Judge: Mark H. Epstein, Case: 23SMCV02250, Date: 2025-01-07 Tentative Ruling
Case Number: 23SMCV02250 Hearing Date: January 7, 2025 Dept: I
The motion to continue is DENIED. Plaintiff contends that discovery had been
started but is not completed. Further,
plaintiff’s counsel’s previously scheduled surgery had to be postponed due to
an illness and is now scheduled for January 8, 2025. Counsel states that the surgery and recovery
time will impede the ability to get to trial.
Plaintiff also contends that only after an expert inspection on June 22,
2024, did plaintiff discover additional damages of over $1 million due to
improper grading and the like.
According to plaintiff, the inspection would have occurred earlier but
for defendant’s cancellation twice on the eve of the inspection. Plaintiff notes that it is filing a motion
for leave to amend to add new allegations, and the hearing is set for later
this month. In opposition, defendant
states that the delayed inspection is plaintiff’s fault and that plaintiff has
not been diligent. For example, even
taking the June 2024, inspection as potentially reasonable, plaintiff has had
the results of the inspection since then and there is no explanation for the
delay in preparing the case for trial or to prepare the experts for deposition. Further, the parties’ experts met, according
to defense counsel, back in October 2024, but still the motion was not made
until December—and the meeting would have been earlier had plaintiff provided
the defense with plaintiff’s expert’s contact information. Defense counsel also claims unfairness in
that plaintiff took defendants’ expert’s deposition months ago. In any event, defendants note, expert
discovery is nowhere near the cut off, and there remains lots of time to get
things done. In short, the defense
position is that there has been plenty of time to get the case ready for trial
and there is no need to delay further and any time crunch is due to a lack of
diligence. As to the knee surgery,
defendants argue that there is still lots of time. The surgery can go forward and counsel can
recover and the case can still be ready for trial. Finally, defense counsel does not believe
that there is good cause to continue due to any supposedly newly discovered
issues because the issues have been plain since at least June.
Trial is currently scheduled for March 17, 2025, and that
date was set in November 2023. That
means that the case, filed in May 2023, will be almost two years old by the
time of trial, and that there will have been 15 months between the time the
trial date was set and the time of trial.
In this relatively straightforward matter, that is ample time. The court is not aware of any specific discovery
that plaintiff seeks to do that it cannot do in a timely fashion. Absent such a showing, there has been no demonstration
of diligence or cause to continue the trial.
That said, if there are complications from the surgery or if the surgery
really causes plaintiff to be unable to be ready for trial, the court is open
to a continuance upon a real showing of need.
As to plaintiff’s counsel’s busy schedule, everyone has a busy
schedule. There has been no showing of
an actual conflict or why this case should be viewed as one having lower import
than plaintiff’s other matters.
That said, the court expects defendant and defense counsel
to be cooperative in discovery. The
court will not be sanguine should plaintiff seek reasonable discovery from the
defense only to have it thwarted or slow-walked due to counsel’s schedule. The court will take defense counsel at face
value that the defense wants the case to go to trial as scheduled. That will required defendant to be
cooperative. Right now, plaintiff has
not articulated any specific discovery being sought that is being unreasonably
delayed or refused due to defense counsel.
The court notes, of course, that trial continuances are
disfavored and require an affirmative showing of good cause. (Rule of Court 3.1332(c).) The court also notes that it has almost 1200
cases on its docket and it is growing by 20 each month. The court is currently setting initial trial
dates 20 months out from the CMC, and even then the court is assuming that 93%
of the cases settle or otherwise resolve.
If the court continues this case (at least unless it continues the case
to September 2026), it means that it will have to bump another case where the
parties have been diligent. The court
sees no justification in doing so, or at least none has been shown.
The court might feel differently if there were a specific
showing of discovery that needed to be done coupled with a showing of diligence
as to why it was not done earlier and why it cannot be done in the time
remaining. But there is no such showing
at present.