Judge: Lee S. Arian, Case: 22STCV37833, Date: 2025-02-14 Tentative Ruling
Case Number: 22STCV37833 Hearing Date: February 14, 2025 Dept: 27
SUPERIOR COURT OF
THE STATE OF CALIFORNIA
FOR THE COUNTY OF
LOS ANGELES - CENTRAL DISTRICT
|
ALEJANDRA ZUNIGA Plaintiff, vs. JOHN DOE, et al Defendants. |
) ) ) ) ) ) ) ) ) ) ) |
[TENTATIVE] LACMTA’s MSJ IS GRANTED Dept. 27 1:30 p.m. February 14, 2025 |
STS’s MSJ
Defendants
Skanska Traylor Shea, a Joint Venture (“STS”); Skanska USA Civil West
California District, Inc. (“Skanska”); Traylor Bros, Inc. (“Traylor”); and J.F.
Shea Construction, Inc. (“Shea”) move for summary judgment. However, on
February 3, 2024, Plaintiff dismissed the moving defendants. Thus, the motion
is moot.
METRO’s MSJ
Background
On
November 4, 2014, defendant Los Angeles County Metropolitan Transportation
Authority (“Metro”) hired Skanska Traylor Shea, a Joint Venture (“STS” or
“Contractor”), to design and construct an extension of the Purple Line subway
from its terminus at Wilshire/Western Station to a new Wilshire/La Cienega
station (the “Purple Line Extension Project”).
On
March 23, 2022, STS employee Alejandro Zuniga (“Decedent”) was working at the
Purple Line Extension Project worksite when he sustained fatal injuries after
being struck by the flat car of a locomotive operated by another STS employee.
Metro
now moves for summary judgment or summary adjudication, arguing that the Privette
doctrine bars liability. Metro seeks adjudication of the following causes of
action:
Undisputed Facts
·
On or about November 4, 2014, Metro
entered into Contract No. C1045 Westside Subway Extension Project, Section 1-
Design/Build (the “Contract”) with STS for STS to design and construct a heavy
rail transit subway extension of the existing Purple Line from its current
terminus at Wilshire/Western Station to a new Wilshire/La Cienega station (the
“Purple Line Extension Project”).
·
STS is the General Contractor for the
Purple Line Extension Project, which remains ongoing to date.
·
STS is a joint venture of which Skanska,
Traylor and Shea” are its members.
·
STS is a separate legal entity from
Metro.
·
Prior to the Incident, STS hired
Decedent as one of its employees to work on the Purple Line Extension Project
·
On the day and at the time of the
Incident, Decedent was employed by STS as a miner and was not an employee of
Metro.
Legal
Standard
In
reviewing a motion for summary judgment or adjudication, courts must apply a
three-step analysis: “(1) identify the issues framed by the pleadings; (2)
determine whether the moving party has negated the opponent’s claims; and (3)
determine whether the opposition has demonstrated the existence of a triable,
material factual issue.”¿(Hinesley v.
Oakshade Town Center (2005) 135 Cal.App.4th 289, 294.)
“[T]he initial burden is always on the
moving party to make a prima facia showing that there are no triable issues of
material fact.”¿(Scalf v. D. B. Log
Homes, Inc. (2005) 128 Cal.App.4th 1510, 1519.)¿A
defendant moving for summary judgment or summary adjudication “has met his or
her burden of showing that a cause of action has no merit if the party has
shown that one or more elements of the cause of action . . . cannot be
established, or that there is a complete defense to the cause of action.”¿(Code
Civ. Proc., § 437c, subd. (p)(2).)¿If
the moving party fails to carry its burden, the inquiry is over, and the motion
must be denied. (See Id.; see also Consumer Cause, Inc. v. SmileCare
(2001) 91 Cal.App.4th 454, 468.)¿Even
if the moving party does carry its burden, the non-moving party will still
defeat the motion by presenting evidence of a triable issue of material fact. (Aguilar
v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 849-50.)
To meet this burden of showing a cause of
action cannot be established, a defendant must show not only “that the
plaintiff does not possess needed evidence” but also that “the plaintiff
cannot reasonably obtain needed evidence.”¿(Aguilar,
supra, 25 Cal.4th at p. 854.)¿It
is insufficient for the defendant to merely point out the absence of evidence.¿(Gaggero
v. Yura (2003) 108 Cal.App.4th 884, 891.)¿The
defendant “must also produce evidence that the plaintiff cannot reasonably
obtain evidence to support his or her claim.”¿(Ibid.)¿The
supporting evidence can be in the form of affidavits, declarations, admissions,
depositions, answers to interrogatories, and matters of which judicial notice
may be taken.¿(Aguilar, supra, 25
Cal.4th at p. 855.)
“Once the defendant … has met that
burden, the burden shifts to the plaintiff … to show that a triable issue of
one or more material facts exists as to the cause of action or a defense
thereto.” (Code Civ. Proc., § 437c, subd. (p)(2).) The plaintiff may not merely
rely on allegations or denials of its pleadings to show that a triable issue of
material fact exists, but instead, “shall set forth the specific facts showing
that a triable issue of material fact exists as to the cause of action.”¿(Ibid.)¿“If
the plaintiff cannot do so, summary judgment should be granted.”¿(Avivi
v. Centro Medico Urgente Medical Center (2008) 159 Cal.App.4th 463,
467.)
The court must “liberally construe the
evidence in support of the party opposing summary judgment and resolve all
doubts concerning the evidence in favor of that party,” including “all
inferences reasonably drawn therefrom.”¿(Yanowitz
v. L’Oreal USA, Inc. (2005) 36 Cal.4th 1028, 1037; Aguilar, supra,
25 Cal.4th at pp. 844-45.) “On a summary judgment motion, the court must
therefore consider what inferences favoring the opposing party a factfinder
could reasonably draw from the evidence.¿While
viewing the evidence in this manner, the court must bear in mind that its
primary function is to identify issues rather than to determine issues.¿[Citation.]¿Only
when the inferences are indisputable may the court decide the issues as a
matter of law.¿ If the evidence is in conflict,
the factual issues must be resolved by trial.”¿(Binder
v. Aetna Life Ins. Co. (1999) 75 Cal.App.4th 832, 839.)¿Further,
“the trial court may not weigh the evidence in the manner of a factfinder to
determine whose version is more likely true.¿[Citation.]¿Nor
may the trial court grant summary judgment based on the court’s evaluation of
credibility. [Citation.]” (Id. at p. 840; see also Weiss v. People ex
rel. Department of Transportation (2020) 9 Cal.5th 840, 864 [“Courts
deciding motions for summary judgment or summary adjudication may not weigh the
evidence but must instead view it in the light most favorable to the opposing
party and draw all reasonable inferences in favor of that party”].)
The
Privette Doctrine
The
Privette doctrine holds that a hirer generally delegates to an
independent contractor all responsibility for workplace safety and is not
liable for injuries sustained by the contractor or its workers while on the
job.” (Gonzalez v. Mathis (2018) 12 Cal.5th 29, 40 (Gonzalez).)
“All tort duties [it] might otherwise owe [to] contract workers” like
Plaintiff, and that “[w]hatever reasonable care would otherwise have demanded
of the hirer, that demand lies now only with contractor.” (Sandoval v.
Qualcomm Inc. (2021) 12 Cal.5th 256, 283.)
Privette
Exceptions
Two exceptions are
recognized to the Privette doctrine. The court in Miller v. Roseville Lodge
No. 1293 (2022) 83 Cal. App. 5th 825, 833-34 described them as follows:
The first exception was
recognized in Hooker, supra, 115 Cal. Rptr. 2d 853 and is usually
referred to as the retained control exception. It applies if: (1) the hirer
retains control over the manner in which the contractor performs the work; (2)
the hirer actually exercises its retained control by involving itself in the
work such that the contractor is not entirely free to do the work in its own
manner; and (3) the hirer’s exercise of retained control affirmatively
contributes to the worker's injury. (Sandoval at 276-77.) Under this
exception, the hirer's delegation of tort duties to the independent contractor
can be seen as “incomplete” or “only
partial[
]” because it retains control over some aspect of the work and actually
exercises that retained control. (Id. at p. 271, 283 Cal.Rptr.3d 519,
494 P.3d 487.)
¿ The second exception was recognized in Kinsman,
supra, 37 Cal.4th 659, 36 Cal.Rptr.3d 495, 123 P.3d 931 and is usually referred
to as the concealed hazard exception. It applies if the hirer is also an owner
or possessor of land, and if “the landowner knew, or should have known, of a
latent or concealed preexisting hazardous condition on its property, the
contractor did not know and could not have reasonably discovered this hazardous
condition, and the landowner failed to warn the contractor about this
condition.” (Id. at p. 664, 36 Cal.Rptr.3d 495, 123 P.3d 931, fn.
omitted.) Under this exception, the hirer’s delegation of tort duties can be
seen as “ineffective” because the independent contractor cannot protect its
workers against a hazard it does not know about and could not reasonably
discover. (Sandoval, supra, 12 Cal.5th at 271).
Evidentiary
Ruling
The
Court overrules the Parties’ objections.
Discussion
Defendant’s
Initial Burden
Defendant
has met its initial burden. Defendant demonstrated that on or about November 4,
2014, Metro entered into a contract with STS for the Purple Line Extension
Project to design and construct a heavy rail transit subway extension of the
existing Purple Line from its terminus at Wilshire/Western Station to a new
Wilshire/La Cienega station. STS was and remains the General Contractor for the
project, which is still ongoing. (SUMF, ¶ 1.)
Under
Section 4.3 of the General Conditions provision of the contract, the Contract
identifies STS as an independent contractor of Metro and provides that STS has
the responsibility for and control over the details and means for performing
the work on the Purple Line Extension Project.
Section
4.3.2 states: “Contractor, as an independent contractor, shall have
responsibility for and control over the details and means for performing the
Work, provided that Contractor is in compliance with the terms of this
Contract.” (SUMF, ¶ 4.)
Section
24.1 further provides: “Contractor shall at all times conduct its operations in
such a manner as to avoid risk of bodily harm to persons or damage to property.
Contractor shall promptly take all reasonable precautions to safeguard against
such risks and shall make regular safety inspections of its operations.
Contractor shall be solely responsible for the discovery, determination and
correction of any unsafe conditions related to Contractor’s performance of the
Work or Goods furnished and/or installed by Contractor.” (SUMF, ¶ 9.)
STS’s
Vice President, Mr. James Bailey, declared that STS controlled the details and
means of performing work at the incident site. (Bailey Decl. ¶ 9.) STS was
responsible for and had control over worksite safety at the incident site. (Id.
¶ 12.) STS had exclusive control over the worksite and the below-ground tunnel
where the incident occurred. It was responsible for safety, construction, and
work methods at the site, including the operation of the locomotive and rail
system. STS implemented, maintained, and oversaw safety programs, including
tunnel safety and locomotive operations. It had a safe work plan in place for
locomotive operation and controlled the means and methods of the work performed
by Decedent, his crew, and the locomotive operator. (Id. ¶ 21.) Plaintiff
received workers’ compensation from STS. (Id. ¶ 22.)
Defendant
has met its initial burden by demonstrating that STS is an independent
contractor hired to construct the Purple Line Extension Project. Plaintiff was
an employee of STS and was receiving workers’ compensation from STS. Defendant
has established that the Privette
presumption applies, barring any exceptions. Notably, Plaintiff does not
dispute the applicability of the Privette
doctrine in opposition but instead argues that the retained control exception
applies.
There
are two exceptions to the Privette doctrine, concealed hazard and
retained control. Plaintiffs did not allege concealment in the FAC. Therefore,
Defendant need not address this exception as it was not raised in the
complaint. Plaintiff’s opposition further clarifies that the dispute between
the parties concerns the retained control exception.
With
respect to the retained control exception, Defendant has provided sufficient
evidence, including the contract between STS and Metro and the declaration of
STS Vice President James Bailey, demonstrating that STS retained control over
the means and methods of the work performed by Decedent, his crew, and the
locomotive operator. STS also maintained control over the safety of the subject
location and the locomotive, while Metro did not exercise actual control over
the site. Accordingly, Defendant has met its initial burden.
Triable
Issue of Fact
The
Hooker exception includes “three key concepts: retained control,
actual exercise, and affirmative contribution.”¿
(McCullar v. SMC Contracting, Inc. (2022) 83 Cal.App.5th 1005,
1014 (McCullar), citing, Sandoval, supra, 12 Cal.5th at p.
274, 283 (emphasis added.); “The Hooker exception to Privette is
triggered only when all three of these concepts—retained control, actual
exercise, and affirmative contribution—are satisfied.” (McCullar, supra, 83
Cal.App.5th at 1015.)¿
This
means Plaintiff must do more than merely show retained control in an abstract
sense through contractual provisions; Plaintiff must establish that Defendant
actually exercised control in practice and that such exercise affirmatively
contributed to the incident. The court in Sandoval
explains that “[u]nlike
‘retained control,’ which is satisfied where the hirer
retains merely the right to become so involved, ‘actual exercise’
requires that the hirer in fact involve itself” (Sandoval, supra,
12 Cal.5th at p. 283.) “such as by directing the manner or methods in which the
contractor performs the work; interfering with the contractor's decisions
regarding the appropriate safety measures to adopt; requesting the contractor
to use the hirer's own defective equipment in performing the work; contractually
prohibiting the contractor from implementing a necessary safety precaution; or
reneging on a promise to remedy a known hazard”
(Gonzalez, supra, 12 Cal.5th at 47; see also Hooker, supra,
27 Cal.4th at p. 209 [“ ‘The mere failure to exercise a power to compel the
subcontractor to adopt safer procedures does not, without more, violate any
duty owed to the plaintiff.’ ”]).
Plaintiff
relies on contractual provisions within Metro’s Construction Safety
and Security Manual and Metro’s contract with STS
to argue that Metro exercised control over the worksite and affirmatively
contributed to the incident. These contracts require STS to comply
with Metro’s safety policies, including submitting an Injury
and Illness Prevention Program (IIPP) for Metro’s approval.
Metro retained oversight authority,
assigning personnel such as a Construction Safety Manager
and Resident
Engineer
to monitor compliance, report unsafe conditions, and oversee STS’s safety
management. Additionally, Metro’s contract mandates that STS safety
representatives be approved by Metro,
with work required to halt if no approved representative is present. The
contract also includes mandatory safety training for STS
employees and subcontractors, along with protocols for worksite
safety compliance. Plaintiff contends these provisions demonstrate Metro’s
retained control over safety operations and its involvement in day-to-day
safety decisions at the worksite.
However,
these provisions largely establish oversight and compliance
monitoring, rather than actual exercise of control
over the specific methods and means of work in a manner that affirmatively
contributed to the incident. “The affirmative contribution requirement can be
satisfied only if the hirer in some respect induced — not just failed to
prevent — the contractor's injury-causing conduct.” Sandoval v. Qualcomm Inc.,
(2021) 12 Cal.5th 256, 277. (See, e.g., Kinney , supra , 87 Cal.App.4th
at p. 36 [requiring that the hirer "induc[e] [the contractor's] injurious
action or inaction through actual direction, reliance on the hirer, or
otherwise"]; McKown v. Wal-Mart
Stores, Inc. (2002) 27 Cal.4th 219, 225 [finding affirmative contribution
where hirer "requested" that contractor use faulty equipment, thus at
least in part inducing the contractor's decision to use it].) It is not enough
for the hirer's exercise of control to incidentally give the hirer the
opportunity to prevent the contractor's injury-causing conduct. (See Hooker,
supra, 27 Cal.4th at p. 209 [finding no affirmative contribution where the
onsite hirer had the authority and opportunity to stop the contractor from
allowing traffic across the overpass, but did not induce the contractor to
allow such traffic — the hirer merely "permitted " the traffic].)
There
is an exception under Ray v. Silverado Constructors
(2002) 98 Cal.App.4th 1120, where the court found that a hirer may retain
control in circumstances where it fails to act.
In Ray,
the defendant’s contract prohibited the independent contractor from erecting
barricades without the defendant’s prior written permission. Because the
contractor’s employees were prevented from independently closing the road when
hazardous conditions arose, the defendant’s failure to act—specifically, not
closing the road despite the hazardous conditions—was deemed an affirmative
contribution to the decedent's injury. This case underscores that retained
control requires more than general oversight; it must reflect the hirer’s
exclusive authority over safety decisions in a way that directly impacts the
injury.
Aside
from Plaintiff’s allegations of control in the abstract, Plaintiff has failed
to demonstrate how Metro affirmatively contributed
to the safety measures or the lack thereof that led to the incident.
Specifically, Plaintiff has not shown that Metro supplied the flatcar to STS
or that Metro promised or retained exclusive control
over track visibility, including the presence of a brakeman. Plaintiff has
provided no testimony, declaration, or documents
showing that Metro promised to provide a brakeman or improve
track visibility but failed to do so. Moreover, Plaintiff
has offered no evidence that Metro held exclusive control
over track visibility, the appointment of a brakeman, or that STS sought to
implement these safety measures but was denied the opportunity by
Metro.
As
to the absence of lights or reflectors on the end of the train (flatcar and/or
muck car), Plaintiff cites Metro’s Red Tag Procedure as evidence of Metro’s exclusive
control over worksite equipment.
Metro’s
Red Tag Procedure provides:
All
equipment, tools, or other items used to complete the work are subject to
periodic inspection by Metro. Any item of the contractor that is rejected as
not conforming to paragraph 1.5.B of this manual, the manufacturer’s
recommendations, or applicable ANSI standards, and presents a potential for
injury when used as directed by the manufacturer, shall be “Red Tagged” by
Metro Construction Safety Staff. The tag will be dated and signed and will note
the unsafe condition.
Any
item so tagged shall not be used until the condition noted on the tag has been
corrected and the tag has been removed by the person who has signed and
attached the tag. Any employee who ignores, removes, damages, or otherwise
tampers with a Metro “Red Tag” shall immediately be removed from the project by
the contractor and shall not return to the project without the written
permission of the Metro Director, Construction Safety, or Construction Safety
Manager.
A
Metro “Red Tag” is considered the equivalent of a Notice of Suspension of Work
for the particular equipment, tools, or other item so tagged. Any violation of
the provisions of this section shall be considered a violation of the Special
Circumstances Special Provision, if included in the Contract, and the violation
may result in the penalties described in the Special Circumstances Special
Provision.
Plaintiff
argues that Metro affirmatively undertook the exclusive responsibility
of inspecting and determining which equipment, tools, or other items were
unsafe for use at the worksite. However, the procedure merely provides
a mechanism for Metro’s inspection and does not prohibit contractors from
identifying, repairing, or modifying defective or unsafe equipment on their own.
The Red
Tag Procedure does not establish exclusive control over the flatcar or the
decision to equip it with lights or reflectors.
Unlike
the scenario in Ray v. Silverado Constructors (2002) 98 Cal.App.4th
1120, where the defendant explicitly prohibited the contractor from erecting
barricades without prior written approval, the Red Tag Procedure does not
prohibit STS from addressing or correcting safety issues on its own initiative.
In Ray, the independent contractor’s inability to take action due to the
hirer’s retained control directly contributed to the injury. Here, STS was not
prohibited from identifying or fixing the absence of lights or reflectors on
the flatcar under Metro’s Red Tag Procedure.
Plaintiff
argues that STS knew or should have known about the lack of lights or
reflectors, citing OSHA violations spanning multiple years. However, under the
applicable case law, this is not relevant unless Plaintiff can show that STS
attempted to remedy the issue but was prevented from doing so by Metro,
or that Metro
promised to fix the issue but failed to follow through.
Without such evidence, the alleged OSHA violations do not establish retained
control or affirmative contribution by Metro.
Conclusion
Overall,
the evidence provided by Plaintiff establishes only general contractual
obligations, which at most indicate Metro’s right to become involved but do not
demonstrate actual exercise of control. As clarified in Sandoval, actual
exercise requires the hirer to actively involve itself in the contractor’s work
in a manner that affirmatively contributes to the injury. Sandoval also
outlines specific scenarios where actual exercise occurs, such as interfering
with the contractor’s safety decisions or preventing the contractor from taking
necessary precautions.
Plaintiff
attempted to rely on Ray by arguing exclusive control, but the evidence
does not support this claim. Plaintiff has not shown that Metro retained
exclusive authority over the safety measures at issue or that STS attempted to
implement safety precautions but was blocked by Metro.
Accordingly,
the motion for summary judgment is granted.
Continuance
Plaintiff’s counsel requests a
continuance declaring that additional discovery is necessary, including but not
limited to depositions of Metro’s agents and employees with knowledge
regarding: (1) the incident itself, (2) the subject project, (3) Metro’s
contract, (4) Metro’s responsibilities with respect to the contract, including
control, ownership, and management over the subject site and project, and (5)
the deposition of the Cal/OSHA investigator, scheduled for February 4, 2025.
Under CCP § 437c(h), a
continuance requires an affidavit showing that:
1. The facts to be
obtained are essential to opposing the motion;
2. There is reason
to believe such facts exist; and
3. There is a valid
reason why additional time is needed to obtain these facts. (Cooksey v.
Alexakis (2004) 123 Cal.App.4th 246, 254.)
The purpose of the affidavit required by
Code of Civil Procedure section 437c, subdivision (h) is to inform the court of
outstanding discovery necessary to oppose the summary judgment motion. “It is
not sufficient under the statute merely to indicate further discovery or
investigation is contemplated. The statute makes it a condition that the party
moving for a continuance show ‘facts essential to justify opposition may
exist.’” (Cooksey v. Alexakis (2004) 123 Cal.App.4th 246, 255.)
Here,
Plaintiff’s declaration fails to meet this standard. The declaration only lists
broad categories of discovery, such as depositions of Metro’s personnel and the
Cal/OSHA investigator, but fails to explain how these depositions would provide
specific facts necessary to oppose summary judgment. Plaintiff does not
articulate how this additional discovery would establish that Metro actually
exercised control or affirmatively contributed to the incident, which is the
critical issue under Sandoval v. Qualcomm and Hooker v. Department of
Transportation.
Furthermore, Plaintiff’s discovery
requests focus on contractual provisions and general oversight authority, but
the Court has already found that contractual oversight alone is insufficient to
establish actual exercise of retained control. The determinative issue is
Metro’s actual involvement in the specific means and methods of STS’s work in a
way that affirmatively contributed to the incident, yet Plaintiff’s requested
discovery does not directly address this issue.
Additionally, this case was filed in
2022, and Plaintiff has had ample opportunity to obtain depositions and other
relevant evidence. Given the voluminous evidence already presented, the Court
has determined that sufficient discovery has been conducted.
Due to the deficient affidavit, the
Court’s determination that Plaintiff has already conducted sufficient
discovery, and Plaintiff’s failure to identify specific evidence necessary to
justify opposition, the request for a continuance is denied.
Parties
who intend to submit on this tentative must send an email to the Court at
SSCDEPT27@lacourt.org indicating intention
to submit on the tentative as directed by
the instructions provided on the court’s website at www.lacourt.org. Please be advised that if you submit on the
tentative and elect not to appear at the hearing, the opposing party may
nevertheless appear at the hearing and argue the matter. Unless you receive a submission from all
other parties in the matter, you should assume that others might appear at the
hearing to argue. If the Court does not
receive emails from the parties indicating submission on this tentative ruling
and there are no appearances at the hearing, the Court may, at its discretion,
adopt the tentative as the final order or place the motion off calendar.
|
|
|
|
|
Hon. Lee S. Arian Judge of the Superior Court |