Judge: James C. Chalfant, Case: 24STCP00451, Date: 2024-08-27 Tentative Ruling
Case Number: 24STCP00451 Hearing Date: August 27, 2024 Dept: 85
Fox Hills Canterbury Co. v.
City of Culver City, 24STCP00451
Tentative decision on demurrers: sustained without leave to amend
Respondents City
of Culver City (“City”) and Intervenor Meadow Forward Action Committee (“MFAC”)
separately demur to the First Amended Petition (“FAP”) of Petitioner/Plaintiff Fox
Hills Canterbury Co. (“Fox Hills”).
The court has
read and considered the moving papers, oppositions, and replies, and renders
the following tentative decision.
A. Statement
of the Case
1. The
First Amended Petition
Petitioner Fox
Hills filed this action against Respondent City on February 13, 2024. The operative pleading is the FAP, filed on
May 24, 2024, alleging causes of action for mandamus, declaratory relief, and
inverse condemnation. The FAP alleges in
pertinent part as follows.
Petitioner owns
real property in the City located at 6300 through 6430 Green Valley Circle and
6100 through 6220 Canterbury Drive (the “Property”). The Property is improved
with 24 separate multi-family apartment buildings, each containing a number of separate
apartment units. The Property and its buildings are commonly referred to as the
Meadows Apartments and are divided into areas commonly known as Meadows South
and Meadows North. FAP, ¶11, Ex. A.
Petitioner constructed
the Meadows Apartments in 1974. Due to
the age of the buildings and infrastructure, plumbing leaks and sewer line
issues have occurred within the concrete slab foundations, requiring extensive
demolition of slab foundations and repairs of plumbing lines, in many cases
requiring the relocation of tenants for the work to be completed. The costs of the repairs have increased
dramatically over the years, averaging $250,000 for each of 2022 and 2023. In light of the significant expense,
Petitioner undertook a project to replace old pipes and infrastructure, both
inside and outside the Meadows South and North buildings, remove significant
portions of drywall, and replace fixtures, cabinets, floors, countertops, and
appliances in each unit (the “Project”). FAP, ¶12.
To implement the
Project, Petitioner paid for, and obtained, in excess of 100 building permits
(the “Permits”) from the City. FAP, ¶13. In reliance on the Permits, Petitioner
performed exterior site work which involved substantial trenching and
installation of new underground pipes and conduit, completing this work by the
August 2019. Completion of the exterior site
work was necessary for the next phase, which involved the utility replacement
and related work inside the buildings. FAP, ¶14.
Petitioner also sought
and obtained Permits for (a) the removal and replacement of plumbing and sewer
lines inside the apartment buildings, issued on September 27, 2017, (b) replacement
of building mechanical systems, issued on September 26, 2017, (c) replacement
and updating of building select electrical systems, issued on October 26, 2016,
and (c) repair and replacement of roofing, issued on April 9, 2019. FAP, ¶15, Ex. B.
In reliance on
the Permits, Petitioner completely renovated each apartment unit in the 117
units of Meadows South, removing and replacing a substantial amount of drywall,
cabinetry and flooring to access the interior plumbing, sewer, and select
electrical lines, replacing substantial interior plumbing and select electrical
lines, and installation of new fixtures, cabinets, floors, countertops and
appliances in each unit. The interior work at the Meadows South required the
units to be vacated. FAP, ¶16.
To date,
Petitioner has paid over $19,700,000 for the construction, Permits, and
inspections. FAP, ¶17. All interior and exterior work on 117 units
in Meadows South was completed in 2021 and the City never attempted to enforce
the relocation provisions in the Tenant Protection Ordinance (“TPO”, sometimes
“Ordinance”) adopted on September 29, 2020.
Nor did the City contend that the Ordinance applied to the work and
tenant relocation occurring at Meadows South. FAP, ¶17.
The exterior site
work has been completed on Meadows North. The remaining work to be completed on
the Meadows North buildings under the Permits will require substantial removal
of the ground floor concrete slabs to reach the water pipes, sewer lines, and
select conduit, removal and demolition of significant portions of drywall,
fixtures, cabinets, flooring and appliances to access and replace interior
piping and select wiring. Such work will
require the tenants in Meadows North buildings to vacate their units. As with Meadows South, all tenants in Meadows
North will be under month-to-month leases when the renovation starts. FAP, ¶18.
On or about
August 12, 2019, the City Council adopted Ordinance No. 2019-011 (“Interim Rent
Control Ordinance”), an urgency ordinance establishing interim rent control
measures for 12 months. The Interim Rent Control Ordinance did not contain any
relocation right or tenant’s right-to-return based upon construction in or
around the rental units. The Interim Rent Control Ordinance was extended,
without amendment, through October 31, 2020. FAP, ¶19.
On or about
September 29, 2020, the City Council adopted the TPO, which added a new
Subchapter 15.09.300 to the Culver City Municipal Code (“CCMC”) The TPO
purports to preclude, inter alia, landlords from relocating tenants from
their units unless the tenants are permitted to return to their units at the
same rent, even though the units have been substantially upgraded. The TPO does not have an exemption for
projects which have vested rights, such as Petitioner’s Project. FAP, ¶20, Ex. D.
Upon the onset
of the Covid-19 pandemic in approximately March of 2020, Petitioner continued
work on the vacant interior units of Meadows South along with other exterior
improvements on Meadows North. FAP, ¶21.
Beginning in the
Fall 2021, as the COVID-19 pandemic became somewhat manageable, Petitioner reached
out to the Mayor, and members of the City Council, and City staff in an effort
to enable the Project to proceed on Meadows North. These attempts continued through 2022 and
2023. On January 25, 2023, the City advised Petitioner that the City Council
voted to have the Petitioner’s concern placed on the agenda for a future City Council
meeting. Notwithstanding, the City did not notice or conduct a hearing on
Petitioner request to work on Meadows North without compliance with the TPO. FAP, ¶22.
On or about
September 6, 2023, Petitioner sought an exemption from the TPO based upon the
vested rights obtained through the issuance of the Permits, work completed, and
the $19.7 million spent in reliance thereon. The City declined to formally respond to
Petitioner’s request for an exemption from the Ordinance. FAP, ¶23.
At a City
Council meeting on December 11, 2023, some tenants of Meadows North spoke
against any exemption to the Ordinance for the additional work required for
Meadows North. FAP, ¶24.
For its mandamus
claim, Petitioner alleges that the City has failed and refused to recognize its
vested right to complete the work authorized by the Permits without the
imposition of new regulations imposed by the TPO. FAP, ¶25.
Petitioner has a clear, present, and legal right to complete the work
authorized by the Permits based upon vested rights, and it is in the best
interest of the community to provide quality housing for the existing and
future residents of the City. The City’s invocation of the Ordinance renders
the Meadows South portion of the financially infeasible. FAP, ¶26.
The City has the duty and ability to authorize that the work be
completed without invocation of the TPO, and it has failed and refused to
perform that duty. FAP, ¶27.
For its
declaratory relief claim, Petitioner alleges that an actual controversy has
arisen and now exists between it and the City relative to their respective
rights and duties. Petitioner contends
that the TPO is invalid and unenforceable against it in that the City is
refusing to exempt the permitted work on the Property from the TPO even though
Petitioner has vested rights to complete the work. As applied, the Ordinance constitutes a
taking of private property under Article I, Section 19 of the California
Constitution and the Fifth Amendment to the U.S. Constitution, applied to the
states through the Fourteenth Amendment. Petitioner is informed and believes, and based
upon such information and belief alleges, that the City disputes these
contentions. FAP, ¶30. Petitioner desires a declaration as to the
inapplicability of the TPO to the Property without subjecting itself to civil
and criminal liability by violating the Ordinance. FAP, ¶31.
For its inverse
condemnation claim, Petitioner alleges that the City has the power of eminent
domain to take private property for public use. FAP, ¶33.
By virtue of Petitioner’s application for, the City’s issuance of, and Petitioner’s
payment for, the Permits, and Petitioner’s incurrence of over $19,700,000 in
reliance, Petitioner has vested rights to complete its work without the City’s
invocation of the TPO. FAP, ¶34.
The purported
administrative process for the adjustment of rent in CCMC section 15.09.225
cannot apply to most, if not all, of the expenses for the Project because the
so-called passthrough for rent adjustments is limited to capital improvement additions
but not replacements. Moreover, the pass-through
exemption in CCMC section 15.09.225 may only be implemented with the tenant’s
consent. In addition, while CCMC section
15.09.220 provides a separate rent adjustment process, it contains a rebuttable
presumption that the landlord is obtaining a reasonable return based upon net operating
income, which would necessarily exclude capital improvements, thus rendering
the rent adjustment process ineffective and futile based on the costs of the
Project. FAP, ¶35.
Petitioner
contends that its vested rights extend to the completion of the work, and these
vested rights constitute distinct, investment backed expectations protected
under Article I, Section 19 of the California Constitution and the Fifth
Amendment of the U.S. Constitution. FAP,
¶36. If the City is entitled to enforce
the Ordinance, the result would constitute a taking of private property without
payment of just compensation. Further,
to the extent the City’s refusal to recognize Petitioner vested rights has
caused delay and increased expenses, Petitioner is entitled to compensation for
the temporary taking of property. FAP,
¶37.
Petitioner prays
for (1) a writ of mandate commanding the City to exempt Petitioner from the TPO
so that the work pursuant to the Permits may be completed; (2) declaratory
relief declaring the respective rights and duties of the parties under the Ordinance;
and (3) just compensation for the temporary taking, in the form of increased
construction costs, lost rent and related expenses, and potentially permanent
taking of private property in violation of Article I, Section 14 of the
California Constitution and the Fifth Amendment of the U.S. Constitution; (4)
attorney’s fees pursuant to CCP section 1036; (5) costs of suit; and (6) such
other and further relief as the court may deem just and proper. FAP at 11.
2. Course
of Proceedings
On April 29,
2024, the City filed a demurrer to the Petition.
On May 14, 2024,
the court granted Intervenor MFAC’s ex parte application to intervene. Intervenor demurred and filed an Answer-in-Intervention
on the same date.
On May 24, 2024,
Petitioner filed the FAP, and the demurrers were taken off calendar.
The parties
subsequently stipulated to a briefing schedule and the instant hearing date for
both demurrers to the FAC.
B. Applicable Law
Demurrers
are permitted in administrative mandate proceedings. CCP §§1108,
1109. A demurrer tests the legal sufficiency of the pleading alone and
will be sustained where the pleading is defective on its face.
Where
pleadings are defective, a party may raise the defect by way of a demurrer or
motion to strike or by motion for judgment on the pleadings. CCP
§430.30(a); Coyne v. Krempels, (1950) 36 Cal.2d 257. The party
against whom a complaint or cross-complaint has been filed may object by
demurrer or answer to the pleading. CCP §430.10. A demurrer is
timely filed within the 30-day period after service of the complaint. CCP
§430.40; Skrbina v. Fleming Companies, (1996) 45 Cal.App.4th 1353,
1364.
A demurrer
may be asserted on any one or more of the following grounds: (a) The court has
no jurisdiction of the subject of the cause of action alleged in the pleading;
(b) The person who filed the pleading does not have legal capacity to sue; (c)
There is another action pending between the same parties on the same cause of
action; (d) There is a defect or misjoinder of parties; (e) The pleading does
not state facts sufficient to constitute a cause of action; (f) The pleading is
uncertain; (g) In an action founded on a contract, it cannot be ascertained
from the pleading whether the contract is written, is oral, or is implied by
conduct; (h) No certificate was filed as required by CCP sections 411.35 or
411.36. CCP §430.10.
A demurrer tests the
sufficiency of a pleading, and the grounds for a demurrer must appear on the
face of the pleading or from judicially noticeable matters. CCP
§430.30(a); Blank v. Kirwan, (1985) 39 Cal.3d 311, 318. The face
of the pleading includes attachments and incorporations by reference (Frantz
v. Blackwell, (1987) 189 Cal.App.3d 91, 94), but it does not include
inadmissible hearsay. Day v. Sharp, (1975) 50 Cal.App.3d 904,
914.
The sole
issue on demurrer for failure to state a cause of action is whether the facts
pleaded, if true, would entitle the plaintiff to relief. Garcetti v.
Superior Court, (1996) 49 Cal.App.4th 1533, 1547; Limandri v. Judkins,
(1997) 52 Cal.App.4th 326, 339. The question of plaintiff’s ability to
prove the allegations of the complaint or the possible difficulty in making
such proof does not concern the reviewing court. Quelimane Co. v.
Stewart Title Guaranty Co., (1998) 19 Cal.4th 26, 47.
The ultimate facts alleged
in the complaint must be deemed true, as well as all facts that may be implied
or inferred from those expressly alleged. Marshall v. Gibson, Dunn
& Crutcher, (1995) 37 Cal.App.4th 1397, 1403. This rule does not
apply to allegations expressing mere conclusions of law, or allegations
contradicted by the exhibits to the complaint or by matters of which judicial
notice may be taken. Vance v. Villa Park Mobilehome
Estates, (“Vance”) (1995) 36 Cal.App.4th 698, 709.
For all
demurrers filed after January 1, 2016, the demurring party must meet and confer
in person or by telephone with the party who filed the pleading for the purpose
of determining whether an agreement can be reached that would resolve the
objections to be raised in the demurrer. CCP §430.31(a). As part of
the meet and confer process, the demurring party must identify all of the
specific causes of action that it believes are subject to demurrer and provide
legal support for the claimed deficiencies. CCP §430.31(a)(1). The
party who filed the pleading must in turn provide legal support for its
position that the pleading is legally sufficient or, in the alternative, how
the complaint, cross-complaint, or answer could be amended to cure any legal insufficiency.
Id. The demurring party is responsible for filing and serving a
declaration that the meet and confer requirement has been met. CCP
§430.31(a)(3).
“[A] demurrer based on a statute of limitations will
not lie where the action may be, but is not necessarily, barred. [Citation.] In
order for the bar of the statute of limitations to be raised by demurrer, the
defect must clearly and affirmatively appear on the face of the complaint; it
is not enough that the complaint shows that the action may be barred.” State
ex rel. Metz v. CCC Information Services, Inc., (2007) 149 Cal.App.4th 402,
413.
If a demurrer is
sustained, the court may grant leave to amend the pleading upon any terms as
may be just and shall fix the time within which the amendment or amended
pleading shall be filed. CCP §472a(c).
However, in response to a demurrer and prior to the case being at issue,
a complaint or cross-complaint shall not be amended more than three times,
absent an offer to the trial court as to such additional facts to be pleaded
that there is a reasonable possibility the defect can be cured to state a cause
of action. CCP §430.41(e)(1).
D. Analysis[1]
The City and Intervenor separately demur to
the FAP’s claims for mandamus, declaratory relief, and inverse condemnation. The parties have meet and conferred in
compliance with CCP section 430.31(a)(3). Sharma Decl., ¶¶ 3-4; Soloff Decl., ¶2.
1. The Traditional
Mandamus Claim
a. The City Has a Ministerial Duty to Respect
Vested Rights
A traditional
writ of mandate is the method of compelling the performance of a legal,
ministerial duty required by statute. See
Rodriguez v. Solis, (1991) 1 Cal.App.4th 495, 501-02. Generally, mandamus will lie when (1) there
is no plain, speedy, and adequate alternative remedy, (2) the respondent has a
duty to perform, and (3) the petitioner has a clear and beneficial right to
performance.” Pomona Police Officers’
Assn. v. City of Pomona, (1997) 58 Cal.App.4th 578, 583-84 (internal
citations omitted). Whether a statute
imposes a ministerial duty for which mandamus is available, or a mere
obligation to perform a discretionary function, is a question of statutory
interpretation. AIDS Healthcare
Foundation v. Los Angeles County Dept. of Public Health, (2011) 197
Cal.App.4th 693, 701.
In the absence
of a ministerial duty, traditional mandamus relief is unavailable unless the
petitioner can demonstrate an abuse of that discretion. An agency decision is an abuse of discretion
only if it is “arbitrary, capricious, entirely lacking in evidentiary support,
unlawful, or procedurally unfair.” Kahn
v. Los Angeles City Employees’ Retirement System, (2010) 187 Cal.App.4th
98, 106. In applying this deferential
test, a court “must ensure that an agency has adequately considered all
relevant factors, and has demonstrated a rational connection between those
factors, the choice made, and the purposes of the enabling statute.” Western States Petroleum Assn v. Superior
Court, (1995) 9 Cal.4th 559, 577.
Mandamus will not lie to compel the exercise of a public agency’s
discretion in a particular manner. American
Federation of State, County and Municipal Employees v. Metropolitan Water
District of Southern California, (2005) 126 Cal.App.4th 247, 261. It is available to compel an agency to
exercise discretion where it has not done so (Los Angeles County Employees
Assn. v. County of Los Angeles, (1973) 33 Cal.App.3d 1, 8), and to correct
an abuse of discretion actually exercised.
Manjares v. Newton, (1966) 64 Cal.2d 365, 370-71. In making this determination, the court may
not substitute its judgment for that of the agency, whose decision must be
upheld if reasonable minds may disagree as to its wisdom. Id. at 371. A writ will lie where the agency’s discretion
can be exercised only in one way. Hurtado
v. Superior Court, (1974) 11 Cal.3d 574, 579.
Petitioner
alleges that “[t]he City has the present legal duty and ability to authorize
that the work be completed without invocation of the Ordinance, but the City
has failed and refused to perform that duty.” FAP, ¶ 27.
The City argues
that the TPO is devoid of any provision where a property owner could apply for
an exemption from its provisions or requirements. The TPO explicitly applies to
tenants where “at least one tenant has continuously and lawfully occupied the
rental unit for 12 months or more.” RJN Ex. G (TPO §15.09.310(A)(2). Petitioner implicitly concedes that the
Meadows North tenants are entitled to the TPO’s tenant protections. Petitioner does not identify any ministerial
duty, nor a corresponding right to the City’s performance of a ministerial act. The City concludes that Petitioner’s mandamus
claim seeks to compel the City to exercise its discretion to exempt Petitioner
from the TPO where such an exemption determination is not authorized. City Dem. at 15-16.
Petitioner
responds that the City has a ministerial duty to comply with constitutional
requirements. Every constitutional provision is self-executing, and cities are
prohibited from taking official actions that contravene constitutional
provisions. See e.g., Leger v. Stockton Unified School District,
(1988) 202 Cal.App.3d 1448, 1454. Where the City enforces a subsequently
adopted regulation in violation of a property owner’s vested rights, the City’s
actions are arbitrary and capricious, and a writ of mandate is merited. Opp. to City Dem. at 15.
This argument
mixes traditional mandamus based on a ministerial duty with traditional mandamus
based on a discretionary duty, which is governed by an arbitrary and capricious
standard. However, it is true that a
constitutional duty serves to justify mandamus just as well as a statutory duty,
and apparently Petitioner relies on principles of due process to assert its vested
right to an exemption. The duty to
comply with vested rights is ministerial.
Petitioner adds
that the City cannot avoid an exemption simply because the TPO is devoid of any
provision where a property owner could apply for one. Such an interpretation would allow a city to
drafts its ordinances in such a way as to bulletproof them -- even if they abrogate
constitutional rights — by not providing any administrative remedy for
exemption. Opp. to City Dem. at 15-16. Plainly,
the City cannot avoid an exemption to the TPO if it is constitutionally
compelled.
b. The Statute of Limitations Has Not
Passed for the Mandamus Claim, But It Is Not Ripe
The City argues
that Petitioner’s mandamus claim is a time-barred facial attack on the TPO. City Dem. at 16.
Code of Civil
Procedure section 338 imposes a three-year statute of limitations for “[a]n
action upon a liability created by statute, other than a penalty or
forfeiture.” A cause of action accrues and the applicable limitations period
begins to run when the plaintiff knows of the alleged injury, or at least has
reason to suspect a factual basis for the elements of the asserted cause of
action. Lyles v. State of California,
(2007) 153 Cal.App.4th 281, 286-87.
To determine the
applicable statute of limitations, courts look beyond a petitioner’s
characterization of its claim and “determine what specific governmental act” is
challenged. County of Sonoma v. Superior
Court, (2010) 190 Cal.App.4th 1312, 1324 (“The true nature of [the] claims
may be found by looking to the allegations of the pleadings and to the relief
requested.”). Because the City has not
acted to enforce the TPO against Petitioner, the only government act that
Petitioner can challenge related to the TPO is the City’s adoption of the Ordinance
on September 29, 2020. As such, the
gravamen of Petitioner’s claim is that the adoption of the TPO itself caused
its claimed injury, rather than any enforcement action. City Reply at 3-4.
The FAP asserts
that the Permits were obtained in 2016 through 2019 (FAP, ¶15, Ex.B) and that
the TPO was adopted on September 29, 2020 (FAP, ¶17). The FAP alleges: “The Ordinance arguably
purports to preclude, inter alia, landlords from relocating tenants from their
prior units unless the tenants are permitted to return to their units at the
same rent, even though the units have been substantially improved and upgraded
at tremendous expense to the landlord.”
FAP, ¶20. City Dem. at 16.
The City notes
that Petitioner provided comment at the public meeting at which the TPO was
adopted, and those comments referenced the unfairness of instituting tenant
protections as renovations were occurring on the Property. RJN, Ex. H. The allegations in the FAP mirror the comments
Petitioner made at the September 2020 hearing, and amount to a disagreement
whether the TPO should exempt circumstances where property owners are in the
process of conducting renovations at the time of enactment. City Dem. at 16-17.
Petitioner could
have challenged the TPO upon adoption but instead waited for over three years to
initiate this lawsuit on February 13, 2024. The three-year statute of
limitations for challenging the TPO began to run as soon as the action could be
challenged. CCP §338; Urban Habitat
Program v. City of Pleasanton, (2008) 164 Cal.App.4th 1561, 1578. Petitioner was aware of the impact of the TPO
on its Property on the date it was enacted, and no circumstances have changed
since then. FAP, ¶17; RJN Ex. H. City Dem. at 17.
Petitioner is
not making a facial challenge. Petitioner’s
argument that it is exempt from the TPO because of its vested rights is an
as-applied challenge to the TPO. It
argues that the Ordinance is only invalid as to its Property because of its
vested rights; application of the Ordinance to other City property owners is
unaffected by this lawsuit. Moreover, a facial challenge can be made as part of
an as-applied challenge. Travis v.
County of Santa Cruz, (2004) 33 Cal.4th 757, 769.
The City then
argues that Petitioner’s as-applied challenge lacks merit because it has taken no
action to enforce the TPO against Petitioner. Petitioner attempted to obtain an exemption
to the TPO from the City in 2022 and 2023, but that is irrelevant because Petitioner
did not take any action to preserve potential claims such as entering into a
tolling agreement. Moreover, as Petitioner admits, the TPO does not include an
application process by which a property owner could obtain an exemption. FAP, ¶20. Any argument that the City purportedly delayed
in rendering a decision on an exemption fails where no such process exists. City Dem. at 17.
Petitioner responds
that the City fails to explain why its lack of enforcement matters. Even if the Property is determined to be
exempt because of Petitioner’s vested rights, the TPO will remain in effect
with respect to other property owners in the City who do not have vested
rights. A facial challenge would void the entire ordinance as to all property
owners in the City - a result Fox Hills has never asked for and does not
seek. Opp. to City Dem. at 16.
The court agrees
that Petitioner is making an as-applied challenge. The court also agrees that the statute of
limitations has not passed for an as-applied challenge, including one that
makes a facial challenge to the TPO.
However, the as-applied mandamus claim is not ripe because the City has made
no discretionary decision to enforce the TPO against Petitioner.
This leaves only
the facial component of an as-applied challenge.[2] This too is not ripe. A timely as-applied challenge where the
petitioner’s injury does not arise solely from the law’s enactment may include
a facial attack on the measure. Travis v. County of Santa Cruz, supra,
33 Cal.4th at 769. The facial challenge is
a component of an action which challenges the enforcement of the measure and
not just its enactment. As such,
the facial challenge to the text of a measure may be made only insofar as it
affects enforcement of the measure against the petitioner. Id. at 767. The ripeness requirement for such claims
is that the property owner must obtain “a final, definitive position regarding
how [the city] will apply the regulations at issue to the particular land in
question.” Williamson County Reginal
Planning Commission v. Hamilton Bank, (1985) 473 U.S. 172, 191. Petitioner
has not obtained a final, definitive position from the City how it will apply
the TPO to Petitioner. Therefore, the
facial component of Petitioner’s as-applied claim is not ripe.
In sum, the statute of limitations has not
passed for Petitioner’s as-applied mandamus claim, but it also is not ripe.
2. Petitioner Has No Vested Right to Be
Exempt from the TPO
Assuming, arguendo, that Petitioner’s mandamus
claim is ripe, the issue becomes whether it has a vested right to be exempt
from the TPO.
“It has long
been the rule in this state and in other jurisdictions that if a property owner
has performed substantial work and incurred liabilities in good faith reliance
upon a permit issued by the government, he acquires a vested right to complete
construction in accordance with the terms of the permit.” Avco Community
Developers Inc. v. South Coast Regional Comm., (“Avco”) (1976) 17
Cal.3d 785, 791. To lock in vested
rights, the relevant point in the land use process is most often construed to
be the issuance of a building permit. City of West Hollywood v. Beverly
Towers, (1991) 52 Cal.3d 1184, 1191-92.
“[T]he vested
rights theory is predicated upon estoppel of the governing body.” Anderson v. City Council of City of
Pleasant Hill, (1964) 229 Cal.App.2d 79, 89. “This is a principle of equitable estoppel
which may be applied against the government where justice and fairness require it.”
Santa Monica Pines, Ltd. v. Rent
Control Bd., (1984) 35 Cal.3d 858, 866–67, disapproved on other grounds,
City of West Hollywood v. Beverly Towers, supra, 52 Cal. 3d at
1192. “An equitable estoppel requiring
the government to exempt a land use from a subsequently imposed regulation must
include (1) a promise such as that implied by a building permit that the
proposed use will not be prohibited by a class of restrictions that includes
the regulation in question, and (2) reasonable reliance on the promise by the
promisee to the promisee’s detriment.” Id. at 867. No vested right exists “unless and until both
of those elements … are established.” Ibid.
The City issued
the Permits to perform its work on the Project.
Petitioner performed substantial work in good faith reliance on the
permits. It expended $19.7 million and
completed 117 units in Meadows South and the exterior infrastructure for
Meadows North. The question is what vested
rights are conferred by this good faith effort?
The City and
Intervenor argue that Petitioner cannot show that the Permits implied a promise
of no further tenant protections.
Nothing in the Permits contains suggests a promise that Petitioner will
be free of future tenant protections enacted by the City. City Dem. at 18; Int. Dem. at l2.
Petitioner
responds that this argument ignores the word “implied” in the first estoppel element
that there must be a promise implied by the building permit that the proposed
use will not be prohibited by a class of restrictions that includes the
regulation in question. See Santa
Monica Pines, Ltd. v. Rent Control Bd., supra, 35 Cal.3d at
867. The whole point of vested rights is
that building permits are an implied promise to complete the project based on
the regulations at the time the permit is issued. There does not have to be an explicit promise
in the Permits that Petitioner will be free of future tenant protections
enacted by the City. Opp. to City Dem.
at 11.
Intervenor argues
that the Permits imply no such promise. The State’s Housing Law requires local
building departments to enforce the State Building Standards Code. See Health & Safety Code §§ 17910, 17960. The purpose of the State’s building standards
is to “regulate[], require[], or forbid[] the method of use, properties,
performance, or types of materials used in the construction, alteration,
improvement, repair, or rehabilitation of a building.” Health & Safety Code
§ 18909(a). To carry out this purpose,
the State Building Standards Code imposes a building permit requirement. See
Health & Safety Code §18902; California Building Code §105.1. Building permits therefore have nothing to do
with landlord-tenant law. The Permits therefore do not imply a promise that
Petitioner would be exempt from changes in landlord-tenant law adopted after
their issuance. Nothing in the Permits’ description of the renovations implies
any such promise. Int. Dem. at 13.
The City adds that Petitioner cannot establish
reasonable reliance. There are no
allegations in the FAP that Petitioner reasonably relied on the Permits to
continue to operate their apartment complex free of any subsequently enacted
police power regulations such as rent or eviction controls. “Rent control, like the imposition of a new
tax, is simply one of the usual hazards of the business enterprise.” Interstate
Marina Dev. Co. v. Cnty. of Los Angeles, (1984) 155 Cal.App.3d 435, 447. Petitioner alleges that it had commenced “a
comprehensive infrastructure and improvement renovation program,” by taking out
numerous, specific building permits for the purpose of conducting specific
improvements. FAP, ¶¶ 3, 13, 14, 15. That is not reasonable reliance. City Dem. at 18.[3]
Petitioner
responds that the City’s argument about lack of reliance allegations in the FAP
is the point of alleging vested rights. Once
the building permit is issued, completion of the project is required free of subsequently
enacted regulations that would interfere with completion of the project. There was no TPO when the Permits were issued.
There is no requirement that Petitioner allege
that it relied on the Permits to be free of tenant occupancy rules that did not
exist when the Permits were issued. That is part and parcel of the vested right
allegation. Opp. to City Dem. at 12.
The court
prefers to view the issue as the proper scope of Petitioner’s rights with
respect to the Permits. The scope of
vested rights is merely to perform the task authorized by the permit. That scope does not give Petitioner the right
not to comply with the TPO. Vested
rights are acquired when a property owner has performed substantial work and
incurred substantial liability in good faith reliance on a permit to complete
construction in accordance with the terms of the permit. Avco, supra, 17 Cal.3d 785 at
791. The rights that vest through
reliance on a government permit are no greater than those specifically granted
by the permit itself. Id. at 793;
Spindler Realty Corp. v. Monning, (“Spindler”) (1966) 243
Cal.App.2d 255, 264-65.
In Russ
Building Partnership v. City and County of San Francisco, (1988) 44 Cal.3d
839, 845-46, the California Supreme Court noted the longstanding rule that a
developer who performs substantial work and incurs substantial liabilities in
good faith reliance on a permit acquires a vested right to finish construction
under the terms of the permit and the government may not change zoning laws to
prohibit that construction. The vested
rights doctrine protects the developer’s right to construct and also to use the
premises as authorized by the permit. Id.
at 846 (developer had vested right to complete construction and occupy the
buildings under the permit conditions but had no vested right to avoid the
assessment authorized by subsequent ordinance because permits contemplated such
assessment).
In Spindler,
the court concluded that grading permits obtained prior to issuance of a
building permit did not result in vested rights accruing to the property owner
to complete construction in accordance with police power regulations (zoning
law) in effect at the time the grading permit was issued. Id. at 264. While the property owner had completed
substantial work in reliance on the grading permit, the grading permit only
amounted to a vested right to complete grading, not to build structures
permitted prior to the change in zoning. Id. at 269. The court noted that work conducted pursuant
to the grading permit amounted to a calculated risk. Id. at 265.
Likewise, in Avco,
the property owner sought and obtained a grading permit and other approvals
from the City to prepare its building, but the permits did not refer to the
buildings that would be constructed there. 17 Cal.3d at 793. The owner completed significant grading work
on the parcel, but the court concluded that there was no vested right to
complete construction without regard to regulations adopted after issuance of
the grading permit. Id. at 798.
The only rights
granted to Petitioner by the Permits are the right to do specified physical
renovation work at the Meadows North.
FAP, ¶¶ 13, 15, Ex. B. Petitioner
does not allege, and could not amend to allege, that the Permits address
Petitioner’s obligations to its tenants. The FAP does not allege that the TPO prohibits
Petitioner’s completion of the specified physical renovation work described in
the Permits. Nor does it allege that the TPO imposes a new condition that
Petitioner must satisfy before it can obtain City permission to perform the
specified renovation work and then, upon completion, obtain a certificate of
occupancy. Int. Dem. at 12.
Intervenor
points out that, unlike the building code or the zoning code, the TPO does not
regulate relations between Petitioner and the government. Rather, the TPO
creates certain obligations by Petitioner to its tenants residing in Meadows
North when renovation work requires them to vacate their apartments. Additionally, the TPO-created tenant
right-to-return only arises after the physical renovation work specified in the
building permits is completed and a certificate of occupancy is issued. It does not prevent Petitioner’s completion of
the renovation work authorized by the Permits.
Int. Dem. at 12.
The City also
relies (City Reply at 5) on Briarwood Properties, Ltd. v. City of Los
Angeles, (1985) 171 Cal.App.3d 1020, 1024-27, where the court considered
the issue of whether a city’s adoption of a relocation assistance ordinance
applied to a particular property that had already secured approval of a
tentative map to convert the property to condominiums. The property owner
contended that the relocation assistance requirements were not applicable to it
because: (1) the relocation assistance requirements were an impermissible
additional condition to its tentative map; and (2) it had vested rights to
preclude the application of the law. Id. at 1029-30.
The court
rejected these arguments. It noted that
the subsequently enacted law was not a new condition and did not effectuate a
“restriction on the right to subdivide at all.” Id. at 1029. The court also noted that the rights that
vest are only those rights specifically granted by the permit itself. Id. at 1030. Thus, vested rights “related only to [the
property owner’s] authority to convert the apartment building as provided in
the tentative map.” Ibid. They did not confer “the right to be free of
any subsequently adopted regulation.” Ibid.
The Permits were
issued for the limited purpose of conducting specific plumbing, mechanical, and
electrical work. Petitioner’s argument
that it has a vested right to continue with its renovation plans free of
subsequently enacted regulations due to its investments in the Property is
similar to the property owner’s failed argument in Spindler. The Permits do not promise Petitioner the
right to operate its apartment complex without complying with tenant
protections.
Petitioner
argues that the separation of the TPO from the Project for which the Permits
were issued ignores the reality that the application of financially onerous
requirements in the guise of tenant protection fundamentally changes the
economics of the Project such that Petitioner would not have chosen this
investment path had it known that it would not be able to charge more for a
renovated unit. The TPO essentially operates as an after-the-fact condition
imposed by government regulation on the Project. Petitioner may not complete the work
authorized by the Permits unless it complies with the TPO’s condition that it
must inform tenants it relocates that it will allow them to reoccupy their
units after renovation at the same rent as before. As applied to Petitioner, the TPO is not some
unrelated police power regulation; it is a direct interference with Petitioner’s
ability to complete its Project under the laws in existence when the Permits
were issued. Opp. to City Dem. at 7, 11.
Not so. Petitioner can complete the improvements
without notifying tenants as required by the TPO.[4] As the City replies (City Reply at 4-5), the
TPO has no direct impact on the cost of the renovations; it merely imposes a
financial obligation for Petitioner to assist with relocation of tenants who
may be displaced by the work, and to allow them to return to their apartment
units when it is completed. Nothing
about the TPO interferes in any way with completion of the Project or its cost,
and no authority supports Petitioner’s theory that the vested rights doctrine
shields it from regulations that would indirectly render permitted work more difficult
to obtain an investment return.
Petitioner
distinguishes Avco and Spindler as cases concerning the vested
rights in a grading permit, which only allow the property owner to complete the
grading and not the entire project. The
cases explain that a grading permit is not far enough along in the
discretionary land use process to vest the entire project, its construction or
its uses. Avco, supra, 17
Cal.3d at 797-98. Indeed, grading does
not commit a property owner to a definite course of action because it is a
preliminary step in the development of property. The moment of vesting occurs when a building
permit is issued. When building permits
are issued, courts exempt projects from regulations imposed following permit
issuance. Avco held that
subdivision improvements (streets, utilities, etc.) or zoning is not
sufficiently far along in the land use process to vest the right to build the
project. But the situation would have
been different if there were building permits for the buildings Avco planned to
construct and construction had begun. Then Avco would have had vested rights. See City of West Hollywood v.
Beverly Towers, supra, 52 Cal.3d at 1191-2 ((where a property owner
had completed all condominium conversion steps under the Subdivision Map Act other
than selling a unit, it had a vested right to be free from later enacted
ordinance requiring conditional use permit).
Opp. to City Dem. at 13.[5]
Petitioner’s
distinction of Avco and Spindler as grading permit cases does not
affect the fact that they stand for the legal proposition that a permit only
authorizes the work specified in the permit, however it may be styled. See Avco, supra, 17
Cal.3d at 93-97. Avco had a tract map, had
installed subdivision improvements, had a grading permit, and had commenced
grading, and still had no vested right to construct the project because no
permit authorized it. Id. at 785, 797.
The Permits
authorize Petitioner to perform its renovation Project and no City enactment
implicates Petitioner’s right to do so. Thus, the vested right doctrine is
inapplicable.[6]
3. The
Inverse Condemnation Claim
This court does
not handle inverse condemnation claims; those matters are assigned to the I/C
courts. Therefore, the court will not
address the merits of Petitioner’s regulatory taking claim. However, it will address its ripeness for
the convenience of the parties.
An as-applied
regulatory takings claim is not ripe unless a challenger can establish that the
government reached a final decision applying the subject regulations to its
property. Pakdel v. City & Cnty.
of San Francisco, (2021) 594 U.S. 474, 475. The challenger must show that “there is no
question ... about how the regulations at issue apply to the particular land in
question.” Id. at 478. A court “cannot determine whether a
regulation has gone ‘too far’ unless it knows how far the regulation goes.” Ibid.
Thus, a challenger’s failure to exploit
available procedures renders a claim unripe. Id. at 480. See Mobilehome Communities Owners
Ass’n v. City of San Buenaventura, (9th Cir. 2004) 371 F.3d 1046, 1053 (as-applied
challenge to ordinance not ripe where property owner did not seek the
adjustment of rent based on, inter alia, capital improvements; property
owner had “engaged in extended negotiations and mediation with the City” but
did not allege it had “sought, and was denied, compensation for losses
resulting from rent or vacancy control.”).
The City notes
that Petitioner concedes it has not availed itself of the mechanisms contained
in the City’s RCO to account for any alleged losses arising as a result of the
City’s RCO and TPO. FAP, ¶ 35. Petitioner alleges that doing so would be
futile, reasoning that (a) its renovations are ineligible for capital
improvement pass-through adjustments under RCO section 15.09.225 because eligible
capital improvements must be for additions, not replacement, and (b0 there is a
rebuttable presumption of a fair return that would preclude any rent
adjustments under RCO section 15.09.220. FAP, ¶35.
The City argues
that Petitioner’s conclusions are speculative.
The City has not rendered any decisions regarding the eligibility of the
Project renovations for capital improvement pass-throughs. Nor has the City concluded that Petitioner is
ineligible for a rent adjustment based on fair return. Petitioner may demonstrate in an application for
rent adjustment that the capital improvements were made beyond that “necessary
to bring the property into compliance or maintain compliance with code
requirements affecting health and safety.” RJN Ex. F (RCO §15.09.225(C)(3)(b)). For a rent adjustment application, Petitioner
is required to demonstrate that an “additional rent increase is necessary to
earn a fair and reasonable return with respect to the operation of their
property.” RCO §15.09.220(C). The City has not had the opportunity to
determine the impact of the regulations on Petitioner or to consider whether it
is entitled to relief. Thus, the inverse
condemnation claim is unripe. City Dem.
at 21-22.
Petitioner
responds that the TPO shows the City’s argument lacks merit. The TPO only
allows a landlord to seek increased rent based upon “eligible capital
improvements.” An eligible capital improvement is defined as “the addition, but
not the replacement of’ certain improvements, including air conditioning,
swimming pool, sauna or hot tub, etc, (15.09.225 B.l), or “substantial
improvements to, but not the replacement of, any structural, electrical,
plumbing, or mechanical system that requires a permit pursuant to State or
local law, such as a required seismic retrofit.” (§15.09.225 B.2). While the
work on the Project is extensive, it constitutes the replacement of electrical,
sewer, plumbing and natural gas lines. By
its terms, the TPO would not authorize a “capital improvement pass-through cost
recovery” because Petitioner’s work constitutes replacement rather than
addition of improvements. Opp. to City
Dem. at 17-18.
Petitioner is
referring to the RCO, not the TPO. The
City notes that there are two relevant rent adjustment processes for Petitioner:
(1) a fair return adjustment to ensure a property owner obtains a fair return
(RCO §15.09.220(A)) and (2) a capital improvement pass-through provision (RCO
§15.09.225). While Petitioner claims
the capital improvement pass-through provision does not apply to it, the City
has not had occasion to consider whether that assertion is correct because
Petitioner failed to submit an application. Even if Petitioner is correct about the
pass-through, it ignores the fact that a fair return petition is a plausible
avenue for Petitioner to obtain a rent increase. The City’s regulations
explicitly state that “Landlords may submit as part of their Application
capital improvement expenses that have not been or are not eligible to be
passed through to tenants through the City’s Capital Improvement Cost Recovery
Pass-Through program.” City Supp. RJN Ex.
A, ¶21. City Reply at 7-8.[7]
The court
agrees. Petitioner’s takings claims is
not ripe because it has not yet participated in the applicable administrative
determination process.
E. Conclusion
The City’s
demurrer to the Petition is sustained without leave to amend.
[1] The City asks the court to judicially notice the
following: (1) Four permits issued to Petitioner (Exs. A-D), (2) the Interim
Rent Control Ordinance (Ex. E); (3) the Rent Control Ordinance No.2020-14 (“RCO”)
(Ex. F); (4) the TPO (Ex. G); and the official minutes of a September 29, 2020
City Council meeting (Ex. H). The requests
are granted. Evid. Code §452(b), (c). In
reply, the City seeks judicial notice of Guideline/Rule No. 2021-RCO2 issued by
its Community Development Director (Supp. Ex. A). The request is granted. Evid. Code §452(c).
Intervenor asks the court to judicially notice
summaries of building permits attached as Exhibit A to the Declaration of Gary
Guthman and to the Declaration of Michael Soloff. Exhibit A to the Guthman declaration is a
summary that is inadequately authenticated.
Exhibit A to the Soloff declaration is a spreadsheet not subject to
judicial notice. The requests are
denied.
In reply, Intervenor asks the court to judicially
notice regulations attached as Exhibits A and B to the Soloff reply
declaration. The exhibits are not
regulations but appear to be official acts and the requests are granted. Evid. Code §452(c).
[2] Petitioner argues that it cannot complete the
improvements without compliance with the TPO requirement that it inform the
tenants it relocates that they may reoccupy their units after renovation at the
same rent as before. Opp. to City Dem.
at 11. But that does not alter the
facial aspect of the as-applied challenge.
[3]
The City notes that, during the period in which Petitioner argues it accrued a
vested right to operate without tenant protections, statewide eviction
protections were enacted via Assembly Bill 1482, signed into law on October 8,
2019. This state law regulates the bases for evictions, requiring landlords to
provide qualifying tenants with relocation assistance for no-fault evictions,
and expressly recognizes cities’ authority to enact “more protective” local
ordinances. Civil Code §1946.2. City Dem. at 18-19. Petitioner notes that the City fails to
explain what this state law has to do with reliance on the Permits. Opp. to City Dem. at 12. True, but the state law clearly authorizes
local governments to enact ordinances such as the TPO.
[4] Petitioner argues that the City does not argue the serious
health or safety concern that is a valid reason for municipalities to impair
vested rights: a. “Generally, a vested right in the land use context may not be
divested through ordinary police power regulations. It may, however, be
impaired or revoked if the use authorized or conducted under it constitutes ‘a
menace to the public health and safety or a public nuisance.’” Stewart
Enterprises, Inc. v. City of Oakland, (2016) 248 Cal. App. 4th 410, 423. Petitioner contends that the City’s unique tenant
reentry right is a political response to tenant requests, not a public health
or safety concern the City needs to avoid some health or safety crisis. Opp. to City Dem. at 13-14. This argument is a strawman. The issue is not an exception to Petitioner’s
vested rights, but rather their scope under the Permits.
[5] Petitioner distinguishes the cases cited by
Intervenor, People v. H&H Properties, (1984) 154 Cal.App.3d 894 and Blue
Chip Properties v. Permanent Rent Control Board, (1985) 170 Cal.App.3d 648,
as condominium conversion cases requiring a tentative tract map involving
little or no construction. Opp. to Int.
Dem. at 4-5.
[6] The City argues that the FAP’s declaratory relief
claim is subsumed within the mandamus claim.
City Dem. at 17, n. 3. Petitioner
does not dispute this fact and does not separately argue the declaratory relief
claim.
[7]
Petitioner suggests that it would be futile to undergo the City’s
administrative process. Opp. to City Dem. at 18. Exhaustion of administrative remedies may be
excused if the administrative agency has made it clear what its ruling would be
such that an administrative appeal would be futile. Huntington
Beach Police Officers' Assn. v. City of Huntington Beach, (1976) 58
Cal.App.3d 492, 499. Futility is shown
when “the petitioner can positively state that the [decision maker] has
declared what its ruling will be in the particular case.” Gantner
& Mattern Co. v. California Employment Com., (1941) 17 Cal.2d
314, 318. The futility exception applies
only if the administrative process would serve no purpose because the agency’s
denial of relief is a fait accompli. See Sea & Sage Audubon Society
v. Planning Commission of the City of Anaheim, (“Sea & Sage”) (1983)
34 Cal.3d 412, 418-19. The futility
exception to the exhaustion requirement is a mixed question of law and
fact. Econ. Empowerment Foundation v.
Quackenbush, (1997) 57 Cal.App.4th 677, 692. Where facts are pled that would show an
administrative remedy is futile, the matter is a question of fact to be decided
when evidence can be presented.
Petitioner has pled no facts that could warrant application of the
futility exception to the exhaustion requirement.