Judge: Mark H. Epstein, Case: 24SMCV02488, Date: 2024-10-14 Tentative Ruling
Case Number: 24SMCV02488 Hearing Date: October 14, 2024 Dept: I
The demurrers are OVERRULED.
This is a construction defect case. Plaintiff, the contractor, sues defendant,
the owner, for breach of contract. The
basic allegations are that defendant retained plaintiff to remodel defendant’s
residence. The amount of the original
contract was $169,610. The project
evolved, however, Plaintiff alleges that
the resulting change orders increased the contractual amount to be paid to
$2,783,983. Plaintiff alleges that it
has demanded payment in full but defendant still owes at least $224,270. Defendant has demurred to various causes of
action and plaintiff opposes.
At the outset, the demurrers for uncertainty are
OVERRULED. Such demurrers are disfavored
and succeed only where the complaint is so vague that no one can really even
understand what the operative allegations are.
(Butler v. Sequeira (1950) 100 Cal.App.2d 143.) That is not this case.
The meat of the demurrer is that the contract fails to
comply with Business and Professions Code section 7159, which requires that
home improvement contracts be in writing and contain certain terms and
statements. This contract was in
writing, but plaintiff concedes that there are at least some aspects of section
7159 that were not strictly followed.
However, that does not mean that the contract is void. It is merely voidable. (Asdourian v. Araj (1985) 38 Cal.3d
276; Arya Group, Inc. v. Cher
(2000) 77 Cal.App.4th 610.) The basic
purpose of this statute is to ensure that construction contracts are in writing
to protect unsophisticated owners.
Indeed, in the seminal Asdourian case, our Supreme Court noted
that it would be unjust to void a construction contract due to a violation of
this statute as that would unjustly enrich the homeowner and accordingly, even
if a contract was illegal in that it violated the statute, in a “compelling
case” it could be enforced to avoid unjust enrichment. Generally, whether to allow a party to void a
construction contract will depend on many factors, including whether the
contract was written or oral (written contracts are less likely to be voided
out, and the cases decided under this statute almost all involve oral contracts),
whether the homeowner is sophisticated, and a myriad of other factors
concerning the parties’ relationship.
Here, the violations about which defendant complains are technical—the
placement of a warning or the font size of it, for example. The court has no reason to believe—at the
pleading stage—that any statutory violation had any effect on anything. Thus, as was the case in Arya, the
matter is not well tested at this stage.
The court also notes that defendant argues that at best plaintiff is
entitled to a quantum meruit recovery rather than contract damages, which,
defendants note, is another cause of action (to which there is no
demurrer). The court is not so
sure. That depends on whether the court
will void the contract based on the particular violations alleged or whether
the court concludes that the violations were trivial and should be overlooked
in this case. Accordingly, the first and
fifth causes of action fail (the fifth cause of action being derivative of the
first). The court acknowledges that
there is some tension in allowing both a quantum meruit cause of action and a
breach of contract action to go forward.
But the court believes that the best way forward is to follow the Arya
Court’s lead. There, the court allowed a
breach of contract to go forward even though it violated the statute, but noted
(albeit in a footnote) that the contract recovery (if any) would be limited to
the amount necessary to prevent unjust enrichment. This court agrees. The court will allow the breach of contract
action to go forward, but there could well be a limit to the recovery if
enforcing the contract in its entirety would do more than avoid unjust
enrichment. There are other reasons to
do it this way. The contract will likely
have other provisions that are relevant, for example, the process for change
orders, an attorneys’ fee clause, payment timing provisions, and other
provisions that might well remain effective.
And if the 7159 breaches are truly trivial (something the court is not
now deciding), it could well be that quantum meruit and contract are the same
because it would be unjust to reduce the contract by any amount for a
trivial issue. Defendant also contends
that the breaches of the contract are not pled adequately because the entire
contract is not attached (meaning the change orders are not attached) and
neither are they adequately quoted. The
court believes that there is enough here.
Further information can be obtained in discovery.
Defendant also says that there is no cause of action for an
account stated because there is no showing that defendant ever agreed that any
particular amount was owed. It is true
that there must be an express or implied agreement between the parties as to
the amount due and a promise to pay it.
(Leighton v. Forster (2017) 8 Cal.App.5th 467.) The problem is that plaintiff alleges as much
at paragraph 11 of the complaint.
Whether the allegation is true or not is not something that can be decided
now. Therefore, the second cause of
action fails.
The third cause of action is for open book. Defendant claims that there is no allegation
that plaintiff kept a “book.” And,
again, it is true that open book requires that the creditor maintain a “book”
that shows the amounts owed as they are incurred and payments made on the
account. However, the “book” need not be
physical. It can be a ledger or it can
be in electronic form. The court
believes that the complaint, liberally read, alleges such a system, at least by
reasonable inference. Frankly, in today’s
world it is hard to imagine that defendant does not have some kind of
accounting software, and almost any such software would suffice. As such, this demurrer fails as well.
The court also notes that these causes of action are pled in
the alternative. In other words,
plaintiff understands, and the court agrees, that it cannot recover on all of
these causes of action and add the damages together.
In any event, the court believes that the complaint passes
muster. The demurrer is OVERRULED. Defendant has 30 days to answer.