Judge: Michael E. Whitaker, Case: 19SMCV01169, Date: 2024-05-22 Tentative Ruling



Case Number: 19SMCV01169    Hearing Date: May 22, 2024    Dept: 207

TENTATIVE RULING

 

DEPARTMENT

207

HEARING DATE

May 22, 2024

CASE NUMBER

19SMCV01169

MOTION

Motion for Summary Judgment/Summary Adjudication

MOVING PARTY

Defendant Baypost Builders Inc.

OPPOSING PARTIES

Plaintiffs Anthony Aldave and Teresa Aldave

 

MOVING PAPERS:

 

  1. Notice of Motion and Motion for Summary Judgment/Summary Adjudication; Memorandum of Points and Authorities
  2. Separate Index of Exhibits
  3. Request for Judicial Notice
  4. Separate Statement of Undisputed Material Facts

 

OPPOSITION PAPERS:

 

  1. Memorandum of Points and Authorities in Opposition to Motion for Summary Judgment/Summary Adjudication
  2. Objections to Evidence
  3. Separate Statement in Opposition to Motion for Summary Judgment/Summary Adjudication
  4. Declaration of Plaintiff Anthony Aldave
  5. Declaration of Steve Norris
  6. Declaration of Jeffrey A. Haile
  7. Declaration of Plaintiff Teresa Aldave
  8. Compendium of Evidence

 

REPLY PAPERS:

 

  1. Reply to Plaintiffs’ Opposition to Motion for Summary Judgment/Summary Adjudication
  2. Objections to Evidence
  3. Responses to Plaintiffs’ Separate Statement

 

BACKGROUND

 

The operative First Amended Complaint (“FAC”) of Plaintiffs Anthony Aldave and Teresa Aldave (“Plaintiffs”) alleges eight causes of action for (1) Removal of Lateral and Subadjacent Support; (2) Negligence Per Se; (3) Negligence; (4) Negligence; (5) Private Nuisance and Request for Temporary Shoring; (6) Public Nuisance and Request for Temporary Shoring; (7) Intentional Trespass and Punitive Damages; and (8) Breach of Contract.

 

Plaintiffs allege construction work done on their uphill adjacent neighbor’s property removed lateral and subadjacent support, causing damage to Plaintiffs’ property.  Plaintiffs alleged that Defendant 1400 Linda Flora Associates owns the neighboring property; Defendant Bay Post Builders, Inc. is the general contractor; Defendant Faradj-Ollah Harouni is the architect; Defendant Leonard Irvin Liston is the civil engineer; and Defendant Jacob William Holt is the engineering geologist. 

 

As to Moving Defendant Bay Post Builders, Inc. (“Moving Defendant” or “Baypost”), Plaintiff has alleged only the second, third, fifth, sixth, and seventh causes of action.

 

Baypost moves for summary judgment on the following issues:

 

1) Defendant Baypost did not have any legal duty owed to Plaintiffs related to the professional services Baypost performed per agreement with the prior owner of the separate, upslope property located at 1400 Linda Flora Drive:

 

a. Baypost did not have any form of agreement with and was not paid by Plaintiffs, or any party to this action other than the prior owner of the separate, upslope property;

 

b. Baypost was retained only by the prior owner of the separate, upslope property and performed no services of any kind under a separate agreement or understanding with Plaintiffs;

 

c. Baypost was not the general contractor for any alleged work performed on Plaintiffs' property;

 

d. Baypost did not perform any excavation, construction, or other grading, and did not design any aspect of the work, allegedly performed on Plaintiffs' property;

 

e. Baypost did not have any responsibility for the means and methods of any of the alleged work performed on Plaintiffs' property;

 

f. Baypost was not the owner or occupier of, and did not have control over, the real property involved in this action and cannot bear any liability for the conditions on such property;

 

g. The work that was performed exclusively on the upslope property located at 1400 Linda Flora Drive and managed by Baypost has performed as designed by independent engineers and approved by the City of Los Angeles Department of Building and Safety;

 

h. Plaintiffs cannot demonstrate any errors and/or omissions attributable to Baypost and cannot establish that any alleged errors and/or omissions on the part of Baypost have resulted in any demonstrable damages; therefore, Plaintiffs cannot assert a tort claim against Baypost;

 

2) Plaintiffs' Seventh Cause of Action for Intentional Trespass is barred by the applicable statute of limitations; and,

 

3) Baypost did not intentionally trespass on Plaintiffs' property as Baypost believed the work had been authorized as necessary and was not aware it was performed on Plaintiffs' property and the condition of Plaintiffs' property was improved by the work performed by others.

 

In the alternative, Moving Defendant moves for summary adjudication of the following issues:

 

1. Baypost did not owe a duty of care to Plaintiffs and prevails on the Second Cause of Action for Negligence per se:

 

a. Baypost did not have any agreement with Plaintiffs and only provided professional services directly for the owner of the separate, upslope property located at 1400 Linda Flora Drive;

 

b. Baypost did not perform any excavation, construction, or other grading on Plaintiffs' property at any time and was not involved in the repairs of the erosional scar on Plaintiffs' property;

 

2. As set forth above, Baypost did not owe a duty of care to Plaintiffs and Baypost prevails on the Third Cause of Action for Negligence;

 

3. As set forth above, Baypost did not owe a duty of care to Plaintiffs and Baypost prevails on the Fifth Cause of Action for Private Nuisance and Request for Temporary Shoring;

 

4. As set forth above, Baypost did not owe a duty of care to Plaintiffs and Baypost prevails on the Sixth Cause of Action for Public Nuisance and Request for Temporary Shoring;

 

5. The Seventh Cause of Action for Intentional Trespass is barred by the applicable statute of limitations; and,

 

6. No intentional trespass occurred as Baypost did not grub/denude, or excavate/grade on, Plaintiffs' property as alleged in the Seventh Cause of Action for Trespass at Paragraphs 119 - 126 of the First Amended Complaint and believed all subsequent landscaping work had been authorized as needed and Baypost was not aware the work was performed on Plaintiffs' property.

 

Plaintiffs oppose the motion and Baypost replies.

 

EVIDENTIARY OBJECTIONS

 

            The Court rules as follows with respect to Plaintiffs’ evidentiary objections:

 

Declaration of Ben Hamid Bayanfar

 

1.     Overruled

2.     Sustained

3.     Overruled

4.     Sustained

5.     Sustained

6.     Sustained

7.     Sustained

8.     Sustained as to the Google Earth photograph references, Overruled as to the grubbed/denuded references.

9.     Sustained as to the Google Earth photograph references, Overruled as to the roadway grading references.

10.  Sustained

11.  Sustained

12.  Sustained

13.  Sustained

14.  Sustained

15.  Sustained

16.  Sustained

17.  Sustained

18.  Sustained

19.  Sustained

20.  Sustained

21.  Sustained

22.  Sustained

23.  Sustained

24.  Sustained

25.  Sustained

26.  Sustained

27.  Sustained

28.  Sustained

29.  Sustained

30.  Sustained

31.  Sustained

32.  Sustained

33.  Sustained

34.  Sustained

35.  Sustained

36.  Overruled

37.  Overruled

38.  Overruled

39.  Sustained

40.  Sustained

41.  Sustained

42.  Sustained

 

Exhibit D: Sustained

Exhibit E: Sustained

Exhibit F: Sustained

Exhibit G: Sustained

Exhibit H: Sustained

Exhibit J: Sustained

Exhibit K: Sustained

Exhibit L: Sustained

Exhibit M: Sustained

Exhibit N: Sustained

 

The Court rules as follows with respect to the Moving Defendant’s objections to Plaintiffs’ evidence:

 

  1. Sustained
  2. Sustained
  3. Overruled
  4. Overruled
  5. Sustained
  6. Sustained
  7. Sustained
  8. Sustained
  9. Overruled
  10. Overruled
  11. Overruled
  12. Overruled
  13. Sustained
  14. Overruled
  15. Sustained
  16. Sustained
  17. Sustained
  18. Overruled
  19. Overruled
  20. Overruled
  21. Overruled
  22. Overruled
  23. Sustained
  24. The reference to Exhibit 10 is incorrect.  As such, the objection is Overruled.
  25. The Court has not received an Exhibit 12 in support of the opposition.  As such, the objection is Overruled.
  26. The Court has not received an Exhibit 13 in support of the opposition.  As such, the objection is Overruled.

 

REQUEST FOR JUDICIAL NOTICE

 

Moving Defendant requests the Court to take judicial notice of (1) Plaintiffs’ First Amended Complaint in this matter; and (2) Baypost’s answer to the First Amended Complaint.

 

Judicial notice may be taken of records of any court in this state.  (Evid. Code, § 452, subd. (d)(1).)  Therefore, the Court may take judicial notice of the First Amended Complaint and Baypost’s Answer thereto (Ibid.)   However, “while courts are free to take judicial notice of the existence of each document in a court file, including the truth of results reached, they may not take judicial notice of the truth of hearsay statements in decisions and court files.  Courts may not take judicial notice of allegations in affidavits, declarations and probation reports in court records because such matters are reasonably subject to dispute and therefore require formal proof.”  (Lockley v. Law Office of Cantrell, Green, Pekich, Cruz & McCort (2001) 91 Cal.App.4th 875, 882 [cleaned up].) 

 

Therefore, the Court takes judicial notice of the existence and legal effect of the First Amended Complaint and Baypost’s Answer, but not the truth of the allegations contained therein.

 

LEGAL STANDARDS – MOTION FOR SUMMARY JUDGMENT/ADJUDICATION

 

“[T]he party moving for summary judgment bears the burden of persuasion that there is no triable issue of material fact and that he is entitled to judgment as a matter of law[.] There is a triable issue of material fact if, and only if, the evidence would allow a reasonable trier of fact to find the underlying fact in favor of the party opposing the motion in accordance with the applicable standard of proof.” ¿(Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 850 (hereafter Aguilar).) ¿“[T]he party moving for summary judgment bears an initial burden of production to make a prima facie showing of the nonexistence of any triable issue of material fact; if he carries his burden of production, he causes a shift, and the opposing party is then subjected to a burden of production of his own to make a prima facie showing of the existence of a triable issue of material fact.” ¿(Ibid.; Smith v. Wells Fargo Bank, N.A. (2005) 135 Cal.App.4th 1463, 1474 [summary judgment standards held by Aguilar apply to summary adjudication motions].) 

 

Further, “the trial court may not weigh the evidence in the manner of a factfinder to determine whose version is more likely true.  Nor may the trial court grant summary judgment based on the court's evaluation of credibility.”  (Aguilar, supra, 25 Cal.4th. at p. 840 [cleaned up]; see also Weiss v. People ex rel. Department of Transportation (2020) 9 Cal.5th 840, 864 [“Courts deciding motions for summary judgment or summary adjudication may not weigh the evidence but must instead view it in the light most favorable to the opposing party and draw all reasonable inferences in favor of that party”].) 

 

A party may move for summary adjudication as to one or more causes of action, affirmative defenses, claims for damages, or issues of duty if that party contends that there is no merit to the cause of action, defense, or claim for damages, or if the party contends that there is no duty owed.  (See Code Civ. Proc., § 437c, subd. (f)(1).)  “A motion for summary adjudication shall be granted only if it completely disposes of a cause of action, an affirmative defense, a claim for damages, or an issue of duty.”  (Ibid.)  A cause of action has no merit if: (1) one or more elements of the cause of action cannot be separately established, even if that element is separately pleaded, or (2) a defendant establishes an affirmative defense to that cause of action.  (See Code Civ. Proc., § 437c, subd. (n); Union Bank v. Superior Court (1995) 31 Cal.App.4th 573, 583.)  Once the defendant has shown that a cause of action has no merit, the burden shifts to the plaintiff to show that a triable issue of material fact exists as to that cause of action.  (See Code Civ. Proc., § 437c, subd. (o)(2); Union Bank v. Superior Court, supra, 31 Cal.App.4th at p. 583.)  Additionally, in line with Aguilar, “[o]n a motion for summary adjudication, the trial court has no discretion to exercise.  If a triable issue of material fact exists as to the challenged causes of action, the motion must be denied. If there is no triable issue of fact, the motion must be granted.”  (Fisherman's Wharf Bay Cruise Corp. v. Superior Court (2003) 114 Cal.App.4th 309, 320.) 

 

DISCUSSION

 

1.     MSJ ISSUE 1: DUTY

 

Moving Defendant first contends that the Court should grant summary judgment as to the causes of action for negligence, negligence per se, private nuisance, and public nuisance, on the grounds that Moving Defendant owed Plaintiffs no duty of care.

 

The elements of a cause of action for private nuisance are (1) an interference with plaintiff’s use and enjoyment of plaintiff’s property; (2) the invasion of plaintiff’s interest must be substantial, i.e., it caused plaintiff to suffer substantial actual damage; and (3) the interference must also be unreasonable, i.e., of such a nature, duration, or amount as to constitute an unreasonable interference with the use and enjoyment of land.  (Today's IV, Inc. v. Los Angeles County Metropolitan Transportation Authority (2022) 83 Cal.App.5th 1137, 1176.)

 

Similarly, the elements of a cause of action for public nuisance are (1) a proscribed act; (2) interference with the comfortable enjoyment of life or property; and (3) whether the act affects a sufficient number of persons.  (People v. McDonald (2006) 137 Cal.App.4th 521, 535.)

 

Because duty is not an element of the causes of action for private nuisance or public nuisance, resolution of whether Baypost owed Plaintiffs a duty of care will not dispose of these causes of action.  Therefore, the Court denies Baypost’s motion for summary judgment.

 

For the same reasons, the Court denies summary adjudication as to Issues 3 and 4.

 

2.     SUMMARY ADJUDICATION ISSUE 1: NEGLIGENCE PER SE

 

“Negligence per se is an evidentiary doctrine, rather than an independent cause of action. It can be applied generally to establish a breach of due care under any negligence-related cause of action.”  (Jones v. Awad (2019) 39 Cal.App.5th 1200, 1210 [cleaned up]; see also Quiroz v. Seventh Ave. Center (2006) 140 Cal.App.4th 1256, 1285–1286 [“negligence per se is not to state an independent cause of action.  The doctrine does not provide a private right of action for violation of a statute”].)   

 

“Under the doctrine of negligence per se, compliance with the standard of conduct established by the relevant statute, ordinance, or regulation is adopted as the duty of care.  This creates a rebuttable presumption of negligence where the statute, ordinance, or regulation is violated.”  (Jones v. Awad, supra, 39 Cal.App.5th at p. 1210.)  Further, under the doctrine, negligence is presumed if (1) defendant violated a statute, ordinance, or regulation; (2) the violation proximately caused plaintiff’s injury; (3) the injury resulted from an occurrence the nature of which the statute, ordinance, or regulation was designed to prevent; and (4) the injured plaintiff was of the class of persons the statute, ordinance, or regulation was designed to protect.  (Ibid.)   Thus, under negligence per se, there is a general duty of care dictated by statute, ordinance, or regulation to those the statute, ordinance, or regulation was designed to protect.

 

Plaintiffs allege Baypost violated Civil Code section 832; California Building Code (2016), Title 24, Chapter 1, Division 2, Part 2, Section 114.1, entitled “Unlawful Acts”; California Building Code section 3304.1, entitled “Excavation and Fill”; and California Building Code section 3307, entitled “Protection of Adjourning Property.”  (FAC ¶ 42.)

 

Section 832 requires the land owner to provide notice to neighboring land owners of excavation work that may endanger a neighboring land owner’s walls or foundation to an adjoining building or structure.  Thus, Section 832 cannot form the basis of negligence per se against Baypoint, who is not the owner of the neighboring property.

 

Building Standards Code section 114.1 provides, “It shall be unlawful for any person, firm or corporation to erect, construct, alter, extend, repair, move, remove, demolish or occupy any building, structure or equipment regulated by this code, or cause same to be done, in conflict with or in violation of any of the provisions of this code.”

 

Building Standards Code section 3304.1 provides, “Excavation and fill for buildings and structures shall be constructed or protected so as not to endanger life or property.”

 

Building Standards Code section 3307 provides, “Adjoining public and private property shall be protected from damage during construction, remodeling and demolition work.  Protection shall be provided for footings, foundations, party walls, chimneys, skylights and roofs.  Provisions shall be made to control water runoff and erosion during construction or demolition activities.  The person making or causing an excavation to be made shall provide written notice to the owners of adjoining buildings advising them that the excavation is to be made and that the adjoining buildings should be protected.  Said notification shall be delivered not less than 10 days prior to the scheduled starting date of the excavation.”

 

Thus, the stated purpose of Section 3307 is to protect adjoining property from construction damage.

 

a.     Baypost’s Evidence

 

Baypost has provided evidence that it was retained as the project manager for the development of the uphill property on August 1, 2015 (UMF Nos. 20, 25) and as general contractor for the construction of a 30-foot retaining wall extension on the property in 2017.  (UMF No. 57.)

 

  Baypost argues it owed Plaintiffs no duty of care because (1) Baypost did not have any agreement with Plaintiffs and (2) Baypost did not perform any excavation, construction, grading, or repairs on Plaintiff’s property.  But the lack of contractual privity or direct work on Plaintiffs’ property does not negate the duty aspect of negligence per se, which is dictated by statute.  Here, the statute was clearly designed to protect adjacent landowners, like Plaintiffs, from property damage during construction, remodeling, and demolition work.

 

As discussed below, Baypost also provides evidence that it did not actually perform the construction work or otherwise control the companies that did actually perform the work, and that the work Baypost managed/oversaw did not cause Plaintiffs’ damage.  But such evidence goes beyond the issues identified in Baypost’s notice of motion – that Baypost owes no duty in negligence per se because it did not have a direct contract with Plaintiffs and did not directly perform any work on Plaintiffs’ property. 

 

Ultimately, even if Baypost did not have a direct agreement with Plaintiffs and did not perform any work directly on Plaintiff’s property, it would still a duty under negligence per se to comply with the building standards codes designed to protect adjacent property owners, like Plaintiffs, from the type of harm that allegedly occurred. 

 

Baypost argues in reply that the building code violations cannot form the basis of negligence per se because there is no private right of action to enforce them.  But a statute containing a private right of action is not a requirement for that statute to form the basis of negligence per se.  Moreover, courts have applied negligence per say to building code violations involving defendants who played professional roles in the design or construction.  (Jones v. Awad, supra, 39 Cal.App.5th at p. 1212 [collecting cases].)

 

Therefore, the Court denies summary adjudication as to issue 1.

 

3.     SUMMARY ADJUDICATION ISSUE 2: NEGLIGENCE

 

“To state a cause of action for professional negligence, a party must show (1) the duty of the professional to use such skill, prudence and diligence as other members of the profession commonly possess and exercise; (2) breach of that duty; (3) a causal connection between the negligent conduct and the resulting injury; and (4) actual loss or damage resulting from the professional negligence.”  (Giacometti v. Aulla, LLC (2010) 187 Cal.App.4th 1133, 1137.)

 

Here again, Baypost argues it owed Plaintiffs no duty of care. 

 

“[T]he lack of privity of contract does not preclude imposition of a duty of care.”  (Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co., Inc. (2004) 125 Cal.App.4th 152, 164 (hereafter Weseloh).)  Thus, the fact that there was no direct contractual relationship between Baypost and Plaintiffs does not automatically mean that Baypost owed Plaintiffs no duty as a matter of law.

 

“The determination whether in a specific case the defendant will be held liable to a third person not in privity is a matter of policy and involves the balancing of various factors, among which are [1] the extent to which the transaction was intended to affect the plaintiff, [2] the foreseeability of harm to him, [3] the degree of certainty that the plaintiff suffered injury, [4] the closeness of the connection between the defendant's conduct and the injury suffered, [5] the moral blame attached to the defendant's conduct, and [6] the policy of preventing future harm.”  (Weseloh, supra, 125 Cal.App.4th at p. 165.)

 

Factor 1: The Extent to which the Construction was Intended to Affect Plaintiffs

 

In Biakanja v. Irving (1958) 49 Cal.2d 647 (hereafter Biakanja), the Supreme Court held a notary public liable for preparing a will (which constituted the unauthorized practice of law), which was found to be invalid because the notary public negligently failed to have the will properly attested, causing the intended beneficiary to inherit only one-eighth of the estate.  In analyzing the first factor, the Supreme Court found that the “end and aim” of the transaction was to pass the entire estate to the plaintiff.  (Id. at p. 650.) 

 

By contrast, although some of the ground cover and irrigation system were inadvertently installed on a portion of Plaintiffs’land, the construction work was not intended to affect Plaintiffs at all. Ideally, the construction and excavation project would have proceeded without incident solely on the uphill neighbor’s property, and Plaintiffs’ property would have been unaffected.  Thus, unlike in Biakanja, Plaintiffs were not an intended beneficiary of the work, nor was the “end and aim” of the construction work designed to impact or affect Plaintiffs at all.  Rather, the intended beneficiary of the work was the uphill landowner.

 

Factor 2: The Foreseeability of Harm to Plaintiffs

 

Here, it was foreseeable that the downhill adjacent neighbor could be harmed by negligent construction on the uphill property.  Such a scenario has already been contemplated and addressed in the Building Standards Code.  Therefore, just because Baypost did not perform any construction or excavation directly on Plaintiffs’ property does not mean that the harm to Plaintiffs was not foreseeable.  However, foreseeability is to be given limited weight in determining whether a duty exists.  (Weseloh, supra, 125 Cal.App.4th at p. 167.)

 

Factor 3: Certainty the Plaintiffs Sustained Injury and the Closeness of the Connection between Baypost’s Conduct and that Injury

 

With regard to certainty that Plaintiffs suffered injury, Baypost has provided evidence of the damage to Plaintiff’s property and does not generally deny that Plaintiffs’ property was damaged.  (UMF Nos. 4-6, 8-9.) 

 

Plaintiffs contend that its property was damaged by virtue of (1) a faulty irrigation system installed to irrigate newly-installed ground cover on the hill; and (2) a retaining wall extension erected that did not allow for proper drainage.  This resulted in three separate scars developing on the hill causing landslides in 2017 and 2018.

 

a.     Baypost’s Evidence

 

With regard to the closeness of the connection between Baypost’s conduct and Plaintiffs’ injury, Baypost has provided evidence that Baypost was retained as the project manager for the development of the uphill property and began work on August 1, 2015.  (UMF Nos. 20, 25.)  In its role as project manager, Baypost’s duties “primarily” included scheduling and coordinating work on the project, scheduling city inspections, confirming completion of work, and recommending payment pursuant to the owner’s contract terms. (UMF No. 21.)  However, this statement does not demonstrate that Baypost was not involved any construction or excavation work.

 

Baypost further argues that a separate company, M&M Landscaping and Gardening Services, with whom Baypost did not personally contract and over whose work Baypost has no control, planted the ground cover and installed jute netting and irrigation.  However, the Court sustains Plaintiff’s objections to much of this evidence, except that Baypost did not hire M&M and did not purchase materials for M&M or otherwise control M&M.  (UMF No. 41, 42.) 

 

Baypost also indicates that for its work as project manager, it was provided repair plans for the scar on Plaintiffs’ property (UMF No. 47.)  Baypost again argues that another company called Geoworks Engineering Group, Inc., with whom Baypost did not directly contract and over whose work Baypost contends it had no control, performed the repair work on the scar. However, the Court also sustains Plaintiff’s evidentiary objections regarding Geoworks Engineering Group.

 

Thus, Baypost has not provided sufficient admissible evidence that it was not involved in installing the ground cover or irrigation system Plaintiffs’ contend caused or exacerbated the damage or repair work on the scar. 

 

Baypost was also retained as the general contractor for the construction of a 30-foot retaining wall extension on the uphill property, just above Plaintiffs’ property.  (UMF No. 57-58.)  Baypost contends that licensed surveyor Steven Opdahl placed the construction stakes for the retaining wall extension, and EGM Construction, Inc. constructed the retaining wall extension, but the Court sustains Plaintiffs’ objections to this evidence.

 

Baypost further contends that in August 2018, roughly 3 years after the irrigation system was installed, its pressure regulator failed, causing two sections of irrigation pipes to separate, creating two erosion scars, but Baypost has not provided the requisite foundation for this evidence.  Baypost left the project on August 31, 2018. (UMF No. 67.)  Bayanfar also declares that in December 2018, a “third failure” occurred “during a very heavy rain.”  (Bayanfar Decl. ¶ 50.)  In context, it appears Bayanfar uses the word “failure” when he means “scar,” as the evidence only establishes one prior failure of the irrigation system’s pressure regulator (resulting in two scars.)  The Court further sustains Plaintiffs’ objections to those portions of Bayanfar’s declaration opining as to the cause of the third scar.

 

In September 2019, Baypost inspected the slope and did not observe any evidence that the retaining wall was failing.  (UMF No. 70.)  During that inspection, Baypost observed that all three scars had been repaired.  (UMF No. 71.)  Baypost also observed during that inspection that a solar panel on a 6-foot tall tower had since been placed on the border line between the properties sometime after August 30, 2018, when Baypost left.  (UMF No. 80-81.)  Baypost had no involvement with the installation of the solar tower or any knowledge of it prior to observing it during the September 2019 site visit.  (UMF No. 80-83, 85.)

 

On February 12, 2024, Baypost was involved in another site inspection.  (UMF No. 73.)  During this inspection, Baypost did not observe any indication that the retaining wall extension was not performing as designed.  (UMF No. 74.)  Baypost also observed during this inspection that the repairs of the three scars appeared intact.  (UMF No. 77, 88.)  Baypost further observed that the solar tower he observed in September 2019 had been removed.  (UMF No. 84.)

 

Thus, Baypost has not met its initial burdens of production and persuasion in demonstrating that Plaintiffs’ harm was not closely connected to Baypost’s conduct.

 

Factor 4: Moral Blame

 

In Biakanja, the notary public was found to be morally blameworthy, because in drafting the will, he engaged in the unauthorized practice of law. 

 

Here, Baypost is alleged to have violated several sections of the California Building Standards Code that were, on their face, enacted to protect adjacent landowners, like Plaintiffs from resulting property damage, like Plaintiffs allegedly suffered.

 

Further, as discussed above, Baypost has not met its initial burdens of production and persuasion that it was not involved in the construction and excavation projects. 

 

As such, the Court cannot say that Baypost was not morally blameworthy.

 

Factor 5: Public Policy of Preventing Future Harm

 

With respect to the public policy of holding a defendant liable to a party with whom it has no privity of contract, Biakanja held that the defendant’s unauthorized practice of law “should be discouraged and not protected by immunity from civil liability, as would be the case if plaintiff, the only person who suffered a loss, were denied a right of action.”  (Biakanja, supra, 49 Cal.2d at p. 651.)

 

Here, the Building Standards Codes cited demonstrate a preexisting public policy of protecting the immediately adjacent property owners from potentially destabilizing construction and excavation of the type conducted on the uphill property. 

 

On the other hand, the general rule for contractor liability to third parties is that “after a contractor has completed a building and it is accepted by the owner, ‘he is not liable to a third person for damages suffered by reason of the condition of the work even though he was negligent in carrying out the contract.’”  (Hale v. Depaoli (1948) 33 Cal.2d 228, 230 (hereafter Hale).) 

 

There are, however, notable exceptions to this general rule, in situations where the construction defect “is of an abnormally dangerous or noxious nature” or “if the nature of a thing is such that it is reasonably certain to place life and limb in peril when negligently made” or is otherwise inherently or imminently dangerous.  (Hale, supra, 33 Cal.2d at pp. 230-232.)  For example, a structural defect in a railing designed to prevent people from falling would be “reasonably certain to place life and limb in peril” but a railing that does not fail for 18 years would not be sufficiently “imminently dangerous” to hold the contractor liable.  (Ibid.)  Here, the nature of excavation/construction on a hill poses an inherent risk to neighboring downhill property, and when done negligently, is inherently of an abnormally and imminently dangerous character, as evidenced by the Building Standards Code sections enacted to protect adjacent property owners from precisely this type of harm, as well as from physical injury.

 

Thus, Baypost’s argument that it was not involved in any construction or excavation work directly on Plaintiffs’ property, even if true, does not necessarily mean that public policy weighs against imposing liability on Baypost as a matter of law.  And as discussed above, Baypost has not met its initial burdens of production and persuasion that it was not involved in the construction and excavation projects such that it would not be culpable for the construction that was performed.

 

Therefore, the Biakanja factors do not preclude liability of an entity like Baypost to Plaintiffs merely because it was not in privity of contract with Plaintiffs, and Baypost has not demonstrated it was only involved in construction and excavation projects intended to be performed on the property of Plaintiffs’ adjacent uphill neighbor.

 

As such, Baypost has not met its initial burdens of production and persuasion that Plaintiff will be unable to establish it was negligent.  Accordingly, the Court denies summary adjudication as to Issue 2.

 

4.     SUMMARY ADJUDICATION ISSUES 5-6: INTENTIONAL TRESPASS – STATUTE OF LIMITATIONS

 

“Trespass is an unlawful interference with possession of property.”  (Staples v. Hoefke (1987) 189 Cal.App.3d 1397, 1406.)  “Liability for trespass may be imposed for conduct which is intentional, reckless, negligent or the result of an extra-hazardous activity.”  (Ibid.) 

 

The FAC alleges Defendants committed intentional trespass by physically entering (or causing their agents to enter) Plaintiffs’ property, removing vegetation, and performing grading and excavation on Plaintiffs’ property.  (FAC ¶ 119.)

 

Code of Civil Procedure section 338 provides that an action for trespass upon or injury to real property shall be brought within three years. 

 

a.     Baypost’s Evidence

 

Baypost contends that the landscaping work where portions of ground coverage and the irrigation system were mistakenly placed on part of Plaintiffs’ property was completed by October 28, 2015. (UMF No. 33-34, 39.) Yet Plaintiffs did not file suit until June 26, 2019, more than three years later.

 

However, as discussed above, because the Court sustains Plaintiff’s’ evidentiary objections in this regard, Baypost has not met its burdens of production and persuasion to demonstrate that it was not involved in the subsequent repair work on the scars on Plaintiff’s property.  Nor has Baypost demonstrated that such repair work was done with Plaintiffs’ knowledge and consent, as opposed to an unlawful interference with Plaintiff’s property.

 

Therefore, Baypost has not demonstrated that it did not unlawfully and intentionally enter Plaintiff’s property within the three years preceding Plaintiff’s June 26, 2019 filing of the original complaint.  As such, the Court denies summary adjudication as to issues 5 and 6.

 

CONCLUSION AND ORDER

 

Therefore, the Court denies Baypost’s Motion for Summary Judgment, or in the alternative Summary Adjudication in its entirety.  Having sustained most of Plaintiff’s evidentiary objections, the Court finds Baypost has not met its initial burdens of production and persuasion, and therefore denies summary adjudication as to all Issues 1-6.  Because the Court denies summary adjudication, it similarly denies summary judgment. 

 

Baypost shall provide notice of the Court’s ruling and file the notice with a proof of service. 

 

 

 

 

 

DATED:  May 22, 2024                                                         ___________________________

                                                                                          Michael E. Whitaker

                                                                                          Judge of the Superior Court