Judge: Katherine Chilton, Case: 21STLC06169, Date: 2022-08-23 Tentative Ruling
Case Number: 21STLC06169 Hearing Date: August 23, 2022 Dept: 25
PROCEEDINGS: MOTION TO RECLASSIFY TO
UNLIMITED CIVIL CASE
MOVING PARTY: Defendants/Cross-Complainants
Armen and Flora Vartanian
RESP. PARTY: None
MOTION TO RECLASSIFY
(CCP § 403.040)
TENTATIVE RULING:
Defendants/Cross-Complainants
Vartanians’ Motion to Reclassify (incorrectly named Motion to Transfer) is
CONTINUED to SEPTEMBER 26, 2022 at 10:00
a.m. in Department 25 at the SPRING STREET COURTHOUSE. Defendants/Cross-Complainants Vartanians are
ordered to serve supplemental papers addressing the issues discussed herein on
the opposing party at least 16 court days before the next scheduled hearing and
file it with the Court at least 5 court days before the next scheduled
hearing. Failure to do so may result in
the Motion being placed off calendar or denied.
SERVICE:
[ X ] Proof of Service Timely Filed
(CRC, rule 3.1300) OK
[ X ] Correct Address (CCP §§ 1013,
1013a) OK
[ X ] 16/21 Court Days Lapsed (CCP §§
12c, 1005(b)) OK
OPPOSITION: Non-Opposition
filed on June 24, 2022 [ ]
Late [ ] None
REPLY: None
filed as of August 19, 2022. [ ] Late [X] None
ANALYSIS:
I.
Background
On August 23, 2021, Plaintiff
Picture Build (“Plaintiff”) filed a complaint against Defendants Armen and
Flora Vartanian (collectively, the “Vartanians”) and Rate Rabbit, Inc. (“Rate
Rabbit”), (collectively “Defendants”), asserting claims for: (1) Breach of
Contract; (2) Account Stated; (3) Quantum Meruit; and (4) Foreclosure of
Mechanic’s Lien. This case is based on a
written agreement (the “Agreement”) between Picture Build, on the one hand, and
the Vartanians, on the other hand. Pursuant
to the Agreement, the Vartanians contracted Picture Build to perform hardscape
and landscape home improvement work at their residence (the
"Project"). The Complaint
alleges that subsequent to entering into the Agreement, several change orders,
including reductions in the scope of work, were agreed to by Picture Build and
the Vartanians. Picture Build alleges
that it incurred additional costs for which it submitted claims to the
Vartanians. However, the Vartanians
allegedly failed to compensate Picture Build for its costs and/or services. (Compl. ¶¶ 7-10, 14.)
On January 31, 2022, the Vartanians
filed an Answer and a Cross-Complaint against Cross-Defendants Picture Build,
Brian Michael Godley (“Godley”), and Hudson Insurance Company (“Hudson”),
(collectively “Cross-Complainants”), asserting claims for: (1) Breach of Contract;
(2) Negligence; (3) Violation of Bus. and Prof. Code, § 7160; (4) Recovery
Against Contractor’s License Bond; and (5) Unlicensed Practice and Disgorgement.
On April
19, 2022, Cross-Defendant Godley’s Demurrer to the Cross-Complaint was
sustained with 20 days leave to amend.
(4-19-22 Minute Order.) The
Vartanians filed an Amended Cross-Complaint on May 4, 2022, but Godley filed a
Demurrer to the Amended Cross-Complaint, which was sustained without leave to
amend. (7-7-22 Minute Order.)
On June 3, 2022, after filing the
Amended Cross-Complaint, the Vartanians filed the instant Motion to Reclassify
(incorrectly named “Motion to Transfer Action”) (“Motion”). On June 24, 2022, Cross-Defendants Picture
Build and Godley filed a Notice of Non-Opposition to the Motion. No reply was filed.
II.
Legal Standard
Code of Civil Procedure § 403.040
allows a plaintiff to file a motion for reclassification of an action within
the time allowed for that party to amend the initial pleading. (Code Civ. Proc., § 403.040(a).) “A party may amend its pleading once without
leave of court at any time before an answer, demurrer, or motion to strike is
filed, or after a demurrer or motion to strike is filed if the amended pleading
is filed and served no later than the date for filing an opposition to the
demurrer to motion to strike. (Code Civ.
Proc., § 472(a).) If the motion is made
after the time for the plaintiff to amend the pleading, the motion may only be
granted if (1) the case is incorrectly classified; and (2) the plaintiff
shows good cause for not seeking reclassification earlier. (Code Civ. Proc. § 403.040(b).)
In Walker v. Superior Court (1991) 53 Cal.3d 257, 262, the California
Supreme Court held that a matter may be reclassified from unlimited to limited
only if it appears to a legal certainty that the plaintiff’s damages will
necessarily be less than $25,000. (Walker v. Superior Court (1991) 53
Cal.3d 257.) If there is a possibility
that the damages will exceed $25,000.00, the case cannot be transferred to
limited. (Ibid.) This high standard is
appropriate in light of “the circumscribed procedures and recovery available in
the limited civil courts.” (Ytuarte v. Superior Court (2005) 129 Cal.App.4th
266, 278.)
In Ytuarte, the Court of Appeal examined the principles it set forth
in Walker and held that “the court
should reject the plaintiff’s effort to reclassify the action as unlimited only when the lack of jurisdiction as an
‘unlimited’ case is certain and clear.”
(Ytuarte, supra, 129
Cal.App.4th at 279 (emphasis added).)
Nevertheless, the plaintiff must present evidence to demonstrate a
possibility that the damages will exceed $25,000.00 and the trial court must
review the record to determine “whether a judgment in excess of $25,000.00 is
obtainable.” (Ibid.)
III.
Discussion
Defendants/Cross-Complainants Vartanians
seek to reclassify this action as an unlimited civil action on grounds that their
First Amended Cross-Complaint (“FAC”) seeks damages “in excess of $150,000” because
they will have to hire a new contractor and subcontractors to complete the
project. (FAC ¶¶ 13, 19.)
The initial Cross-Complaint,
seeking damages in excess of $150,000, was filed on January 31, 2022, and
Cross-Defendants have filed answers and demurrers subsequent to filing of the
Cross-Complaint. Thus, the Vartanians
must show good cause for not seeking reclassification earlier. Nothing in the Motion or attached counsel’s
declaration explains why the Vartanians did not seek reclassification earlier.
Furthermore, other than referring
to the FAC’s general statement seeking damages in excess of $150,000, there are
no estimates or proof in the form of declaration or exhibits to demonstrate
that a judgment above $25,000 is obtainable.
Defendants/Cross-Complainants
have not their burden of showing good cause for reclassification or that a
judgment above $25,000 is obtainable.
Given that Cross-Defendants Picture Build and Godley have filed a Notice
of Non-Opposition to the Motion to Reclassify, the Court continues the hearing
to allow Defendants/Cross-Complainants an opportunity to file supplemental
papers showing good cause and supporting a request for damages above $25,000.
IV.
Conclusion & Order
For the
foregoing reasons, Defendants/Cross-Complainants Vartanians’ Motion to Reclassify
(incorrectly named Motion to Transfer) is CONTINUED to SEPTEMBER 26, 2022 at 10:00 a.m. in Department 25 at the
SPRING STREET COURTHOUSE. Defendants/Cross-Complainants
Vartanians are ordered to serve supplemental papers addressing the issues
discussed herein on the opposing party at least 16 court days before the next
scheduled hearing and file it with the Court at least 5 court days before the
next scheduled hearing. Failure to do so
may result in the Motion being placed off calendar or denied.
Moving party is
ordered to give notice.