under Measure HR; (3) development of the undeveloped 17 acres under
state-permitted maximum density; (4) development of all 35 developable acres by
Hillside standards under Measure HR after demolition of the Center; and (5) development
of all 35 developable acres under state-permitted maximum density after
demolition of the Center. Ex. C. Of these scenarios, the Meadows Project with
an ADU and JADU on each parcel would result in the most units, 126. Ex. C.
The City Attorney did not analyze development of the Meadows Project under
SB 9’s maximum density because he did not find that scenario economically
feasible. Ex. C. While SB 9 would allow the subdivision of 42
parcels and development of two units on each of the 84 new parcels, it would
entail the demolition of new homes and subdivision on a lot-by-lot basis, which
would be unlikely because of construction costs. Ex. C.
The City Attorney noted that the Meadows
Project would allow the City Council and the Planning Commission to exercise
discretion during review. Ex. C. Measure HR would reduce this discretion because
the Housing Accountability Act constrains the City’s ability to deny a project
when the proposal “complies with applicable, objective general plan, zoning,
and subdivision standards and criteria[.]” Ex. C.
e. The July 12, 2022 City
Council Meeting
The City Attorney presented the 9212
Report at a July 12, 2022 City Council meeting.
Michel Decl., ¶5. A chart from
the report showed that the maximum theoretical development potential of the Meadows
Project was 126 units, assuming ADUs and JADUs on each of the Project’s 42
housing units. Michel Decl., ¶5. A more realistic estimate of the development
was 1% of 3,800 housing units for a total of 38 units. Michel Decl., ¶5.
The chart also showed that zoning
the 17 acres of the Meadows Project as Hillside would result in eight lots
because each lot must be at least two acres.
Michel Decl., ¶6. The City
Attorney reiterated that SB 9’s urban lot split provision would allow
homeowners to divide each lot in half to create 16 lots. Michel Decl., ¶6. Through either a combination of homes and
ADUs or duplexes, this could result in two units per lot for a total of 32
units. Michel Decl., ¶6.
Real Parties/Councilmembers Robert Parkhurst
and Kelly Kreibs asked if a developer could take the 17 acres and perform the
lot split before work on development starts, which would reduce the minimum
area per parcel to one acre and create 16 lots from the start. Michel Decl., ¶7. The City Attorney confirmed that once the
Planning Commission approved a tentative tract map with eight two-acre plots,
the developer could go to the City and have it approve an urban lot split
without asking the Planning Commission.
Michel Decl., ¶7. When asked if the
developer could use that to make plans for 32 housing units before construction
begins, Giragosian replied that he was unsure if the SMMC permitted combining
that many steps into one. Michel Decl.,
¶7.[4]
f. The Argument Against
The Argument Against as currently
set to appear on the November 8, 2022 General Election Ballot Pamphlet,
authored by City Councilpersons Gene Goss and Rachelle Arizmendi, states that
Measure HR is an ill-conceived initiative and a potential disaster for the
City. Pet. Ex. B. “Do we want 6,500 square foot mansions smack
dab in the middle of a residential neighborhood of three-to-four-bedroom single
family homes? With the recent change in state law, SB 9, a developer could build
as many as 68 units with limited design approval by the City.” Ex. B.
The Argument Against asks voters whether that is the intended “look and
character” of the Property. Ex. B.
The Argument Against contended that
Measure HR would bypass the General Plan and circumvent zoning recognized by the
City Council and would restrict mater Dolorosa from modifying or changing the
Center. Ex. B. It targets one private property owner and
exposes the City to legal action. The proponents
of Measure HR might not have realized its consequences when they collected
signatures for the petition. Ex. B.
g. The
Rebuttal Argument Against
On August 28, 2022, Real
Parties Gene Goss, Rachelle Arizmendi, Edward Garcia, Kelly Kriebs, and Robert
Parkhurst, the five members of the City Council, submitted the Rebuttal Argument
Against to the City Clerk. Michel
Decl., ¶15, Ex. G. The Rebuttal Argument
Against asserts that Measure HR is misleading and misguided. Ex. G.
While most property owners would prefer to leave the area as open space,
Measure HR would not prevent private property owners from building. Ex. G.
In fact, “developers can build immense “MANSION-sized homes that do not
fit the [City’s] character, and then allow homeowners to split the lots,
resulting in as many as 68 units.” Ex.
G. This would not fit the Residential
Zoning in the neighborhoods surrounding all sides of the Property any more than
the hospitals and retirement facilities that the Property’s owner, Mater
Dolorosa could, but chooses not to, build under the Property’s current
zoning. Ex. G. Real Parties claim that Measure HR unfairly
restricts the owner's private property rights.
Ex. G.
2. Respondent City Clerk’s and
Real Parties’ Evidence
Developer New Urban West, Inc., Sierra
Madre (“NUWI”) and Mater Dolorosa first proposed the Meadows Project on the
Center’s open space in 2020. Giragosian
Decl., ¶7, Ex. 9. Mater
Dolorosa therefore opposes Measure HR. Giragosian
Decl., ¶7, Ex. 9.
On March 14, 2022, the City Attorney
drafted the agenda report and the City’s SB 9 Ordinance for for the March 22
City Council meeting. Aguilar Decl., ¶3,
Ex. 1; Giragosian Decl., ¶3.
The Planning Commission held
meetings for public comment on the Meadows Project on April 7, May 5, June 2,
July 7, and August 4, 2022. Giragosian
Decl., ¶5, Exs. 4-8. Public comments
concerned the effect of the Meadows Project on the Property. Giragosian Decl., ¶5, Exs. 4-8. Petitioner Neuhausen spoke at all meetings
except the April 7, 2022 meeting.
Giragosian Decl., ¶5, Exs. 5-8.
On July 12, 2022, the City Attorney presented
the 9212
Report at a City Council meeting. Giragosian
Decl., ¶6. On August 12, 2022, the
City Attorney submitted a Revised 9212 Report to the City Clerk for
publication on the City website. Giragosian
Decl., ¶7, Ex. 9. He prepared both
reports in collaboration with City executive staff, including the Director of
Planning. Giragosian Decl., ¶8.
The Revised 9212 Report explained that Measure
HR’s rezoning of the Property to Hillside would increase the minimum lot
size. Giragosian Decl., ¶7, Ex. 9. Measure HR would make the Meadows Project in
its current form impossible because rezoning the Property alters the required
lot size. Giragosian Decl., ¶7, Ex. 9.
If the Center were demolished, the
35 developable acres on the Property would yield 17 two-acre lots. Giragosian Decl., ¶7, Ex. 9. SB 9 would then permit subdivision into 34
lots. Giragosian Decl., ¶7, Ex. 9. Through either duplexes or some combination
of single-family homes and ADUs or JADUs, this could lead to 68 units. Giragosian Decl., ¶7, Ex. 9. Alternatively, if only the vacant 17 acres
were developed, it would result in eight initial two-acre lots, up to 16
subdivided lots, and up to 32 housing units.
Giragosian Decl., ¶7, Ex. 9.
On August 29, 2022, the City Clerk
received rebuttals from both proponents and opponents of Measure HR that
would appear on the ballot. Aguilar
Decl., ¶8, Exs. 2-3. The Rebuttal
Argument Against asserts that Measure HR empowers Property residents to block
the Meadows Project. Aguilar Decl., ¶8,
Ex. 3. The Rebuttal Argument Against contends
that the City Council’s statement that Measure HR would allow a developer to
build 68 units is a lie because only homeowners who agree to live in a home for
three years can apply to have the lot on which it sits split; the City then has
to approve the request. Ex. 3. “No developer can build 68 units with limited
review. Don’t be fooled.” Ex. 3.
The City’s zoning ordinances also include significant protections and
restrictions for Hillside zones. Ex.
3.
Measure HR makes zoning
consistent because it changes the zoning of the Property to match other parcels
abutting the mountains. Ex. 3. In doing so, it reflects the same values as
the General Plan and Zoning Ordinances – preserving and protecting hillside
lands, while allowing Mater Dolorosa to continue operation. Aguilar Decl., ¶8, Ex. 3.
E. Analysis
Petitioner Neuhausen seeks
to delete or amend the following statement in the Argument Against: “With the
recent change in state law, SB 9, a developer could build as many as 68 units
with limited design approval by the City.”
As Respondent City Clerk and Real Parties (collectively, “City Council”)
argue (Opp. at 7), Petitioner must show that this statement is false or
misleading by clear and convincing evidence.
1. The Statement is False
In
determining whether statements are false, courts look to whether the challenged
statement is subject to verifiability, as distinct from “typical hyperbole and
opinionated comments common to political debate.” Huntington Beach, supra, 94
Cal.App.4th at 1432. An “outright
falsehood” or a statement that is “objectively untrue” may be stricken. Id.
The court will issue a writ of mandate when a petition contains undisputed,
objective untruths calculated to mislead and misinform a reasonable voter. San Francisco Forty-Niners v. Nishioka,
supra 75 Cal.App.4th at 650.
Factual matters subject to dispute are not the type of untruths that may
be deleted or edited by a court. Id.
Petitioner argues that a developer cannot legally build 68
units on the Property. Both SB 9 and the
City’s own SB 9 Ordinance preclude a developer from doing so because a single
owner cannot subdivide more than one adjacent parcel (Govt. Code
§66411.7(a)(3)(G)) and the applicant must occupy the property to be subdivided
(Govt. Code §664.11.7(g)(1)). The SB
Ordinance also requires an applicant to occupy one of the housing units on the
subdivided property as the occupant’s principal residence for at least three
years. SMMC §16.18.070.A(5),(10). A commercial developer simply cannot satisfy
this requirement. Mot. at 11-12.
The City Council knew this was the case. The City Attorney informed the City Council
that SB 9 is really for property owners who live in their units and the
Legislature wanted to prevent private entity developers from purchasing a bunch
of lots next to each other and splitting them to achieve a big profit on the
development. The City Attorney explained
that the requirement that the applicant live in one lot for three years is
intended to prevent private equity firms from dividing lots, selling them, and
leaving. Michel Decl., ¶¶ 2, 4. Petitioner argues that, despite their
knowledge that SB 9 categorically prevents “a developer” from subdividing
property in this way, the City Council authorized the Argument Against
statement that a developer could build as many as 68 units, which is
categorically false. Mot. at 12.
The City Council notes that Merriam-Webster’s online
dictionary defines the term “developer” as “a person who develops real estate”,
and that it encompasses both commercial developers and homeowners who add on to
their home. The City Council acknowledges
that the statement’s reference to “a developer” is perhaps imprecise because it
could refer to one or more developers.
But the reference does not mean only commercial developers as Petitioner
suggests. Opp. at 11.
The City Council further notes that the statement is made in the
context of an argument about the type of homes (6500 square foot mansions) and
the number of units (68) permitted by Measure HR, and that this would be
outside the “look and character” of the City.
The City Council argues that these threats to the character of the City
may be made by any developer, not just a commercial developer. The development may not occur immediately,
but it could happen over the years as lots are sold and resold the prospect of
SB 9 development increases. The voters
should receive this relevant information and the number of developers involved is
not significant. Opp. at 12.
The statement is not just imprecise, it is false. No matter whether a commercial entity or an
individual, no single person could develop the Property’s 35 acres into 68
units. Neither SB 9 nor the City’s SB 9
Ordinance would permit it. Yet, the
statement’s plain meaning is that a single developer could build up to 68 units
on the Property. The use of the word
“build” associated with “a developer” is significant. The statement implies that a developer could build
68 units not over decades but rather in a single project of 68 units on 34
lots. That is simply not true. The point of the statement, of course, is to
suggest that the Meadows Project’s more limited development of 42 single-family
detached residential units on the Property’s 17 undeveloped acres is vastly
preferable.
Petitioner has shown by clear and convincing evidence that the
statement is false by referring to a developer’s ability to build 68
units on the Property.[5]
2. The Statement is Not Misleading in Its Reference to
a Maximum of 68 Units
The
courts distinguish between fact and opinion in determining whether a statement
is false. “Almost all, if not all,
statements concerning the effect or application of an initiative
can only be the opinion of the interpreter, and the voting public is generally
aware of this.” Chavez, supra,
84 Cal. App. 3d at 82 (emphasis in original). Opinion statements concerning the potential
benefit or harm from an initiative measure are not subject to proof of their
truth or falsity. Mandicino v.
Maggard, supra 210 Cal. App. 3d at 1420. Context may show that a statement that in one
sense can be said to be literally true is still materially misleading. Huntington Beach, supra, 94
Cal.App.4th at 1432.
Petitioner
argues that the statement is misleading.
Measure HR is a response to the Meadows Project. The Argument Against presents Measure HR as
inviting 6500 square foot mansions in residential neighborhoods of three or
four bedroom homes with a developer building as many as 68 units with limited
design approval by the City.
Petitioner suggests that the voters will be misled because
Meadows Project concerns only the development of 17 acres on the Property and
they will assume that the City Council is contending that 68 units can be built
on those 17 acres. Yet, the City
Attorney analyzed six different scenarios and most of them have a lower unit
count than the Meadows Project. Mot. at
14.
Importantly, the City Council’s 68-unit figure is based on a
number of improbable assumptions: (1) Mater Delorosa decides to demolish the
Center, making all 35 acres available for development, despite its public
assurance that it looks forward to continuing events at the Center for the
decades to come (Michel Decl., Ex. D); (2) the entire 35 acres would be
subdivided; (3) each lot would have to be developed by its owner with a house
and an ADU; and (4) all 17 homeowners would have to occupy one of the homes as
a primary residence for three years. Petitioner describes this chain of events as
highly unlikely, thereby misleading voters.
Mot. at 16.
The Terner Center’s analysis of SB 9 also supports the
conclusion that it is unlikely that every lot on the Property would be
split. Some owners will have no interest
in splitting their lot and others will find it financially infeasible. Michel Decl., Ex. F. The City Council also was advised that fewer
than 1% of homes in the City have ADUs. The
City Attorney even refused to consider the application of a SB 9 lot split to
the Meadows Project because it would not be economically feasible to build the
new homes only to demolish them in favor of lot splitting. Therefore, the Argument Against’s reference
to “as many as 68 units” on the Property without any qualification makes the
statement materially misleading. Mot. at
15.
Additionally, a developer cannot construct these units with
“limited design review.” By designating
the Property as Hillside, strict development standards would exist for
development, including flood plan suitability analysis, and site specific
archeological, historic and paleontological reports, and grading
requirements. Even the application of
only objective standards in the Hillside Management Ordinance would require
significant City oversight. Mot. at 16.
Petitioner concludes that voters are being asked to weigh
Measure HR against the Meadows Project and are entitled to accurate
information. The Argument Against
statement materially misleads voters by suggesting that Measure HR will result
in a large scale 68-unit development by a developer without meaningful
review. Mot. at 16.
Leaving aside the falsity discussed ante, clear and
convincing evidence does not show the statement to be misleading. The City Council points out (Opp. at 8-9) that
the statement is a projection of the worst-case scenario. In their Argument Against, Real Parties chose
not to speculate on how many units would actually be developed, only stating
that “as many as 68 units” can be developed.
Real Parties were not required to refer to a speculative “likely” number
and could instead refer to a legal maximum.
Petitioner acknowledges that the 68-unit number is the legally permitted
maximum development for the Property’s 35 acres and her focus on economic
probability rather than legal maximum does not make the statement misleading.
While its position may be based on a chain of events that
Petitioner considers improbable, the City Council argues that Petitioner’s
claim also rests on an assumption that Mater Dolorosa will maintain the
Center in the future. For this
conclusion, Petitioner relies on statements made by Mater Dolorosa in support
of the Meadows Project and not in the face of Measure HR. The City Council correctly concludes that Petitioner
cannot predict what Mater Dolorosa will do if Measure HR passes, the Property
is rezoned, and the Meadows Project which Mater Dolorosa supports is terminated. Opp. at 10.
Nor does the Argument Against’s discussion of 68 units draw a
misleading comparison to the Meadows Project’s smaller 17-acre footprint as
Petitioner contends. The Argument
Against does not expressly refer to the Meadows Project. Nor is Measure HR is limited to the 17 acres
of the Meadow Project; it applies to all 38 acres owned by Mater Dolorosa, 35
acres of which can be developed with a legally permissible maximum density of
68 units.
Apart from its falsity in referring to a single developer, the
statement has not been shown by clear and convincing evidence to be misleading
by referring to the maximum legally permissible development of units on the
Property.
F. Conclusion
The Petition is granted in part. The Argument Against’s statement: “With the
recent change in state law, SB 9, a developer could build as many as 68 units
with limited design approval by the City” is false in that no single developer
could build 68 units. Apart from this
falsity, the statement is not misleading in that it is undisputed that 68 units
legally could be built on the 35-acres of developable Property and the
statement expressly refers to this legal maximum.
The City Council argues that Petitioner’s proposed remedy of
an amendment that refers to 34 units on 17-acres is not proper. Any remedy must address the purpose of the
statement, which is to inform voters that a maximum of 68 units could be
built. Opp. at 15-16.
The court agrees. A
writ shall issue directing Respondents to modify the statement to read as
follows: “With the recent change in state law, SB 9, as many as 68 units
ultimately could be built with limited design approval by the City”.
[1]
All further statutory references are to the Election Code unless otherwise
stated.
[2]
Petitioner Neuhausen requests judicial notice of (1) Chapter 16.18 to Title 17 of the
Sierra Madre Municipal Code (“SMMC”) (Michel Decl., ¶¶ 12-13, Ex. E); and (2)
Chapter 17.52 to Title 17 of the SMMC (Michel Decl., ¶¶ 17-18, Ex. I). The requests are granted. Evid. Code §452(b).
Respondent
Aguilar and Real Parties-in-Interest request judicial notice of (1) The Agenda
Packet for the SB 9 Ordinance for the City Council’s March 22, 2022
meeting (Aguilar Decl., ¶3, Ex. 1); (2) the Rebuttal to Argument in Favor of
Measure HR (Aguilar Decl., ¶8, Ex. 2); (3) the Rebuttal to Argument Against
Measure HR (Aguilar Decl., ¶8, Ex. 3); (4) the minutes of Planning Commission
meetings on April 7, 2022 (Giragosian Decl., ¶5, Ex. 4), May 5, 2022 (Giragosian
Decl., ¶5, Ex. 5), June 2, 2022 (Giragosian Decl., ¶5, Ex. 6), July 7
(Giragosian Decl., ¶5, Ex. 7), and August 4, 2022 (Giragosian Decl., ¶5, Ex.
8); and (5) a Revised Section 9212 Report (“Revised 9212 Report”) dated August 12, 2022 (Giragosian
Decl., ¶7, Ex. 9). All requests are
granted. Evid. Code §§ 452(b), (c).
[3]
Real Parties’ and Respondents’ written objections to Petitioner’s evidence are
overruled.
[4] On
August 30, 2022, the City Attorney released an Impartial Analysis of Measure HR
to its proponents. Michel Decl., ¶16, Ex.
H. The analysis explained that Measure
HR would change only the Mater Dolorosa Property’s General Plan land use
designation to “Residential Low Density – Hillside” and the zoning designation
to Hillside. Ex. H. This would render the Center a non-conforming
use, which the owners could maintain and repair but might not be able to
enlarge or alter. Ex. H.
[5]
The City Council contends that any defect in the statement was cured by the
Rebuttal to the Argument Against which points out that a single developer who
is not a homeowner could not even apply for a SB 9 lot split. Opp. at 13.
The City Council cites no authority that a false statement in a ballot
argument can be cured by the other side pointing out its falsity.