Judge: Melvin D. Sandvig, Case: 22CHCV00184, Date: 2025-01-24 Tentative Ruling
Counsel wishing to submit on a tentative ruling may inform the clerk or courtroom assisant in North Valley Department F47, 9425 Penfield Ave., Chatsworth, CA 91311, at (818) 407-2247. Please be aware that unless all parties submit, the matter will still be called for hearing and may be argued by any appearing/non-submitting parties. If the matter is submitted on the court's tentative ruling by all parties, counsel for moving party shall give notice of ruling. This may be done by incorporating verbatim the court's tentative ruling. The tentative ruling may be extracted verbatim by copying and specially pasting, as unformatted text, from the Los Angeles Superior Court’s website, http://www.lasuperiorcourt.org. All hearings on law and motion and other calendar matters are generally NOT transcribed by a court reporter unless one is provided by the party(ies).
Case Number: 22CHCV00184 Hearing Date: January 24, 2025 Dept: F47
Dept. F47
Date: 1/24/25
Case #22CHCV00184
DEMURRER &
MOTION TO STRIKE TO THE SECOND AMENDED COMPLAINT
Demurrer filed on 10/30/24.
MOVING PARTY: Defendants Beitler & Associates, Inc.
and Second Riverton Development, LLC
RESPONDING PARTY: Plaintiff CLC Builders, Inc.
NOTICE: ok
Demurrer is to the entire Second Amended Complaint:
1. Breach of Contract
2. Foreclosure of Mechanic’s Lien
3. Fraud and Deceit
4. Work, Labor and Services (Quantum Meruit)
5. Money Due on an Open Book Account (Quantum
Meruit)
6. Reasonable Value of Services Rendered
(Quantum Meruit)
RELIEF REQUESTED IN MOTION TO STRIKE: An order
striking the following portions of the Second Amended
Complaint: (1) ¶13, p.4:27-28: “the 5263 Cartwright Project which is the
subject of this Action;” (2) ¶58, p.23:18-28 (punitive damages) and (3) ¶3,
p.27:28-p.28:1 (prayer for punitive damages re: 3rd cause of
action).
RULING: The demurrer is sustained and the motion
to strike is granted, both with 30 days leave to amend
SUMMARY OF ACTION & PROCEDURAL HISTORY
This action arises out of Plaintiff CLC Builders, Inc.’s
(Plaintiff) claims that it was engaged by Defendant Beitler & Associates,
Inc. (Beitler) and multiple Beitler affiliated entities to perform general
commercial contractor services in building apartment complexes and other
commercial structures.
In this action, Plaintiff alleges that it performed
substantial work at a project known as Defendant Second Riverton Development,
LLC (Riverton) which was allegedly operated and managed by Barry Beitler, now
deceased, and its Chief Operating Officer and de facto in-house counsel, Donald
Rezak. Plaintiff alleges that although
Beitler made payments toward Plaintiff’s invoices on the Riverton project,
Beitler failed to pay the entire balance due leaving $73,793.61 unpaid.
On 3/18/22, Plaintiff filed this action against Beitler
and Riverton for: (1) Breach of Contract and (2) Foreclosure of Mechanic’s Lien. On 3/2/23, Plaintiff filed its First Amended
Complaint alleging causes of action for: (1) Breach of Contract, (2)
Foreclosure of Mechanic’s Lien, (3) Fraud and Deceit, (4) Work, Labor and
Services (Quantum Meruit), (5) Money Due on Open Book Account (Quantum Meruit),
(6) Reasonable Value of Services Rendered (Quantum Meruit) and (7) Unfair
Business Practices (Business & Professions Code 17200).
On 6/10/24, pursuant to a Stipulation and Order,
Plaintiff filed the subject Second Amended Complaint for: (1) Breach of
Contract, (2) Foreclosure of Mechanic’s Lien, (3) Fraud and Deceit, (4) Work,
Labor and Services (Quantum Meruit), (5) Money Due on an Open Book Account
(Quantum Meruit) and (6) Reasonable Value of Services Rendered (Quantum Meruit). After meet and confer efforts failed to
resolve the issues Beitler and Riverton (collectively, Defendants) had with the
Second Amended Complaint, on 10/30/24, Defendants filed and served the instant
demurrer to the entire Second Amended Complaint and motion to strike which
seeks to strike the following portions of the Second Amended Complaint: (1)
¶13, p.4:27-28: “the 5263 Cartwright Project which is the subject of this
Action;” (2) ¶58, p.23:18-28 (punitive damages allegations in the 3rd
cause of action) and (3) ¶3, p.27:28-p.28:1 (prayer for punitive damages re: 3rd
cause of action). (See Hurwitz
Decl.). Plaintiff has opposed the
demurrer and motion to strike and Defendants have filed a joint reply to the
oppositions.
ANALYSIS
Among others, a demurrer may be based on the grounds that
a complaint does not state facts sufficient to constitute a cause of action
and/or in an action based on a contract, it cannot be
ascertained from the complaint whether the contract is written, oral, or
implied by conduct. See CCP
430.10(e), (f).
1st cause of action – Breach of Contract
The elements of a breach of contract cause of action are:
(1) the contract, (2) plaintiff’s performance or excuse for nonperformance, (3)
defendant’s breach and (4) resulting damages to plaintiff. Reichert (1968) 68 C2d 822, 830. Plaintiff has failed to allege sufficient
facts to satisfy the first element of the cause of action as it cannot be
ascertained what contract forms the basis of the claim.
The title of the cause of action does not indicate
whether the claim is for breach of a written, oral or implied contract. (See Second Amended Complaint (SAC)
p.1:13, p.11:4-6). Plaintiff seems to
base the claim on a written agreement, the “Second Riverton Agreement.” (Second Amended Complaint ¶¶23-27, 29). However, Plaintiff admits that such agreement
is “incomplete and/or not fully-executed.”
(See SAC ¶23 and Ex.1 thereto).
Additionally, Beitler, who is named as a defendant in the breach of
contract cause of action, is not identified as a party in the incomplete/not
fully-executed contract. (SAC,
Ex.1). The facts appearing in the
exhibit attached to the Second Amended Complaint (i.e., parties to the contract
and the unexecuted status of the contract) take precedence over inconsistent
allegations in the pleading. See Dodd
(1990) 222 CA3d 1624, 1627. To the extent
Plaintiff intended to state a cause of action for breach of written contract,
the Second Amended Complaint fails to allege sufficient facts to state such a
cause of action. CCP 430.10(e).
The opposition to the demurrer implies that Plaintiff may
be attempting to state a claim for breach of oral contract by arguing
“[w]hether it was the parties’ mutual intention that an oral agreement to the
terms contained in a proposed written agreement should be binding…” or,
perhaps, a claim for breach of implied contract based on the argument that “the
contracted-for work by Plaintiff was fully performed by Plaintiff, repeatedly
accepted by Defendants incrementally as the work was performed, and partially
paid for by BEITLER throughout.” (See
Opposition, p.5:5-18). Based on the
foregoing, the 1st cause of action is subject to demurrer because it
cannot be ascertained from the Second Amended Complaint whether the contract on
which cause of action is based is written, oral, or implied by conduct. See CCP 430.10(f).
4th cause of action – Work, Labor and
Services (Quantum Meruit); 5th cause of action – Money Due On An
Open Book Account (Quantum Meruit) & 6th cause of action –
Reasonable Value of Services Rendered (Quantum Meruit)
The 4th, 5th and 6th
causes of action all incorporate and rely on the “Second Riverton Agreement”
which seemingly forms the basis for the deficient 1st cause of
action. (See ¶¶23, 61, 64, 66,
67, 69, 71, 72, 73, 77). Since that
agreement is admittedly “incomplete and/or not fully-executed,” these claims
also fail to allege sufficient facts to state a cause of action. (SAC ¶23); CCP 430.10(e); Ephraim
(1946) 28 C2d 824, 833; Stafford (1953) 117 CA2d 326, 327.
2nd cause of action – Foreclosure of
Mechanic’s Lien
A contractor may not enforce a mechanic’s lien unless the
contractor records the lien within 90 days after completion of its work. Civil Code 8412(a). Plaintiff identifies the subject lien as the
document attached to the Second Amended Complaint as Exhibit 2 which shows that
it was recorded on 12/20/21. (SAC ¶32). As such, the Court may disregard the contradictory
allegation in the Second Amended Complaint that Plaintiff recorded the lien on
or about 12/15/21. See Dodd,
supra.
In its First Amended Complaint, Plaintiff alleged that it
ceased performance of its work on, and it sought to recover interest from and
after, 9/15/21, which is more than 90 days before the mechanic’s lien was
recorded. (First Amended Complaint (FAC)
¶¶12, 59, 64, 70). Under the sham
pleading doctrine, Plaintiff cannot avoid the foregoing admission by merely
eliminating it from the Second Amended Complaint, without explanation. See Deveny (2006) 139 CA4th
408, 425-426; Reichert, supra at 836; Amid (1989) 212 CA3d
1383, 1387-1391.
The opposition admits that the date on the lien indicates
a recordation date more than 90 days after the alleged date of completion. (See Opposition, p.5:25-26). Plaintiff then claims that it “will show that
the lien was submitted for recording well within the period provided by law”
and makes the unsupported argument that “Plaintiff should therefore be
permitted to bring the appropriate motion for relief from this technical error,
which was not the fault of Plaintiff in the first place.” (See Opposition, p.5:25-28). There is no indication that Plaintiff has
made any effort to file any motion in an attempt to obtain relief from the
purported technical error.
Additionally, the lien shows that Beitler was not an
owner of the property and that Plaintiff did not provide Beitler with notice of
the lien. (See SAC, Ex.2). As such, any allegation that anyone other
than Riverton is an owner of the property may be disregarded. See Dodd, supra; (SAC
¶¶9, 34).
3rd cause of action – Fraud and Deceit
The elements of a fraud cause of action are: (1) misrepresentation
(false representation, concealment or nondisclosure), (2) knowledge of falsity
or scienter, (3) intent to defraud (induce reliance), (4) justifiable reliance
and (5) resulting damage. Lazar
(1996) 12 C4th 631, 638. A fraud cause
of action must be pled with particularity including facts showing how, when,
where, to whom and by what means the representations were made. Id. at 645.
Here, Plaintiff alleges that the representations which
form the basis of the fraud claim were made by “Barry Beitler, REZAK and DOES 2
TO 200.” (See SAC ¶40). Plaintiff failed to meet the particularity
requirement as it is not clear who the 198 other individuals are who
purportedly made misrepresentations are, those individuals’ authority to speak
on behalf of Defendants, what they said or wrote, when, etc.
Fraud in the inducement/promissory fraud is a subset of
the tort of fraud and may lie where a defendant fraudulently induces the
plaintiff to enter into a contract by making promises the defendant did not
intend to perform. See Lazar,
supra at 638. To the extent
Plaintiff attempts to state a claim for fraudulent inducement to enter a
contract, the claim fails to allege sufficient facts to state a cause of action
because, as noted above, Plaintiff has failed to adequately allege the
underlying contract. Additionally,
Plaintiff has failed to allege sufficient facts to establish that Defendants
did not intend to perform under the purported contract as Plaintiff admits that
only some of the invoices, amounting to $73,793.61, were not paid on the $2
million+ project. (See SAC ¶¶23,
28).
The Court finds that Defendants’ argument that the fraud
claim fails under the economic loss rule is without merit as Plaintiff has
alleged damages in addition to the contract damages. (See SAC ¶57).
Since Plaintiff has failed to sufficiently allege the
fraud and deceit cause of action, there is no basis for its allegations
regarding and the prayer for punitive damages.
Plaintiff admits that its reference to the “5263
Cartwright Project” at ¶13, p.4:28, in the Second Amended Complaint is a
typographical error that needs correction.
(See Opposition to Motion to Strike, p.2:1-5).
CONCLUSION
The demurrer is sustained and the motion to strike is
granted. Due to the liberal policy of
allowing leave to amend and since this is the first time the pleading is before
the Court, Plaintiff is granted 30 days leave to amend.