Judge: Latrice A. G. Byrdsong, Case: 23STCP03034, Date: 2023-12-26 Tentative Ruling
*** Please Note that the Judicial Officer Presiding in Department 25 is Commissioner Latrice A. G. Byrdsong ***
If you desire to submit on the tentative ruling, you may do so by e-mailing Dept. 25 at the Spring Street Courthouse up until the morning of the motion hearing. The e-mail address is SSCdept25@lacourt.org. The heading on your e-mail should contain the case name, number, hearing date, and that you submit. The message should indicate your name, contact information, and the party you represent. Please note, the above e-mail address is to inform the court of your submission on the tentative ruling. All other inquiries will not receive a response.
Due to overcrowding concerns of COVID-19, all parties shall make every effort to schedule a remote appearance via LACourtConnect (https://my.lacourt.org/laccwelcome) for their next hearing. The parties shall register with LACourtConnect at least 2 hours prior to their scheduled hearing time.
Case Number: 23STCP03034 Hearing Date: December 26, 2023 Dept: 25
Tentative Ruling
Commissioner Latrice A. G. Byrdsong
Department 25
Confidential – Court-Privileged Document
Hearing Date: Tuesday, December 26, 2023
Case Name: RAPID
PLUMBING v. PEGGY PIGSLEY
Case No.: 23STCP03034
Motion: Petition to Enforce Mechanic’s
Lien
Moving Party: Petitioner,
Rapid Plumbing
Responding Party: None
Notice: OK
Recommended Ruling: Petitioner Rapid Plumbing’s Petition to
Enforce Mechanic’s Lien is CONTINUED to ______________________at _______ in Department
25 at Spring Street Courthouse. Petitioner is ordered to file
supplemental papers addressing the deficiencies noted herein at least 16 court
days before the scheduled hearing. Failure to do so may result in the hearing
being placed off calendar or denied.
SERVICE:
[ ] Proof of Service Timely Filed (CRC,
rule 3.1300) NO
[X]
Correct Address (CCP §§ 1013, 1013a) OK
[X]
16/21 Court Days Lapsed (CCP §§ 12c, 1005(b)) OK
OPPOSITION: None filed as of December
13, 2023 [ ] Late [X] None
REPLY: None filed as
of December 13, 2023 [ ] Late [X] None
BACKGROUND
On August 22, 2023, Petitioner Rapid Plumbing
(“Petitioner”) brings the instant petition to enforce Mechanic’s Lien
(“Petition”) against Respondent Peggy Pigsley (“Respondent”).
No opposition has been filed. Default has not been entered
against the Respondent.
MOVING PARTY
POSITION
Petitioner seeks to enforce the
mechanic’s lien against Respondent.
OPPOSITION
No
opposition has been filed.
REPLY
No reply
has been filed.
ANALYSIS
I. Legal
Standard
To hold an enforceable lien, a claimant of a mechanic’s
lien must record the lien “before the earlier of the following times [¶] (a)
Ninety days after completion of the work of improvement. [¶] (b) Sixty days
after the owner records a notice of completion or cessation.” (Civ. Code, §
8412.) Completion occurs upon “any of the following events: [¶] (1) Actual
completion of the work improvement. [¶] (2) Occupation or use by the owner
accompanied by cessation of labor. [¶] (3) Cessation of labor for a continuous
period of 60 days. [¶] Recordation of a notice of cessation after cessation of
labor for a continuous period of 30 days.” (Civ. Code, § 8180, subd. (a).) If a
claimant does not timely commence an action “the claim of lien expires and is
unenforceable.” (Civ. Code, § 8460, subd. (a).)
II. Discussion
Petitioner claims a mechanic’s lien
for the labor or services, or equipment or materials that were furnished by
Claimant at the request of Respondent (Mechanic’s Lien ¶¶ 1-2.) The parties entered
a written contract for sewer and water line repairs on Respondent’s property
(“Project”). Actual completion of Project services occurred on May 12, 2023,
which the moving papers note was around the same time that payment became due. As
such, the Court presumes that the May 12, 2023, date is the date of completion
for the purpose of CCP § 8412. Petitioner provides the Court with a notarized
acknowledgement of Alex Itkis, who swears the truth of the matters set forth by
the Petitioner. (Alex Itkis Notary Acknowledgment.)
However, the Court finds the
following deficiencies with the Petition. First, the Petition contains no
evidence such as proof of service, that notice of the petition and summons was
served on the Respondent thus presenting the Court with a jurisdictional issue.
The Court notes that Petitioner does include a proof of service, however the
proof of service filed was for notice of intent to lien and does not satisfy
the service requirements under CRC, rule 3.1300. Second, Petitioner does not
supply the Court with proof of when the mechanic’s lien was recorded. The Court
notes that Petitioner provides the Court with a copy of the mechanic’s lien
however the document does not indicate whether it was recorded. Moreover, based
on the document Petitioner provided, Petitioner sought to have the mechanic’s
lien recorded on August 19, 2023, which is more than ninety (90) days from when
work was purported to be completed and would thus make the Petition improper
under Civil Code § 8412.
Thus, for the foregoing reasons the Court CONTINUES the
hearing on the Petition.
III. Conclusion
Petitioner’s Petition to Enforce Mechanic’s Lien is CONTINUED to
______________________ at _______ in Department 25 at Spring Street
Courthouse. Petitioner is ordered to file supplemental papers addressing the
following deficiencies: 1) proof of service indicating that Respondent was
served with notice of the petition and summons; and 2) evidence indicating when
the mechanic’s lien was properly recorded, at least 16 court days before the
scheduled hearing. Failure to do so may result in the hearing being placed off
calendar or denied.
Moving party
is ordered to give notice.