Judge: Mark C. Kim, Case: 22LBCV00120, Date: 2022-09-20 Tentative Ruling
Case Number: 22LBCV00120 Hearing Date: September 20, 2022 Dept: S27
1. Background
Facts
Plaintiff, Ziming He filed this
action against Defendant, Shawn Khan for breach of contract and common
counts. The judicial council form
complaint is short on factual allegations, and the nature of the parties’
relationship is not clear from a review of the complaint. Plaintiff filed his complaint on
3/22/22. Defendant filed an answer and
cross-complaint on 4/20/22.
2. Motion
for Leave to File Supplemental Complaint
a.
Parties’ Positions
Plaintiff seeks leave to file a
supplemental complaint. He contends a
cause of action for foreclosure of mechanic’s lien is necessary, as Plaintiff
recorded a mechanic’s lien on 6/23/22 and served Defendant with the lien on
6/11/22.
Defendant opposes the motion. He argues the mechanic’s lien was not timely
recorded, and therefore a cause of action to foreclose on any such lien is fatally
defective and the defect could not be cured.
Plaintiff, in reply, contends the
lien was timely recorded and the action is proper.
b. Law
Governing Leave to Amend
The court may, in furtherance of
justice, and on such terms as may be proper, allow a party to amend any
pleading. (CCP §§473 and 576.) Judicial policy favors resolution of all
disputed matters between the parties and, therefore, leave to amend is
generally liberally granted. Ordinarily,
the court will not consider the validity of the proposed amended pleading in
ruling on a motion for leave since grounds for a demurrer or motion to strike
are premature. However, the court does
have discretion to deny leave to amend where a proposed amendment fails to
state a valid cause of action as a matter of law and the defect cannot be cured
by further amendment. (California
Casualty General Ins. Co. v. Superior Court (1985) 173 Cal.App.3d 274,
281.)
c. Analysis
As an initial note, Plaintiff brings
this motion pursuant to the Federal Rules of Civil Procedure. This is state court, not federal court. Therefore, the California Code of Civil
Procedure applies to the action, not the Federal Rules of Civil Procedure. CCP §473(a) permits the filing of an amended
complaint as detailed above, and the Court will analyze the motion under the applicable
California standard.
Turning to the merits of the
motion, Civil Code §8412 governs the timing of recording a mechanic’s lien, and
it provides:
A direct contractor may not enforce
a lien unless the contractor records a claim of lien after the contractor
completes the direct contract, and before the earlier of the following times:
(a) Ninety days
after completion of the work of improvement.
(b) Sixty days
after the owner records a notice of completion or cessation.
Defendant cites Howard S. Wright
Constr. Co. v. BBIC Inv’rs, LLC (2006) 136 Cal.App.4th 228, 243 to
stand for the position that when an owner anticipatorily breaches the parties’
contract by stating that no further payments will be made, the 90 days commences
running at that time. Defendant argues
Plaintiff admitted, in his complaint and declaration, that the termination took
place on 3/11/22. The lien, however, was
not recorded until 6/23/22, more than 90 days later. Howard Wright, however, was decided based on
Civil Code §3115, which was repealed; notably, the issue in the case was whether
the lien was recorded prematurely, not whether it was recorded too late.
Plaintiff argues, in opposition to
the motion, that Civil Code §3092 governs, and makes clear that the time period
commences running after 60 continuous days of work cessation. §3092, however, was also repealed in
2012.
Both parties rely on previously
repealed statutes and/or case law construing those statutes. The Court finds the currently operative
section, §8412, requires one of two events to occur before the 90 days
commences running: either the work is completed, or the owner records a notice of
completion or cessation. Neither of
those events is alleged to have occurred in this case, and therefore there is
no evidence that the 90 days has run.
The motion for leave is granted. The Court asks Plaintiff, in compliance with
the Code of Civil Procedure, to file a First Amended Complaint, rather than a supplemental
complaint. The FAC must be one document
that includes all causes of action pled by Plaintiff against Defendant. Plaintiff must do so within twenty days. Defendant must file a responsive pleading
within the statutory time thereafter.
Plaintiff is ordered to give
notice.
Parties who intend to submit
on this tentative must send an email to the court at gdcdepts27@lacourt.org indicating intention to submit on the tentative as
directed by the instructions provided on the court website at www.lacourt.org. If the department
does not receive an email indicating the parties are submitting on the tentative
and there are no appearances at the hearing, the motion may be placed off calendar. If a party submits on the tentative, the
party’s email must include the case number and must identify the party submitting
on the tentative. If any party does not submit on the tentative, the party
should make arrangements to appear remotely at the hearing on this matter.