Judge: Katherine Chilton, Case: 22STCP01224, Date: 2022-08-09 Tentative Ruling
Case Number: 22STCP01224 Hearing Date: August 9, 2022 Dept: 25
PROCEEDINGS: PETITION
TO RELEASE PROPERTY FROM MECHANIC’S LIEN
MOVING PARTY: Petitioners
Prince and Alison Jones, Trustees of the Jones Trust
RESP. PARTY: None
PETITION TO RELEASE PROPERTY FROM MECHANIC’S LIEN
(Civ. Code § 8480, et seq.)
TENTATIVE RULING:
Petitioners Prince and Alison Jones’s Petition to Release
Property from Mechanic’s Lien is
CONTINUED TO SEPTEMBER 12, 2022 at 10:00 a.m. in Department 25 at the SPRING
STREET COURTHOUSE. At least 16 court
days before the next scheduled hearing, Petitioners must file and serve
supplemental papers addressing the errors discussed herein. Failure to do so
may result in the Petition being placed off calendar or denied.
SERVICE:
[X] Proof of Service Timely Filed (CRC,
rule 3.1300) OK
[X] Correct Address (CCP §§ 1013, 1013a)
OK
[X] At least 15 Days Lapsed (Civ. Code §
8486(b)) OK
[X] Correct Manner of Service (Civ. Code
§ 8486(b)) OK
OPPOSITION: None filed as of August 4,
2022 [ ] Late [X]
None
REPLY: None filed as
of August 4, 2022 [ ] Late [X] None
ANALYSIS:
I.
Background
On April 5, 2022, Petitioners Prince and Alison Jones,
Trustees of the Jones Trust (“Petitioners”) filed the instant verified Petition
for Release of Property from Mechanic’s Lien (the “Petition”) against
Respondent Selah Roofing Corporation (“Respondent”). The Petition seeks an order releasing property
commonly known as 5989 West 75th Street, Los Angeles, CA 90045 (the “Subject
Property”) from a mechanic’s lien filed on December 2, 2021, by Respondent. (Pet. ¶¶ 1, 3.)
Petitioners filed a proof of service demonstrating
Respondent was served by mail with the Petition and Notice of Hearing on July 6,
2022, at 9501 Slauson Avenue, Pico Rivera, CA 90660. (7-6-22
Proof of Service.)
Respondent did not file a response.
II.
Legal
Standard
After a mechanic’s lien has been
recorded, “[t]he owner of property or the owner of any interest in property
subject to a claim of lien may petition the court for an order to release the
property from the claim of lien if the claimant has not commenced an action to
enforce the lien within the time provided in Section 8460.” (Civ. Code, § 8480(a).) A claimant must commence an action to enforce
a lien within 90 days of recording the lien, otherwise, “the claim of lien
expires and is unenforceable.” (Civ.
Code, § 8460(a).) However, the 90-day
time limit to commence an action to enforce a lien does not apply if there was
an agreement to extend credit and a notice of that fact was recorded within 90
days after recordation of the claim of lien or more than 90 days after
recordation of the claim of lien but before a purchaser or encumbrancer for
value and in good faith acquires rights in the property. (Civ. Code, § 8460(b).)
Civil Code § 8484 requires that the petition for release
order be verified by the petitioner and allege the following:
(a) The date of recordation of the claim of lien. A certified copy of
the claim of lien shall be attached to the petition.
(b) The county in which the claim of lien is recorded.
(c) The book and page or series number of the place in the official
records where the claim of lien is recorded.
(d) The legal description of the property subject to the claim of lien.
(e) Whether an extension of credit has been granted under Section 8460,
if so to what date, and that the time for commencement of an action to enforce
the lien has expired.
(f) That the owner has given the claimant notice under Section 8482
demanding that the claimant execute and record a release of the lien and that
the claimant is unable or unwilling to do so or cannot with reasonable
diligence be found.
(g) Whether an action to enforce the lien is pending.
(h) Whether the owner of the property or interest in the property has
filed for relief in bankruptcy or there is another restraint that prevents the
claimant from commencing an action to enforce the lien.
A property owner may not petition for a
release order until he or she gives the claimant notice demanding that the
claimant execute and record a release of lien claim at least ten days before
filing the petition. (Civ. Code § 8482.)
III.
Discussion
A. Service Requirements
“The petitioner shall serve a copy of the petition
and a notice of hearing on the claimant at least 15 days before the
hearing. Service shall be made in the
same manner as service of summons, or by certified or registered mail, postage
prepaid, return receipt requested, addressed to the claimant as provided in Section
8108.”
(Civ. Code § 8486(b).) Civil Code
§ 8108 provides addresses at which a respondent must be served, depending on
the title of the person to be served.
For example, a claimant should be served at the address on the
“claimant’s contract, preliminary notice, claim of lien, stop payment notice…
[etc.].” (Civ. Code § 8108(e).) The petitioner bears the burden of proving
that he or she complied with service and date for hearing requirements. (Civ. Code. § 8488(a).)
Respondent was served with
Petition and Notice of Hearing on July 6, 2022, at 9501 Slauson Avenue, Pico Rivera, CA
90660, which is the address that is listed
for Respondent on the Claim of Mechanic’s Lien filed with the County Recorder’s
Office. (7-6-22 Proof of Service;
Petition p. 10 – Ex. 2.) Service was
made through United States mail. (7-6-22
Proof of Service.)
The service requirements of Civil
Code § 8486 have been satisfied.
B. Petition
Requirements
Petitioners state that the Respondent completed all work
on their Property and they made all payments on or before April 21, 2021. (Pet. ¶ 3, 5.) However, Respondent recorded the lien on
December 2, 2021, in violation of Civil Code § 8412. (Pet. ¶ 4.)
Civil Code § 8412 requires a direct contractor to record a claim of lien
after completing its obligations in the contract and before the earlier of “(a)
[n]inety days after completion of the work of improvement” or “(b)[s]ixty days
after the owner records a notice of completion or cessation.” Petitioners state that no work was performed
after April 20, 2021, and no Notice of Completion was recorded. (Pet. ¶ 5.)
Since the lien was recorded on December 2, 2021, more than ninety (90)
days after the work was completed, the recording was not timely. Respondent has not filed an opposition.
Furthermore, on December 14, 2021, Petitioners sent Respondent a written
demand to remove the lien at Respondent’s address listed on the Claim of
Mechanics’ Lien. (Pet. ¶ 5; Ex. 3.) Petitioner contends that “Respondent is
unwilling to execute a release of its lien.”
(Pet. ¶ 5.) Subsequently,
Petitioners filed the instant verified Petition accompanied by a copy of the Claim of Mechanic’s Lien,
Document No. 20211786080, filed with the Los Angeles County Recorder’s Office
on December 2, 2021. (Pet. ¶ 3,
Verification, Ex. 2.) The Court notes
that the copy of the Claim is not certified.
(Ibid.) The Petition sets
forth the legal description of the Subject Property in Exhibit 1. (Pet. 7 – Ex. 1.) Finally, “Petitioner has not filed for relief
under any law governing bankruptcy, and there exists no other restraint to prevent
Respondent from filing to foreclose the lien.”
(Pet. ¶ 7.) Petitioners do not
state whether there has been an extension of credit or whether an action to
enforce the lien is pending. However,
since the recording of the lien was not timely, this information is not
necessary.
The Court finds that Petitioners
have satisfied all requirements of filing the instant Petition, except for
filing a certified copy of the Claim of Mechanic’s Lien. The hearing is CONTINUED, to allow
Petitioners an opportunity to submit a certified copy of the Claim of
Mechanic’s Lien.
IV.
Conclusion
& Order
For the foregoing reasons, Petitioners Prince and Alison
Jones’s Petition to Release Property from Mechanic’s Lien is CONTINUED TO SEPTEMBER 12, 2022 at
10:00 a.m. in Department 25 at the SPRING STREET COURTHOUSE. At least 16 court days before the next
scheduled hearing, Petitioners must file and serve supplemental papers
addressing the errors discussed herein. Failure to do so may result in the
Petition being placed off calendar or denied.
Moving parties are ordered to give
notice.