Judge: Melvin D. Sandvig, Case: 22CHCV00075, Date: 2023-10-31 Tentative Ruling

Counsel wishing to submit on a tentative ruling may inform the clerk or courtroom assisant in North Valley Department F47, 9425 Penfield Ave., Chatsworth, CA 91311, at (818) 407-2247.  Please be aware that unless all parties submit, the matter will still be called for hearing and may be argued by any appearing/non-submitting parties. If the matter is submitted on the court's tentative ruling by all parties, counsel for moving party shall give notice of ruling. This may be done by incorporating verbatim the court's tentative ruling. The tentative ruling may be extracted verbatim by copying and specially pasting, as unformatted text, from the Los Angeles Superior Court’s website, http://www.lasuperiorcourt.org. All hearings on law and motion and other calendar matters are generally NOT transcribed by a court reporter unless one is provided by the party(ies).


Case Number: 22CHCV00075    Hearing Date: October 31, 2023    Dept: F47

Dept. F47

Date: 10/31/23

Case #22CHCV00075

 

SUMMARY JUDGMENT/SUMMARY ADJUDICATION

 

Motion filed on 7/21/23.

 

MOVING PARTY: Defendant State of California Department of Forestry and Fire Protection

RESPONDING PARTY: Plaintiff TNT Tanker Services, Inc.

NOTICE: ok

 

RELIEF REQUESTED: An order granting summary judgment in favor of Defendant and against Plaintiff on Plaintiff’s complaint for breach of contract and breach of the implied warranty/covenant of good faith and fair dealing.  Alternatively, Defendant seeks summary adjudication of each cause of action in Plaintiff’s complaint. 

 

RULING: The request for summary judgment is granted. 

 

SUMMARY OF FACTS & PROCEDURAL HISTORY

 

This action arises out of contractual dispute between Plaintiff TNT Tanker Services, Inc. dba Class 1 Fire (Plaintiff) and Defendant State of California Department of Forestry and Fire Protection/Cal Fire (Defendant). 

 

Plaintiff is a California business that provides water tender services.  (Separate Statement (SS) 4).  Defendant is a California agency dedicated to fire protection and stewardship over 31 million acres of California’s privately owned wildlands.  (SS 5).  To achieve its mission and operations, Defendant enters into standard supplier equipment rental agreements with numerous suppliers in the State of California.  (SS 6).  Plaintiff is one of many equipment suppliers that provide water tender services to Defendant.  (SS 7).

 

On 4/18/21, Plaintiff entered into an Emergency Equipment Rental Agreement (EERA) with Defendant for a term of 5/1/21 – 4/30/23.  (SS 8).  The EERA provides that “[s]ince the equipment needs of the State and availability of Supplier’s equipment during an emergency incident cannot be determined in advance, it is mutually agreed that, upon request of the State, the Supplier shall furnish the equipment listed herein to the extent the Supplier is willing and able at the time of order.”  (SS 9). 

 

The EERA incorporates by reference “The Hired Equipment Program Supplier Participation Manual [HEPSPM] with the same force and effect as if it were given in full text” and details the roles and responsibilities of the parties.  (SS 10).  The HEPSPM provides that the “Hired Equipment Program works to obtain those resources which exactly meet the needs of the Incident Commander at a price that is fair to the Supplier and represents a prudent expenditure of state taxpayer funds.”  (SS 11).  The “manual defines the rules and standards required of Suppliers and equipment in order to be eligible for program participation” and the “manual further includes payment rates, instructions to initiate an agreement, and guidance for what to expect during incident dispatch and assignment.”  (SS 12). 

 

The HEPSM provides that “[n]o Supplier is guaranteed any amount of business upon entering into an EERA with [Defendant].” (SS 13).  With regard to operations, the HEPSPM provides that “[Defendant] uses established internal policy to distribute assignments for incident fire suppression and support equipment” and that “Cal Fire Incident Commanders determine what equipment is needed to support an incident logistically and operationally to accomplish incident objectives; suppliers are not participants in the process of determining incident equipment needs.”  (SS 14).  The HEPSPM also contains a Supplier Code of Conduct, which provides that the supplier will immediately notify Defendant of any instances in which the supplier cannot comply with Defendant orders, as follows:

 

“4. I will promptly comply with lawful orders of Department supervision. Immediately notify CAL FIRE of any instance in which compliance with assignment requirements and/or the Hired Equipment Program Supplier Participation Manual is not possible.” (SS 15).

 

The HEPSPM also provides that operators must communicate the operational limitations of their equipment or their own ability to perform, as follows:

 

“Operators are responsible to recognize the capabilities and limits of the equipment they are operating and communicate them appropriately to CAL FIRE supervision. Operators should refuse assignments beyond the mechanical capability of the equipment or their own ability to perform.”  (SS 16).

 

Additionally, the HEPSPM provides the following when suppliers do not comply with the program:

 

“Supervising incident personnel shall take immediate action to resolve any issues by hired equipment Suppliers and/or their employees that involve safety, productivity, operational effectiveness, or are in violation of the Hired Equipment Program Supplier Participation Manual.

 

If immediate resolution is not possible the situation shall be documented in writing and sent to the Statewide Hired Equipment Coordinator, Unit Chief, and Unit Hired Equipment Coordinator for the Unit that generated EERA. The Incident Commander may release hired equipment from the incident for non-compliance issues. In this case, no payment shall be issued for return to point of hire.”  (SS 17).

 

The HEPSPM further sets forth instances when suppliers may be bypassed for assignment and the conditions when a supplier may be released from the scene, as follows:

 

“Equipment does not meet the type requirements of the request. If, after the time of order, CAL FIRE is advised by the Supplier/operator that the hired equipment will not be able to meet, or if equipment does not arrive at the incident by, the required date and time, the resource can be released and replaced by a resource that can meet the requirement. If a resource which has been released for this reason arrives at the reporting location and there is an operational need, the resource may be retained at the discretion of the Incident Commander.

 

Equipment. Upon arrival at an incident, or as soon as possible thereafter, incident personnel will inspect each piece of equipment to ensure that the vehicle and operator meet all requirements for complement, capacity, and capability, and that the vehicle and operator are in a condition to work safely.”  (SS 18).

 

The “Dixie” fire was the largest single wildfire in California recorded history, spanning several counties.  (SS 19).  The fire, which burned approximately 963,276 acres, began in the Feather River Canyon near Cresta Dam on 7/13/21 and was contained on 10/25/21.  (SS 19). 

 

On 8/5/21, Defendant called Plaintiff to service.  (SS 20).  Upon reaching the staging site, Defendant requested Plaintiff to fill its 2019 Kenworth Water Tanker with “Phos-Chek,” a fire retardant material, in order to spray the various roadways.  (SS 21).  Plaintiff’s representative objected to the request on the grounds that this was outside the scope of services contracted and beyond the mechanical capability of the equipment and the driver’s own ability to perform.  (SS 22).  Plaintiff believed that the use of Phos-Chek was incompatible with the use for which the equipment was intended, could damage the equipment, and was prohibited under the manufacturer’s warranty.  (SS 23).  Plaintiff further objected on the grounds that it was not trained in the handling and use of Phos-Chek or any other fire retardant material.  (SS 24).  Once Plaintiff objected to Defendant’s request, the Incident Commander released Plaintiff from the site.  (SS 25).  Plaintiff was paid for the day of operation.  (SS 26).

 

Plaintiff contends that Defendant breached the contract by: (1) assigning Plaintiff tasks outside the scope of water tender services contracted for, (2) ordering Plaintiff to misuse its equipment in violation of clear warnings, which would subject the equipment to significant damage, and void manufacturer’s warranty, among other things, and (3) terminating the Dixie Fire Contract without cause before the end of the Dixie Fire, releasing the 2019 Kenworth Water Tender and ordering Plaintiff to return the equipment and operator to storage facility in Castaic, California, thereby preventing Plaintiff from completing performance under the contract to meet Defendant’s water tender needs through the duration of the Dixie fire.  (SS 27).

 

Plaintiff also contends that Defendant breached its implied covenant of good faith and fair dealing under the Dixie Fire Contract by terminating the Dixie Fire Contract without cause, releasing Plaintiff’s equipment and ordering Plaintiff to return the equipment and operator without cause, thereby preventing Plaintiff Fire from performing water tender services under the contract for the duration of the Dixie fire.  (SS 28).  Plaintiff alleges that such conduct was in bad faith and in retaliation for Plaintiff’s justified refusal (1) to follow Defendant’s improper directive to perform work outside the scope of its contracted water tender services and misuse its equipment, and (2) to accept tasks that the equipment was not designed for and the operator was not trained for, among other things.  (SS 29).

 

Therefore, on 1/31/22, Plaintiff filed this action against Defendant for: (1) breach of contract and (2) breach of covenant of good faith and fair dealing.  On 7/21/23, Defendant filed and served the instant motion seeking an order granting summary judgment in favor of Defendant and against Plaintiff on Plaintiff’s complaint for breach of contract and breach of the implied warranty/covenant of good faith and fair dealing.  Alternatively, Defendant seeks summary adjudication of each cause of action in Plaintiff’s complaint.  Plaintiff has opposed the motion and Defendant has filed a reply to the opposition.

 

ANALYSIS

 

Plaintiff’s Request for Judicial Notice is denied.  (See below - Defendant’s objections to the request are sustained).

 

Defendant’s objection (no.1) to the entirety of the declaration of Douglas J. Lannon is sustained.    Based on the sustaining of Defendant’s objection to the entire Lannon declaration, Defendant’s objections (nos. 2-5) to specific portions of the declaration are moot.  

 

Defendant’s objection (no.6) to the declaration of Craig Taraello is sustained.

 

Defendant’s objections (nos. 7 and 8) to Plaintiff’s Request for Judicial Notice are sustained. 

 

A defendant may move for summary judgment on the ground that the action has no merit.  CCP 437c(a)(1).  A cause of action has no merit if one or more elements of the cause of action cannot be separately established or a defendant establishes an affirmative defense to the cause of action.  CCP 437c(o).  A defendant has met its burden of establishing a cause of action has not merit if the defendant establishes that that one or more elements of the cause of action, even if not separately pleaded, cannot be established, or that there is a complete defense to the cause of action.  CCP 437c(p)(2).  Once a defendant has met that initial burden, the burden shifts to the plaintiff to show that a triable issue of one or more material facts exists as to the cause of action or a defense thereto.  Id.  The plaintiff cannot meet its burden by relying on the allegations or denials of its pleadings but rather must set forth specific facts showing that a triable issue of material fact exists as to the cause of action or a defense thereto.

 

To prevail on a breach of contract cause of action, a plaintiff must prove: (1) the existence of a contract between plaintiff and defendant, (2) plaintiff’s performance or excuse for nonperformance of the contract, (3) defendant’s breach and (4) resulting damage to plaintiff.  Richman (2014) 224 CA4th 1182, 1186.  A covenant of good faith and fair dealing is implied in every contract.  Kransco (2000) 23 C4th 390, 400; CalFarm Ins. Co. (2005) 131 CA4th 273, 285-286.  The implied covenant does not impose substantive terms and conditions beyond those to which the contracting parties agreed.  Avidity Partners, LLC  (2013) 221 CA4th 1180, 1203-1204.  Generally, courts will enforce the breach of a contract only through contract law, except when the actions that constitute the breach violate a social policy that merits the imposition of tort remedies.  Robinson Helicopter Co., Inc. (2004) 34 C4th 979, 992.

 

Here, Plaintiff and Defendant entered an executory contract whereby Plaintiff was to provide services at Defendant’s request.  (SS 8).  Plaintiff’s acceptance of Defendant’s assignment was a condition to Defendant’s performance under the contract.  See JMR Construction Corp. (2015) 243 CA4th 571, 593; Civil Code 1437, 1582.  Here, Plaintiff’s refusal, justifiable or not, of Defendant’s assignment to fill Plaintiff’s water tanker with fire retardant excused Defendant’s further performance.  See Habitat Trust for Wildlife, Inc. (2009) 175 CA4th 1306, 1335; Britschgi (1953) 41 C2d 138, 144; Colaco (2018) 25 CA5th 1172, 1182-1183.  Once Plaintiff refused the assignment, each parties’ obligations to perform were terminated for the assignment and Plaintiff was paid for its day on site.  (SS 26). 

 

Plaintiff points to no contract term which required Defendant to reassign Plaintiff to another location and/or use its services for the duration of the Dixie Fire.  To the contrary, the contract specifically does not require Defendant to use Plaintiff’s services for any specific amount of time and provides that Plaintiff is not guaranteed any sum of business as a result of being dispatched.  (SS 9, 11, 13).  The contract specifically provides that suppliers, such as Plaintiff, do not participate in the process of determining incident equipment needs.  (SS 14).  The contract also sets forth what is to occur if a supplier cannot perform which is what occurred here.  (SS 15-16).  As such, the expert opinion of Douglas J. Lannon offered by Plaintiff to justify its refusal to accept the assignment is irrelevant to the facts of this case where Defendant’s obligation to further perform under the contract was excused once Plaintiff refused the specific assignment. 

 

Plaintiff’s  refusal to accept the assignment also constitutes a failure of consideration which excused Defendant’s performance.  A failure to perform constitutes a failure of consideration which excuses the performance of the other party.  Bliss (1947) 30 C2d 240, 248-249; Civil Code 1689(b)(4).

 

In other words, to the extent Plaintiff’s dispatch to the site created an obligation on the part of Defendant, such obligation was met when Plaintiff was paid for the day of operation after being released from the incident.  (SS 25-26).  Otherwise, pursuant to the terms of the contract, once Plaintiff refused the assignment (i.e., failed to perform), Defendant had no obligation under the contract to reassign Plaintiff, and did not breach same.  (SS 13-19).  Therefore, Plaintiff’s breach of contract cause of action fails. 

 

A breach of the covenant of good faith and fair dealing implied in a contract which relies on the same acts and seeks the same damages as a breach of contract claim may be disregarded as superfluous.  See Careau & Co. (1990) 222 CA3d 1371, 1395.  As noted above, in order to recover in tort for a breach of contract, the breach must violate some social policy such as fraud or a party intentionally breaches intending or knowing that such conduct will cause severe, unmitigable harm in the form of mental anguish, personal hardship, or substantial consequential damages.  See Erlich (1999) 21 C4th 543, 553-554; Robinson Helicopter Co., Inc., supra.

 

Here, Plaintiff’s breach of the implied covenant of good faith and fair dealing cause of action is essentially the same as its breach of contract claim.  (SS 26-29).  As set forth above, the evidence shows that Defendant’s further performance under the contract was excused (i.e., Defendant did not breach the  contract).  Even if Defendant’s performance was not excused or could be deemed a breach of the contract, Plaintiff has not shown that Defendant’s conduct deviated from socially useful business practices such that imposing tort liability would aid rather than discourage commerce.  See Erlich, supra at 554.  As such, the breach of implied covenant of good faith and fair dealing cause of action fails. 

 

CONCLUSION

 

Summary judgment in favor of Defendant and against Plaintiff on the causes of action in Plaintiff’s complaint is granted.