Judge: Joseph Lipner, Case: 25STCV00573, Date: 2025-03-27 Tentative Ruling
Case Number: 25STCV00573 Hearing Date: March 27, 2025 Dept: 72
SUPERIOR COURT OF CALIFORNIA
COUNTY OF LOS ANGELES
DEPARTMENT 72
TENTATIVE RULING
FOREST CONSTRUCTION COMPANY, INC., Plaintiffs, v. HEIDI CORPORATION, et al. Defendants. |
Case No: 25STCV00573 Hearing Date: March 27, 2025 Calendar
Number: 10 |
Defendant Heidi Corporation d/b/a Donald J.
Scheffler’s Construction (“Scheffler”) demurs to the Complaint and moves to
strike portions of the Complaint.
Defendant Scheffler’s Demurrer is OVERRULED and
the Motion to Strike is DENIED.
Defendant to answer in 20 days.
Background
On February 8, 2023, Plaintiff Forest Construction Co.,
Inc. entered into a subcontract (“Subcontract”) with Defendant Heidi
Corporation d/b/a Donald J. Scheffler’s Construction (“Scheffler”). Pursuant to the Subcontract, Scheffler would
provide the structural concrete work for a project located at 3525 Padaro Lane
Caprinteria, CA 93013 (the “Project”). Scheffler
commenced work on the Project and a dispute arose regarding 17 of the 25 piles
that were installed. The engineer of
record deemed the 17 piles to be substandard.
As
a result of the dispute over the 17 substandard piles, Plaintiff and Scheffler
entered into an Interim Partial Settlement Agreement and Completion Addendum
(“Interim Agreement”) on June 20, 2024.
Under the Interim Agreement, Plaintiff would absorb the $600,000 in
additional cost and delay caused by Scheffler's substandard work. In exchange, Scheffler agreed to perform all
remaining work in its scope based upon all drawings in existence as of the
signing of the Interim Agreement for $1.3 million. Scheffler also acknowledged full payment for
all work performed to date.
Plaintiff
alleges Scheffler breached the parties’ Subcontract as modified by the Interim
Agreement when it refused to perform the remaining work on the project. Scheffler refused to perform on grounds that Plaintiff
was required under the “new agreement” to provide a single plan page, signed by
the architect, engineer, contractor and owner, which included all information
set forth in the stamped and approved plans and specifications for the Project. Work did not proceed and the mock-up was
never completed or approved.
After
refusing to perform for three months, Plaintiff indicated it would terminate
Scheffler for cause if it did not commence work as required under the Interim
Agreement and Subcontract. Scheffler
refused to commence work and Plaintiff provided Scheffler with a 48-hour notice
of default and demand to cure on October 1, 2024. In response, Scheffler demobilized and
abandoned the Project. Plaintiff was
required to hire a new subcontractor and has incurred $1.4 million in costs due
to Scheffler’s breach.
Plaintiff
alleges Scheffler had no intention of actually continuing work on the Project. Plaintiff alleges Scheffler fraudulently
induced Plaintiff into executing the Interim Agreement by misrepresenting its
intention. Plaintiff alleges damages in
the amount of $1.8 million due to Scheffler’s fraudulent inducement.
On
January 9, 2025, Plaintiff filed a complaint against Scheffler alleging (1)
breach of contract and (2) fraud in the inducement. On February 26 and 27, 2025, Scheffler filed
a motion to strike and demurrer to the complaint respectively. On March 14, 2025, Plaintiff filed
oppositions to the demurrer and motion to strike. On March 20, 2025, Scheffler filed replies to
Plaintiff’s opposition.
Discussion
Meet and Confer
Defense
counsel sent a letter to on February 10, 2025 requesting a conference to meet
and confer on the pleading, offering February 10, 11 and 12th as
available dates. (Ruiz Dec., Ex.
C.) No response to the letter was
received. (Ruiz Dec., ¶¶9 and 10.) Plaintiff’s counsel did not see the letter
until February 12th. (Opposition,
Rudman Dec., ¶5.) Defendant’s meet and
confer declaration states that he attempted to meet and confer and no response
was received. This is sufficient under
CCP §430.10(a)(B).
Demurrer
Scheffler demurs to both
causes of action in the complaint for breach of contract and fraudulent
inducement. Scheffler argues the breach
of contract claim fails to allege the specific breach against Scheffler and is
uncertain. Scheffler argues the fraud in
the inducement claim fails because there are no factual allegations
establishing a fraudulent motive or its intent not to perform. Scheffler also argues the fraud claim fails
to identify the individual who made the fraudulent representations, when they
were made, how they were made and the authority by which the person made them
on Scheffler’s behalf.
Breach of Contract
The elements for a
breach of contract cause of action are: (1) the existence of a contract; (2)
plaintiff’s performance or excuse for nonperformance; (3) defendant’s breach;
and (4) resulting damages. (Reichert
v. General Ins. Co. (1968) 68 Cal.2d 822, 830.) A written contract may be pleaded either in
haec verba (word for word) or generally “according to its legal intendment and
effect” (e.g., “Defendant agreed to sell the described property to Plaintiff
for $100,000”). (Construction
Protective Services, Inc. v. TIG Specialty Ins. Co. (2002) 29 Cal.4th 189,
198–199.)
Plaintiff alleges that the parties entered
into an Interim Partial Settlement and Completion Addendum on June 20,
2024. (Complaint, ¶14.) Plaintiff alleges the terms of the Interim
Agreement by attaching the agreement (Complaint, Ex. C) and by alleging the
specific material terms allegedly breached (Complaint, ¶16.) Plaintiff alleges Defendant was required to
“perform all remaining work in its scope based upon all drawings in existence
as of the signing of this Addendum for the total price of [$1.3 million]” and
that it acknowledged full payment to date.
(Complaint, ¶16.)
Plaintiff alleges that
during the three-month period following execution of the Interim Agreement,
Scheffler refused and continued to refuse to perform as required of it. (Complaint, ¶18.) Plaintiff alleges Scheffler has refused to
complete the Project, claiming Plaintiff must first provide it with a single
plan page, signed by the architect, engineer, contractor and owner, which
included all the information set forth in the stamped and approved plans and
specifications for the Project.
(Complaint, ¶18.) Plaintiff
denies that there was ever such a requirement under the Interim Agreement or
any other agreement. (Complaint, ¶19.)
Plaintiff’s allegation
of breach—that Scheffler has refused to complete the Project and has not done
so—is an allegation of fact that must be accepted as true. Plaintiff need not allege facts showing its
performance under the Interim Agreement per CCP §457, which states: “In pleading the performance of conditions
precedent in a contract, it is not necessary to state the facts showing such
performance, but it may be stated generally that the party duly performed all
the conditions on his part, and if such allegation be controverted, the party pleading
must establish, on the trial, the facts showing such performance.” (CCP §457.)
Plaintiff’s allegation
that the breach of contract claim “assum[es] that the Interim Agreement was not
fraudulently induced and is not enforceable” does not render the cause of
action uncertain. Plaintiff is entitled
to allege alternative theories of relief if it is unsure of the facts or legal
theories upon which it may recover. “Pleading
of alternative theories of relief on the same set of facts is, of course, quite
proper and is often done where there is a legally recognized basis for recovery
in both contract and tort.” (Gebert
v. Yank (1985) 172 Cal.App.3d 544, 554 (plaintiff properly pled alternative
theories of recovery for breach of bailment contract and negligence, two causes
of action with differing burdens of proof).)
Plaintiff’s allegation
that the parties intended the Interim Agreement to settle the dispute over the
17 substandard piles and modify the Subcontract is supported by the title of
the Interim Agreement is “Interim Partial Settlement and Completion Addendum to
Subcontract.” (Complaint, Ex. C.) Parties clearly intended from the title of
the agreement to make it a part of the larger Subcontract as an addendum. (Id.)
For this reason, Plaintiff’s interpretation of the Interim Agreement as
part of the Subcontract is reasonable and this interpretation must be accepted
as true on demurrer. (Requa v.
Regents of University of California (2012) 213 Cal.app.4th 213,
223.)
Plaintiff therefore
sufficiently identifies Defendant’s breach of a material term of the Interim
Agreement, which was intended to be a part of the Subcontract. Plaintiff sufficiently alleges the material
terms of the Interim Agreement, as well as damages. Defendant’s arguments attack the truth of the
allegations or raise disputed facts outside of the Complaint as defenses. Defendant’s demurrer to the first cause of
action is OVERRULED.
Fraudulent
Inducement
The elements of fraud
are: (1) misrepresentation (false representation, concealment, or
nondisclosure); (2) knowledge of falsity (scienter); (3) intent to defraud or
induce reliance; (4) justifiable reliance; and (5) damages. (Civil Code §1709.)
Fraud actions are subject to strict requirements of particularity in
pleading. (Committee on Children’s
Television, Inc. v. General Foods Corp. (1983) 35 Cal. 3d 197, 216.)
Consistent with the rule
requiring specificity in pleading fraud, a complaint must state ultimate facts
showing that the defendant intended or had reason to expect reliance by the
plaintiff or the class of persons of which he is a member. (Geernaert v. Mitchell (1995) 31 Cal.
App. 4th 601, 608.) A plaintiff must
allege what was said, by whom, in what manner (i.e. oral or in writing), when,
and, in the case of a corporate defendant, under what authority to bind the
corporation. (Goldrich v. Natural Y
Surgical Specialties, Inc. (1994) 25 Cal.App.4th 772, 782.)
Plaintiff alleges it
relied on Scheffler’s fraudulent representation that Scheffler “was prepared to
remobilize immediately, and perform the balance of the work called for under
its Subcontract of the total remaining price of $1,300,000.” (Complaint, ¶31.) Plaintiff alleges Scheffler intended for
Plaintiff to rely on “its representations, including those in the Interim
Agreement, as it provided that Scheffler would continue to perform the project
for $1,300,000.”) (Complaint, ¶33.) Plaintiff alleges “conversely, Plaintiff
believes that Scheffler had no intention of actually continuing with the work
on the Project and was inducing the Interim Agreement to avoid the damages claims
against it for its previously unaccepted pile construction.” (Complaint, ¶34.) Plaintiff alleges that it suffered $1.8
million in damages due to Scheffler’s fraudulent misrepresentation. (Complaint, ¶37.)
Plaintiff’s second cause
of action for fraudulent inducement alleges the Interim Agreement itself
contains the fraudulent misrepresentations, specifically Scheffler’s promises
to perform the rest of the work for $1.3 million and to use its best efforts to
timely provide and accomplish specific contractual milestones. The date of the misrepresentations are
therefore the date of the Interim Agreement, June 20, 2024, and the individual
making the misrepresentations was Donald J. Scheffler, Scheffler’s President. (Complaint, Ex. C.) Plaintiff therefore alleges the
misrepresentations, how they were made, who made them, when they were made and
the authority by which the speaker made the representations on Scheffler’s
behalf.
Plaintiff’s second cause
of action for fraudulent inducement also alleges another species of
fraud—promissory fraud. So long as
Plaintiff alleges a valid cause of action, even one not intended by it, the
demurrer must be overruled. (New
Livable Calif. v. Association of Bay Area Governments (2020) 59 Cal.App.5th
709, 714-715.)
Defendant also argues
lack of evidentiary facts to support a finding of fraudulent intent. However, “[i]ntent, like knowledge, is a
fact. Hence, the averment that the representation was made with the intent to deceive
the plaintiff, or any other general allegation with similar purport, is
sufficient.” (5 Witkin, Cal. Proc.
(6th ed. 2021) Plead § 725. Purely
evidentiary matters—usually circumstantial evidence or admissions showing lack
of that intention—should not be pleaded. Hence, the only necessary averment is
the general statement that the promise was made without the intention to
perform it, or that the defendant did not intend to perform it.” (Beckwith
v. Dahl (2012) 205 Cal. App. 4th 1039, 1060.) Plaintiff need only allege ultimate facts,
not evidentiary facts. Thus, Plaintiff’s
allegation that Defendant made promises to complete the work for $1.3 million
without the intent to perform is an allegation of ultimate fact and it must be
accepted as true on demurrer.
Defendant argues there
are insufficient evidentiary facts alleged to support a finding of reasonable
or justifiable reliance. However,
Plaintiff alleges that Defendant promised it complete the work on the Project
for $1.3 million pursuant to a written agreement and in exchange for a release
of any liability for the 17 disputed piles.
Plaintiff alleges sufficient facts to support a finding of reasonable
reliance. “Except in the rare case where
the undisputed facts leave no room for a reasonable difference of opinion, the
question of whether a plaintiff's reliance is reasonable is a question of
fact.” (Beckwith, supra, 205
Cal.App.4th at 1067.)
Defendant’s demurrer to
the second cause of action for fraudulent inducement is overruled.
Motion to Strike
Defendant moves to
strike certain key allegations from the Complaint. Defendant moves to strike Plaintiff’s
allegations (1) of Defendant’s fraudulent intent; (2) Plaintiff’s performance
of all obligations under the contract; (3) allegations that Defendant’s actions
reflected Defendant’s motivation for fraudulently inducing the Interim
Agreement (avoidance of liability for the 17 disputed piles); (4) purportedly
deficient allegations of fraud; (5) allegations regarding Defendant’s intent
and motivation based on Plaintiff’s belief.
Defendant argues these
allegations must be stricken based on the standards required to plead causes of
action for breach of contract and fraud on demurrer. Defendant apply the wrong standard. A motion to strike is intended to strike
allegations that are irrelevant, false or improper. (CCP §436.)
Moreover, as discussed in connection with the demurrer, intent is a fact
and averment thereof is sufficient. In
addition, the fraud and breach of contract claims are also sufficiently alleged
and the targeted allegations are either essential ultimate facts to state both
claims, or they are evidentiary or background facts that are relevant and
proper. Defendant’s motion to strike is
denied.