Judge: James C. Chalfant, Case: 23STCV05901, Date: 2023-08-03 Tentative Ruling
Case Number: 23STCV05901 Hearing Date: August 3, 2023 Dept: 85
RNWD JV, LLC, v. Lexham Torrance,
LLC, 23STCV05901
Tentative decision on application
for a right to attach order: denied
Plaintiff
RNWD JV, LLC (“Tenant”), applies for a right to attach order against Defendant Lexham
Torrance, LLC (“Landlord”) for $453,044.81, including $10,000 in costs and $200,000
in attorney’s fees.
The
court has read and considered the moving papers, opposition, and reply, and
renders the following tentative decision.
A. Statement of the Case
1.
Complaint
Plaintiff Tenant filed the Complaint
against Landlord on March 17, 2023, alleging (1) breach of contract, (2) breach
of the implied covenant of good faith and fair dealing, and (3) declaratory
relief. The Complaint alleged in
pertinent part as follows.
On June 22, 2022, Landlord and Tenant
entered into a Lease Agreement (“Lease”) to rent suite #400 at 3655
Lomita Blvd, Torrance, CA 90505 (“Premises”). Tenant prepaid $15,372 in rent and a $226,672.81
security deposit. A $207,615.84 portion
of the security deposit was in the form of a letter of credit from U.S. Bank
National Association (“Letter of Credit”).
Under the terms of the Lease,
Landlord was required to install HVAC and the necessary cooling, demise walls, install
drywall, stub the building for electricity to the perimeter, and provide
electricity with a dedicated 200-amp panel (collectively, “Landlord Work”)
prior to delivery of the Premises on August 1, 2022. Landlord failed to complete its work or
delivery of the Premises on that date. An
addendum between the parties extended the deadline to September 30, 2022 (“Addendum”),
but Landlord also failed to finish the Landlord Work by that date.
The Lease gives Tenant the right to
terminate upon Landlord’s failure to substantially complete the Landlord Work
and deliver the Premises within 30 days of the deadline, provided that Tenant
gives ten days’ written notice before doing so.
Landlord must then return any pre-paid rent and security deposit,
including the Letter of Credit.
Landlord has admitted that it failed
to complete the Landlord Work and deliver the Premises to Tenant by October 30,
2022. Tenant tried for months to work
with Landlord, but it became clear that Landlord was not operating in good
faith. The Landlord Work remained
unfinished as of February 15, 2023.
Research has revealed that Landlord had not even obtained the necessary
permits for some of the Landlord Work.
Throughout this time, Landlord’s
conspired with its contractor to keep Tenant off the Premises so that it could
not see how far behind the Landlord Work was.
The contractor, whom the Landlord suggested, also charged over three
times the market rate for the agreed-upon Landlord Work.
On February 15, 2023, Tenant sent a
Notice of Termination terminating the Lease on February 26, 2023. Landlord refused to recognize Tenant’s right
to termination and to return the pre-paid rent and security deposit. Tenant’s business has suffered significant
losses because it is unable to open the dental office it planned after
significant investment.
Tenant seeks damages according to
proof, prejudgment interest, and a judicial declaration that the Lease was terminated
on February 26, 2023. The declaration
should compel Landlord to return all pre-paid rent and security deposits and
not draw on the Letter of Credit. Injunctive
relief should also issue to prevent Landlord from drawing on the Letter of
Credit. Tenant further seeks attorney’s
fees and costs.
2. Cross-Complaint
Landlord filed a Cross-Complaint
against Tenant on May 1, 2023, alleging (1) breach of contract, (2) breach of
the implied covenant of good faith and fair dealing, and (3) declaratory
relief. The Cross-Complaint alleged in
pertinent part as follows.
The Lease defined the Commencement
Date as the completion of the Landlord Work and delivery of the Premises,
originally August 1, 2022. The parties
agreed that Tenant would not pay rent for the first nine months after the
Commencement Date and the pre-paid rent was for the tenth month of the
Lease.
Under the Lease, Landlord was to (1)
demise the Premises as shown on an attached Premises Floor Diagram; (2) bring
and stub the building’s plumbing, HVAC, and electricity to the perimeter of
Premises; and (3) install a dedicated 200-amp panel for Tenant’s electricity. Landlord was not required to perform any other
work for the Premises. The parties
agreed that the Landlord was to substantially complete the work by August 1,
2022, subject to delays outside of Landlord’s reasonable control, including
those caused by Tenant or force majeure.
After the Landlord Work is
substantially completed, Tenant agreed to be solely responsible for all required
and desired improvements and alterations to prepare the Premises for Tenant’s
use and occupancy thereof (“Tenant Work”).
The Tenant Work was to be performed under the Landlord’s supervision and
pursuant to building permits, approvals, and other licenses as required by
governmental agencies. Tenant was required
to “diligently prosecute” said work to completion.
Tenant was required to execute and
deliver a statement in writing to the Landlord or proposed mortgagee or
purchaser (“Estoppel Certificate”) within ten days of such a written request
from the Landlord. The Landlord may then
rely on such a statement or certificate.
A Tenant default under the Lease includes abandonment
of the Premises, failure to pay rent within five days of the due date, and failure
to take possession of the Premises and begin Tenant Work and/or commercial use
after completion of Landlord Work and delivery of the Premises.
Upon default, Landlord may terminate the Tenant’s
right to possession and recover all damages incurred. This includes the cost of recovery, reletting
expenses, costs of necessary renovation, reasonable attorney’s fees, and the
worth of the amount by which unpaid future rent exceeds what the Tenant proves
Landlord could have reasonably avoided.
Unpaid rent and other installments would also accrue 10% annual
interest.
After Tenant signed the Lease, it decided
to alter the floor plan for the Premises and asked Landlord to alter the
Landlord Work’s demising of the walls to accommodate it. To accommodate this request, Tenant agreed to
the Addendum which changed the deadline for Landlord Work under the Lease to
September 30, 2022. Because the parties
signed the Addendum on August 30, 2022, which means that Tenant was still
modifying the floor plans three months after it signed the Lease.
Landlord hired Shamma Construction,
Inc. (“Shamma”)[1] as
its general contractor for Landlord Work.
Shamma finished demising the walls of the Premises and stubbing the
building’s plumbing, HVAC, and electricity to the perimeter in mid-September
2022. Landlord also mounted two 100-amp
panels in late September 2022 because Shamma recommended them in lieu of one
200-amp panel for the Premises’ size and Tenant’s needs. The Landlord Work was substantially completed
by the Addendum deadline of September 30, 2022.
Tenant asked Landlord to keep the
demising walls free of drywall to allow later inspectors to inspect the
construction of the walls. This also
accommodated Tenant’s delays in finalizing its floor plans and hiring a general
contractor to start Tenant Work. Landlord
also applied for a common hallway permit and installed a hallway corridor door. None of this changed the fact that Landlord
had substantially completed Landlord Work as of September 30, 2022.
When Tenant asked for a referral to
a contractor for the Tenant Work, Landlord recommended Shamma due to its
familiarity with the building. Shamma
commenced the Tenant Work as early as November 2022. Tenant has paid Shamma $30,000 for Tenant
Work. None of the work Shamma performed for
Tenant Work was included in Landlord Work under the Lease.
On November 15, 2022, Peter Abruzzo
(“Abruzzo”), Tenant Manager and Renew LLC’s (“Renew”) president, visited the
Premises along with Steve Siemers (“Siemers”).
Neither one asked Shamma or Premises property manager Jennifer Moore
(“Moore”) questions about the state of the Landlord Work.
On January 16, 2023, Tenant executed
a Tenant Estoppel Certificate to Community West Bank, N.A. The estoppel certificate warranted that the
Lease was not in default and that Tenant did not know of any event that
constituted a default by Landlord. Both
Landlord and the Lender proceeded in good faith in reliance on this 2023 Certificate.
In the following months, Tenant vacillated
on finalizing its plans for the Premises, delayed its efforts to select a
general contractor, and at times appeared to conduct no activities at the
Premises. It later complained to
Landlord that Shamma’s construction costs exceeded Tenant estimates and asked
to terminate the Lease. When Landlord
refused, Tenant filed this Complaint.
In reality, Landlord substantially completed
Landlord Work in September 2022 and fully completed it on the week of February
13, 2023.
Tenant’s failure to pay rent and
Direct Expenses due under the Lease resulted in damages of at least $5
million. Costs incurred to complete
Landlord Work totaled $250,000. Landlord
seeks these compensatory damages, attorney’s fees and costs, interest accrued,
and a declaration that (1) the Lease is valid, (2) Tenant wrongfully terminated
it, and (3) Landlord is entitled to draw on the Letter of Credit, the security
deposit, and the pre-paid rent.
2.
Course of Proceedings
On March 17, 2023, the
court denied Tenant’s ex parte application for a temporary restraining
order (“TRO”) and order to show cause (“OSC”) why a preliminary injunction
should not issue to enjoin Landlord from drawing funds from the Letter of
Credit, and to compel Landlord to withdraw any prior requests to draw from the Letter
of Credit.
On March 31, 2023,
Tenant served Landlord with the Complaint and Summons.
On May 1, 2023, Landlord
filed and its Answer and Cross-Complaint.
On June 2, 2023, Tenant
filed an Answer to the Cross-Complaint.
Effective August 7,
2023, the case is reassigned from Department 72 (Hon. Curtis A. Kin) to
Department 72 (Hon. Joseph Lipner).
B.
Applicable Law
Attachment
is a prejudgment remedy providing for the seizure of one or more of the
defendant’s assets to aid in the collection of a money demand pending the
outcome of the trial of the action. See
Whitehouse v. Six Corporation, (1995) 40 Cal.App.4th 527, 533. In 1972, and in a 1977 comprehensive
revision, the Legislature enacted attachment legislation (CCP §481.010 et
seq.) that meets the due process requirements set forth in Randone v.
Appellate Department, (1971) 5 Cal.3d 536.
See Western Steel & Ship Repair v. RMI, (12986) 176
Cal.App.3d 1108, 1115. As the attachment
statutes are purely the creation of the Legislature, they are strictly
construed. Vershbow v. Reiner,
(1991) 231 Cal.App.3d 879, 882.
A
writ of attachment may be issued only in an action on a claim or claims for
money, each of which is based upon a contract, express or implied, where the
total amount of the claim or claims is a fixed or readily ascertainable amount
not less than five hundred dollars ($500).
CCP §483.010(a). A claim is
“readily ascertainable” where the amount due may be clearly ascertained from
the contract and calculated by evidence; the fact that damages are unliquidated
is not determinative. CIT
Group/Equipment Financing, Inc. v. Super DVD, Inc., (2004) 115 Cal.App.4th
537, 540-41 (attachment appropriate for claim based on rent calculation for
lease of commercial equipment).
All
property within California of a corporation, association, or partnership is
subject to attachment if there is a method of levy for the property. CCP §487.010(a), (b). While a trustee is a natural person, a trust
is not. Therefore, a trust’s property is
subject to attachment on the same basis as a corporation or partnership. Kadison, Pfaelzer, Woodard, Quinn &
Rossi v. Wilson, supra, 197 Cal.App.3d at 4.
The
plaintiff may apply for a right to attach order by noticing a hearing for the
order and serving the defendant with summons and complaint, notice of the
application, and supporting papers any time after filing the complaint. CCP §484.010.
Notice of the application must be given pursuant to CCP section 1005,
sixteen court days before the hearing. See
ibid.
The
notice of the application and the application may be made on Judicial Council
forms (Optional Forms AT-105, 115). The
application must be supported by an affidavit showing that the plaintiff on the
facts presented would be entitled to a judgment on the claim upon which the
attachment is based. CCP §484.030.
Where the defendant is a corporation, a general
reference to “all corporate property which is subject to attachment pursuant to
subdivision (a) of Code of Civil Procedure Section 487.010” is sufficient. CCP §484.020(e). Where the defendant is a partnership or other
unincorporated association, a reference to “all property of the partnership or
other unincorporated association which is subject to attachment pursuant to
subdivision (b) of Code of Civil Procedure Section 487.010” is sufficient. CCP §484.020(e). A specific description of property is not
required for corporations and partnerships as they generally have no exempt
property. Bank of America v. Salinas
Nissan, Inc., (“Bank of America”) (1989) 207 Cal.App.3d 260, 268.
A
defendant who opposes issuance of the order must file and serve a notice of
opposition and supporting affidavit as required by CCP section 484.060 not
later than five court days prior to the date set for hearing. CCP §484.050(e). The notice of opposition may be made on a
Judicial Council form (Optional Form AT-155).
The
plaintiff may file and serve a reply two court days prior to the date set for
the hearing. CCP §484.060(c).
At
the hearing, the court determines whether the plaintiff should receive a right
to attach order and whether any property which the plaintiff seeks to attach is
exempt from attachment. The defendant
may appear the hearing. CCP
§484.050(h). The court generally will
evaluate the attachment application based solely on the pleadings and
supporting affidavits without taking additional evidence. Bank of America, supra, 207
Cal.App.3d at 273. A verified complaint may be used in lieu of or in addition
to an affidavit if it states evidentiary facts.
CCP §482.040. The plaintiff has
the burden of proof, and the court is not required to accept as true any
affidavit even if it is undisputed. See
Bank of America, supra, at 271, 273.
The
court may issue a right to attach order (Optional Form AT-120) if the plaintiff
shows all of the following: (1) the claim on which the attachment is based is
one on which an attachment may be issued (CCP §484.090(a)(1)); (2) the
plaintiff has established the probable validity of the claim (CCP
§484.090(a)(2)); (3) attachment is sought for no purpose other than the
recovery on the subject claim (CCP §484.090(a)(3); and (4) the amount to be
secured by the attachment is greater than zero (CCP §484.090(a)(4)).
A
claim has “probable validity” where it is more likely than not that the
plaintiff will recover on that claim.
CCP §481.190. In determining this
issue, the court must consider the relative merits of the positions of the
respective parties. Kemp Bros.
Construction, Inc. v. Titan Electric Corp., (2007) 146 Cal.App.4th 1474,
1484. The court does not determine
whether the claim is actually valid; that determination will be made at trial
and is not affected by the decision on the application for the order. CCP §484.050(b).
Except
in unlawful detainer actions, the amount to be secured by the attachment is the
sum of (1) the amount of the defendant’s indebtedness claimed by the plaintiff,
and (2) any additional amount included by the court for estimate of costs and
any allowable attorneys’ fees under CCP section 482.110. CCP §483.015(a); Goldstein v. Barak
Construction, (2008) 164 Cal.App.4th 845, 852. This amount must be reduced by the sum of (1)
the amount of indebtedness that the defendant has in a money judgment against
plaintiff, (2) the amount claimed in a cross-complaint or affirmative defense
and shown would be subject to attachment against the plaintiff, and (3) the
value of any security interest held by the plaintiff in the defendant’s property,
together with the amount by which the acts of the plaintiff (or a prior holder
of the security interest) have decreased that security interest’s value. CCP §483.015(b); see also CCP
§483.010(b) (“an attachment may not be issued on a claim which is secured by
any interest in real property arising from agreement, statute, or other rule of
law…However, an attachment may be issued where the claim was originally so
secured but, without any act of the plaintiff or the person to whom the
security was given, the security has become valueless or has decreased in value
to less than the amount then owing on the claim). A defendant claiming that the amount to be
secured should be reduced because of a cross-claim or affirmative defense must
make a prima facie showing that the claim would result in an attachment
against the plaintiff.
Before
the issuance of a writ of attachment, the plaintiff is required to file an
undertaking to pay the defendant any amount the defendant may recover for any
wrongful attachment by the plaintiff in the action. CCP §489.210.
The undertaking ordinarily is $10,000. CCP §489.220. If the defendant objects, the court may increase
the amount of undertaking to the amount determined as the probable recovery for
wrongful attachment. CCP §489.220. The court also has inherent authority to
increase the amount of the undertaking sua sponte. North Hollywood Marble Co. v. Superior
Court, (1984) 157 Cal.App.3d 683, 691.
C. Statement of Facts
1. Tenant’s Evidence
a. Background
Landlord has admitted in court that it
is a special purpose vehicle that owns only the building in which the Premises
are located. Salim Decl., ¶4.
b. The Lease
On June 22, 2022, the parties
entered into the Lease for the Premises.
Abruzzo Decl., ¶3, Ex. 1. In
connection thereto, Tenant prepaid $15,372 in rent,
paid a cash security deposit of $20,056.97, and tendered the $207,615.84 Letter
of Credit. Abruzzo Decl., ¶6, Ex. 1.
The Term of the Lease is ten years
and nine months, and the rent increases over time. Abruzzo Decl., ¶4, Ex. 1. The Lease defines the Commencement Date as
the date of completion of Landlord Work and delivery of possession to Tenant. Ex. 1, p. 1.
Article 36 defines the Landlord Work to include: (1) demising the
Premises based on an attached Premises Floor Diagram; (2) bringing and stubbing
the plumbing, HVAC, and electricity to the perimeter of Premises; and (3)
installing a dedicated 200-amp panel for Tenant’s electricity. Ex. 1, p. 34.
The completion date for the Landlord work was to be no later than August
1, 2022, subject to delays outside of Landlord’s reasonable control, including force
majeure and delays caused by Tenant.
Id.
Article 36 states that, if the
Landlord failed to substantially complete Landlord Work and deliver possession
within 30 days of the intended delivery date, Tenant had the right to terminate
the Lease after ten days’ prior written notice. Id.
Landlord must then return any prepaid rent and security deposit,
including the Letter of Credit. Id. If the Landlord substantially completes the
Landlord Work and delivers possession of the Premises during the ten-day notice
period, the termination notice will be null and void. Id.
Under Article 35, apart from the
Landlord Work, Tenant shall be solely responsible for all required and desired
improvements at its sole cost and expense (Tenant Work). Ex. 1, p. 33.
Tenant shall perform all Tenant Work pursuant to building permits, approvals
and other licenses as required by governmental agencies, in compliance with all
applicable laws, rules and regulations and in a good and workmanlike manner
using reputable licensed contractors which Landlord approved. Id.
Article 23.f defines Tenant’s failure to perform such Tenant Work as one
form of default. Ex. 1, p. 27.
Article 26 provides that, upon
request from Landlord at any point during the Lease, Tenant shall execute,
acknowledge, and deliver an Estoppel Certificate to either the Landlord or
proposed mortgagee or purchaser. Ex. 1,
p. 28. If Tenant did not execute and
deliver such an Estoppel Certificate, the Landlord may do so in Tenant’s name
and on Tenant’s behalf. Id. Landlord and any prospective purchaser or
encumbrancer may then rely on the Estoppel Certificate. Id.
Article 30(xii) entitled the
prevailing party in any action to enforce the Lease to recover attorney’s fees
and costs. Abruzzo Decl., Ex. 1.
On August 30, 2022, the parties
signed the Addendum that modified the deadline for Landlord Work and delivery
of the Premises to September 30, 2022.
Abruzzo Decl., ¶7, Ex. 2.
c. Breach
On August 22 and 31, 2022 Tenant
sent revised plans to Landlord through contractor Sharma. Siemers Decl., ¶2, Ex. 1, pp. 8-9. Landlord received clarification that the revised
wall demising plan replaces one of the plans attached to the Lease. Id., p. 7. On September 1, 2022, Landlord asked how to
resolve the fact that general contractor Shamma’s door delivery would not be
for another 17-20 weeks. Id., p.
6. Landlord explained that because the
doors were part of the demising for Landlord Work, it would not be finished by
September 30. Id. Landlord did not think it would affect Tenant
because Tenant still needed eight to ten weeks for its own plan check and four
months for construction. Id.
Landlord did not finish Landlord
Work by September 30, 2022 or 30 days later on October 30, 2022. Abruzzo Decl., ¶9. Tenant worked with Landlord to avoid
termination of the Lease because it was eager to operate a dental center on the
Premises. Abruzzo Decl., ¶10.
On January 10, 2023, a general
contractor sent Siemers a bid for review.
Siemers Decl., ¶3, Ex. 2, p. 15-16.
The contractor explained that the bid was a first draft because of
uncertainties as to the HVAC control and fire alarm control panel
capacity. Siemers Decl., ¶3, Ex. 2. After some exchanged emails, on January 16,
2023, the contractor said that the electrical panel boxes on the Premises were
too small and must be a 42-breaker panel per engineered electrical plans. Id., p. 11.
In January 2023, Landlord presented
Tenant with the Estoppel Certificate for execution. Abruzzo Decl., ¶12.[2] Tenant understood that Landlord was
refinancing its mortgage and needed the Estoppel Certificate to assist those
efforts. Abruzzo Decl., ¶12. Abruzzo signed the Estoppel Certificate with
the understanding that under Article 26 Landlord could otherwise execute it on
Tenant’s behalf. Abruzzo Decl.,
¶12.
On February 2, 2023, Tenant’s electrical
contractor Kunle Olofinboba (“Olofinboba”) of the AYK Group, Inc. (“AYK”) informed
Siemers that Landlord’s contractor Shamma had told AYK to stop work on the
premises until further notice. Siemers
Decl., ¶4, Ex. 3. Olofinboba confirmed
that Landlord had not yet installed a 200-amp panel as part of Landlord’s work
and the City of Torrance (“City”) had not inspected or approved the electrical
portion of Landlord’s Work. Siemers
Decl., ¶4.
On February 15, 2023, another Tenant
contractor, Mark Sirianni (“Sirianni”), sent Tenant pictures of the Premises. Siemers Decl., ¶5, Ex. 4. Sirianni commented that it looked like there
was work ongoing on the Premises, all in the common areas. Siemers Decl., ¶5, Ex. 4. This showed Tenant that Landlord had not
completed the Landlord Work. Siemers Decl.,
¶5, Ex. 4.
Tenant researched whether Landlord
obtained the necessary permits for inspection needed to complete Landlord
Work. Abruzzo Decl., ¶14. On February 28, 2023, Tenant emailed the City’s
Permit Center Supervisor to ask if any permits or inspections been issued or
called pertaining to the Premises.
Siemers Decl., ¶6, Ex. 5. On
March 5, the Permit Center Supervisor responded that Olofinboba had picked up
two corrections on February 14, 2023.
Siemers Decl., ¶6, Ex. 5.[3]
As of February 2023, Landlord failed
to (1) demise the Premises; (2) install drywall; (3) bring and stub the
building for electricity to the perimeter of the Premises; (4) provide the
cooling necessary for the HVAC for the Premises; and (5) install a dedicated
200 amp-panel for Tenant’s electricity. Abruzzo
Decl., ¶13.
When Tenant representatives tried to
access the Premises to see the progress on Landlord Work, Landlord’s
contractors refused to let them in.
Abruzzo Decl., ¶15. Earlier, when
Tenant was looking for a contractor to complete Tenant Work, Landlord had
recommended its contractor at triple the market rate. Abruzzo Decl., ¶15.
d. Termination
On February 15, 2023, Tenant sent
Landlord a ten-day Notice of Termination.
Abruzzo Decl., ¶16, Ex. 4. The
Notice of Termination asserted that Landlord failed to (1) demise the Premises,
which still had no drywall; (2) bring and stub the building for the electricity
to the perimeter; (3) provide the tons of cooling necessary for the HVAC; and
(4) install a dedicated 200-amp panel for electricity. Abruzzo Decl., ¶16, Ex. 4, p. 57. Landlord also did not have the Landlord Work
permitted or inspected. Id. A Landlord representative had admitted in
writing the failure to timely perform Landlord’s Work. Id.
Tenant demanded return of the $15,372 rent, $20,056.97 cash security
deposit, and $207,615.84 Letter of Credit from U.S. Bank by February 28. Id., p. 58.
On February 20, 2023, Landlord
replied that it had substantially completed the Landlord Work as set forth in
the Lease and agreed upon by the parties.
Abruzzo Decl., ¶18, Ex. 5, p. 60.
Landlord also delivered possession of the Premises by September 30,
2022. Id. Landlord asserted that Tenant had taken
possession of the Premises and had begun Tenant Work. Id.
Landlord cited the Estoppel Certificate in which Tenant accepted
possession of the Premises and stated that the Lease Term commenced on
September 30, 2022. Id. Per the Estoppel Certificate, Tenant also
admitted that it was performing the Tenant Work and had started paying rent,
that there was no condition that constituted a Landlord default to Tenant’s
knowledge, that Landlord had fully satisfied and performed all applicable
conditions and obligations, and that Tenant had no defenses or offenses to Landlord’s
enforcement of the Lease. Id. Landlord asserted that because Tenant had
accepted possession of the Premises, the provision of the Lease that Tenant
relied on for the Notice of Termination was no longer in effect. Id.
Pursuant to the Notice of Termination,
Tenant terminated the Lease on February 26, 2023. Abruzzo Decl., ¶17.
On March 3, 2023, Tenant responded to Landlord’s February
20, 2023 letter. Abruzzo Decl., ¶19, Ex.
6. Tenant asserted that Landlord
admitted on September 1, 2022 that demising work would not be finished by the
deadline. Abruzzo Decl., ¶19, Ex. 6, p.
62. In any case, local officials had
confirmed that Landlord did not have the necessary permits or inspections for the
Landlord Work. Id. Therefore, the Landlord Work was not
substantially complete. Id. Substantial completion of this work and
delivery of the Premises were separate conditions to fulfill before the Commencement
Date listed in the Lease and this has not occurred. Id., p. 63.
Landlord never responded to this
letter. Abruzzo Decl., ¶19. Landlord has since drawn on the Letter of
Credit and has not refunded the security deposit or prepaid rent. Abruzzo Decl., ¶20.
e. Attorney’s Fees
Tenant’s counsel are a law firm partner
who bills $1,250 per hour and an associate who bills $825 per hour. Salim Decl., ¶2. The law firm already has billed $53,512.50 in
fees and $1,917.06 in costs, for a total of $55,429.56. Salim Decl., ¶2.
Tenant’s counsel expects to bill an
additional $144,497.50 in fees to finalize this application for writ of
attachment, file a reply brief, attend the hearing, serve discovery, depose
Landlord and its contractor, defend depositions of Tenant and its contractors,
draft and oppose any summary motions, and try the case. Salim Decl., ¶3. Counsel also expects to incur an additional
$8,082.94 in costs. Salim Decl., ¶3.
A conservative total estimate of attorney’s fees and costs is $200,000
and $10,000, respectively. Salim Decl.,
¶3.
2. Landlord’s Evidence
a. The Landlord Work
Morlin Asset Management LP
(“Morlin”) performed asset management services for Landlord in connection with
the Premises. Moore Decl., ¶1.
In July 2022, Landlord contacted
Shamma to discuss work on the Premises.
Shamma Decl., ¶3. The scope of
work was to prepare the Premises for Tenant to build out tenant improvements
for a dental implant center. Shamma
Decl., ¶3. On July 3, Shamma received a
preliminary plan that matched the Lease’s plan for demised walls as part of
Landlord Work. Shamma Decl., ¶3.
On July 11, 2022, Tenant
representative Steve Siemers (“Siemers”) emailed Shamma the preliminary
plan. Shamma Decl., ¶4. The next day, he emailed Shamma questions and
a request to move the exit doors. Shamma
Decl., ¶4.
On July 13, 2022, Siemers emailed Landlord
and Shamma with additional questions about the preliminary plan. Shamma Decl., ¶5. Shamma hired an architect to prepare revised
plans that would accommodate Tenant’s requests.
Shamma Decl., ¶5. Siemers and
Shamma continued to revise the demising walls plans over the following
month. Shamma Decl., ¶6. Siemers did not seem in a hurry during this
time and would often delay in his response to emails. Shamma Decl., ¶6.
On August 22, 2022, Shamma emailed
revised demising wall plans to Siemers and Landlord representative Thomas
Bailey (“Bailey”) for approval. Shamma
Decl., ¶7, Ex. A. Siemers approved these
plans on August 31, 2022. Shamma Decl.,
¶7, Ex. B. Shamma then sent a proposal
to Bailey, who approved it on September 7, 2022. Shamma Decl., ¶8; Bailey Decl., ¶3.
Shamma completed the extension of
plumbing into the Premises between September 8 and 20, 2022. Shamma Decl., ¶10.
Shamma started the demising walls work
on September 13, 2022. Shamma Decl., ¶9;
Bailey Decl., ¶4. By September 22, 2022,
it had finished the wall framing. Shamma
Decl., ¶9. Shamma did not install the drywall
on exterior and interior side of the demising walls because, after Tenant
finished its interior tenant improvements, the City inspector would ask to
inspect electrical work on the interior of the demising walls. Shamma Decl., ¶9; Bailey Decl., ¶5. Siemers agreed that Shamma should leave the
demising walls open to allow such inspection.
Shamma Decl., ¶9. Thus, by the
end of September Shamma had substantially completed demising the walls as part
of the Landlord Work. Shamma Decl., ¶9;
Moore Decl., ¶4; Bailey Decl., ¶5.
Although the Lease provided for a
single 200-amp electrical panel as part of Landlord Work, Siemers and Shamma
agreed to instead install two 100-amp panels on either side of the
Premises. Shamma Decl., ¶12; Bailey
Decl., ¶4. Siemers did not approve the
plans for installation of the electrical panels until September 7, 2022, and he
understood that the electrical panels had a lead time of four to six
weeks. Shamma Decl., ¶12. The panels could have been installed on
perimeter walls, but Tenant required that they be installed on interior walls during
the Tenant Work. Bailey Decl., ¶4.
By September 26, 2022, Shamma had
installed electrical conduits, wires, and cans.
Shamma Decl., ¶12. He had also brought
and stubbed the electricity to the perimeter of the Premises. Shamma Decl., ¶12; Bailey Decl., ¶4.
On October 13, 2022, Shamma received
the two 100-amp panels. Shamma Decl.,
¶12. On October 18, 2022, Siemers sent
modified electrical plans for Shamma to follow.
Shamma Decl., ¶12, Ex. C. Siemers
instructed Shamma to install these panels on interior partition walls based on
the October 18, 2022 modified electrical plans.
Shamma Decl., ¶12, Ex. C.
Because the HVAC was already stubbed
to the perimeter of the Premises, it required no changes as a part of Landlord
Work before Tenant took possession. Shamma
Decl., ¶11. Siemers accepted the HVAC
system as it was. Shamma Decl., ¶11.
Based on this work, Landlord had
substantially completed the Landlord Work by the Addendum’s deadline of September
30, 2022. Bailey Decl., ¶4.
Landlord has in good faith applied
for a common hallway permit and installed a hallway corridor door. Bailey Decl., ¶10. It was under no Lease obligation to do
so. Bailey Decl., ¶10.
b. The Tenant Work
In mid-August 2022, Tenant asked
Landlord to refer a general contractor for interior tenant improvements of the
Premises. Bailey Decl., ¶8. Landlord referred Shamma. Bailey Decl., ¶8.
On October 31, 2022, at Siemers’
request, Shamma sent Tenant a proposal for improvements that were not a part of
the Landlord Work. Shamma Decl., ¶13,
Ex. D. The work included framing and
bracing of partition walls. Shamma
Decl., ¶13, Ex. D. Shamma would also
install backing and bracing for various fixtures, ceiling tiles, power sources
and conduits for a dental chair and other equipment, data wires, plumbing, a
concrete floor, medical gas piping, fire extinguisher cabinets, and laminate
cabinets. Shamma Decl., ¶13, Ex. D. Siemers gave Shamma approval to start the
Tenant Work based on this proposal.
Shamma Decl., ¶13.
In November 2022, Shamma began work
on interior construction of the Premises for Tenant, which the Lease defines as
the Tenant Work. Bailey Decl., ¶8. Tenant has paid Shamma $30,000 for interior
door framing. Bailey Decl., ¶9. It has not paid Shamma for interior doors it
ordered, which Shamma has now stored in a warehouse. Bailey Decl., ¶9.
Siemers and Tenant President Peter Abruzzo
(“Abruzzo”) planned to visit the Premises on November 15, 2022. Shamma Decl., ¶14. Siemers instructed Shamma to frame the
interior partition walls as part of the Tenant Work before the visit. Shamma Decl., ¶14. Shamma employee Antonio Rodriguez’s timecard
shows that he worked on the interior partition walls every weekday between
November 3 and 15 ,2022. Shamma Decl.,
¶14, Ex. E.
When
Siemers and Abruzzo visited the Premises on November 15, 2022, they were very
pleased with the layout of the interior partition walls and the floor markings for
the electrical outlets and panels. Shamma
Decl., ¶15. Siemers told Shamma to
install the two electrical panels on those walls at a later time. Shamma Decl., ¶15. Siemers and Abruzzo did not ask any questions
about the walls’ demising or other issues with the Premises. Moore Decl., ¶7. Based on Bailey’s experience with Siemers and
Abruzzo, they would have raised any problems that they had with the
Premises. Bailey Decl., ¶7.
During
the visit, Siemers and Abruzzo voiced some concerns about Shamma’s high air
conditioning bid. Moore Decl., ¶6. Morlin Senior Portfolio Manager Moore
explained that this was because of supply chain issues and parts costs. Moore Decl., ¶6. She also asserted that Tenant was asking for over-standard
air conditioning capabilities. Moore
Decl., ¶6. When asked, she opined that Shamma
was trustworthy. Moore Decl., ¶6. Siemers and Abruzzo also met with Shamma to
discuss the air conditioning proposal and Tenant Work. Moore Decl., ¶7.
After multiple conference calls
between Siemers, Shamma, and electrical contractor Olofinboba, on December 14,
2022, Siemers sent updated design plans to update the electrical plans for
revisions associated with Tenant Work for the washer and dryer. Olofinboba Decl., ¶12, Ex. I.
In January 2023, at Siemers’
request, Shamma replaced the two 100-amp panels on the interior partition walls
with two 42-breaker 100-amp panels. Shamma
Decl., ¶16. Tenant continued to modify
tenant improvement plans over the following months, which caused further
delay. Shamma Decl., ¶16. When Shamma spoke to Siemers on February 1,
2023 about payment owed for those improvements, Siemers hung up. Shamma Decl., ¶16.
On February 17, 2023, Shamma installed
drywall on the exterior side of demised walls on Landlord’s instructions. Shamma Decl., ¶17; Bailey Decl., ¶13. He also installed sheetrock and soundboard on
walls common side of corridor. Bailey
Decl., ¶13. On February 24, 2023, Shamma
installed drywall on the interior side, again on Landlord’s instructions. Shamma Decl., ¶17; Bailey Decl., ¶14.
At some point, Siemers requested Morin to provide
general contractor candidates for the Tenant Work. Moore Decl., ¶8. Moore has reviewed four of the five bids
Renew received from general contractors, including Shamma. Moore Decl., ¶9.[4] Two of them are for prices higher than
Shamma’s proposal. Moore Decl., ¶9. While CMM’s bid seems lower, it was missing
several material items that would have made the price higher than Shamma’s
proposal. Moore Decl., ¶9.
c. The Estoppel Certificate
On January 16, 2023, Tenant signed
the Estoppel Certificate. Lewis Decl., ¶3,
Ex. 1. It stated that the Landlord may
rely upon the truth and accuracy of all statements therein. Lewis Decl., ¶3, Ex. 1.
The Estoppel Certificate states that
the Lease is not in default, is valid, and is in full force and effect. Lewis Decl., ¶4, Ex. 1. The Lease has not been modified and represents
the entire agreement between Landlord and Tenant with respect to the Premises. Id.
Tenant had accepted possession of the Premises and is performing Tenant
Work as defined in the Lease. Id.
The Lease began on September 30,
2022. Id.
Tenant agreed that, to the best of
its knowledge, no event has occurred and no condition exists which would
constitute Landlord’s default under the Lease. Id.
Tenant affirmed that it has no defenses or offsets against Landlord’s enforcement
of the Lease. Id. Landlord had made all required contributions for
tenant improvements except for Landlord Work as described in Article 36 and
Tenant Improvement Allowance as described in Article 35. Id. The Estoppel Certificate may be relied upon
and shall inure to the benefit of Lender and Landlord knowing it will reply
upon the truth and accuracy if it. Id.
The Estoppel Certificate concluded
that it shall inure to the benefit of the Landlord and its Lender, Community
West Bank, N.A (“Lender”). Id. Both parties know that they will rely on the
truth and accuracy of all statements therein.
Id.
d. The Tenant Electrical Work
On July 12, 2022, Shamma contacted
Olofinboba to request a proposal for electrical design consulting work at the
Premises. Olofinboba Decl., ¶3. Olofinboba, on behalf of his company, AYK,
sent a proposal the same day and a revised proposal on July 17, 2022, both
addressed to Shamma. Olofinboba Decl.,
¶¶ 3-4, Ex. A. On July 18, 2022, Shamma
forwarded the revised proposal to Siemers.
Olofinboba Decl., ¶4, Ex. B.
At Siemers’ request, on September 1,
2022, Olofinboba resent the electrical design consulting proposal directly to
him. Olofinboba Decl., ¶5, Ex. C. On September 20, 2022, Siemers sent
Olofinboba the proposal with references to Tenant in place of Shamma. Olofinboba Decl., ¶6, Ex. D. Neither Olofinboba nor anyone else at AYK
sent the proposal to Tenant, and his practice was to contract with Shamma. Olofinboba Decl., ¶6.
Olofinboba asked for clarification
on who was responsible for paying AYK.
Olofinboba Decl., ¶7, Ex. E.
After a conference call, Shamma, Siemers, and Olofinboba agreed that
Shamma would hold the contract with AYK so it would receive all invoicing and
billing. Olofinboba Decl., ¶8. Shamma and AYK executed a contract to that
effect. Olofinboba Decl., ¶9, Ex.
F.
On February 1, 2023, Siemers asked
Olofinboba if he could pay AYK to pick up plan check comments from the
City. Olofinboba Decl., ¶13, Ex. J. Siemers asserted that Shamma was no longer
involved in the project, and that a mechanical engineer was now handling its
plans. Olofinboba Decl., ¶13, Ex.
J. Olofinboba replied that AYK could
pick up the comments and charge the same hourly rate as it had for Shamma. Olofinboba Decl., ¶14, Ex. K.
Olofinboba became concerned about
how Siemers and Renew offered to pay AYK directly when Shamma held the
contract. Olofinboba Decl., ¶14. When he asked Shamma, he was told to stop
work on the project until further notice.
Olofinboba Decl., ¶14. Olofinboba
informed Siemers of this fact via email on February 2, 2023. Olofinboba Decl., ¶15, Ex. L. Olofinboba also said that Shamma held AYK’s contract
on the project. Olofinboba Decl., ¶15,
Ex. L. He meant that AYK could not enter
into a separate contract for work in connection with the Premises until Tenant had
paid Shamma in full for its contract.
Olofinboba Decl., ¶15.
On February 6, 2023, Siemers emailed
Olofinboba that Tenant was no longer working with Shamma due to its high-priced
bid. Olofinboba Decl., ¶16, Ex. M. On February 9, Siemers asserted that Tenant had
paid in full AYK’s invoice under its contract with Shamma. Olofinboba Decl., ¶16, Ex. M. Olofinboba replied that Shamma would not cut
AYK loose until all outstanding invoices were paid. Olofinboba Decl., ¶16, Ex. M. He asked Siemers to resolve them with Shamma
so AYK could move forward with the project.
Olofinboba Decl., ¶16, Ex. M. Siemers
reiterated that Renew had paid all invoices before it cut Shamma loose for
overpricing the job. Olofinboba Decl.,
¶16, Ex. M. Siemers requested that AYK
keep construction separate from design services and permitting, for which it
never wanted to use a general contractor again.
Olofinboba Decl., ¶16, Ex. M.
On February 13, 2023, Olofinboba advised
Siemers to resolve the issue with Shamma, who did not treat design and
construction as separate services. Olofinboba
Decl., ¶16, Ex. M. These conversations made
Olofinboba realize that Siemers was attempting to circumvent AYK’s contract
with Shamma. Olofinboba Decl., ¶16.
On February 15, 2023, Olofinboba
picked up the electrical plan check comments from the City and then emailed
these comments to Siemers. Olofinboba
Decl., ¶17, Ex. N. On March 23, 2023, Olofinboba
resubmitted plan check corrections to the City.
He received notice on April 17 that the City approved the corrected
plan. Olofinboba Decl., ¶17. He forwarded that notification to Shamma on
April 21, 2023. Olofinboba Decl., ¶17,
Ex. O.[5]
e. Tenant’s Termination
Efforts
On February 7, 2023, Siemers called Bailey
to discuss the money Tenant owed to Shamma for the Tenant Work. Bailey Decl., ¶11. Later that day, Siemers asked if Landlord
would consider buying Tenant out of the Lease; it would not. Bailey Decl., ¶11. Landlord declined. Id.
By the time Landlord received
Tenant’s Notice of Termination on February 20, 2023, it had completed the Landlord
Work. Lewis Decl., ¶6. That day, Landlord responded with a letter asserting
that per Tenant’s warranties in the Estoppel Certificate, the provision of the
Lease on which Tenant relied for its Notice of Termination was no longer
applicable. Lewis Decl., ¶7, Ex. 2.
On March 3, 2023, Tenant gave notice
that it still intended to terminate the Lease, asserting that it never waived
its right to terminate the Lease. Lewis
Decl., ¶8, Ex. 3.
Tenant had underestimated the costs
of Tenant Work by as much as $200,000.
Lewis Decl., ¶5; Bailey Decl., ¶11.
On March 7, 2023, Abruzzo again asked if Tenant could buy out the Lease
at a discounted price. Lewis Decl.,
¶5. Landlord rejected the offer. Lewis Decl., ¶5.
3. Reply
Evidence[6]
a. City
Building Code
Section
81.2.2 of the City Building Code lists the types of construction work that is
exempted from a permit. Siemers Supp.
Decl., ¶6, Ex. A. This list does not
include any of the Landlord Work like demising walls, bringing and stubbing
plumbing, HVAC, and electricity, or installing electrical panels. Siemers Supp. Decl., ¶6, Ex. A (City Building
Code §81.2.2). The City Building
Official may require that a registered design professional evaluate unpermitted
work and prepare mitigation plans to mitigate such work. Siemers Supp. Decl., ¶7, Ex. A (City Building
Code §81.2.4).
b. Permits
During a
phone conversation in November 2022, Shamma told Siemers that he had not pulled
a permit for any work performed at the Premises since 2014. Siemers Supp. Decl., ¶10.
Once
Tenant discovered that the Landlord Work on the Premises was performed without
permits, Tenant could not proceed with Tenant Work. Siemers Supp. Decl., ¶9. This was because, when the City came to
permit the Tenant Work, it would discover the lack of permits for the Landlord
Work and could evaluate and prepare mitigation plans for it. Siemers Supp. Decl., ¶9.
As of July
31, 2023, a search on the City’s website yielded six permits for the Premises
from 2022 thereafter. Siemers Supp.
Decl., ¶12, Ex. B. One was filed in May
2023, months after the Notice of Termination.
Siemers Supp. Decl., ¶14, Ex. B.
The other five are either labeled “TEN IMP” or are to relocate or
install air units. Siemers Supp. Decl.,
¶13, Ex. B. This shows that all these
permits are for the Tenant Work, not the Landlord Work. Siemers Supp. Decl., ¶13.
c. Substantial
Completion
Sirianni’s
February 2023 pictures of the Premises (Siemers Decl., ¶5, Ex. 4) show that the
electrical panels were the wrong size and had the wrong number of
breakers. Siemers Supp. Decl., ¶17. Another of Tenant’s contractors confirmed
this (Siemers Decl., ¶3, Ex. 2). Siemers
Supp. Decl., ¶17. Wires were loose and
too short to connect to the panels.
Siemers Supp. Decl., ¶19. The
HVAC ran through the framing. Siemers Supp.
Decl., ¶19.
The
pictures also show that Landlord did not install drywall on the demising
walls. Siemers Supp. Decl., ¶18. Although Landlord asserts that this was to
allow for City inspection of the Tenant Work, this explains the lack of drywall
on the interior side and not the exterior.
Siemers Supp. Decl., ¶21. A
permit holder only needs to tell the City that it will place drywall on the
exterior side but needs an inspection before it can place drywall on the
interior side. Siemers Supp. Decl.,
¶21.
d. Changes
to the Design
After the
parties executed the Lease, Landlord asked to alter the Premises’ floor plans
to maximize rentable space for other tenants.
Siemers Supp. Decl., ¶25.
On August
1, 2022, Shamma informed Siemers that it needed to relocate the tank storage
room to create a common corridor.
Siemers Supp. Decl., ¶30, Ex. E.
Siemers agreed but asked why a corridor was necessary. Siemers Supp. Decl., ¶30, Ex. E. Shamma replied that some of the leftover
space was land-locked. Siemers Supp.
Decl., ¶31, Ex. E. Landlord added that
this felt like a good compromise because it only needs a corridor if another
tenant exists. Siemers Supp. Decl., ¶31,
Ex. E. On August 2, 2022, Siemers asked
if Landlord wanted to plan the Premises with only one corridor and as if it
would not continue south to the stairs.
Siemers Supp. Decl., ¶31, Ex. E.
Shamma suggested the switch from one
200-amp panel to two 100-amp panels.
Siemers Supp. Decl., ¶33. Tenant deferred to Shamma and agreed. Siemers Supp. Decl., ¶33.
Any assertion that the Addendum was
due to changes that Tenant made to the Premises plan is false. Siemers Supp. Decl., ¶34. Shamma’s delay in obtaining interior doors is
what made the September 30 target date impossible to meet. Siemers Supp. Decl., ¶35.
e. Contract for Tenant Work
Tenant never executed a contract
with Shamma for the Tenant Work. Siemers
Supp. Decl., ¶38. Shamma provided
construction plans and began to perform based on the assumption that it would
receive the contract. Siemers Supp.
Decl., ¶38. Although Tenant paid
$30,000, this was as a sign of good faith and not performance under any
contract. Siemers Supp. Decl., ¶38.
Tenant did not pay for the interior
doors because Shamma bought those doors without any authorization from or
contract with Tenant. Siemers Supp.
Decl., ¶40.
D. Analysis
Tenant
applies for a right to attach order against Landlord for $453,044.81, including
$10,000 in costs and $200,000 in attorney’s fees.
1.
A Claim Based on a Contract and on Which Attachment May Be Based
A
writ of attachment may be issued only in an action on a claim or claims for
money, each of which is based upon a contract, express or implied, where the
total amount of the claim or claims is a fixed or readily ascertainable amount
not less than five hundred dollars ($500). CCP §483.010(a).
Tenant’s
application is based on breach of the Lease and seeks recovery of $15,372 in
rent, a cash security deposit of $20,056.97, and a $207,615.84 Letter of Credit
from U.S. Bank. Abruzzo Decl., ¶6, Ex.
1. Attachment may be based on this contract
claim.
2.
An Amount Due That is Fixed and Readily Ascertainable
A
claim is “readily ascertainable” where the damages may be readily ascertained
by reference to the contract and the basis of the calculation appears to be
reasonable and definite. CIT Group/Equipment Financing, Inc. v. Super
DVD, Inc., (“CIT”) (2004) 115 Cal.App.4th 537, 540-41. The
fact that the damages are unliquidated is not determinative. Id.
But the contract must furnish a standard by which the amount may be ascertained
and there must be a basis by which the damages can be determined by
proof. Id. (citations omitted).
When
the parties executed the Lease, it required Tenant to prepay one month of rent,
or $15,372. Abruzzo Decl., ¶6, Ex.
1. It also required Tenant to post a
security deposit in two parts. The first
was $20,056.97 in cash. Abruzzo Decl.,
¶6, Ex. 1. The second was a $207,615.84
Letter of Credit from U.S. Bank. Abruzzo
Decl., ¶6, Ex. 1. Landlord does not
dispute that Tenant has met these obligations.
Abruzzo Decl., ¶6, Ex. 1. Damages
of $15,372 + $20,056.97 + $207,615.84 = $243,044.81 are ascertainable.
Article
30(xii) of the Lease entitles the prevailing party in any action to enforce the
Lease to recover attorney’s fees and costs.
Abruzzo Decl., Ex. 1.
Tenant
asserts that counsel has already billed $53,512.50 in fees in this matter and
$1,917.06 in costs, a total of $55,429.56.
Salim Decl., ¶2. Based on hourly
rates and the anticipated future steps in this litigation, Tenant’s counsel estimates
that attorney’s fees and costs will total $200,000 and $10,000,
respectively. Salim Decl., ¶3.
Landlord
asserts that attorney’s estimates of fees and costs are insufficient without proper
itemization. Opp. at 15. It cites Royals v. Lu, (“Royals”),
(2022) 81 Cal. App. 5th 328, 348, to assert that a court may reject attorney’s
fees and costs when the moving party provides no itemization. Opp. at 15-16. In Royals, the court rejected a $3,440,000
attachment based on “punitive damages and estimated attorney’s fees and costs.” 81 Cal. App. 5th at 348. The court concluded that some portion of this
amount supported attachment (compensatory damages, attorney’s fees, and costs)
and some did not (punitive damages). Id.
at 349. On the evidence the amount was
unsupported and should have been rejected by the trial court. Id.
Although the court would reduce it if attachment were ordered (see post),
the $210,000 in estimated attorney’s fees and costs is not disallowed.
Damages
of $243,044.81 + $210,000 = $453,044.81 are ascertainable.
3.
Probability of Success
A
claim has “probable validity” where it is more likely than not that the
plaintiff will recover on that claim. CCP §481.190. In determining
this issue, the court must consider the relative merits of the positions of the
respective parties. Kemp Bros. Construction, Inc. v. Titan Electric
Corp., (2007) 146 Cal.App.4th 1474, 1484. The court does not
determine whether the claim is actually valid; that determination will be made
at trial and is not affected by the decision on the application for the
order. CCP §484.050(b).
a.
Landlord’s Breach
(1).
Substantial Completion
The
Lease set the deadline for substantial completion of Landlord Work as August 1,
2022. Abruzzo Decl., ¶5, Ex. 1. The Addendum changed deadline this to September
30, 2022. Abruzzo Decl., ¶7, Ex. 2. The Landlord Work included: (1) demising the
Premises based on a Premises Floor Diagram attached to the Lease; (2) bringing
and stubbing the plumbing, HVAC, and electricity to the perimeter of Premises;
and (3) installing a dedicated 200-amp panel for Tenant’s electricity. Abruzzo Decl., ¶5, Ex. 1.
If
the Landlord failed to substantially complete Landlord Work within 30 days of
this deadline, Tenant had the right to terminate the Lease after ten days’
prior written notice. Abruzzo Decl., ¶8,
Ex. 1. If the Landlord substantially
completed the Landlord Work and delivered possession of the Premises during the
ten-day notice period, the termination notice would be null and void. Abruzzo Decl., ¶8, Ex. 1.
On February
15, 2023, Tenant sent Landlord the ten-day Notice of Termination. Abruzzo Decl., ¶16, Ex. 4. Pursuant to the Notice of Termination, Tenant
terminated the Lease on February 26, 2023. Abruzzo Decl., ¶17. If Landlord substantially completed the Landlord
Work within ten days of the Notice of Termination, Tenant’s termination of the
Lease was void.
Tenant
asserts that as of February 2023, Landlord failed to: (1) demise the Premises;
(2) install drywall; (3) bring and stub the building for electricity to the
perimeter of the Premises; (4) provide the cooling necessary for the HVAC for
the Premises; and (5) install a dedicated 200-amp panel for Tenant’s electricity.
Abruzzo Decl., ¶13.
Landlord presents undisputed
evidence on issues (3) and (4). By
September 26, 2022, Shamma had installed electrical conduits, wires, and cans. Shamma Decl., ¶12. He had also brought and stubbed the
electricity to the perimeter of the Premises.
Shamma Decl., ¶12; Bailey Decl., ¶4.
Because the HVAC was already stubbed to the perimeter of the Premises,
it required no changes as a part of Landlord Work before Tenant took
possession. Shamma Decl., ¶11. Siemers accepted the HVAC system as it
was. Shamma Decl., ¶11.
This leaves issues (1), (2), and (5).
Electrical
Panels
Tenant
cites an email from a general contractor who asserted that the electrical panel
boxes were too small and needed to be 42-breaker panels per engineered
electrical plans. Siemers Decl., ¶3, Ex.
2.
Landlord
presents persuasive evidence that Tenant agreed to switch the original 200-amp
panel for two 100-amp panels. Shamma
Decl., ¶12; Bailey Decl., ¶4. When
Siemers’ told Shamma to replace those panels with 42-breaker 100-amp panels, he
complied. Shamma Decl., ¶16. Although the panels were improperly small
(Reply at 11), Tenant does not present any evidence that Landlord or Shamma
should not have complied with Tenant’s request.
See Siemers Supp. Decl., ¶37.
Tenant
cites pictures sent by its contractor, Sirianni, on February 15, 2023. Siemers Decl., ¶5, Ex. 4. Sirianni stated that work was still ongoing
on the Premises, all in the common areas. Siemers Decl., ¶5, Ex. 4. Wires were loose and too short to connect to
the panels. Siemers Supp. Decl., ¶19. Tenant
asserts that these pictures showed Tenant that Landlord had not completed the
Landlord Work. Siemers Decl., ¶5, Ex. 4.
Whether
the unfinished work in those pictures was part of Landlord Work or Tenant Work
is unclear. Tenant was responsible for
all improvements and alterations to prepare the Premises for Tenant’s use and
occupancy and the operation of Tenant’s business therefrom. Abruzzo Decl., Ex. 1. The pictures show the electrical panels and
the lack of any drywall. Siemers Decl.,
¶5, Ex. 4, pp. 32, 34. The Lease defined
demising walls as part of Landlord Work.
Abruzzo Decl., ¶5, Ex. 1.
However, Landlord’s
evidence is that Tenant changed the nature of Landlord Work so that the
electrical panels were to be placed on interior walls. On
October 13, 2022, Shamma received the two 100-amp panels. Shamma Decl., ¶12. On October 18, 2022, Siemers sent modified
electrical plans for Shamma to follow. Shamma
Decl., ¶12, Ex. C. Siemers instructed
Shamma to install these panels on interior partition walls based on the October
18, 2022 modified electrical plans.
Shamma Decl., ¶12, Ex. C.
Tenant
also cites to a February 2, 2023 email where subcontractor AYK informed Siemers
that Shamma told it to stop work on the Premises until further notice. Siemers Decl., ¶4, Ex. 3. Tenant asserts that this is because Landlord
had not installed the necessary electrical panel. Mot. at 12.
Landlord
provides evidence that this email did not stem from a failure to complete the Landlord
Work. The parties agreed that Shamma
would contract with AYK for the electrical work. Olofinboba Decl., ¶¶ 8-9, Ex. F. Yet, on February 1, 2023, Siemers asked
Olofinboba if he could pay AYK to pick up plan check comments from the City. Olofinboba Decl., ¶13, Ex. J. Olofinboba became concerned that Tenant was
attempting to poach his services.
Olofinboba Decl., ¶14. He told
Shamma, who ordered AYK to stop work until further notice. Olofinboba Decl., ¶14. The point of AYK’s email to Tenant was that
AYK would not enter into a separate contract for work on the Premises until Tenant
paid Shamma in full. Olofinboba Decl.,
¶15, Ex. L. AYK’s email does not suggest
that either Shamma or AYK failed to complete the Landlord Work.
Tenant
has not shown a probability of success with respect to the electrical panels.
Demise
and Drywall
Shamma started the demising walls work on September 13,
2022. Shamma Decl., ¶9; Bailey Decl.,
¶4. By September 22, 2022, it had
finished the wall framing. Shamma Decl.,
¶9.
Landlord
presents a compelling explanation for why it did not install the drywall panels
on demising walls. A proposal for Tenant
Work included the installation of power sources and conduits for a dental chair
and other equipment. Shamma Decl., ¶13,
Ex. D. Once Tenant finished interior
improvements for inspection, the inspector would ask to inspect electrical work
on the interior of the demising walls. Shamma
Decl., ¶9; Bailey Decl., ¶5. Siemers
agreed that Shamma should leave the demising walls open to allow such
inspection. Opp. at 7, 14; Shamma Decl.,
¶9; Moore Decl., ¶4; Bailey Decl., ¶5.
Although
Tenant argues in reply (Reply at 11) that Landlord could have drywalled one
side of the interior walls, it does not rebut Landlord’s point that Tenant
agreed otherwise. Siemers Supp. Decl.,
¶21.
Tenant
has not shown a probability of success with respect to demise and drywall.
Permits
Tenant
asserts that Landlord cannot have finished the Landlord Work as to the 200-amp
panel because it has not had the City approve or inspect the installation. Mot. at 12.
Tenant notes that the City confirmed in February 2023 that no permits
have been issued as to the Premises. Siemers
Decl., ¶6, Ex. 5.
The
Lease does not directly address which party will pull the permits. Article 35 states that Tenant will be
responsible for performing the Tenant Work pursuant to building permits,
approvals, and other regulations. Abruzzo
Decl., Ex. 1, p. 33. Article 36 contains
no such provision. Ex. 1, p. 34.
Landlord
argues that it never agreed to obtain permits, and Tenant does not demonstrate
that the Landlord Work would require a permit.
Opp. at 13, n. 7. On the other
hand, the Tenant Work is expressly required to take place subject to completion
of the Landlord Work and delivery of the Premises to Tenant. Ex. 1, p. 33 (Art. 35).
Tenant
shows in reply that, with some inapplicable exceptions, the City Building Code requires
permits for all construction work. Siemers
Supp. Decl., ¶6, Ex. A (City Building Code §81.2.2). It would seem that permits have to be issued
by the City before the Landlord Work is performed; some portion of the Landlord
Work may have to be inspected by City inspectors before the Tenant Work begins. Siemers Supp. Decl., ¶6, Ex. A (City Building
Code §81.2.4).
Tenant
asserts that when it checked City records online in July 2023, all the permits
shown concerned the Tenant Work and not the Landlord Work. Supp. Decl., Ex. B.
Tenant
has an argument that the Landlord Work is not complete until permits relating
to that work are issued. Landlord has
yet to pull any permits for the Landlord Work and Tenant relies on that fact to
conclude that the Landlord Work is not complete. However, Landlord need only “substantially
complete” the Landlord Work within 30 days of the completion date of September
30, or within the ten-day cure period after the February 15, 2023 Notice of Termination.
Abruzzo Decl., ¶16, Ex. 4.
There
is a factual question as to which party was required to obtain permits, what
permits were required, and whether Landlord’s completion of the Landlord Work
within the ten-day cure deadline but without permits was substantial compliance. The court is not prepared to decide these
factual issues on this application; the matter must be decided at trial.
(2).
The Estoppel Certificate
The
Lease allows Landlord to require the Tenant to execute, acknowledge, and
deliver an Estoppel Certificate to either the Landlord or proposed mortgagee or
purchaser. Abruzzo Decl., Ex. 1. The Landlord may then rely on such a statement
or certificate. Abruzzo Decl., Ex. 1. If
the Tenant did not execute and deliver such an Estoppel Certificate, the
Landlord may do so in Tenant’s name and on Tenant’s behalf. Abruzzo Decl., Ex.
1.
On January 16, 2023, Tenant signed the Estoppel
Certificate. Lewis Decl., ¶3, Ex.
1. It stated that the Landlord may rely
upon the truth and accuracy of all statements therein. Lewis Decl., ¶3, Ex. 1. The Estoppel Certificate states that the
Lease is not in default, is valid, and is in full force and effect. Lewis Decl., ¶4, Ex. 1. The Lease has not been modified and represents
the entire agreement between Landlord and Tenant with respect to the Premises. Id.
Tenant had accepted possession of the Premises and is performing Tenant
Work as defined in the Lease. Id.
The Lease began on September 30,
2022. Id.
Tenant agreed that, to the best of
its knowledge, no event has occurred, and no condition exists, which would
constitute Landlord’s default under the Lease.
Id. Tenant affirmed that
it has no defenses or offsets against Landlord’s enforcement of the Lease. Id. Landlord had made all required contributions
for tenant improvements except for Landlord Work as described in Article 36 and
Tenant Improvement Allowance as described in Article 35. Id. The Estoppel Certificate may be relied upon
and shall inure to the benefit of Lender and Landlord knowing it will reply
upon the truth and accuracy if it. Id.
Article
36 of the Lease allows Tenant to terminate if Landlord fails to both
substantially complete Landlord Work and deliver possession of the Premises
within 30 days of the deadline. Abruzzo
Decl., ¶8, Ex. 1. Tenant does not
dispute that the Estoppel Certificate shows that Tenant took possession of the
Premises. Lewis Decl., ¶4, Ex. 1.
Tenant
asserts that an Estoppel Certificate is not binding as to disputes between the
Tenant and Landlord. Reply at 8. The Estoppel Certificate states that both
Landlord and its lender can rely on the representations therein. Lewis Decl., ¶4, Ex. 1. There is no evidence that the Landlord took
action, or failed to take action, in reliance on the Estoppel Certificate. Reply at 8.
The
short answer is that Landlord is relying on the Estoppel Certificate now. Moreover, Article 26 of the Lease has no
limit; it states that the Landlord may rely on any such certificate. Abruzzo Decl., ¶8, Ex. 1, p. 28.
Tenant
asserts that the Estoppel Certificate proves Landlord’s default because it states
that Landlord had made all required contributions except for the Landlord
Work and the Tenant Improvement Allowance. Mot. at 13; Reply at 7.
The Estoppel
Certificate states that the Landlord Work is an exception to Landlord’s
contributions to tenant improvements, but the Lease requires only that the
Landlord Work be substantially complete, a less rigorous standard. The Estoppel Certificate does not necessarily
support Tenant on this point. Moreover, Tenant
ignores the Estoppel Certificate’s other warranties that, to the best of its
knowledge, no event or condition exists which would constitute Landlord’s
default under the Lease and that Tenant has no defenses or offsets against
Landlord’s enforcement of the Lease.
Landlord
further argues that the Estoppel Certificate demonstrates Landlord’s compliance
because Tenant admitted that the Tenant Work had begun. Opp. at 12; Lewis Decl., ¶4, Ex. 1. Tenant understood that it could begin the Tenant
Work only after it has taken possession of the Premises, and therefore it
conceded that Landlord had substantially completed the Landlord Work. Opp. at 15.
Tenant
argues that the claim that it began Tenant Work is false. Reply at 7.
Shamma submitted proposals for the work and acted on them before Tenant
ever agreed to the proposal. Reply at 7-8;
Siemers Supp. Decl., ¶¶ 38-40. To the
extent that Tenant has represented otherwise in the Estoppel Certificate, this
is irrelevant. Nevertheless, the Lease’s
provision on the Tenant Work is not as strong as Landlord argues. Tenant was required to commence the Tenant
Work promptly following Landlord’s delivery of possession of the Premises. Opp. at 12; Abruzzo Decl., ¶8, Ex. 1. That duty does not preclude Tenant from
starting preliminary steps on the Tenant Work before delivery of possession.
Overall,
the Estoppel Certificate is strong evidence favoring Landlord’s position. Tenant tries to minimize the blow by arguing
that under the Lease either Tenant could sign, or Landlord could sign on Tenant’s
behalf. Abruzzo Decl., ¶12. This apparently is a suggestion that Tenant
had no choice and is frivolous. Nothing
in the Lease forced Tenant to sign a false Estoppel Certificate.
(3).
Conclusion
Tenant
has failed to demonstrate a probability of success because Landlord completed
the Landlord Work within the required ten-day cure period, with the exception
of any duty to obtain permits, and the Estoppel Certificate is strong evidence
that Tenant believed Landlord had substantially completed the Landlord Work.
b.
Offset
The
amount of an attachment must be reduced by the amount claimed in a
cross-complaint or affirmative defense and shown would be subject to attachment
against the plaintiff. CCP
§483.015(b)(2). A defendant claiming
that the amount to be secured should be reduced because of a cross-claim or
affirmative defense must make a prima facie showing that the claim would result
in an attachment against the plaintiff.
Landlord
asserts that it did not fail to complete the Landlord Work and Tenant breached
the Lease by trying to terminate it.
Opp. at 16. Damages from this
breach total $5 million in unpaid future Rent under the Lease. Abruzzo Decl., ¶8, Ex. 1. These damages exceed the amount that Tenant
seeks to attach. Opp. at 16. This is not an issue of offset but rather
defense.
4.
Attachment Sought for a Proper Purpose¿
Attachment
must not be sought for a purpose other than the recovery on the claim upon
which attachment is based.¿ CCP §484.090(a)(3).
Tenant seeks attachment for a proper purpose.
E. Conclusion
The
application for a right to attach order is denied.
[1]
Although the parties at times refer to its President Bill Shamma (Shamma Decl.,
¶1), his actions are always in his capacity as an officer of the construction
company.
[2]
Although Tenant purports to attach the Estoppel Certificate, the exhibit is
another copy of the Addendum. Abruzzo
Decl., ¶12, Ex. 3.
[3] Tenant
attached search results from the City’s website on July 12, 2023 to confirm
that there were no permits associated with the Premises in the past ten
years. Salim Decl., ¶5, Ex. 1. It concedes in reply that this search used
the wrong address. Reply at 6, n.4.
[5] On May 16, 2023, Tenant’s counsel requested that Olofinboba
sign a declaration. Olofinboba Decl., ¶19,
Ex. P. Olofinboba declined because the
declaration was inaccurate. Olofinboba
Decl., ¶19, Ex. P. He explained that
AYK’s contract for electrical work was with Shamma, not Tenant, and that
Siemers had agreed to this arrangement. Olofinboba
Decl., ¶¶ 19-20, Ex. P. AYK always
invoiced Shamma and received payment through it, not Tenant. Olofinboba Decl., ¶¶ 19-20, Ex. P.
[6] In
reply, Tenant seeks judicial notice of the City’s Building Code (Ex. A) and its
permit records for the Property (Ex. B).
The requests are granted. Evid.
Code §452(c).