Judge: John J. Kralik, Case: 20STCV47586, Date: 2023-04-21 Tentative Ruling
Counsel who wish to submit on the tentative ruling may do so by emailing BURDeptB@lacourt.org
PLEASE WRITE THE CASE NUMBER AND PARTY YOU REPRESENT. YOU MAY ONLY SUBMIT ON BEHALF OF THE PARTY YOU REPRESENT. YOU MAY NOT SUBMIT ON BEHALF OF ANOTHER PARTY.Counsel are directed to cc all other counsel if you are submitting on the tentative ruling.
IF YOU HAVE QUESTIONS OR NEED CLARIFICATION ON THE TENTATIVE, YOU MUST APPEAR AND ADDRESS YOUR QUESTIONS TO THE COURT.
IF BOTH SIDES SUBMIT ON THE TENTATIVE RULING, THE TENTATIVE RULING THEN BECOMES THE ORDER OF THE COURT ON THE MOTION DATE AND NO APPEARANCES ARE NECESSARY.
THERE WILL BE NO RESPONSES TO ANY INQUIRIES SUBMITTED THROUGH THIS SITE.
THANK YOU!
Case Number: 20STCV47586 Hearing Date: April 21, 2023 Dept: NCB
North
Central District
|
710
east verdugo townhomes association, Plaintiff, v. 710 east
verdugo, llc, et al., Defendants. |
Case No.: 20STCV47586 Hearing Date: April 21, 2023 [TENTATIVE]
order RE: motion to compel further |
BACKGROUND
A.
Allegations
Plaintiff 710 East Verdugo Townhomes
Association (“Plaintiff”) is a condominium complex consisting of 5 condominiums
in Burbank. Plaintiff exists for the
purpose of governing, preserving, repairing, operating, maintaining, and
managing the project for the benefit of its residents. Plaintiff alleges that Defendant 710 East
Verdugo, LLC (“Verdugo Developer”) acted as the general contractor/owner/developer/seller
of the project; Defendant Gaveet Construction, Waterproofing, LLC (“GCW”) was
the roofing, balcony, and walkway subcontractor; and Narvan Construction
Company (“NCC”) was a subcontractor on the project. Plaintiff also alleges that Defendant Vanik
Manooki (“Manooki”) is a managing member and president/principal of Verdugo
Developer and NCC and that Defendants Alis Merzakhani (“Merzakhani”) and Arthur
H. Gasamanian are managing members of Verdugo Developer. Plaintiff alleges that as managing members,
Manooki, Merzakhani, and Gasamanian directly authorized and participated in the
tortious conduct alleged.
Plaintiff alleges that Defendants
performed work in the common areas, but they violated the residential
construction standards enumerated in Civil Code, § 896 for numerous reasons as stated
in paragraph 5 on page 7 of the SAC.
The second amended complaint (“SAC”),
filed October 7, 2022, alleges a single cause of action for violation of
standards under Civil Code, § 896, et seq.
On March 29, 2021, Verdugo Developer and
NCC filed a cross-complaint against Gaveet Construction, Inc., EBN Plumbing,
Serj Air Condition, Calmex Fireplace Equipment Manufacturing Company, Inc.,
Lion Iron Works, Inc., and M5 Steel for: (1) breach of written contract; (2)
breach of written contract to obtain insurance; (3) breach of written contract
to indemnify and defend; (4) total equitable indemnity; (5) partial equitable
indemnity; (6) implied indemnity; (7) contribution and repayment; (8) declaratory
relief for duty to obtain insurance, duty to defend, duty to indemnity, duty to
obtain insurance, and duty to contribute; and (9) negligence.
On April 19, 2021, Noraeir Hovsepain dba
Gaveet Construction filed a cross-complaint against Vanik Manooki, NCC, NCC (a
proprietorship), and Verdugo Developer for: (1) negligent misrepresentation;
(2) negligence; (3) equitable indemnity; (4) contribution; (5) implied
contractual indemnity; and (6) declaratory relief.
On December 5, 2022, Noraeir Hovsepain dba
Gaveet Construction filed a cross-complaint against Vanik Manooki, NCC, NCC (a
proprietorship), Verdugo Developer, Alis Merkakhani, and Arthur H. Gasamanian
for: (1) equitable indemnity; (2) contribution; (3) implied contractual
indemnity; and (4) declaratory relief.
On April 3, 2023, Cross-Complainants
dismissed without prejudice Cross-Defendant Alis Merkakhani.
B.
Motion on Calendar
On March 21, 2023,
Defendant 710 East Verdugo, LLC (“Defendant” for the purposes of this motion) filed
a motion to compel Plaintiff’s further and supplemental responses to Special
Interrogatories, set two (“SROG”).
On April 3, 2023,
Plaintiff filed an opposition to the motion.
On April 11, 2023,
Defendant filed a reply brief.
DISCUSSION
Defendant moves to compel
Plaintiff’s further responses to SROG Nos. 33-98. Defendant argues that the 66 new SROGs asks
the same 4 questions over 24 defects identified by Plaintiff in its complaint
at paragraph 5, subparts (a) to (x) in the 1st cause of action. (Although Plaintiff cites to subparts (a) to
(x), it appears that the SROGs seek further responses as to subparts (i)
to (x) only.)
For
example, SROG Nos. 33-36 ask:
·
SROG No. 33:
As to each defect identified in the complaint at paragraph 5(i), stating
stucco staining at parapet wall and down spouts indicative of water intrusion, state
the date that this was first observed by Plaintiff.
·
SROG No. 34:
As to each defect identified in the complaint at paragraph 5(i), state
the total amount spent by you to repair, correct, restore, or rebuild the
subject property to correct these defects.
·
SROG No. 35:
As to each defect identified in the complaint at paragraph 5(i), state
the date each payment, whether in part or in full, was paid to repair, correct,
restore, or rebuild the defect.
·
SROG No. 36:
As to each defect identified in the complaint at paragraph 5(i), state
the name, address, telephone number, email, or other contact for each person or
entity to whom you paid money to repair, correct, restore, or rebuild, for each
defect alleged in paragraph 5(i).
In paragraph 5(i) to (x) of the 1st
cause of action, Plaintiff alleges the following violations of the residential
construction standard enumerated in Civil Code, § 896:
·
i) Stucco staining at parapet wall and
downspouts indicative of water intrusion (SROG Nos. 33-36)
·
j) Lack of weep holes for stucco walls and
parapet walls (SROG Nos. 37-40)
·
k) Stucco separation at diato flashing
(SROG Nos. 41-44)
·
l) Stucco EPS trim deteriorated (SROG Nos.
45-48)
·
m) Inadequate waterproofing of planters
allowing leaks (SROG Nos. 49-52)
·
n) Driveway retaining wall’s waterproofing
is inadequate with efflorescence and staining present (SROG Nos. 53-56)
·
o) CMU wall cracking (SROG Nos. 57-60)
·
p) Plumbing leaking causing damage to
gypsum wallboard and ceilings (SROG Nos. 61-64)
·
q) Concrete cracking and spalling on floor
in garage (SROG Nos. 65-68)
·
r) Walls on property line tilting (SROG
Nos. 69-72)
·
s) Concrete flatwork cracking (SROG Nos.
73-76)
·
t) Entry gate out-of-square and corroded
(SROG Nos. 77-80)
·
u) Stucco stop and door frame finger-joint
separation (SROG Nos. 81-84)
·
v) Improper fittings at connection points
of sewage pipes (SROG Nos. 85-88)
·
w) Settling issues under investigation
(SROG Nos. 89-92)
·
x) HVAC system installed improperly (SROG
Nos. 93-96)
To SROG No. 33 (and each of the
similar SROGs per alleged violation), Plaintiff objected to the SROG on the
grounds that it was vague as to the terms “defect,” “your,” “complaint,”
“observed,” and “you”; sought the premature discovery of expert opinion; was
compound; sought a legal conclusion; and sought information protected by the
attorney-client privilege and/or work product doctrine. Without waiving objections, Plaintiff
responded that on January 16, 2019, a homeowner of one of the condominiums that
comprise the subject property reported a leak from his ceiling; Plaintiff’s
expert opined that there were various construction defects; Plaintiff’s expert
conducted his initial inspection on November 4, 2020 during which the defects
were first observed by the expert; and the expert has not yet concluded his
investigation.
The objections are essentially boilerplate
in nature. Where such general
“boilerplate” objections are made, this Court has the authority to order a
further response. (See Best Prods., Inc. v. Superior Court
(2004) 119 Cal.App.4th 1181, 1189.) The
SROG is not vague as asked and does not seek legal conclusions. Further, the SROG does not ask for the
opinions (reports or writings) of an expert, but asks when Plaintiff observed a
violation of the premises, as described in paragraph 5, subparts (i) to
(x). Finally, it is unclear how the
attorney-client privilege and/or attorney work product doctrine would be
implicated here where Defendant is merely asking when Plaintiff observed the
alleged violations.
Plaintiff’s response does not address SROG
No. 33 as asked. SROG No. 33 asks for
the date that Plaintiff first observed the defect. Plaintiff’s response only provides when
someone from the condominium complex reported the defect to Plaintiff and when
Plaintiff’s expert observed the leak (which was one month before the filing of
the lawsuit). Plaintiff has not provided
any response when it or its employees/agents/representatives observed the
violation. If Plaintiff (or its agents) did
not take steps to observe the violation, then it should state as such in its
response. The motion is granted as to
SROG No. 33 and the subsequent SROGs asking when Plaintiff first observed the
violations in paragraph 5(i) to (x).
To SROG No. 34, Plaintiff made
similar objections on the grounds that the SROG was vague and compound, sought
the premature discovery of expert opinion and legal conclusions, and sought
privileged information. Plaintiff
responded that it was unable to provide a direct response as it was unclear
what Defendant was asking as the SROG sought legal conclusion and expert
opinions. Plaintiff responded that it
continued to suffer from the describe defects despite repair attempts and no
successful repairs to the defects have been completed. Plaintiff also cited documents
(PLA000236-PLA000469, PLA000794-PLA000830, and PLA001148-PLA001157) as
responsive to the SROG. To SROG
No. 35, Plaintiff made similar objections and responses, but also responded
that No. 35 is duplicative of No. 34.
As discussed above, the objections and
claims of privilege are overruled. Here,
SROG Nos. 34 and 35 are not vague in that they ask for the total amount
Plaintiff spent to remedy the subject property to correct the alleged defect in
paragraph 5(i) (and thereafter, each of the subparts in the other SROGs),
as well as the date of payment. Plaintiff’s
responses do not provide the costs Plaintiff has incurred, which would support
Plaintiff’s claim for damages.
In opposition, Plaintiff argues that it
responded as best as it could and that it cited to responsive documents. Under limited circumstances, a party may
specify other “writings from which the answer may be derived or ascertained.”
(See CCP § 2030.230.) A party may only
do so when: (1) answering an interrogatory “would necessitate the preparation
or the making of a compilation, abstract, audit, or summary of or from” the
responding party’s documents; and (2) “the burden or expense of preparing or
making it would be substantially the same for the party propounding the
interrogatory as for the responding party.”
(Id.) The response by
document production must specifically also cite to Section 2030.230 and contain
“sufficient detail to permit the propounding party to locate and to identify,
as readily as the responding party can, the documents from which the answer may
be ascertained.” (CCP § 2030.230.) Making an unwarranted
or insufficiently specific response
(by document production) is grounds for a motion to compel a further
response. (CCP § 2030.300(a)(1).) While Plaintiff has identified Bates Stamped
pages, the pages span over 250 pages of documents without specifying which
documents are responsive to which SROG.
Instead, the same pages are identified in response to each version of
SROGs 34 and 35 with respect to the different violations listed in paragraph 5(i)
to (x). Thus, the motion is granted as
to SROG Nos. 34 and 35 and the subsequent SROGs asking for the amounts spent
and date of payment to repair, correct, restore, or rebuild the defect specified
in paragraph 5(i) to (x).
To SROG No. 36, Plaintiff made
similar objections on the grounds that the SROG was vague and compound, sought
the premature discovery of expert opinion and legal conclusions, and sought
privileged information. Without waiving
objections, Plaintiff gave the same response as it did to SROG No. 34 and
identified the same documents.
For the same reasons discussed above, the
Court overrules the objections raised by Plaintiff. The SROG as asked is straightforward, as it
essentially seeks the identity and contact information of those who repaired, corrected,
restored, or rebuilt the alleged defects in paragraph 5(i) to (x). The motion is granted to SROG No. 36 and the
subsequent SROGs asking for the identity and contact information of those who
repaired, corrected, restored, or rebuilt the alleged defects specified in
paragraph 5(i) to (x).
Defendant did not request sanctions
in connection with the motion.
Plaintiff seeks sanctions in the
amount of $3,150 against Defendant. The
request for sanctions is denied.
CONCLUSION
AND ORDER
Defendants
710 East Verdugo, LLC’s motion to compel Plaintiff’s further responses to the
Special Interrogatories, set two, is granted.
Plaintiff is ordered to provide further responses, without objection, to
the discovery within 20 days of notice of this order.
No
sanctions shall be awarded in connection with this motion.
Defendant
shall give notice of this order.