Judge: Michael E. Whitaker, Case: 19SMCV01966, Date: 2024-01-24 Tentative Ruling
Case Number: 19SMCV01966 Hearing Date: January 24, 2024 Dept: 207
TENTATIVE RULING
|
DEPARTMENT |
207 |
|
HEARING DATE |
January 24, 2024 |
|
CASE NUMBER |
19SMCV01966 |
|
MOTION |
Motion for Determination of Good Faith Settlement |
|
MOVING PARTY |
Defendant Rapid Duct Testing and Air Balancing, Inc. |
|
OPPOSING PARTY |
(none) |
BACKGROUND
This case arises from alleged construction defects to the home of
Plaintiffs Michael Levine and Zorbey Ozdilek (“Plaintiffs”). Plaintiffs brought suit against the
architects, general contractor, and subcontractors who worked on the project.
On October 17, 2023, the Court approved the good faith settlement
between Plaintiffs and Defendant subcontractor E & J Lopez Plumbing, Inc.
in the amount of $120,000 and between Defendant/Cross-Complainant Denver Thomas
Dale IV dba Residential Construction Company and Cross-Defendant E & J
Lopez Plumbing in the amount of $30,000.
Defendant Rapid Duct Testing and Air Balancing, Inc. (“Rapid” or
“Defendant”) now moves for determination of a good faith settlement between
itself and Plaintiffs in the amount of $50,000.
Rapid’s motion is unopposed.
ANALYSIS
A.
THE LAW GOVERNING GOOD FAITH SETTLEMENTS
Under
section 877.6 of the Code of Civil Procedure,[1] “[a] determination by the court that [a]
settlement was made in good faith shall bar any other joint tortfeasor . . .
from any further claims against the settling tortfeasor . . . for equitable
comparative contribution, or partial or comparative indemnity, based on
comparative negligence or comparative fault.”
(§ 877.6, subd. (c).)
Additionally, a determination that a settlement was made in good faith
will reduce the claims against the non-settling defendants by the amount
specified in the settlement agreement.
(§ 877.6, subd. (a).) “The party
asserting the lack of good faith has the burden of proof on that issue.” (§ 877.6, subd. (d).)
Section
877.6 requires “that the courts review [settlement] agreements made under its
aegis to insure that the settlements appropriately balance the . . . statute’s
dual objectives” (i.e., providing an “equitable sharing of costs among the
parties at fault” and encouraging parties to resolve their disputes by way of
settlement). (Tech-Bilt, Inc. v.
Woodward-Clyde & Associates (1985) 38 Cal.3d 488, 494 (hereafter Tech-Bilt).) In Tech-Bilt, the California Supreme
Court set forth the factors to consider when determining whether a settlement
was made in good faith. The Tech-Bilt factors are: (1) a rough
approximation of plaintiff’s total recovery and the settlor’s proportionate
liability; (2) the amount paid in settlement; (3) the allocation of settlement
proceeds among plaintiffs; (4) a recognition that a settlor should pay less in
settlement than he would if he were found liable after a trial; (5) the
financial conditions and insurance policy limits of settling defendants; and
(6) the existence of collusion, fraud, or tortious conduct aimed to injure the
interests of the non-settling defendants. (Id. at pp.
498-501.) “Practical considerations
obviously require that the [trial court’s] evaluation [of the settlement] be
made on the basis of information available at the time of settlement.” (Id. at p. 499.)
“The
party asserting the lack of good faith . . . [is] permitted to demonstrate, if
he can, that the settlement is so far ‘out of the ballpark’ in relation to [the
above] factors as to be inconsistent with the equitable objectives of [Section
877.6]. Such a demonstration would
establish that the proposed settlement was not a ‘settlement made in good
faith’ within the terms of section 877.6.”
(Tech-Bilt, supra, 38 Cal.3d at pp. 499–500.)
The moving party on an unopposed motion for
determination of good faith settlement, however, is not required to set forth a
full discussion of the Tech-Bilt factors by declaration or affidavit.
The moving party on an unopposed motion for determination of good faith
settlement need only advance a motion setting forth the basic grounds for the
determination of good faith and a declaration setting forth a brief background
of the case. (City of Grand Terrace v. Superior Court (1987) 192
Cal.App.3d 1251, 1261.)
B.
APPLICATION OF THE TECH-BILT FACTORS
TO THE FACTS OF THE CASE
1.
A ROUGH APPROXIMATION OF PLAINTIFF’S TOTAL
RECOVERY AND THE SETTLOR’S PROPORTIONATE LIABILITY.
The
first Tech-Bilt factor consists of two parts – a rough approximation of
Plaintiff’s total recovery and the settlor’s proportionate liability. When approximating a plaintiff’s total
recovery or the settling defendant’s proportionate liability, “judges should .
. . not yearn for the unreal goal of mathematical certainty. Because the application of section 877.6
requires an educated guess as to what may occur should the case go to trial,
all that can be expected is an estimate, not a definitive conclusion.” (North County Contractor’s Assn. v.
Touchstone Ins. Services (1994) 27 Cal.App.4th 1085, 1090 (hereafter North
County).)
Additionally,
“a court not only looks at the alleged tortfeasor’s liability to the plaintiff,
but it must also consider the culpability of the tortfeasor vis-à-vis other
parties alleged to be responsible for the same injury. Potential liability for indemnity to a
nonsettling defendant is an important consideration for the trial court in
determining whether to approve a settlement by an alleged tortfeasor. [Citation.]”
(TSI Seismic Tenant Space, Inc. v. Superior Court (2007) 149
Cal.App.4th 159, 166.)
In the Fourth Amended Complaint (FAC), Plaintiffs allege they
purchased the subject property for over two million dollars $2,000,000.00 and
that the construction project was estimated to cost two million five hundred
eighty thousand dollars ($2,580,000.00).
(FAC ¶¶ 33-34.) Plaintiffs
further allege that they paid in excess of four million dollars ($4,000,000) on
the project, and then had to spend three million more dollars ($3,000,000) to
remediate construction mistakes and defects.
(FAC ¶ 44.) In total, the FAC
seeks nine million dollars ($9,000,000) in actual damages. (FAC Prayer at ¶¶
a-b.)
Rapid
was hired by the HVAC subcontractor Defendant Temperature Equipment (“Temperature”)
to conduct Title 24 “HERS” (home energy rating service) testing. Rapid’s involvement in the construction
project was limited to a single day of work, wherein Rapid measured the air
flow into the house and any air leakage from the ductwork. According to Rapid, “[t]he testing passed and
Rapid reported the results to the State Energy Commission and was issued a
rough stage Certificate by the State” which Rapid turned over to
Temperature. (Motion at p. 3.)
Six
months after Rapid’s test, the HVAC system underwent follow-up HERS testing by
another testing company and failed. (Motion
at p. 4; FAC ¶¶ 132-138.) Plaintiff
alleges Rapid was involved in a scheme with Temperature and the general
contractor to falsify the initial HERS testing results. (FAC ¶¶ 120-138; Motion at p. 4.) Rapid contends that several changes were made
to the HVAC system and ductwork after it conducted its HERS testing and before
the follow-up HERS testing was performed, including:
·
March 22, 2019 – Repair work included
installation of new dampers throughout the house, correction of air leaks,
performance of air balancing and the making of appropriate adjustments.
·
April 30, 2019 – Rusting in observed in the duct
work.
·
May 6, 2019 – Questioning whether the furnaces
are contributing to the moisture issue that caused the sheet metal fittings to
rust.
·
May 21, 2019 – Rain water possibly getting
sucked into the vents and duct work.
·
June 11, 2019 – HVAC Action Items Meeting:
1. Insulate bare ducts which are uninsulated.
2. Reseal existing ductwork.
3. Seal ducts around light fixtures.
·
June 18, 2019 – Large amounts of
rusting/deterioration observed in the HVAC duct work.
(Motion at pp.
4-5.)
Rapid
thus contends that in light of the changes to the HVAC system after Rapid
conducted its HERS test, it is not liable at all. While the Court acknowledges that Rapid may
be determined to owe no liability at trial, Rapid could also be determined to
be liable for its alleged role in falsely reporting that the HVAC system
originally passed the HERS test.
Although
Plaintiffs seek a total of nine million dollars ($9,000,000.00) in damages, Plaintiffs
allege that as a result of the defendants’ defective workmanship, they paid
$4,000,000 on what was supposed to be a remodel costing $2,580,000, and then
they had to pay an additional $3,000,000 on remediation. Unlike some of the other defendants, there
are no allegations that Plaintiffs paid Rapid in excess of what Rapid was
entitled to. (See e.g., FAC ¶¶ 34-35;
37-39; 75-85.) Thus, of the $4,420,000
differential between what Plaintiffs expected to pay ($2,580,000) and the
amount they actually paid on the construction of their home ($7,000,000), the
only damages Rapid would be responsible for would be its proportion of those
damages incurred to remediate defective HVAC work that were caused by Rapid’s
allegedly erroneous test results.
In this regard, the HVAC system is just one small part of the entire
home construction project. Plaintiffs
allege there were major defects in project design, roofing, home waterproofing,
HVAC, and electrical/lighting, as well as ancillary issues with tiling and door
installation. Thus, the HVAC was one of
approximately five major issues with the home (design, roofing, waterproofing,
HVAC, and electrical/lighting). Dividing
the $4,420,000 differential by five results in an average estimation of $884,000
attributable to HVAC issues, although the Court notes that this amount is an
estimation, and the actual amount could be higher, if the HVAC issues constituted
a disproportionately large percentage of the repairs.
Rapid is only alleged to have played a small role in affecting the
HVAC system, which was otherwise the responsibility of Temperature, as the
primary HVAC subcontractor. Thus, Rapid’s
extremely limited role in testing the HVAC system on one day further limits
Rapid’s liability for the HVAC issues to approximately 10% at most. Thus, Rapid’s maximum potential liability likely
would not exceed $100,000.
2. THE
AMOUNT PAID IN SETTLEMENT.
‘“[A] defendant’s settlement figure must not be grossly
disproportionate to what a reasonable person, at the time of the settlement,
would estimate the defendant’s liability to be.’ [Citation.]”
(Tech-Bilt, supra, 38 Cal.3d at p. 499.) However, even though “an offer of settlement
must bear some relationship to one’s proportionate liability, bad faith is not
‘established by a showing that a settling defendant paid less than his
theoretical proportionate or fair share.’
[Citation.]” (North County,
supra, 27 Cal.App.4th at p.1090.) “Such a rule would unduly discourage
settlements” and “convert the pretrial settlement approval procedure into a
full-scale mini-trial.” (Tech-Bilt,
supra, 38 Cal.3d at p. 499.) Rather,
in order to meet the proportionality requirement, “all that is necessary is
that there be a ‘rough approximation’ between a settling tortfeasor’s offer of
settlement and his proportionate liability.
[Citation.]” (North County,
supra, 27 Cal.App.4th at pp. 1090–1091.) In determining whether the settling
defendant’s settlement figure is “within the ballpark” of his fair share of
liability, the Court may rely on “the judge’s personal experience” and the
experience of “experts in the field.” (Tech-Bilt,
supra, 38 Cal.3d at p. 500.)
For perspective, the Court granted E & J Plumbing’s motion for
good faith settlement wherein E & J paid a total of $150,000 on the
complaint and cross-complaint for the allegedly defective plumbing work
throughout the home.
Furthermore, Rapid’s strong defenses regarding the changes made to the
HVAC system between the time Rapid did its HERS testing and when the follow-up
HERS testing was done, plus the fact that the parties are settling their claims
instead of litigating them through trial similarly reduces the total liability
attributable to Rapid.
Therefore, Rapid’s settlement amount of $50,000 is “within the
ballpark” of Rapid’s fair share of liability, given Rapid’s small portion of
the total liability on the overall construction project and Rapid’s strong
defenses.
3.
THE ALLOCATION OF SETTLEMENT PROCEEDS AMONG PLAINTIFFS.
The
allocation of settlement proceeds among plaintiffs is only relevant if there is
more than one plaintiff. (See Cahill
v. San Diego Gas & Electric Co. (2011) 194 Cal.App.4th 939, 968
(hereafter Cahill).) Here, there
are two Plaintiffs, but both Plaintiffs are parties to the settlement. Therefore, this factor is irrelevant.
4.
A RECOGNITION THAT A SETTLOR SHOULD PAY LESS
IN SETTLEMENT THAN HE WOULD IF HE WERE FOUND LIABLE AFTER TRIAL.
The Court expressly recognizes that a settlor should pay less in
settlement than he would if he were found liable after trial. Here, the settlement represents approximately
50% of Rapid’s total potential share of the damages. A 50% discount from the amount Rapid could be
found liable for after trial is reasonable, in light of Rapid’s strong defenses
that it owes no liability whatsoever.
This factor supports the present motion for good faith
determination. (See Cahill, supra,
194 Cal.App.4th at p. 968.)
5.
THE FINANCIAL CONDITIONS AND INSURANCE
POLICY LIMITS OF SETTLING DEFENDANTS.
An
exception to the proportionality requirement described above is that “a
disproportionately low settlement figure is often reasonable” when the settling
defendant is “relatively insolvent” and uninsured or underinsured. (Tech-Bilt, supra, 38 Cal.3d at p.
499; see Schmid v. Superior Court (1988) 205 Cal.App.3d 1244, 1245–6
[holding that “a settlement of a personal injury lawsuit is in ‘good faith[]’ .
. . where a defendant pays the plaintiff the limit of the defendant’s insurance
policy and has no assets, even though the amount paid in settlement is far less
than the likely amount of a judgement against the defendant were the case to go
to trial”]; see also County of Los Angeles v. Guerrero (1989) 209
Cal.App.3d 1149, 1157–8 [finding that the settling defendant’s “modest”
financial condition and insurance limits “are necessarily controlling and
effectively override the other Tech-Bilt factors”].)
Because
the Court has not determined that the settlement amount is disproportionately
low, the exception does not apply.
6.
THE EXISTENCE OF COLLUSION, FRAUD, OR
TORTIOUS CONDUCT AIMED TO INJURE THE INTERESTS OF THE NON-SETTLING DEFENDANTS.
“Any
negotiated settlement involves cooperation, but not necessarily collusion. It becomes collusive when it is aimed to
injure the interests of an absent tortfeasor.
Although many kinds of collusive injury are possible, the most obvious
and frequent is that created by an unreasonably cheap settlement.” (River Garden Farms, Inc. v. Superior
Court (1972) 26 Cal.App.3d 986, 996.)
“Prevention of collusion is but a means to the end of preventing
unreasonably low settlements which prejudice a nonparticipating
tortfeasor. The price of a settlement is
the prime badge of its good or bad faith.
Construed in the light of [section 877.6’s] objectives, the good faith
release clause extends the obligation of good faith beyond the parties to the
negotiations, embracing an absent tortfeasor.”
(Ibid.)
Here,
there is no argument or evidence that the settlement was made in bad faith to
harm the remaining defendants.
CONCLUSION AND ORDER
For the reasons stated, the Court grants Rapid’s unopposed Motion for
a Determination of Good Faith Settlement.
Rapid is ordered to provide notice of the Court’s ruling and file
proof of service of such.
DATED: January 24, 2024 ___________________________
Michael
E. Whitaker
Judge
of the Superior Court