Judge: John J. Kralik, Case: 20STCV47586, Date: 2023-03-17 Tentative Ruling
Case Number: 20STCV47586 Hearing Date: March 17, 2023 Dept: NCB
North
Central District
|
710
east verdugo townhomes association, Plaintiff, v. 710 east
verdugo, llc, et al., Defendants. |
Case No.: 20STCV47586 Hearing Date: March 17, 2023 [TENTATIVE]
order RE: Demurrers |
BACKGROUND
A.
Allegations
Plaintiff 710 East Verdugo Townhomes
Association (“Plaintiff”) is a condominium complex consisting of 5 condominiums
in Burbank. Plaintiff exists for the
purpose of governing, preserving, repairing, operating, maintaining, and
managing the project for the benefit of its residents. Plaintiff alleges that Defendant 710 East
Verdugo, LLC (“Verdugo Developer”) acted as the general
contractor/owner/developer/seller of the project; Defendant Gaveet
Construction, Waterproofing, LLC (“GCW”) was the roofing, balcony, and walkway
subcontractor; and Narvan Construction Company (“NCC”) was a subcontractor on
the project. Plaintiff also alleges that
Defendant Vanik Manooki (“Manooki”) is a managing member and
president/principal of Verdugo Developer and NCC and that Defendants Alis
Merzakhani (“Merzakhani”) and Arthur H. Gasamanian are managing members of
Verdugo Developer. Plaintiff alleges
that as managing members, Manooki, Merzakhani, and Gasamanian directly
authorized and participated in the tortious conduct alleged.
Plaintiff alleges that Defendants
performed work in the common areas, but they violated the residential
construction standards enumerated in Civil Code, § 896 for numerous reasons as stated
in paragraph 5 on page 7 of the SAC.
The second amended complaint (“SAC”),
filed October 7, 2022, alleges a single cause of action for violation of
standards under Civil Code, § 896, et seq.
On March 29, 2021, Verdugo Developer and
NCC filed a cross-complaint against Gaveet Construction, Inc., EBN Plumbing,
Serj Air Condition, Calmex Fireplace Equipment Manufacturing Company, Inc.,
Lion Iron Works, Inc., and M5 Steel for: (1) breach of written contract; (2)
breach of written contract to obtain insurance; (3) breach of written contract
to indemnify and defend; (4) total equitable indemnity; (5) partial equitable
indemnity; (6) implied indemnity; (7) contribution and repayment; (8) declaratory
relief for duty to obtain insurance, duty to defend, duty to indemnity, duty to
obtain insurance, and duty to contribute; and (9) negligence.
On April 19, 2021, Noraeir Hovsepain dba
Gaveet Construction filed a cross-complaint against Vanik Manooki, NCC, NCC (a
proprietorship), and Verdugo Developer for: (1) negligent misrepresentation;
(2) negligence; (3) equitable indemnity; (4) contribution; (5) implied
contractual indemnity; and (6) declaratory relief.
On December 5, 2022, Noraeir Hovsepain dba
Gaveet Construction filed a cross-complaint against Vanik Manooki, NCC, NCC (a
proprietorship), Verdugo Developer, Alis Merkakhani, and Arthur H. Gasamanian
for: (1) equitable indemnity; (2) contribution; (3) implied contractual
indemnity; and (4) declaratory relief.
B.
Demurrers on Calendar
There are 4
demurrers on calendar. On January 19,
2023, Defendants Alis Merzakhani, Verdugo Developer, Arthur H. Gasamanian, and
Vanik Manooki each filed a demurrer to the SAC.
On March 3, 2023,
Plaintiff filed an opposition brief to each demurrer.
DISCUSSION
Defendants
each demur to the SAC, arguing that it fails to allege sufficient facts to
constitute a cause of action, it is uncertain, and it is barred by the
applicable statute of limitations in CCP § 895 et seq. In the demurrers, Defendants inform the Court
that the demurrer arguments are essentially the same and that the demurrer
filed by Merakhani is the “lead” demurrer.
First,
Defendants argue that the SAC does not allege sufficient facts showing that
Verdugo Developer is in fact a “California Corporation,” which would give rise
to the subsequent formation of the HOA and the adoption of the CC&Rs.
However, Defendants have not provided legal citations showing that this is a
necessary allegation to the complaint or for a cause of action of Violation of Civil
Code, § 896, et seq.
Plaintiff cites to CACI 4570, which
provides the elements for “Right to Repair Act – Construction Defects –
Essential Factual Elements (Civ. Code, § 896)”:
[Name of
plaintiff] claims that [he/she/nonbinary pronoun]
has been harmed because of defects in [name of
defendant]’s original construction of [name of
plaintiff]’s home. To establish this claim, [name of plaintiff] must prove [one or
more of the following:]
[Specify all
defects from Civil Code
section 896, e.g., that a defectively constructed door allowed unintended
water to pass beyond, around, or through it.]
(CACI
4570.) The aforementioned information
sought by Defendants is not an element for this cause of action and will not be
a ground to sustain the demurrers.
Next, Defendants argue that the SAC
only incorporates paragraphs 1-14 in the 1st cause of action and not
paragraphs 15 to 26. However, the Court
does not read the allegations of the 1st cause of action in a
vacuum, but reads the allegations of the SAC as a whole. The Court will not sustain the demurrer on
this basis. There is only one cause of
action in the SAC. It should be
understood by the parties that the entirety of the SAC’s allegations is in
support of the 1st and only cause of action alleged.
Defendants also argue that
Plaintiff’s allegations regarding NCC (a subcontractor) are insufficient
because Plaintiff has not alleged that it is a corporation affiliated with NCC
or the status of NCC. However, the demurrers
at issue are not brought by NCC and, thus, arguments regarding NCC are not
necessarily relevant to the demurrers before the Court.
The Court overrules the demurrers on
the basis that they fail to allege sufficient facts to constitute causes of action
against Defendants.
Second, Defendants argue that the
SAC fails to allege specific and articulable facts to establish a cause of
action against Defendants as members of the LLC. Defendants argue that the complaint and FAC
were only alleged against Verdugo Developer and that the public records show
that Manooki was a member of the LLC and Plaintiff should have been aware of
this fact but argues that Merzakhani and Gasamanian are not in the public
records. The Court is not in receipt of
any judicially noticeable documents to verify this information. At this time, the Court takes the allegations
of the SAC as true and the SAC alleges that these individual defendants were
members of the Verdugo Developer LLC. As
such, the demurrer on this basis is overruled.
Third, Defendants argue that the SAC is
uncertain because the 1st cause of action does not incorporate all
of the preceding paragraphs. As
discussed above, the demurrer on this basis is overruled. Defendants also argue that there is ambiguity
as to the allegations regarding the individual defendants being managing
members of Verdugo Developer. However,
as discussed above, the Court overrules the demurrer on this basis as
well.
Fourth, Defendants argue that the
SAC is barred by the statute of limitations.
Defendants argue that it is unclear why Plaintiff did not name the
individuals as Doe Defendants when filing the original complaint in December
2020 and waited 2 years to file the SAC in October 2022 naming the individual
defendants.
Defendants argue there is a bar to
bringing this action beyond 10 years from the completion of the project (even
if applying tolling) and that Civil Code, § 896 includes shorter statute of
limitations periods.
CCP § 337.15 provides for a 10-year
statute of limitations period after the substantial completion of a development
or improvement for construction/improvement projects to real property based on latent
deficiencies or injury arising out of any such latent deficiency. (CCP § 337.15(a).) At this time, the Court cannot ascertain when
the date of completion of the project was.
The SAC does not allege the dates of the project. At most, the only relevant date provided is
that Plaintiff sent Defendant Notice of Commencement of Legal Proceedings on
September 10, 2020 pursuant to Civil Code, §§ 895 et seq. and 6000 et
seq. (SAC, ¶19.) “In order for the bar of the statute of
limitations to be raised by demurrer, the defect must clearly and affirmatively
appear on the face of the complaint; it is not enough that the complaint shows
merely that the action may be barred.” (E-Fab, Inc. v. Accountants, Inc. Services (2007)
153 Cal.App.4th 1308, 1315-16.) Thus,
the Court cannot ascertain whether this action would be time-barred under the
10-year statute of limitations.
Next, Defendants argue that shorter
statute of limitations periods apply pursuant to Civil Code, § 896. While section 896 includes some statute of
limitations periods, it is again unclear when the period for the time accrual
would begin. For example, in section
896(f), it states that no action for electrical systems shall be brought
pursuant to the subdivision more than 4 years from the close of escrow. The SAC does not allege the date of the close
of escrow, such that the Court cannot make a determination on whether the statute
of limitations period has elapsed.
In opposition, Plaintiff argues that
the action should be tolled as a result of its recordation of the Notice of
Completion on September 21, 2010 and sending the Notice of Commencement of
Legal Proceedings on September 10, 2020 (Civ. Code, § 6000, 180 days) and
COVID-19 Emergency Rule 9 (tolling and extension of the statute of
limitations). The action was likely
tolled during this period, but the Court need not reach the merits of the
tolling in light of the fact that the demurrers on the basis of the statute of
limitations are overruled.
CONCLUSION AND ORDER
Defendants
Alis Merzakhani, 710 East Verdugo, LLC, Arthur H. Gasamanian, and Vanik
Manooki’s demurrers to the Second Amended Complaint and the sole cause of
action are overruled.
Defendants
shall give notice of this order.