Judge: James C. Chalfant, Case: 22STCV31381, Date: 2023-04-27 Tentative Ruling
Case Number: 22STCV31381 Hearing Date: April 27, 2023 Dept: 85
Tri-West, Ltd. v. Kolay Flooring International
LLC et al, 22STCV31381
Tentative decision on application
for right to attach order against Defendants KFI and Kolay: denied
Plaintiff
Tri-West, Ltd. (“Tri-West”) applies for right to attach orders against
Defendants Kolay Flooring International LLC (“KFI”) and MODM Kolay
Manufacturing, LLC (“Kolay”).
The
court has read and considered the moving papers, opposition, and reply, and
renders the following tentative decision.
A. Statement of the Case
1.
Complaint
Plaintiff Tri-West filed the Complaint
on September 26, 2022, against Defendants Kolay, KFI, and Daniel Mitchell
(“Mitchell”) alleging (1) breach of contract, (2) fraud, (3) conversion, (4)
unjust enrichment, (5) common counts, (6) theft under Penal Code section 496,
and (7) UCL violations. The Complaint
alleges in pertinent part as follows.
Tri-West is a flooring distributor
and Kolay purports to be a flooring manufacturer. In May 2021, Kolay misrepresented to Tri-West
that newly-opened manufacturing facility in Las Vegas, Nevada can begin
promptly producing multiple high-quality flooring products meeting certain
specifications and in significant volumes.
Kolay agreed to produce 14 products and produce one million feet of
product per month. It also agreed to produce
and deliver product upon receipt of advance payment deposits.
In reliance on these statements, in
August 2021, Tri-West and Kolay entered a Purchase and Supply Agreement
(“Agreement”) for the purchase of products from Kolay. Tri-West agreed to advance pay 50% of all
purchase orders and pay the rest upon delivery while Kolay agreed to use all
reasonable efforts to meet requested delivery dates. If Kolay could not timely fulfill an order, Tri-West
could cancel the purchase order and obtain a refund.
On August 12, 2021, Tri-West wired $557,160.80
as advances for 29 purchase orders.
Kolay guaranteed to use this money to produce over 500,000 square feet
of flooring at its Las Vegas factory, and over 8,000 trim pieces for that
flooring. Kolay spent months promising
that the flooring would ship. When a
limited portion of the product did ship, it was defective and did not lock
properly. Tri-West believes that Kolay
is unable to produce the promised product. After
months of waiting, Tri-West cancelled the order and requested the refund. Kolay representatives like Mitchell promised
reimbursement in writing. Kolay has not
refunded the money even after a written demand on August 19, 2022.
Tri-West seeks recovery of the $557,160.80
in advance payments, plus $500,000 in lost sales and profits, punitive damages,
restitution, disgorgement, treble damages, and attorney’s fees and costs.
2.
Course of Proceedings
On September 30, 2022, Tri-West
served KFI with the Complaint and Summons by substitute service, effective October
10, 2022.
On October 3, 2022,
Tri-West served Kolay with the Complaint and Summons.
On October 4, 2022,
Tri-West served Mitchell with the Complaint and Summons by substitute service,
effective October 14, 2022.
On November 10, 2022, Kolay’s
default was entered by the clerk.
On November 22, 2022,
Mitchell filed his Answer.
On December 1, 2022,
Kolay and KFI filed an Answer.
On February 15, 2023,
the parties stipulated to vacate the default of Defendant’s Kolay and KFI.
On April 20, 2023,
Defendants filed a motion for leave to file a First Amended Answer. Department 51 (Hon. Upinder S. Kalra) will
hear this motion on June 30, 2023.
B.
Applicable Law
Attachment
is a prejudgment remedy providing for the seizure of one or more of the
defendant’s assets to aid in the collection of a money demand pending the
outcome of the trial of the action. See
Whitehouse v. Six Corporation, (1995) 40 Cal.App.4th 527, 533. In 1972, and in a 1977 comprehensive
revision, the Legislature enacted attachment legislation (CCP §481.010 et
seq.) that meets the due process requirements set forth in Randone v.
Appellate Department, (1971) 5 Cal.3d 536.
See Western Steel & Ship Repair v. RMI, (12986) 176
Cal.App.3d 1108, 1115. As the attachment
statutes are purely the creation of the Legislature, they are strictly
construed. Vershbow v. Reiner,
(1991) 231 Cal.App.3d 879, 882.
A
writ of attachment may be issued only in an action on a claim or claims for
money, each of which is based upon a contract, express or implied, where the
total amount of the claim or claims is a fixed or readily ascertainable amount
not less than five hundred dollars ($500).
CCP §483.010(a). A claim is
“readily ascertainable” where the amount due may be clearly ascertained from
the contract and calculated by evidence; the fact that damages are unliquidated
is not determinative. CIT
Group/Equipment Financing, Inc. v. Super DVD, Inc., (2004) 115 Cal.App.4th
537, 540-41 (attachment appropriate for claim based on rent calculation for
lease of commercial equipment).
All
property within California of a corporation, association, or partnership is
subject to attachment if there is a method of levy for the property. CCP §487.010(a), (b). While a trustee is a natural person, a trust
is not. Therefore, a trust’s property is
subject to attachment on the same basis as a corporation or partnership. Kadison, Pfaelzer, Woodard, Quinn &
Rossi v. Wilson, supra, 197 Cal.App.3d at 4.
The
plaintiff may apply for a right to attach order by noticing a hearing for the
order and serving the defendant with summons and complaint, notice of the
application, and supporting papers any time after filing the complaint. CCP §484.010.
Notice of the application must be given pursuant to CCP section 1005,
sixteen court days before the hearing. See
ibid.
The
notice of the application and the application may be made on Judicial Council
forms (Optional Forms AT-105, 115). The
application must be supported by an affidavit showing that the plaintiff on the
facts presented would be entitled to a judgment on the claim upon which the
attachment is based. CCP §484.030.
Where the defendant is a corporation, a
general reference to “all corporate property which is subject to attachment
pursuant to subdivision (a) of Code of Civil Procedure Section 487.010” is
sufficient. CCP §484.020(e). Where the defendant is a partnership or other
unincorporated association, a reference to “all property of the partnership or
other unincorporated association which is subject to attachment pursuant to
subdivision (b) of Code of Civil Procedure Section 487.010” is sufficient. CCP §484.020(e). A specific description of property is not
required for corporations and partnerships as they generally have no exempt
property. Bank of America v. Salinas
Nissan, Inc., (“Bank of America”) (1989) 207 Cal.App.3d 260, 268.
A
defendant who opposes issuance of the order must file and serve a notice of
opposition and supporting affidavit as required by CCP section 484.060 not
later than five court days prior to the date set for hearing. CCP §484.050(e). The notice of opposition may be made on a
Judicial Council form (Optional Form AT-155).
The
plaintiff may file and serve a reply two court days prior to the date set for
the hearing. CCP §484.060(c).
At
the hearing, the court determines whether the plaintiff should receive a right
to attach order and whether any property which the plaintiff seeks to attach is
exempt from attachment. The defendant
may appear the hearing. CCP
§484.050(h). The court generally will
evaluate the attachment application based solely on the pleadings and
supporting affidavits without taking additional evidence. Bank of America, supra, 207
Cal.App.3d at 273. A verified complaint may be used in lieu of or in addition
to an affidavit if it states evidentiary facts.
CCP §482.040. The plaintiff has
the burden of proof, and the court is not required to accept as true any
affidavit even if it is undisputed. See
Bank of America, supra, at 271, 273.
The
court may issue a right to attach order (Optional Form AT-120) if the plaintiff
shows all of the following: (1) the claim on which the attachment is based is
one on which an attachment may be issued (CCP §484.090(a)(1)); (2) the
plaintiff has established the probable validity of the claim (CCP
§484.090(a)(2)); (3) attachment is sought for no purpose other than the
recovery on the subject claim (CCP §484.090(a)(3); and (4) the amount to be
secured by the attachment is greater than zero (CCP §484.090(a)(4)).
A
claim has “probable validity” where it is more likely than not that the
plaintiff will recover on that claim.
CCP §481.190. In determining this
issue, the court must consider the relative merits of the positions of the
respective parties. Kemp Bros.
Construction, Inc. v. Titan Electric Corp., (2007) 146 Cal.App.4th 1474,
1484. The court does not determine
whether the claim is actually valid; that determination will be made at trial
and is not affected by the decision on the application for the order. CCP §484.050(b).
Except
in unlawful detainer actions, the amount to be secured by the attachment is the
sum of (1) the amount of the defendant’s indebtedness claimed by the plaintiff,
and (2) any additional amount included by the court for estimate of costs and
any allowable attorneys’ fees under CCP section 482.110. CCP §483.015(a); Goldstein v. Barak
Construction, (2008) 164 Cal.App.4th 845, 852. This amount must be reduced by the sum of (1)
the amount of indebtedness that the defendant has in a money judgment against
plaintiff, (2) the amount claimed in a cross-complaint or affirmative defense
and shown would be subject to attachment against the plaintiff, and (3) the
value of any security interest held by the plaintiff in the defendant’s
property, together with the amount by which the acts of the plaintiff (or a
prior holder of the security interest) have decreased that security interest’s
value. CCP §483.015(b); see also
CCP §483.010(b) (“an attachment may not be issued on a claim which is secured
by any interest in real property arising from agreement, statute, or other rule
of law…However, an attachment may be issued where the claim was originally so
secured but, without any act of the plaintiff or the person to whom the
security was given, the security has become valueless or has decreased in value
to less than the amount then owing on the claim). A defendant claiming that the amount to be
secured should be reduced because of a cross-claim or affirmative defense must
make a prima facie showing that the claim would result in an attachment
against the plaintiff.
Before
the issuance of a writ of attachment, the plaintiff is required to file an
undertaking to pay the defendant any amount the defendant may recover for any
wrongful attachment by the plaintiff in the action. CCP §489.210.
The undertaking ordinarily is $10,000. CCP §489.220. If the defendant objects, the court may increase
the amount of undertaking to the amount determined as the probable recovery for
wrongful attachment. CCP §489.220. The court also has inherent authority to
increase the amount of the undertaking sua sponte. North Hollywood Marble Co. v. Superior
Court, (1984) 157 Cal.App.3d 683, 691.
C. Statement of Facts[1]
1. Tri-West’s Evidence
In the spring of 2021, Tri-West
President Allen Gage (“Gage”) met with Kolay’s president, Mitchell, and other
Kolay representatives. Gage Decl.,
¶2. Kolay told Gage that it had a new
facility that could promptly produce multiple flooring products in significant
volumes. Gage Decl., ¶2. The representatives also said that Kolay had
the equipment needed to produce product that met key specifications. Gage Decl., ¶2. These statements led Gage to believe that Kolay
could be a successful manufacturing partner for Tri-West. Gage Decl., ¶2.
On August 5, 2021, KFI’s Dalila
Chamberlain (“Chamberlain”) emailed Tri-West to confirm a guaranty that Kolay
would produce 529,200 square feet of flooring at its Las Vegas facility upon
receipt of a $500,094 deposit. Gage
Decl., ¶6, Ex. 4. She also guaranteed
that KFI would produce 8,260 trim pieces at a facility in the City of Industry
upon receipt of a $56,413.70 deposit. Gage
Decl., ¶6, Ex. 4.
On August 11, 2021, Tri-West and both
Kolay companies entered a year-long Agreement for Tri-West to purchase flooring
products from Kolay. Gage Decl., ¶3, Ex.
1. Under the Agreement, Tri-West was
authorized to distribute purchased products.
Gage Decl., ¶3, Ex. 1. Tri-West would
issue purchase orders with definite delivery schedules, which it could only
cancel in advance of manufacturing. Gage
Decl., ¶3, Ex. 1. Kolay was to use all
reasonable efforts to fulfill these orders by the listed due dates, or within a
reasonable period if no due date was specified.
Gage Decl., ¶3, Ex. 1.
Tri-West agreed to a 50% advance
payment for all purchase orders and pay the balance within 30 days of product delivery. Gage Decl., ¶4, Ex. 1. In return, Kolay agreed to use all reasonable
efforts to meet requested delivery dates. Gage Decl., ¶4, Ex. 1. If Kolay could not fulfill an order in a
reasonable time frame, Tri-West could cancel the purchase order and obtain a
refund of its advance payment. Gage
Decl., ¶4, Ex. 1.
The parties were to use all best
efforts to promote, sell, and service products within the territory at issue
and promote the goodwill associated with the products. Gage Decl., ¶4, Ex. 1.
On August 12, 2021, Tri-West wired
$557,160.80 as advance payment for 29 purchase orders, as reflected in
Chamberlain’s August 5, 2021 email. Gage
Decl., ¶¶ 5-6, Exs. 2-3. $500,152.80 of
this payment was to Kolay, and the remaining $57,008 was to KFI. Gage Decl., ¶5, Exs. 2-3. Tri-West relied on the promise that Kolay had
the capacity to fulfill the orders and would refund Tri-West’s advance if it
failed. Gage Decl., ¶6.
Defendants led Tri-West along for
months with promises that they would provide the promised product. Gage Decl., ¶7. What little they did provide was defective in
that the flooring would not lock properly and was not properly finished. Gage Decl., ¶7. Tri-Weset’s efforts to raise these issues
failed. Gage Decl., ¶7. Tri-West never received the product for which
it had spent over half a million dollars.
Gage Decl., ¶7.
After months of waiting, Tri-West
asked Kolay to cancel all the August 2021 purchase orders and refund the $557,160.80
advance payment. Gage Decl., ¶8. In June 2022, Mitchell replied that to keep
payment accurate, he needed time to review documentation of all of the “triumphs
orders” for which he believed “we’re not paid”, but he would keep in touch and
“it will happen shortly.” Gage Decl.,
¶8, Ex. 5. To date, Kolay has not
returned any of the funds. Gage Decl.,
¶9.
2. Defendants’ Evidence
a. Background
KFI is a leading
distributor of luxury flooring coverings founded in 2011. Mitchell Decl., ¶3. Kolay is a manufacturer of luxury flooring
coverings founded in 2019. Mitchell
Decl., ¶4.
Launched in 2019, Kolay
started to look for a partnership to sell Kolay products on an original
equipment manufacturer (“OEM”) basis whereby Kolay manufactures the flooring
while the other company provides branding for the end consumers. Mitchell Decl., ¶13. One company, now known as LL Flooring,
launched one Kolay color in summer of 2022 and has since grown to offer four
colors of Kolay products. Mitchell
Decl., ¶¶ 14-16.
b. Meeting Tri-West
Tri-West is one of the
top flooring distributors on the West Coast.
Mitchell Decl., ¶17. In 2020,
Kolay’s sales team members introduced Tri-West’s owners to Kolay’s
manufacturing line. Mitchell Decl.,
¶18. On March 22, 2021, Daniel Mitchell,
President and CEO of KFI and Kolay, invited Tri-West founders to visit the
Vegas facility in person. Mitchell Decl., ¶¶ 1, 22, Ex. 503.
c.
The May 2021 Plan
On
May 6, 2021, Johnston circulated a summary of Tri-West’s tour a day earlier.
Mitchell Decl., ¶24, Ex. 505.
During the tour, the parties had agreed to create
a new line of products with 14 stock-keeping units (“SKU”), or colors. Mitchell Decl., ¶24, Ex. 505. The
email said that Kolay would work up to 1 million feet per month as the
parties built their business together. Mitchell Decl., ¶24, Ex. 505. The parties needed further discussion on
certain features and the marketing budget.
Mitchell Decl., ¶24, Ex. 505. Kolay
would send product to another company for trim until it had the capacity to do
the trimming itself. Mitchell Decl.,
¶24, Ex. 505. Both companies needed to
start the color development process ASAP.
Mitchell Decl., ¶24, Ex. 505.
Tri-West responded that they were very impressed and excited and would
work to keep things moving on their part.
Mitchell Decl., ¶25, Ex. 506.
On May 13, 2021, as the
parties discussed their shared excitement, Mitchell asked Tri-West to think of
them as a team and that it takes money to get things going. Mitchell Decl., ¶27, Ex. 507. Tri-West said it was well-capitalized and
Koly would never have to worry about its credit. Mitchell Decl., ¶27, Ex. 507. Mitchell was excited to enter into this
partnership with Tri-West. Mitchell
Decl., ¶26. As soon as Tri-West was
ready to put up significant capital, Kolay was ready to devote the majority of
its resources to getting the new product line off the ground. Mitchell Decl., ¶27.
On May 19, 2021,
Tri-West sent Kolay a draft business plan whereby Tri-West would provide wood
samples for Kolay to scan and use as a basis for the colors for their flooring
product. Mitchell Decl., ¶28, Ex.
508. Tri-West would review the finished
products and provide additional scan samples if needed. Mitchell Decl., ¶28, Ex. 508. The listed specifications on the plan included
the possibility of three locking systems: “Unilin Push,” “I4F,” and
“angle.” Mitchell Decl., ¶28, Ex.
508.
The May 2021 plan also
provided that the parties would select 12 to 14 SKU’s of product for a stacker
display. Mitchell Decl., ¶28, Ex.
508. The initial launch would include
300 to 400 sets of samples placed in the field.
Mitchell Decl., ¶28, Ex. 508. The
initial order would be 1 or 2 full truck loads per SKU. Mitchell Decl., ¶28, Ex. 508.
On
May 21, 2021, Kolay replied that it agreed with all but a couple of points in
the May 2021 plan. Mitchell Decl., ¶29, Ex. 509. On May 27, 2021, Kolay responded to each
bullet point in the plan. Mitchell
Decl., ¶30, Ex. 510. This included a
note that while Kolay’s locking system was “5 GI,” it could provide “I4F.” Mitchell Decl., ¶30, Ex. 510.
On May 28, 2021,
Tri-West replied that its goal was to grow with Kolay and agreed with Kolay’s
May 27 email. Mitchell Decl., ¶29, Ex.
510.
d. The Agreement
By mid-June, Kolay and
Tri-West were still working on developing the best colors. Mitchell Decl., ¶32. On June 15, 2021, Tri-West sent 4-6 SKUs in
addition to the 20 samples it already sent.
Mitchell Decl., ¶32, Ex. 512. Tri-West
noted that this was a brand-new and unique product not yet on the market. Mitchell Decl., ¶32, Ex. 512. The scanning process was costly, but Kolay
was willing to invest the resources to contribute to the partnership. Mitchell Decl., ¶32.
On June 22, 2021,
Tri-West identified a list of open items to resolve before Tri-West could issue
purchase orders for formal test product for the new line. Mitchell Decl., ¶33, Ex. 513. These included the colors for the new
line. Mitchell Decl., ¶33, Ex. 513.
On August 4, 2021,
Tri-West submitted purchase orders for the “Sinanian project” with an order
total of $178,775.10. Mitchell Decl.,
¶36, Ex. 516. Tri-West was willing to wire
that without a “Guarantee of Performance” agreement but wanted Mitchell or
another Kolay individual to sign one before any further transfers. Mitchell Decl., ¶36, Ex. 516. A short paragraph would suffice for such an
agreement. Mitchell Decl., ¶36, Ex. 516. This is what led to Chamberlain’s email on
August 5, 2021 (Gage Decl., ¶6, Ex. 4). Mitchell Decl., ¶36. Kolay fully satisfied this order, but this
was only for one of the 12 to 14 SKUs in the May 2021 plan. Mitchell Decl., ¶¶ 37-38.
Before Kolay devoted
more of its own resources to develop Tri-West’s full product line, it wanted
Tri-West to make a good faith deposit so that both parties would have a stake
in success. Mitchell Decl., ¶39. The parties agreed that Tri-West would issue
a series of purchase orders for all the SKUs in the new product line -- named
the Patriot Line -- and use them as the basis for an investment with Kolay’s
manufacturing capability, along the lines of a 50% deposit on the purchase
orders. Mitchell Decl., ¶39. Across all SKUs, the estimated cost for
purchase orders was $1,000,000 in flooring products and $100,000 in flooring
accessory or molding products. Mitchell
Decl., ¶39. Based on this estimate,
Tri-West would deposit $500,000 for flooring and $50,000 for molding. Mitchell Decl., ¶39.
Tri-West insisted a
written contract before investing across the entire product line. Mitchell
Decl., ¶40. Kolay had no prior
agreements to draw from and asked Tri-West for the language to use in the
Agreement. Mitchell Decl., ¶40, Ex.
517. Tri-West responded with a draft of
the Agreement, which was only intended to cover purchase orders and not every
aspect of the partnership. Mitchell
Decl., ¶41. The draft provided that
Tri-West would provide a 50% deposit for any purchase order, and Kolay would fulfill
the order in a reasonable time. Mitchell
Decl., ¶41. Both sides understood that
it would take time to launch the new products, so the draft gave that
flexibility and asked both parties to use best efforts to make the product
successful. Mitchell Decl., ¶41.
The draft’s cancellation
provisions protected both sides.
Mitchell Decl., ¶42. Paragraph 5
allowed Tri-West to cancel an order if Kolay was not performing, but paragraph
3 provided that Tri-West could not cancel an order after manufacturing had
begun. Mitchell Decl., ¶42. This was because the products were a custom
line unique to Tri-West that only Tri-West could sell. Mitchell Decl., ¶42. For these reasons, Mitchell signed the
Agreement. Mitchell Decl., ¶43.
e. The Purchase Orders
Since at least the plant
tour in May 2021, Tri-West knew that Kolay did not yet have the capacity to
make molding products. Mitchell Decl.,
¶44. The $57,008 payment to KFI (Gage
Decl., ¶5, Ex. 3) was for molding
because KFI would take the agreed-on designs and have its overseas partners
make them. Mitchell Decl., ¶44. The $500,152.80 deposit was to Kolay (Gage
Decl., ¶5, Ex. 2) which would make the
flooring planks in-house. Mitchell
Decl., ¶44. Once Tri-West made these
payments, Kolay dedicated 60-75% of its resources to Tri-West orders. Mitchell Decl., ¶45.
After the Agreement,
Tri-West began to move the goalposts for the project. Mitchell Decl., ¶46. First, it wanted the Patriot Line to have
beveled edges instead of Kolay’s usual flat edges. Mitchell Decl., ¶46. This required an additional step where
machines slice off a small portion of the flooring’s edge at an angle. Mitchell Decl., ¶47. This makes the process more expensive, but Kolay
agreed to try. Mitchell Decl., ¶47.
Tri-West then wanted
Kolay to add wood grain images onto the beveled edge. Mitchell Decl., ¶48. In an email on October 13, 2021, Kolay
explained that the digital printer it uses had difficulty printing that image
onto the edge, but technicians believed they had fixed that problem. Mitchell Decl., ¶49, Ex. 518. Kolay also reported “milling” issues with the
locking mechanisms. Mitchell Decl., ¶49,
Ex. 518.
Although Kolay
eventually figured out how to add paint to a beveled edge to make it look more
like wood, this introduced a new problem whereby excess paint would dry on the
edges and remove some of the paint on the plank surface when it chipped. Mitchell Decl., ¶50. Kolay added another step that addressed this
extra paint. Mitchell Decl., ¶50.
With technical
challenges almost behind them, on November 18, 2021, Mitchell sent Tri-West’s
owners mock-ups of the full Patriot Line with images of logos that use the
American flag. Mitchell Decl., ¶51, Ex.
519. The executives went back and forth
about which logo to use. Mitchell Decl.,
¶51, Ex. 519. The next day, Mitchell
sent an image of 12 of the 14 SKUs with the logo affixed. Mitchell Decl., ¶51, Ex. 519. Johnston asked Mitchell to tell him when all
14 were done and added with a smiley face that “As far as I’m concerned the
jobs not done yet.” Mitchell Decl., ¶51,
Ex. 519. Mitchell replied that the other
two would be done the next Monday.
Mitchell Decl., ¶51, Ex. 519.
At the start of 2022,
both sides were still not on the same page about the Patriot Line’s
launch. Mitchell Decl., ¶52. Mitchell had reason to believe that White and
Johnston were not Tri-West owners. Mitchell
Decl., ¶52, Ex. 520. On February 26,
2022, he texted Gage that he only wanted to deal with a Tri-West owner going
forward. Mitchell Decl., ¶52, Ex.
520. That day, Gage responded that White
and Johnston were Tri-West owners with full authority to make decisions. Mitchell Decl., ¶52, Ex. 520.
On March 3, 2022,
Mitchell texted Gage about progress regarding product testing after Tri-West
had demanded more changes to the colors, wood-grain lines, and knot placement. Mitchell Decl., ¶53, Ex. 520. Mitchell was concerned that Tri-West was
growing weary of the pace. Mitchell
Decl., ¶53, Ex. 520. Gage responded that
a few days’ delay was not an issue.
Mitchell Decl., ¶53, Ex. 520.
On March 10, 2022,
Mitchell went to Tri-West offices to meet with the owners and show all 14
designs that Kolay had developed, with the beveled and painted edge that Tri-West
wanted. Mitchell Decl., ¶54. On March 16, 2022, Mitchell asked Tri-West
for updates. Mitchell Decl., ¶55, Ex.
520. Gage responded that Tri-West was
waiting for Mitchell to update it on changing the locking system from I4F to a
Uniclic system. Mitchell Decl., ¶55, Ex.
520. An installation instructor had
complained that the I4F joints were “milled a bit too tight” which made it
difficult to bring pieces together.
Mitchell Decl., ¶55, Ex. 520.
Mitchel was disappointed
that Tri-West was moving the goalposts a second time. Mitchell Decl., ¶56. On March 21, 2022, Mitchell texted Gage that
while the Uniclic system was possible, Kolay would need to pay a licensing fee
of $0.10 per foot. Mitchell Decl., ¶57,
Ex. 520. It would also take 6-8 weeks
for the necessary equipment to arrive.
Mitchell Decl., ¶57, Ex. 520. On
March 30, 2022, Mitchell said the cutter blades should arrive within 3-4
weeks. Mitchell Decl., ¶57, Ex.
520.
f. Tri-West’s Breach
In May 2022, Gage told
Mitchell that Tri-West had decided to use a different manufacturer. Mitchell Decl., ¶58. Gage then demanded its deposits back. Mitchell Decl., ¶58. KFI had already used its $57,008 payment to
order the custom molding from overseas partners, and that molding was
enroute. Mitchell Decl., ¶58. For the $500,152.80 deposit, Kolay had
produced $1 million worth of product for Tri-West before the requests to switch
to painted beveled edges and a new locking system. Mitchell
Decl., ¶58. Kolay had fully performed
and cannot be held responsible for delays because Tri-West repeatedly changed
its mind. Mitchell Decl., ¶58.
During the work on the
Patriot Line, Kolay delivered other product that Tri-West did not pay for,
including the Triumph Line. Mitchell
Decl., ¶59. Tri-West had not paid the
full amount for this product. Mitchell
Decl., ¶59. Mitchell’s June 2022
email (Gage Decl., ¶8, Ex. 5) refers to the Triumph Line and was not an
admission that Tri-West was entitled to its money. Mitchell
Decl., ¶59.
In reliance on
Tri-West’s commitment to the partnership, Kolay invested $2,368,668.11
solely for Tri-West’s product from August 2021 through April 2022. Watts Decl., ¶¶ 4-5, Ex. 522.
On June 19, 2022, White
texted to Mitchell that he hopes they can restore the partnership soon. Mitchell Decl., ¶63, Ex. 521.
3. Reply Evidence
When Kolay and KFI solicited
Tri-West’s business as a flooring distributor, Tri-West understood that it
would issue purchase orders that Kolay would fill in exchange for payment. Johnson Decl., ¶2. At no time did anyone from Kolay or KFI
assert that they were in a joint venture or partnership with Tri-West. Johnson Decl., ¶3. Kolay and KFI also never informed Tri-West
that it would be responsible for expenses incurred in producing product. Johnson Decl., ¶3.
As
part of its efforts to market to Tri-West, Kolay asserted it could quickly
replicate Tri-West samples for production.
Johnson Decl., ¶4. On April 1,
2021, representative Jaime Topete (“Topete”) informed Tri-West that Kolay had run
samples of a paradigm that Tri-West had provided. Johnson Decl., ¶4, Ex. 6. Topete sent samples that Kolay finished in
half a day as proof of how fast Kolay can “strike off” color. Johnson Decl., ¶4, Ex. 6. On April 12, Topete reiterated that the
strike-offs only took five hours to do.
Johnson Decl., ¶4, Ex. 6.
E. Analysis
Plaintiff
Tri-West applies for a right to attach order against Defendants Kolay and KFI in
the amount of $557,160.80.
1.
A Claim Based on a Contract and on Which Attachment May Be Based
A
writ of attachment may be issued only in an action on a claim or claims for
money, each of which is based upon a contract, express or implied, where the
total amount of the claim or claims is a fixed or readily ascertainable amount
not less than five hundred dollars ($500). CCP §483.010(a).
Tri-West’s
claim is for breach of the Agreement for failure to refund the $557,160.80
in advance payments after failing to fill the purchase orders within a
reasonable time. Gage Decl., ¶¶
3-5, Exs. 1-3. This is a claim on which
attachment may be based.
2.
An Amount Due That is Fixed and Readily Ascertainable
A
claim is “readily ascertainable” where the damages may be readily ascertained
by reference to the contract and the basis of the calculation appears to be
reasonable and definite. CIT Group/Equipment Financing, Inc. v. Super
DVD, Inc., (2004) 115 Cal.App.4th 537, 540-41. The fact that the
damages are unliquidated is not determinative. Id. But the
contract must furnish a standard by which the amount may be ascertained and
there must be a basis by which the damages can be determined by proof. Id.
(citations omitted).
The
Agreement required Tri-West to pay in advance 50% of all purchase orders. Gage Decl., ¶4, Ex. 1. If Defendants did not fulfill an order in a
reasonable time, Tri-West could cancel the purchase order and obtain a refund of
the advance payment. Gage Decl., ¶4, Ex.
1. Tri-West has presents evidence that
it wired $500,152.80 to Kolay and $57,008 to KFI as advance payments. Gage
Decl., ¶5, Exs. 2-3.
Defendants
note that Kolay and KFI are separate entities.
Opp. at 14-15. Tri-West responds
that both Kolay and KFI are defined as “Kolay” in the Agreement and that Kolay
is responsible for any refund. Reply at
1. The court agrees that both Kolay and
KFI would be responsible for any amount owed under the Agreement.
4.
Probability of Success
A
claim has “probable validity” where it is more likely than not that the
plaintiff will recover on that claim. CCP §481.190. In determining
this issue, the court must consider the relative merits of the positions of the
respective parties. Kemp Bros. Construction, Inc. v. Titan Electric
Corp., (2007) 146 Cal.App.4th 1474, 1484. The court does not
determine whether the claim is actually valid; that determination will be made
at trial and is not affected by the decision on the application for the
order. CCP §484.050(b).
Tri-West
presents evidence that, on August 11, 2021, it, Kolay, and KFI entered the
year-long Agreement for Tri-West to purchase flooring products. Gage Decl., ¶3, Ex. 1. Pursuant to the Agreement, Tri-West would
issue purchase orders with definite delivery schedules, which could only be canceled
in advance of manufacturing. Gage Decl.,
¶3, Ex. 1. Kolay would use all reasonable efforts to fulfill these orders by
the listed due dates, or within a reasonable period if no due date was
specified. Gage Decl., ¶3, Ex. 1. Tri-West
agreed to advance a 50% payment for all purchase orders and pay the rest within
30 days of product delivery. Gage Decl., ¶4, Ex. 1. If Defendants could not fulfill an order in a
reasonable timeframe, Tri-West could cancel the purchase order and obtain a
refund of its advance payment. Gage Decl., ¶4, Ex. 1.
Tri-West
alleges that Defendants strung it along for months after the products were
ordered and the advance payments were made on August 12, 2021. Gage Decl., ¶7. What little product Defendants did provide
was defective. Gage Decl., ¶7. As a result, Tri-West cancelled the purchase
orders and demanded a refund. Gage
Decl., ¶¶ 7-8.
Defendants
suggest that the parties entered into a partnership or a joint venture (which
is a project-specific partnership). They
provide evidence that Tri-West toured Koray’s facility on May 6, 2021 and was
very impressed. Mitchell Decl., ¶25, Ex. 506. On
May 13, 2021, Mitchell asked Tri-West to think of them as a team. Mitchell Decl., ¶27, Ex. 507. Mitchell was excited to enter into a
partnership with Tri-West and, as soon as Tri-West was ready to put up
significant capital, Kolay was ready to devote the majority of its resources to
getting the new product line off the ground.
Mitchell Decl., ¶¶ 26-27.
Tri-West sent Kolay a
draft business plan and the parties eventually agreed upon it. Mitchell Decl., ¶¶ 28-30, Ex. 508, 509, 510. On May 28, 2021, Tri-West replied that its
goal was to grow with Kolay. Mitchell
Decl., ¶29, Ex. 510. The scanning process was costly, but Kolay was
willing to invest the resources to contribute to the partnership. Mitchell Decl., ¶32. Tri-West insisted a written contract before
investing across the entire product line.
Mitchell Decl., ¶40. The
Agreement was only intended to cover purchase orders and not every aspect of
the partnership. Mitchell Decl.,
¶41. Both sides understood that it would
take time to launch the new products, so the draft Agreement gave them flexibility
and asked both parties to use best efforts to make the product successful. Mitchell Decl., ¶41.
Despite Defendants’
reference to a partnership and a joint venture, they provide no specific terms
of such a joint venture beyond the Agreement.
The hallmark of a partnership or a joint venture is a sharing of profits
and losses. April Enterprises, Inc.
v. KTTV (1983), 147 Cal. App. 3d 805, 819.
Defendants provide no terms of profit and loss sharing, and it is clear
from the Agreement and the purchase orders that the parties were not going to
share profits and losses. In fact,
Defendants refer to the August 4, 2021 $178,755.10 purchase order for the
Sinanian project as a completed purchase order with no discussion of shared
profit. Mitchell Decl., ¶36, Ex.
516. As Tri-West asserts, this reflects a
merchant relationship of purchase and supply.
Reply at 7. Defendants have not
shown that there was a partnership or joint venture.
Defendants assert
that the Agreement does not permit Tri-West to cancel a purchase order after
Kolay began manufacturing the product.
Opp. at 9; Mitchell Decl.,
¶42. Paragraph 5 allows Tri-West to
cancel an order if Kolay was not performing, but paragraph 3 provides that
Tri-West could not cancel an order after manufacturing had begun. Mitchell Decl., ¶42. This was because the products were a custom
line unique to Tri-West that only Tri-West could sell. Mitchell Decl., ¶42. By the time Tri-West cancelled the purchase
orders, KFI had already used its $57,008 payment to order the custom molding
from overseas partners, and that molding was enroute. Mitchell Decl., ¶58. Similarly, Kolay already had produced over $1
million of product for Tri-West before the latter made design changes for
painted beveled edges and a new locking system.
Mitchell Decl., ¶58. Defendants argue
that Tri-West could not cancel the two purchase orders and breached the
Agreement in doing so. Opp. at 11.
As
Tri-West observes, Kolay provides no documentary evidence to support its
assertion that the $57,008 for molding was enroute from overseas partners. Reply at 4, n.3.
Defendants
misread the Agreement. Contract
interpretation is a matter of law. Civil Code §§ 1636, 1639.
Courts should interpret a contract based on the usual and
ordinary meaning of the contractual language and the circumstances under which
the agreement was made. Rice v. Downs, (2016) 248 Cal. App. 4th
175, 185-86. No extrinsic evidence may be received to vary the terms of a
contract that is fully integrated. The existence of an integration clause
in the contract is a key factor in determining whether the parties intended the
contract as a final and complete expression of their agreement. Grey
v. Am. Mgmt. Servs., (2012) 204 Cal.App.4th 803,
807. When the parties dispute the meaning of contract language, the first
issue is whether the language is reasonably susceptible to the interpretation
urged by the party. Dore v. Arnold Worldwide, Inc., (2006) 39
Cal.4th 384, 393. If so, the court must consider all credible
evidence offered to prove the intention of the parties. Pacific Gas
& Electric Co. v. G.W. Thomas Drayage, (1968) 69 Cal.2d 33,
39-40. The parties’ undisclosed intent or understanding is irrelevant to
contract interpretation. Iqbal v. Ziadeh, (2017) 10 Cal.App.5th 1,
8-9.
Applying
the principles of contract interpretation, Paragraph 3 permits Tri-West to
cancel an accepted purchase order for no reason only prior to
manufacturing. Paragraph 5 provides that
Tri-West may cancel a purchase order, and obtain a refund, if Defendants are unable
to fulfill the purchase order in a reasonable time. Reply at 6; Gage Decl., ¶4, Ex. 1. In other words, Tri-West may cancel a
purchase order for any reason if Kolay has not begun manufacturing to fill the
order. Tri-West may cancel a purchase
order after Kolay has begun manufacturing the product only if Kolay fails to
deliver in a reasonable time. In that
circumstance, Tri-West is entitled to a refund.
Defendants
failed to deliver the ordered products on time.
The issue is whether Defendants have shown that Tri-West’s changes made
timely delivery infeasible.
Tri-West
asserts that Defendants cannot rely on the affirmative defenses excuse or
prevention of performance because the operative Answer does not plead. Kolay has filed a motion for leave to file a
First Amended Answer (“FAA”) including these defenses which will be heard by
the I/C court. As such, these defenses
are waived. Cal. Academy of Sciences
v. City of Fresno, (“Academy”) (1987) 192 Cal.App.3d 1436, 1442. Reply at 3.
Tri-West’s
assertion that the defenses are waived is untenable. An answer raising affirmative defenses is not
essential for purposes of attachment and Tri-West points to no authority to the
contrary. Academy is a summary
judgment case in which the county’s waiver and estoppel arguments had not been
pled as affirmative defenses in its answer.
Id. at 1442. Plainly, a failure
to plead an affirmative defense at the summary judgment stage differs from a
provisional remedy such as attachment which may issue long before an answer is
ever filed. Moreover, Defendants’
pending motion for leave to amend its Answer to add these affirmative defenses
suffices to meet any pleading requirement for an affirmative defense to
attachment.
Tri-West
asserts that on August 5, 2021, Koly’s Chamberlain emailed Tri-West to confirm
a guaranty that Kolay would produce 529,200 square feet of flooring at its Las
Vegas facility upon receipt of a $500,094 deposit. Gage Decl., ¶6, Ex. 4. She also guaranteed that KFI would produce
8,260 trim pieces at a facility in the City of Industry upon receipt of a $56,413.70
deposit. Gage Decl., ¶6, Ex. 4.
Defendants suggest that, after the Sinanian
project was completed, Tri-West wanted a short performance guarantee before any
further payment transfers. For
this reason, Chamberlain wrote the August 4, 2021 email guaranteeing production
in response to the two purchase orders for $56,413.700 and $500,094.00. Mitchell Decl., ¶36, Ex. 516. Whatever the reason, Defendants guaranteed
Tri-West their performance on these purchase orders.[2]
This
brings the court to Defendants’ argument that Tri-West prevented timely
performance by Defendants due to continuing changing specifications. Defendants provide substantial evidence that
Tri-West’s changing demands caused the production delays.
After
the parties entered into the Agreement, Tri-West asked for beveled edges that
require an extra step to make. Mitchell
Decl., ¶¶ 46-47. Tri-West attempts to
cast Defendants’ statements as an admission that beveled edges were always the
plan. Reply at 6. Not so.
Defendants’ evidence is that Tri-West asked for beveled edges arose after
the parties signed the Agreement.
Mitchell Decl., ¶¶ 46, 48. In an
October 13, 2021 email, Kolay explained that this request had caused delays
because the digital printer had difficulty printing that image onto the
edge. Mitchell Decl., ¶49, Ex. 518. Kolay also had to develop a method to remove
extra paint before it dried on the edges so that it would not chip off. Mitchell Decl., ¶50.
Tri-West
asserts that Kolay found a method that worked no later than November 2021, and
the request did not prevent performance.
Reply at 8. True, but the beveled
edges issue influences what timeframe for performance was “reasonable” for Tri-West’s
purchase order.
By
November 18, 2021, Kolay had finished 12 of the 14 SKUs agreed upon with
Tri-West. Mitchell
Decl., ¶51, Ex. 519. On March 3,
2022, Kolay’s CEO Mitchell texted Tri-West’s CEO Gage about product
testing. Mitchell Decl., ¶53, Ex.
520. When Mitchell asked Gage whether he
could start mass production immediately after, Gage responded that the main
focus was getting things right even if it took a few days. Mitchell
Decl., ¶53, Ex. 520. On March 10, 2022,
Mitchell presented the finished SKUs to Tri-West’s owners. Mitchell Decl., ¶54. During that conversation, Gage asked Kolay to
switch the agreed upon I4F interlocking system to a Uniclic system. Mitchell Decl., ¶55, Ex. 520.
Tri-West
argues that the switch to a Uniclic system did not change the goalposts because
its draft business plan listed the Unilin Push 14F system only was
preferred. Mitchell Decl., ¶28, Ex.
508. Kolay attempted to use this locking
system but it caused significant issues.
On October 13, 2021, Kolay reported “milling” issues with the I4F locking
mechanisms. Mitchell Decl., ¶49, Ex.
518. As of March 2022, Tri-West informed
Kolay that the locking system was still “a bit too tight”. Mitchell Decl., ¶52, Ex. 520. Tri-West then asked Koly to use a different
locking mechanism. Id. Kolay did not object to this change or argue
that Tri-West was moving the goalposts. Kolay
instead tried to accommodate the request.
Mitchell Decl., ¶¶ 55-56, Ex. 520.
Kolay never was able to produce a finished product and, after nearly a year
of waiting, Tri-West canceled its orders.
Reply at 8.
Tri-West
fails to explain why Kolay’s attempts to be flexible impedes its argument that
Tri-West’s changes excused or prevented Kolay’s performance, and that the delay
in its performance remained reasonable under the Agreement. On March 21, 2022, Mitchell texted Gage that
Kolay would need to wait 6-8 weeks for the necessary equipment to arrive and it
would add $0.10 per foot in cost. Mitchell Decl., ¶57, Ex. 520. Tri-West did not wait for Kolay to finish the
new interlocking system. Instead, Tri-West
terminated the relationship in May 2022.
Mitchell Decl., ¶58.
Based
on the evidence presented, Tri-West’s changes made Defendants’ delay in
production reasonable. Performance is
excused when prevented or delayed by the act of the creditor. Civil Code §1511. See Taylor v. Sapritch, (1940)
38 Cal.App.2d 478, 481 (performance excused when prevented by acts of the
opposite party). As such, Tri-West has
not shown that it was entitled to cancel the purchase orders under the
Agreement. Tri-West has failed to demonstrate a probability of success that
Defendants breached the Agreement, and that Tri-West is entitled to a
refund.
5.
Offset
Any
amount to be secured by attachment must be reduced by the amount claimed in a
cross-complaint or affirmative defense and shown would be subject to attachment
against the plaintiff. CCP
§483.015(b)(2).
In
general, expenses necessarily incurred by the nonbreaching party in good faith,
in anticipation of, or in preparation for, performance by the other party are
recoverable as an element of damages for breach of contract. Walpole v Prefab Mfg. Co. (1951) 103
Cal.2d 472. The court in Lewis Jorge
Constr. Mgmt., Inc. v. Pomona Unified Sch. Dist. (2004) 34 Cal.4th 960,
968-69, found that consequential damages are recoverable if the special or
particular circumstances from which they arise were actually communicated or
known or should have been known by the breaching party.
Defendants
present evidence that, in reliance on
Tri-West’s commitment to the business plan, Kolay invested $2,368,668.11
solely for Tri-West’s product from August 2021 through April 2022. Watts Decl., ¶¶ 4-5, Ex. 522.
Tri-West
replies that Defendants have pled no cross-claim, do not allege this in their
Answer, and have never raised this demand during months of litigation. Reply at 9.
The court need not consider these arguments because Tri-West is correct
that the claim is not available for attachment.
Reply at 9. While Defendants may
claim $2,368,668.11 in damages at trial, they are not available for
offset. The damages awardable on a
cross-claim can only offset the amount to be attached if the cross-claim damages
themselves would be eligible for attachment.
See CCP §483.015(b)(2).
This means that the cross-claim damages must be readily ascertainable
from the contract. See CCP
§483.010(a). There is no provision in
the Agreement from which Defendants’ investment of monies to build the products
Tri-West wanted is readily ascertainable.
Assuming that Defendants can obtain damages from Tri-West’s
breach, these damages are not available for offset.
6.
Attachment Sought for a Proper Purpose¿
Attachment
must not be sought for a purpose other than the recovery on the claim upon
which attachment is based.¿ CCP §484.090(a)(3).
Tri-West seeks attachment for a proper purpose.
E. Conclusion
Tri-West’s
applications for right to attach orders are denied.
[1]
The court has ruled on both parties’ written evidentiary objections, sometimes
overruling an objection based on Fibreboard Paper Products Corp. v. East Bay
Union of Machinists, Local 1304, Seelworkers of America, AFL-CIO, (1964)
227 Cal.App.2d 675, 712 (court may overruled objection if any portion of
objected to material is admissible). The
clerk is directed to scan and electronically file the court’s rulings.
[2] Tri-West
replies that the Sinanian project is irrelevant because it is not part of the
purchase orders issued pursuant to the Agreement. Reply at 5, n. 4. It is background evidence for Tri-West’s
request for the guarantees.