Judge: Mark A. Young, Case: 22SMCV02209, Date: 2025-05-07 Tentative Ruling
Case Number: 22SMCV02209 Hearing Date: May 7, 2025 Dept: M
CASE NAME: Massara, et al., v. KFG
Properties, LLC, et al.
CASE NO.: 22SMCV02209
MOTION: Demurrer to the First Amended
Cross-Complaint
HEARING DATE: 5/7/2025
LEGAL STANDARD
A demurrer for sufficiency tests whether
the complaint states a cause of action. (Hahn v. Mirda (2007) 147
Cal.App.4th 740, 747.) When considering demurrers, courts read the allegations
liberally and in context. In a demurrer proceeding, the defects must be
apparent on the face of the pleading or via proper judicial notice. (Donabedian
v. Mercury Ins. Co. (2004) 116 Cal.App.4th 968, 994.) A demurrer tests the
pleadings alone and not the evidence or other extrinsic matters. Therefore, it
lies only where the defects appear on the face of the pleading or are
judicially noticed. (CCP §§ 430.30, 430.70.) At the pleading stage, a plaintiff
need only allege ultimate facts sufficient to apprise the defendant of the
factual basis for the claim against him. (Semole v. Sansoucie (1972) 28
Cal. App. 3d 714, 721.) A “demurrer does not, however, admit contentions,
deductions or conclusions of fact or law alleged in the pleading, or the
construction of instruments pleaded, or facts impossible in law.” (S. Shore
Land Co. v. Petersen (1964) 226 Cal.App.2d 725, 732, internal citations
omitted.)
A special demurrer for uncertainty is
disfavored and will only be sustained where the pleading is so bad that
defendant cannot reasonably respond—i.e., cannot reasonably determine what
issues must be admitted or denied, or what counts or claims are directed
against him/her. (CCP § 430.10(f); Khoury v. Maly’s of Calif., Inc.
(1993) 14 Cal.App.4th 612, 616.) Moreover, even if the pleading is somewhat
vague, “ambiguities can be clarified under modern discovery procedures.” (Ibid.)
Any party, within the time allowed to
respond to a pleading may serve and file a notice of motion to strike the whole
or any part thereof. (CCP § 435(b)(1); Cal. Rules of Court, Rule 3.1322(b).)
The court may, upon a motion or at any time in its discretion and upon terms it
deems proper: (1) strike out any irrelevant, false, or improper matter inserted
in any pleading; or (2) strike out all or any part of any pleading not drawn or
filed in conformity with the laws of California, a court rule, or an order of
the court. (CCP §§ 436(a)-(b); Stafford v. Shultz (1954) 42 Cal.2d 767,
782 [“Matter in a pleading which is not essential to the claim is surplusage;
probative facts are surplusage and may be stricken out or disregarded”].)
“Liberality in permitting amendment is
the rule, if a fair opportunity to correct any defect has not been given.” (Angie
M. v. Superior Court (1995) 37 Cal.App.4th 1217, 1227.) It is an abuse of
discretion for the court to deny leave to amend where there is any reasonable
possibility that plaintiff can state a good cause of action. (Goodman v.
Kennedy (1976) 18 Cal.3d 335, 349.) The burden is on plaintiff to show¿in
what manner¿plaintiff can amend the complaint, and¿how¿that
amendment will change the legal effect of the pleading.¿(Id.)
ANALYSIS
Cross-Defendants LC
Engineering Group Inc. and Calwest Geotechnical demurs and moves to strike the
First Amended Cross-Complaint (FACC) filed by Cross-Complainants KFG Properties
LLC (KFG), Northstar Development & Construction, Inc. (Northstar), and
Klodian Gjoka (Gjoka).
Certificate of Merit (CCP § 411.35)
In both motions, Cross-Defendants
assert that the FACC fails to state a claim and should be stricken because Cross-Complainants
failed to comply with Code of Civil Procedure (CCP) section 411.35. Cross-Defendants
assert that a Certificate of Meritorious Cause was not filed prior to the
service of the Cross-Complaint on any Cross-Defendant and was only recently
filed nearly 18 months after the initial filing of the Cross-Complaint. CCP
section 411.35, in relevant part, provides:
(a)
In every action, including a cross-complaint for damages or indemnity, arising
out of the professional negligence of a person holding a valid architect's
certificate … or of a person holding a valid registration as a professional …
or a person holding a valid land surveyor's license … on or before the date of
service of the complaint or cross-complainant on any defendant or
cross-defendant, the attorney for the plaintiff or cross-complainant shall file
and serve the certificate specified by subdivision (b).
(b)
A certificate shall be executed by the attorney for the plaintiff or
cross-complainant declaring one of the following:
(1)
That the attorney has reviewed the facts of the case, that the attorney has
consulted with and received an opinion from at least one architect,
professional engineer, or land surveyor who is licensed to practice and
practices in this state or any other state, or who teaches at an accredited
college or university and is licensed to practice in this state or any other
state, in the same discipline as the defendant or cross-defendant and who the
attorney reasonably believes is knowledgeable in the relevant issues involved
in the particular action, and that the attorney has concluded on the basis of
this review and consultation that there is reasonable and meritorious cause for
the filing of this action. The person consulted may not be a party to the litigation.
The person consulted shall render his or her opinion that the named defendant
or cross-defendant was negligent or was not negligent in the performance of the
applicable professional services.
(2)
That the attorney was unable to obtain the consultation required by paragraph
(1) because a statute of limitations would impair the action and that the
certificate required by paragraph (1) could not be obtained before the
impairment of the action. If a certificate is executed pursuant to this
paragraph, the certificate required by paragraph (1) shall be filed within 60
days after filing the complaint.
(3)
That the attorney was unable to obtain the consultation required by paragraph
(1) because the attorney had made three separate good faith attempts with three
separate architects, professional engineers, or land surveyors to obtain this
consultation and none of those contacted would agree to the consultation.
[…]
(g)
The failure to file a certificate in accordance with this section shall be
grounds for a demurrer pursuant to Section 430.10 or a motion to strike
pursuant to Section 435.”¿
(CCP § 411.35.)
Here, Cross-Complainants filed their
initial Cross-Complaint on June 30, 2023. No certificate of merit was filed
with the Cross-Complaint, or within 60 days thereafter. It was not until
November 13, 2024, that Cross-Complainants filed their FACC with a supporting Certificate
of Merit.
Cross-Complainants’ submission of the
Certificate of Merit contemporaneously with the FACC cured their failure to
file the Certificate within 60 days of their initial Cross-Complaint. A party can
cure these defects with the Certificate as long as the
Certificate is filed with an amended pleading, within the applicable statute of
limitations period. (See Price v. Dames & Moore (2001)
92 Cal.App.4th 355, 358-362 (failure to file a timely Certificate with an original
complaint may be cured by filing the Certificate with an amended complaint.) In
Price, after failing to file a certificate with the initial complaint in
March 1998, Price filed a Certificate of merit on March 15, 1999, an amended
certificate the next day, and a first amended complaint on March 25, 1999. On that
record, the court found that sustaining a demurrer without leave was in error. “Since
a certificate was on file before the first amended complaint was served, Price
cannot be faulted for untimeliness… [¶] [B]y granting leave to file an amended
complaint the court can give the plaintiff an opportunity to fully comply with
the statutory requirements for filing a certificate of merit.” (Id., at 359-360.)
Although the Certificate in Price was filed outside of the 60-day period
following the filing of the initial complaint and was substantively defective
(as it was not signed by plaintiff’s counsel of record), the Price court
still held that the defects were curable and the trial court should have permitted
leave to amend.
In
Curtis Eng’g Corp., the court of appeal found that a certificate filed after
expiration of the statute of limitations and more than 60 days after
filing the original pleading cannot “relate back” to the filing of the original
pleading and thus requires dismissal. (Curtis Eng'g Corp. v. Superior Ct.,
(2017) 16 Cal. App. 5th 542, 545, 548-551.) There, a crane operator was injured
in May 2014 when his crane tipped over. (Id., at 545.) The crane
operator filed his original complaint in May 2016 against an engineer, without
filing a Certificate. (Id.) In December 2016, the crane operator filed
and served a first amended complaint which included a certificate. (Id.)
The trial court overruled the engineer’s demurrer, holding that amended
pleading, along with the attached Certificate, related back to the original
complaint. The court of appeal found this to be an error, reasoning that the two-year
statute of limitations applicable to the negligence cause of action had expired
seven months before the filing of the certificate, and the 60-day period for
filing a certificate under section 411.35(b)(2) expired about five months
before the filing of the certificate. (Id., at 548-551.) The Curtis
Eng’g Corp court further observed that this defect could not be cured by the
application of the relation-back doctrine. The doctrine would essentially enable
a plaintiff to file the certificate at any time during a suit and completely
undermine the purpose of the Certification statute. (Id.) The court thus
issued a writ instructing the trial court to sustain the demurrer without leave
to amend.
Here, Cross-Defendant
does not address whether the Certificate of Merit filed in this action on
November 13, 2024, was filed outside of the applicable statute of limitations period.
Thus, the defect was curable. Accordingly, Cross-Defendant’s demurrer cannot be
sustained, and the motion to strike cannot be granted for Cross-Complainants’ failure
to comply with section 411.35.
Demurrer- Negligence, Duty
The elements of
negligence are a duty the defendant owes to the plaintiff, a breach of that
duty by the defendant, a causal connection between the breach and the
plaintiff's injury, and actual injury. (Williams v. Beechnut Nutrition Corp.
(1986) 185 Cal.App.3d 135, 141.) In California, negligence may be pleaded
in general terms. (Landeros v. Flood (1976) 17 Cal.3d 399, 407-408.)
Cross-Defendants assert that they owe no tort duties to Cross-Complainants
under the pled facts because Cross-Complainants were engaged in the project to
sell the property as a commercial enterprise, and that none of the Cross-Complainants
are ultimate purchasers/owners of the subject property for residential
purposes. Cross-Defendants posit no authority which would hold that the FACC
fails to state a claim. Instead, Cross-Defendants cite a case where a subcontractor
was dismissed at summary judgment after showing that there was no dispute of
material fact concerning the imposition of a duty. (Weseloh Family Ltd.vs.
K.L. Wessel Construction Co. (2004) 125 Cal.App.4th 152; see Lynch v.
Peter & Associates, Engineers, Geologists, Surveyors, Inc. (2024) 104
Cal.App.5th 1181 [summary judgment reversed where firm
owed property owner a duty of care to perform its inspection with skill
expected of professional in its position, even though firm was not in
contractual privity with property owner]; Beacon Residential Cmty. Assn. v.
Skidmore, Owings & Merrill LLP (2014) 59 Cal. 4th 568 [reversing a
sustained demurrer; despite a lack of privity, architects owed a duty to
homeowners for construction design defects after balancing the Biakanja/Bily
factors].)
Weseloh
is distinguishable from the instant case. In Weseloh, the designers of a
retaining wall (Randle and Owen) produced undisputed evidence showing
they did not owe the Weseloh plaintiffs (owners of the subject property) or
Wessel (the general contractor hired to construct a car dealership) a duty with
respect to designing the subject retaining walls. (Weseloh, supra, 125 Cal.App.4th at 164.) There, Randle and Owen produced
undisputed evidence that (1) the Weseloh plaintiffs contracted with Wessel to
construct automobile dealership facilities at the property; (2) Randle worked
for Sierra; (3) Sierra built the retaining walls at the project; (4) a portion
of the retaining walls failed; (5) neither Randle nor Owen had a “role in the
construction” of the retaining walls; (6) neither Randle nor Owen entered into
a contract with the Weseloh plaintiffs; (7) neither Randle nor Owen entered
into a contract with Wessel; and (8) neither Randle nor Owen was ever
compensated by the Weseloh plaintiffs or Wessel for any work performed for the
project. (Id.) The Weseloh court then examined the plaintiffs’ evidence,
and found that the evidence failed to demonstrate: (1) Randle and Owen's design
was primarily intended to affect the Weseloh plaintiffs and Wessel; (2) the
closeness of the Weseloh plaintiffs' and Wessel's injury to Randle and Owen's
conduct; (3) any moral blame implicated by Randle and Owen's conduct; or (4)
how, by imposing expanded liability on design engineers under similar
circumstances, future harm would be prevented. (Id. at 167-172.)
Subsequent cases have
repeatedly held that the holding in Weseloh is limited to its specific
factual circumstances. Weseloh itself expressly warned:
“In
light of the Weseloh plaintiffs and Wessel's failure to carry their burden
under Code of Civil Procedure section 437c, subdivision (p)(2), the trial court
properly concluded Randle and Owen did not owe them a duty of care. Our
holding should not be interpreted to create a rule that a subcontractor who
provides only professional services can never be liable for general negligence
to a property owner or general contractor with whom no contractual privity
exists. There might be a set of circumstances that would support such a duty,
but it is not presented here.”
(Id.
at 173.) The court in Lynch echoed this warning: “we
were very clear that Weseloh should 'not be interpreted to create a rule
that a subcontractor who provides only professional services can never be
liable for general negligence to a property owner... with whom no contractual
privity exists.' We found it altogether conceivable that 'a set of
circumstances that would support such a duty' could exist. And here we have
such a case." (Lynch, supra, 104 Cal.App.4th at 1193, citations
omitted.)
Similarly,
the Beacon court found a duty to third party homeowners at the pleading
stage, despite the duty analysis in Weseloh. (Beacon, supra, 59
Cal.4th at 586-587.) The Beacon court distinguished Weseloh,
emphasizing the differences between a demurrer and summary judgment. “In the
present case, which is before us on demurrer, no similar causation problem
confronts us. According to the complaint, defendants approved the use of
defective windows and designed a defective ventilation system, all of which
created conditions that made the homes uninhabitable for portions of the year.
The complaint sufficiently alleges the causal link between defendants'
negligence and plaintiff's injury that was lacking in Weseloh.”
(Id. at 587.) The Beacon court saw Weseloh’s limited holding as “merely
suggest[ing] that an architect's role in a project can be so minor and so
subordinate to the role or judgment of other design professionals as to
foreclose the architect's liability in negligence to third parties.” (Id.)
Turning to the allegations here, the FACC establishes facts
which support the imposition of a duty of care. KFG owned the Subject Property
located at 6325 Malibu Park Lane in Malibu, California 90265. (FACC ¶ 25.) Northstar
was contracted to build, and did build, a home on the Subject Property. (¶ 26.)
KFG contracted with and retained Vitus to
help obtain permits and approval from the City of Malibu for the construction project.
(¶ 27.) Vitus’s job duties included:
• Reviewing geo/soils requirements with project structural
engineer.
• Generate construction documents based on compliance with city
reviews and
geotechnical requirements.
• Coordinate preparation of site plans and building sections as
required by project
geologist, soils engineer, septic design specialist, civil and
structural engineers
(Id.)
Vitus subcontracted with Calwest Geotech, a division of LC
Engineering, to
perform
the geotechnical soils study/investigation at the Subject Property. (FACC ¶
28.) Calwest Geotech would prepare a geological soils report required for
approval by the City of
Malibu
to allow Northstar to build on the Subject Property. (Id.) Northstar
subcontracted with various other cross-defendants to perform construction work
on the Property. (¶ 29.) After Northstar completed the home, Plaintiffs Darren
Massara and Shaun Bernier bought the Subject Property. (¶ 30.) After moving in,
Plaintiffs discovered several issues with the newly built home on the Property,
including cracks in the wall and ground, periodic flooding, sloping issues
causing separation between walls, floors, and ceilings, and cracks in the
asphalt. (¶ 31.) The issues with the Subject Property allegedly stem from
Defendants/Cross-Complainants failure to properly perform sufficient evaluation
of the soil on the Subject Property prior to building the foundation. (¶32.)
LandPhases, Inc. and KFG entered into a contract where LandPhases,
Inc. would be the geologic engineering company to perform the inspection of the
Subject Property and submit a proposal/report. (FACC ¶ 33.) As part of this
agreement between LandPhases, Inc. and KFG, there is clear indication that
Vitus was consulted regarding LandPhases, Inc.’s work on behalf of KFG. (¶ 36.)
LandPhases, Inc. recommended and confirmed Calwest Geotech would perform the
required geotechnical engineering study. (Id.)
For instance, on July 14, 2014, Calwest Geotech’s proposal to
perform geotechnical engineering investigation services at the Subject Property
was addressed to Cross-Complainant Gjoka c/o Vitus Matare and
Associates, Inc. (¶ 34.) Calwest Geotech submitted multiple Notice of Field
Observation forms to its “client” KFG from October 2016 through August 2017, regarding
the Subject Property relating to the geotechnical investigation. (¶ 35.) LandPhases,
Inc. submitted to KFG a Report of Engineering Geologic Study for the Subject
Property on October 20, 2014. (¶ 38.) Vitus and Calwest Geotech were noted and/or
cc’d as recipients of this report. (Id.) On August 23, 2017, a soils engineer,
Leonard I. Liston, for Calwest Geotech signed off on the Supervised Rough
Grading Inspection Certificate for the Subject Property. (¶42.) The
engineer verified that for the Subject
Property that “the earth fills placed…were placed upon competent and properly
prepared soil base material and compacted under my supervision and in
compliance with the requirements of the Malibu Building Code and sound
engineering practices” and the additional verification that, “where the
report(s) of an Engineering Geologist, relative to this site, has recommended
the installation off stabilization measures, such earthwork construction has
been completed in accordance with the approved design. Fill slop surfaces have
been compacted in accordance with my recommendations. Subdrains have been
property installed where required.” (Id.) There is also reference to a June 28,
2017, As-Built Report by Calwest Geotechnical. (Id.) Vitus then applied for
permits to fix the issues at the Subject Property that were overlooked and not
noted in the report submitted by Vitus’ subcontractor, Calwest Geotech, a
division of LC Engineering. (¶ 44.) Cross Complainants relied on this report.
(Id.) The City of Malibu also relied the same report to approve permits for construction
at the Subject Property. (Id.)
The FACC further alleges that the Subcontractors caused and/or
contributed to Plaintiffs’ alleged damages. (FACC ¶ 48.) Cross-Defendants are
legally responsible for said injuries and damages, and for separate and
independent harm and damages to Northstar. (Id.) Vitus, Calwest Geotech, LC
Engineering “had a duty of care” to Cross-Complainants to perform the work each
was subcontracted to do at the Subject Property for the Cross-Complainants as a
reasonable prudent contractor and/or professional engineer and within the
standards of the industry. (FACC ¶ 61.) Calwest Geotech and LC Engineering
breached their duty by failing to supervise and manage sub-contractors and
failing to investigate, inspect, and report on the geological state of the
soils at the Subject Property consistent with industry standards. (¶ 64.) As a
result, Cross-Complainants have been damaged. (¶ 65.)
At the pleading stage, and unlike at summary judgment, the Court
must take the charging allegations as true. As alleged throughout the FACC, Cross-Defendant’s
services and work was intended to benefit Cross-Complainants as the owners of
the Property. It is foreseeable that owners of a property would
be harmed if a geotechnical expert fails to investigate, inspect and report on
the geological state of the soils at a property consistent with
industry standards. Both Cross-Complainants and the City relied on the
Grading Inspection Certificate to issue certain permits and construct the
subject Home. Cross-Defendants’ allegedly negligent work would therefore risk improper
construction on Cross-Complainants’ Property, directly resulting in the claimed
damage to the property. Cross-Complainants allege both direct damage to
themselves and for indemnity of any damage suffered by Plaintiffs. Cross-Defendants’
negligent conduct is closely connected to those injuries suffered, since the negligent
work resulted in the alleged defects in the construction. The policy of
preventing future harm to homeowners would be met, since homeowners need to
rely on the specialized geotechnical skills of contractors such as
Cross-Defendants in order to safely construct their homes. The safety risks
involved in improper geotechnical reports also bolster the “moral blame” factor
against negligent geotechnical inspectors. Thus, the factors support imposition of a duty against Calwest Geotech and LC Engineering in
favor of Cross-Complainants.
Accordingly, the demurrer is OVERRULED.
Motion
to Strike - Attorneys’ Fees
Cross-Defendants move to strike the request for attorneys’ fees.
They note that the FACC sets forth no contract or statute upon which to base
the demand for attorney's fees.
Cross-Complainants do not cite any contractual or statutory
right to recover attorneys’ fees. Cross-Complainants cite allegations that they
hired Cross-Defendants to provide professional geotechnical engineering consultation
services and perform a geotechnical soils studies and investigation. (FACC ¶¶
27, 28.) They also cite allegations that Cross-Defendants were “aware” that the
agreement was for the benefit of the Cross-Complainants. (FACC ¶ 28, 63.)
Neither set of allegations show that Cross-Defendants agreed to pay attorneys’
fees or cite a statute in support of such a claim.
Cross-Complainants also cite a “proposed,” “unsigned” agreement
with CalWest Geotechnical, which contains an attorneys’ fees provision. This unalleged
contract does not support a claim for attorneys’ fees, since Cross-complainants
admit that they did not enter into this agreement with CalWest Geotechnical.
Thus, there is no reasonable probability that Cross-Complaints will successfully
plead a claim for fees. Accordingly, the motion to strike is GRANTED without
leave to amend as to the attorneys’ fees request.