Judge: Mark A. Young, Case: 23SMCV05896, Date: 2024-11-27 Tentative Ruling

Case Number: 23SMCV05896    Hearing Date: November 27, 2024    Dept: M

CASE NAME:           Goldstein, et al., v. Kanner, et al.

CASE NO.:                23SMCV05896

MOTION:                  Motion for Reconsideration;

                                    Motion to Set Aside Interim Settlement/Judgment; and

                                    Motion to Tax Costs

HEARING DATE:   11/27/2024

 

 

Legal Standard

 

Vacate Judgment

 

Code of Civil Procedure section 473(d) provides that the “court may, upon motion of the injured party, or its own motion, correct clerical mistakes in its judgment or orders as entered, so as to conform to the judgment or order directed, and may, on motion of either party after notice to the other party, set aside any void judgment or order.”

 

Reconsideration

 

A non-prevailing party may make a motion to reconsider and enter a different order under the following conditions: (1) brought before the same judge that made the order sought to be reconsidered; (2) made within 10 days after service upon the party of the notice of entry of the order (extended under CCP § 1013 for type of service); (3) based on new or different facts, circumstances or law than those before the court at the time of the original ruling; (4) supported by a declaration stating the previous order, by which judge it was made, and the new or different facts, circumstances or law claimed to exist; and (5) the motion must be made and decided before entry of judgment. (CCP, § 1008.)  

 

Tax Costs

 

In general, the “prevailing party” is entitled as a matter of right to recover costs for suit in any action or proceeding. (CCP § 1032(b); Santisas v. Goodin (1998) 17 Cal.4th 599, 606.) “Prevailing party” includes the party with a net monetary recovery, a defendant in whose favor a dismissal is entered, a defendant where neither plaintiff nor defendant obtains any relief, and a defendant as against those plaintiffs who do not recover any relief against that defendant. (CCP § 1032 (a)(4).) 

 

“Allowable costs shall be reasonably necessary to the conduct of the litigation rather than merely convenient or beneficial to its preparation.” (CCP § 1033.5(c)(2).) “If the items appearing in a cost bill appear to be proper charges, the burden is on the party seeking to tax costs to show that they were not reasonable or necessary.” (Ladas v. California State Auto. Assn. (1993) 19 Cal. App. 4th 761, 774.) On the other hand, if the items are properly objected to, they are put in issue and the burden of proof is on the party claiming them as costs. (Id.) 

 

 

 

EVIDENTIARY ISSUES

 

Plaintiffs’ objections are OVERRULED.

 

Defendants’ objections are OVERRULED.

 

Analysis

 

Defendants H. Mitchell Kanner and Lucy M. Kanner move for the following:

 

1.     Reconsideration of the Court’s ruling on plaintiffs Michael H. Goldstein and Emily S.

Blumenthal’s (together, “Plaintiffs”) application for entry of judgment based on Defendants’

defaults under the March 6, 2024 interim settlement;

           

2.     For an order vacating the interim settlement agreement or, if entered, the proposed

judgment submitted by Plaintiffs; and

 

3.     To strike the plaintiffs’ memorandum of costs (claiming $14,358.75) filed and served on June 27, 2024.

 

Since the motions were filed, the judgment was entered, and an appeal was taken. As such, most of the issues have become moot and/or the Court has lost jurisdiction to rule on the issues. The parties agree that the Court has jurisdiction to hear a single issue: whether the judgment is void under Code of Civil Procedure section 473(d). Defendants argue that the judgment is void as it includes an unenforceable penalty which bears no reasonable relation to the damages that would result from breach of the interim settlement agreement.

 

A “stipulated judgment that includes an unlawful liquidated damages provision is void and may be vacated under section 473(d).” (Vitatech Int’l Inc. v. Sporn, (2017) 16 Cal. App. 5th 796, 807.) Generally, a contractual liquidated damages provision is valid unless the party seeking to invalidate the provision establishes that it was unreasonable under the circumstances at the time the contract was made. (Civ. Code § 1671(a)-(b).) However, for cases involving residential leases, liquidated damages provisions are presumptively invalid. (Civ. Code § 1671(c).) Civ. Code § 1671(d) states: “a provision in a contract liquidating damages for the breach of the contract is void except that the parties to such a contract may agree therein upon an amount which shall be presumed to be the amount of damage sustained by a breach thereof, when, from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage.”

 

“A penalty provision operates to compel performance of an act and usually becomes effective only in the event of default upon which a forfeiture is compelled without regard to the damages sustained by the party aggrieved by the breach. The characteristic feature of a penalty is its lack of proportional relation to the damages which may actually flow from failure to perform under a contract.’ ” (Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977.)

 

A liquidated damages clause will generally be considered an unreasonable penalty “if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach. The amount set as liquidated damages must represent the result of a reasonable endeavor by the parties to estimate a fair average compensation for any loss that may be sustained. In the absence of such relationship, a contractual clause purporting to predetermine damages must be construed as a penalty. The validity of the liquidated damages provision depends upon its reasonableness at the time the contract was made and not as it appears in retrospect. Accordingly, the amount of damages actually suffered has no bearing on the validity of the liquidated damages provision.” (Vitatech, supra, 16 Cal. App. 5th at 805–06, internal citations and quotations omitted.) The court must focus on whether the amount of the judgment “reasonably relate[s] to the damages likely to arise from the breach of the stipulation, not the alleged breach of the underlying contract, because it is the breach of the stipulation that allows [the claimant] to enter judgment . . ..” (Id. at 806.) “In determining the reasonableness of a provision for liquidated damages, ‘the court should place itself in the position of the parties at the time the contract was made and should consider the nature of the breaches that might occur and any consequences that were reasonably foreseeable.’” (Id. at 808.)

 

“Absent a relationship between the liquidated damages and the damages the parties anticipated would result from a breach, a liquidated damages clause will be construed as an unenforceable penalty.” (Purcell v. Schweitzer (2014) 224 Cal.App.4th 969, 974 [stipulated judgment for nearly $60,000 constituted illegal penalty for breach of settlement agreement requiring payment of $38,000].) A contractual provision imposing such a penalty is ineffective, and the wronged party can collect only the actual damages sustained. (Ridgley, supra, 17 Cal.4th at 976-977 [loan provision that required the borrower to pay a prepayment fee equal to six months of interest if the borrower sought to prepay the loan after making late interest payments was invalid because the amount of the fee bore no reasonable relationship to the damages the parties anticipated the borrower's late interest payments would cause]; see Sybron Corp. v. Clark Hosp. Supply Corp. (1978) 76 Cal.App.3d 896, 900 [stipulated judgment for $100,000 constituted illegal penalty for failure to make timely installment payment on $72,000 settlement].)

 

In Vitatech, the court found no reasonable relationship between the damages that could have been anticipated based on their failure to pay the $75,000 settlement amount and the stipulated judgment for more than $300,000. (Vitatech, supra, 16 Cal. App. 5th at 805–806.) Vitatech had sued for breach of contract, alleging the appellants failed to pay for various products manufactured for them. On the eve of trial, the parties settled and stipulated to entry of judgment “in the full prayer of the Complaint” and Vitatech agreed to “forbear from the filing [of the stipulation for entry of judgment and to] accept, as full settlement of its claims ... the principal sum of Seventy-Five Thousand Dollars ($75,000), payable in one (1) payment on or before June 5, 2015.” (Id. at 810.) The defendants failed to make the required payment and had the judgment entered against them. (Id. at 802-803.) The defendants sought to vacate the judgment on grounds it was an unlawful penalty, but the trial court rejected their argument, holding that “the amount of the judgment did not represent a penalty; the lower amount [in the settlement] represented a discount to Defendant.” (Id. at 803.) The Vitatech court found that nothing in the stipulation or appellate record established a reasonable relationship between Appellants’ failure to pay the $75,000 settlement amount and the $303,000 judgment. (Id. at 810.)

 

The Vitatech court explained that the “the parties made no effort to anticipate the damages that might flow from Appellants’ failure to pay the settlement amount. Instead, the parties simply selected the amount Vitatech had sought as damages in the underlying lawsuit. The record, however, lacks any evidence suggesting Vitatech was likely to recover all of the damages it sought if it proceeded to trial. Moreover, we cannot conceive of any meaningful relationship between Appellants’ failure to pay the amount Vitatech agreed to accept in settlement of its disputed claims and a judgment that is more than four times that amount.” (Id. at 811.)

 

In Greentree, the Court of Appeal applied the foregoing principles to reverse a stipulated judgment. There, the plaintiff alleged a breach of contract, claiming that the defendant failed to pay $45,000 for financial services. (Greentree, supra, 163 Cal.App.4th at 498-500.) The parties settled the action before trial; defendant would pay plaintiff $20,000 in installments, and if defendant failed to make any payments, plaintiff could enter judgment for the full amount sought in the complaint, including interest and attorney fees. (Id. at 500.) In the stipulation, the parties each disclaimed any wrongdoing, fault, liability, or violation of law. (Ibid.) The defendant failed to make the first payment, and plaintiff asked the trial court to enter judgment against the defendant for more than $61,000, consisting of $45,000 in damages for breach of the financial services contract, $14,000 in prejudgment interest, and $2,000 in attorney fees and costs. (Id. at 498.) The Court of Appeal reversed, holding that the parties “did not attempt to anticipate the damages that might flow from a breach of the stipulation. Rather, they simply selected the amount [the plaintiff] had claimed as damages in the underlying lawsuit.” (Id. at 499-500.) The Court noted the dearth of information showing plaintiff’s chances of complete success on the merits. The Court held the $61,232.50 judgment bore no reasonable relationship to the range of actual damages the parties could have anticipated from a breach of the stipulation to settle the dispute for $20,000. (Id.)

 

The Greentree court explained what would have been acceptable: “the judgment would have been enforceable if it had been designed to encourage [the defendant] to make its settlement payments on time, and to compensate [the plaintiff] for its loss of use of the money plus its reasonable costs in pursuing the payment.” (Greentree, supra, 163 Cal.App.4th at 500.) The $61,000 judgment, on the other hand, was not designed to compensate plaintiff for defendant’s failure to pay the $20,000 settlement amount. Instead, it impermissibly punished the defendant for its failure to pay. The plaintiff argued the amount specified in the judgment was reasonably related to the damages plaintiff suffered based on the defendant's breach of the underlying financial services agreement. (Id. at 499-500.) The Greentree court rejected that argument because the relevant breach was the breach of the settlement stipulation, not the breach of the underlying financial services agreement. (Ibid.)

 

On the other hand, the Jade Fashion court found that canceling a settled “discount” for late payments did not constitute an unenforceable penalty or forfeiture. (Jade Fashion & Co. v. Harkham Indus., Inc. (2014) 229 Cal. App. 4th 635, 645-651.) There, a garment supplier agreed to forebear on collecting its debt and allowed a buyer to deduct $17,500 from a pre-existing $341,628 debt, contingent upon timely weekly installment payments under a repayment plan. (Id. at 639-640.) After the first two installments, Harkham did not fully and timely pay the installments. (Id. at 640) Jade Fashion asserted that the failure to timely make all of the weekly installment payments precluded it from applying the $17,500 discount to the final payment. (Id.) The Jade Fashion agreed and held that this was not an unenforceable penalty since the agreement was to forbear on collection of a debt that was indisputably due and owing. Harkham argued that the $17,500 discount was an impermissible penalty because it bore no reasonable relationship to the damages that Jade Fashion actually suffered as a result of the late payments. But unlike the stipulations at issue in cases like Greentree, the Jade Fashion agreement and continuing guaranty made clear that the parties did not enter into an agreement to compromise the original debt for a lesser amount subject to a penalty for late payment. (Id. at 649.) Instead, Harkham indisputably continued to owe Jade Fashion the original balance of $341,628.77 for the purchased goods, and that Harkham would make weekly installment payments of $25,000 “for a total amount of $341,628 until the entire balance due is paid in full.” (Id.) Thus, the agreement between Jade and Harkham was not an agreement to settle or compromise a disputed claim, rather, it was an agreement to forbear on the collection of a debt that was admittedly owed for goods that had been delivered so long as timely installment payments were made. (Id. at 648.)

 

The Settlement and Stipulated Judgment

 

The parties identify several material terms of the underlying settlement. Principally, the parties cite four provisions which required Defendant to: (1) return possession of the Property by April 30, 2024; (2) pay $16,000 of partial rent for March and April 2024; (3) participate in a non-binding mediation regarding the disputed rent; and (4) provide evidence that Plaintiffs were named as additional insured on Defendants’ liability policy.

 

The stipulated judgment provided the following material terms:

 

1. Plaintiffs shall have and recover from Defendants, jointly and severally, Two Hundred Thirty-One Thousand Four Hundred Twenty Five Dollars ($231,425.00).

2. Interest shall accrue on the sum awarded against Defendants at the legal rate of 10% per annum from the date this Judgment is entered as allowed by law until paid in full.

3. Plaintiffs are entitled to recover costs pursuant to a Memorandum of Costs to be served and filed by Plaintiffs.

4. Plaintiffs are entitled to recover from Defendants post-Judgment enforcement attorneys’ fees and costs as allowed by law and as provided by the Interim Settlement recited into the record before the Court and agreed to by all parties on March 6, 2024.      

 

The hearing record notes that the stipulated judgment would be against Defendants for unpaid rents owed under the Lease, including $69,300 (rent for Nov. 23 – Feb. 29, 2024), $577.50 per diem for each day after March 1, 2024, until surrender, plus fees and costs.

 

Reasonable Relationship

 

Defendants claim that the $231,425 judgment ($245,783 with costs) has no reasonable relationship to the range of actual damages the parties could have anticipated from a breach of the stipulation to settle the dispute. The record does not show any reasonable endeavors by the parties to estimate fair compensation for any loss that may be sustained by Plaintiffs for Defendants’ failure to return possession by April 30, 2024, to pay the partial or per diem rents, to participate in the mediation, or to name Plaintiffs as additional insureds.

 

The parties never explained or reasoned how the failure to return possession, pay $16,000.00 in partial rent, or pay the per diem for each day after March 1, 2024, could result in any figure approximating the stipulated judgment. Indeed, such failures could only reasonably result in the tens of thousands of dollars of damages, rather than the hundreds of thousands claimed and awarded by the Court. In fact, Defendants would need to overstay more than 6 months for the per diem costs to break $100,000.00. In comparison, the stipulated judgment awards Plaintiffs the disputed rent and attorneys’ fees incurred pursuant to the underlying breach of the Lease. Such damages were unambiguously incurred before the settlement agreement was reached. Moreover, they are still the subject of dispute and were not resolved by the settlement agreement.

 

There is also no apparent relationship between the stipulated judgment and any damages stemming from the failure to mediate. As Plaintiffs observed during the March 6 , 2024, hearing, Plaintiffs would be owed the amounts under the lease even if the non-binding mediation failed. The non-binding nature of the mediation also undercuts the claim. At best, the Court speculates that the parties could have anticipated Plaintiffs’ loss of time and costs associated with starting the mediation process (for example, the 50% of the mediation fees and costs that Plaintiffs expended), but there is no evidence that the parties could reasonably anticipate that this damage could reach any figure near the judgment.

 

There is also no apparent relationship between the stipulated judgment and the failure to name Plaintiffs as insureds. Plaintiffs claim that default subjects Plaintiffs to the risk of potential liability and defense costs if a personal injury or property damage claim is ever asserted against Plaintiffs (within two years for a personal injury claim, and/or within three years for a property damage claim). (Goldstein Decl. ¶ 4.) However, the record shows no reasonable estimate of the value of the risk of liability.

 

To sum, the record does not establish a reasonable relationship with the range of damages that the parties could have anticipated would flow from a breach of the interim settlement agreement and the amount of the stipulated judgment. As such, the stipulated judgment must be construed as a penalty.

 

Plaintiff does not present authority that estoppel would allow the court to enter a void judgment. The above cases found unenforceable penalties despite the fact that they involved settlements which prevented trial from moving forward. Therefore, the Court is not inclined to judicially estop Defendants from denying the stipulated judgment portion of the settlement agreement.

 

Accordingly, the judgment is void and the motion must be GRANTED.