Judge: Michael E. Whitaker, Case: 21SMCV00045, Date: 2024-05-22 Tentative Ruling

Case Number: 21SMCV00045    Hearing Date: May 22, 2024    Dept: 207

TENTATIVE RULING

 

DEPARTMENT

207

HEARING DATE

May 22, 2024

CASE NUMBER

21SMCV00045

MOTION

Motion for Summary Judgment/Summary Adjudication

MOVING PARTY

Defendant Baypost Builders Inc.

OPPOSING PARTIY

Plaintiff H. Jewel Engstrom

 

MOVING PAPERS:

 

  1. Notice of Motion and Motion for Summary Judgment/Summary Adjudication; Memorandum of Points and Authorities
  2. Separate Index of Exhibits
  3. Request for Judicial Notice
  4. Separate Statement of Undisputed Material Facts

 

OPPOSITION PAPERS:

 

  1. Opposition to Motion for Summary Judgment/Summary Adjudication
  2. Objections to Evidence
  3. Separate Statement of Undisputed and Disputed Material Facts
  4. Separately Bound Exhibits
  5. Declaration of Plaintiff H. Jewel Engstrom
  6. Declaration of Steve Norris
  7. Declaration of Keith J. Turner

 

REPLY PAPERS:

 

  1. Reply to Plaintiff’s Opposition to Motion for Summary Judgment/Summary Adjudication
  2. Objections to Evidence
  3. Responses to Plaintiff’s Further Undisputed Material Facts

 

BACKGROUND

 

Plaintiff H. Jewel Engstrom, individually and as trustee of the Engstrom Family Trust, (“Plaintiff”) filed the operative Complaint on January 1, 2021 against Defendants 1400 Linda Flora Associates, LLC and Bay Post Builders, Inc. (“Baypost”), alleging five causes of action for (1) trespass; (2) negligence; (3) private nuisance; (4) public nuisance; and (5) financial elder abuse. 

 

Plaintiff alleges construction work done on her uphill adjacent neighbor’s property “repeatedly trespassed onto Plaintiff’s Property; have constructed a roadway, retaining wall, cell phone tower and related improvements on Plaintiff’s Property; and in excavating the 1400 Property, have damaged Plaintiff’s Property.”  (Complaint ¶ 11.)  Defendant 1400 Linda Flora Associates allegedly owns the neighboring uphill adjacent property and Defendant Bay Post Builders, Inc. is alleged to be the general contractor for the project.

 

Baypost has moved for summary judgment, or in the alternative, summary adjudication, on the following issues:

 

1)     The expiration of the applicable statutes of limitation as to all causes of action asserted against Baypost bar all causes of action, except the Fifth Cause of Action for Financial Elder Abuse;

 

2)     The expiration of the applicable statute of limitations as to the First Cause of Action for Trespass bars the cause of action as against Baypost;

 

3)     Baypost did not intentionally trespass on Plaintiff’s property as it was not on-the project at the time most of the alleged acts constituting trespass occurred, Baypost did not intentionally trespass on Plaintiff’s property as it was not aware at the time that the landscaping and irrigation work by M&M was being performed on Plaintiff’s property, Plaintiff’s property was not damaged by Baypost's entry, and its condition was actually improved;

 

4)     Defendant Baypost did have any legal duty owed to Plaintiff related to the professional services Baypost performed per agreement with the prior owner of the separate, upslope property located at 1400 Linda Flora Drive:

 

a.      Baypost did not have any form of agreement with and was not paid by Plaintiff, or any party to this action other than the prior owner of the separate, upslope property;

 

b.     Baypost was retained only by the prior owner of the separate, upslope property and performed no services of any kind under a separate agreement or understanding with Plaintiff;

 

c.      Baypost was not the general contractor for any alleged work performed on Plaintiff’s property;

 

d.     Baypost did not perform any excavation, construction, or other grading, and did not design any aspect of the work, allegedly performed on Plaintiff’s property;

 

e.      Baypost did not have any responsibility for the means and methods of any of the alleged work performed on Plaintiff’s property;

 

f.      Baypost was not the owner or occupier of, and did not have control over, the real property involved in this action and cannot bear any liability for the conditions on such property;

 

g.     The work that was performed exclusively on the upslope property located at 1400 Linda Flora Drive and managed by Baypost has performed as designed by independent engineers and approved by the City of Los Angeles Department of Building and Safety;

 

h.     Plaintiff cannot demonstrate any errors and/or omissions attributable to Baypost and cannot establish that any alleged errors and/or omissions on the part of Baypost have resulted in any demonstrable damages; therefore, Plaintiff’s cannot assert a tort claim against Baypost; and,

 

5)     Plaintiff cannot demonstrate any errors and/ or omissions attributable to Baypost and  cannot establish that any alleged errors and/or omissions on the part of Baypost have resulted in any demonstrable damages; therefore, Plaintiff cannot assert a tort claim against Baypost; and,

 

6)     As set forth above, Baypost did not owe a duty of care to Plaintiff, Baypost did not take any action to appropriate, take, and/or retain any of Plaintiff’s real and/or personal property, and Plaintiff cannot satisfy the elements for Elder Abuse as against Baypost; therefore Baypost prevails on the Fifth Cause of Action for Financial Elder Abuse.

 

Plaintiff opposes the motion and Moving Defendant replies.

 

EVIDENTIARY OBJECTIONS

 

            The Court rules as follows with respect to Plaintiff’s evidentiary objections:

 

Declaration of Ben Hamid Bayanfar

 

1.     Overruled

2.     Sustained

3.     Overruled

4.     Sustained

5.     Sustained

6.     Sustained

7.     Sustained

8.     Sustained as to the Google Earth photograph references, Overruled as to the grubbed/denuded references.

9.     Sustained as to the Google Earth photograph references, Overruled as to the roadway grading references.

10.  Sustained

11.  Sustained

12.  Sustained

13.  Sustained

14.  Sustained

15.  Sustained

16.  Sustained

17.  Sustained

18.  Sustained

19.  Sustained

20.  Sustained

21.  Sustained

22.  Sustained

23.  Sustained

24.  Sustained

25.  Sustained

26.  Sustained

27.  Sustained

28.  Sustained

29.  Sustained

30.  Sustained

31.  Sustained

32.  Sustained

33.  Sustained

34.  Sustained

35.  Sustained

36.  Overruled

37.  Overruled

38.  Overruled

39.  Sustained

40.  Sustained

41.  Sustained

42.  Sustained

 

Exhibit D: Sustained

Exhibit E: Sustained

Exhibit F: Sustained

Exhibit G: Sustained

Exhibit H: Sustained

Exhibit J: Sustained

Exhibit K: Sustained

Exhibit L: Sustained

Exhibit M: Sustained

Exhibit N: Sustained

 

The Court rules as follows with respect to the Moving Defendant’s objections to Plaintiff’s evidence:

 

  1. Sustained
  2. Overruled
  3. Overruled
  4. Overruled
  5. Overruled
  6. Overruled
  7. Overruled
  8. Sustained
  9. Sustained
  10. Overruled
  11. Overruled
  12. Overruled
  13. Sustained
  14. Overruled
  15. Sustained
  16. Sustained
  17. Sustained
  18. Overruled
  19. Overruled
  20. Overruled

20.5 Sustained

  1. Sustained
  2. Overruled
  3. Sustained
  4. Overruled
  5. Overruled
  6. Sustained
  7. Overruled
  8. Sustained
  9. Sustained

 

REQUEST FOR JUDICIAL NOTICE

 

Moving Defendant requests the Court to take judicial notice of (1) Plaintiff’s Complaint in this matter; and (2) Baypost’s answer to the Complaint.

 

Judicial notice may be taken of records of any court in this state.  (Evid. Code, § 452, subd. (d)(1).)  Therefore, the Court may take judicial notice of the First Amended Complaint and Baypost’s Answer thereto (Ibid.)   However, “while courts are free to take judicial notice of the existence of each document in a court file, including the truth of results reached, they may not take judicial notice of the truth of hearsay statements in decisions and court files.  Courts may not take judicial notice of allegations in affidavits, declarations and probation reports in court records because such matters are reasonably subject to dispute and therefore require formal proof.”  (Lockley v. Law Office of Cantrell, Green, Pekich, Cruz & McCort (2001) 91 Cal.App.4th 875, 882 [cleaned up].) 

 

Therefore, the Court takes judicial notice of the existence and legal effect of the Complaint and Baypost’s Answer, but not the truth of the allegations contained therein.

 

LEGAL STANDARDS – MOTION FOR SUMMARY JUDGMENT/ADJUDICATION

 

“[T]he party moving for summary judgment bears the burden of persuasion that there is no triable issue of material fact and that he is entitled to judgment as a matter of law[.] There is a triable issue of material fact if, and only if, the evidence would allow a reasonable trier of fact to find the underlying fact in favor of the party opposing the motion in accordance with the applicable standard of proof.” ¿(Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 850 (hereafter Aguilar).) ¿“[T]he party moving for summary judgment bears an initial burden of production to make a prima facie showing of the nonexistence of any triable issue of material fact; if he carries his burden of production, he causes a shift, and the opposing party is then subjected to a burden of production of his own to make a prima facie showing of the existence of a triable issue of material fact.” ¿(Ibid.; Smith v. Wells Fargo Bank, N.A. (2005) 135 Cal.App.4th 1463, 1474 [summary judgment standards held by Aguilar apply to summary adjudication motions].) 

 

Further, “the trial court may not weigh the evidence in the manner of a factfinder to determine whose version is more likely true.  Nor may the trial court grant summary judgment based on the court's evaluation of credibility.”  (Aguilar, supra, 25 Cal.4th. at p. 840 [cleaned up]; see also Weiss v. People ex rel. Department of Transportation (2020) 9 Cal.5th 840, 864 [“Courts deciding motions for summary judgment or summary adjudication may not weigh the evidence but must instead view it in the light most favorable to the opposing party and draw all reasonable inferences in favor of that party”].) 

 

A party may move for summary adjudication as to one or more causes of action, affirmative defenses, claims for damages, or issues of duty if that party contends that there is no merit to the cause of action, defense, or claim for damages, or if the party contends that there is no duty owed.  (See Code Civ. Proc., § 437c, subd. (f)(1).)  “A motion for summary adjudication shall be granted only if it completely disposes of a cause of action, an affirmative defense, a claim for damages, or an issue of duty.”  (Ibid.)  A cause of action has no merit if: (1) one or more elements of the cause of action cannot be separately established, even if that element is separately pleaded, or (2) a defendant establishes an affirmative defense to that cause of action.  (See Code Civ. Proc., § 437c, subd. (n); Union Bank v. Superior Court (1995) 31 Cal.App.4th 573, 583.)  Once the defendant has shown that a cause of action has no merit, the burden shifts to the plaintiff to show that a triable issue of material fact exists as to that cause of action.  (See Code Civ. Proc., § 437c, subd. (o)(2); Union Bank v. Superior Court, supra, 31 Cal.App.4th at p. 583.)  Additionally, in line with Aguilar, “[o]n a motion for summary adjudication, the trial court has no discretion to exercise.  If a triable issue of material fact exists as to the challenged causes of action, the motion must be denied. If there is no triable issue of fact, the motion must be granted.”  (Fisherman's Wharf Bay Cruise Corp. v. Superior Court (2003) 114 Cal.App.4th 309, 320.) 

 

DISCUSSION

 

1.     ISSUES 1 & 2: STATUTE OF LIMITATIONS

 

Code of Civil Procedure section 338 provides “An action for trespass upon or injury to real property” must be brought within three years.  Moving Defendants contend that the most recent potential trespass or injury to real property occurred from the repair of the January 2017 erosion scar, which was completed on September 24, 2017, more than three years before Plaintiff filed suit on January 11, 2021.

 

a.     Baypost’s Evidence

 

            In support of its argument, Baypost has provided the following evidence:

 

·       The first scar occurred on the Engstrom property in or about January 2017 (UMF No. 5.)

·       The solar tower did not exist when Baypost left the project on or about the 31st of August 2018, and Baypost knew nothing about the solar tower prior to viewing it in 2019 (UMF No. 81.)

 

Baypost also contends that the repair was performed by Geoworks Engineering Group (UMF No. 49), and the repair was completed by September 24, 2017 (UMF No. 90), but the Court has sustained Plaintiff’s objections to this evidence.  Therefore, Baypost has not submitted admissible evidence in support of these contentions.

 

Baypost also contends that two additional scars occurred on the neighboring Aldave property in August 2018 (UMF No. 6), although the Court sustains Plaintiff’s objections to the evidence submitted in support of that statement, and Baypost has provided admissible evidence that a third scar occurred on the Aldave slope during heavy rains in December of 2018 (UMF No. 8.) 

 

Thus, Baypost has presented evidence that the only damage to Plaintiff’s property occurred in January 2017, but Baypost has not presented admissible evidence that the repair of that scar was completed by September 24, 2017.  As such, Baypost has not met its initial burdens of production and persuasion that it last entered or damaged Plaintiff’s property more than three years before Plaintiff brought suit on January 11, 2021.  Therefore, the Court denies summary judgment as to issues 1 and 2. 

 

2.     ISSUE 3: INTENTIONAL TRESPASS

 

Baypost next contends it did not commit intentional trespass because it was not on the project when most of the trespass occurred, the trespass was not intentional because it was not aware that the landscaping and irrigation work was being performed on Plaintiff’s property; and Plaintiff’s property was not damaged by Baypost’s entry.

 

“Trespass is an unlawful interference with possession of property.”  (Staples v. Hoefke (1987) 189 Cal.App.3d 1397, 1406.)  “Liability for trespass may be imposed for conduct which is intentional, reckless, negligent or the result of an extra-hazardous activity.”  (Ibid.) 

 

Because liability for trespass may be imposed for reckless, negligent, or extra-hazardous activity, it does not matter whether Baypost’s trespass was intentional or whether it damaged Plaintiff’s property.

 

a.     Baypost’s Evidence

 

With regard to Baypost’s contention that it was not on the project when most of the trespass occurred, Baypost concedes that it originally believed the Aldave and Engstrom slopes were included in the project because they had been grubbed/denuded along with the adjacent project slope (UMF No. 33), that it now knows portions of the slope belong to the Aldave and Engstrom properties (UMF No. 34), that the ground cover and irrigation were installed on the properties from September 16, 2015 to October 28, 2015 (UMF No. 39.)

 

However, Baypost argues that a separate company, M&M Landscaping and Gardening Services, actually planted the ground cover and installed the irrigation, pursuant to a direct agreement between the owner of the upslope property and M&M (UMF No. 35-44.)  Baypost further argues that yet another company, Geoworks Engineering Group, Inc. did the work to repair the 2017 scar on the Engstrom property (UMF No. 48-56.)  Finally, Baypost provides evidence that in 2017 it was retained as general contractor for the construction of a 30-foot long retaining wall extension on the Linda Flora property (UMF No. 57), which it contends was staked by surveyor Steven Opdahl and constructed by EGM Construction, Inc. (UMF Nos. 57-65), and that Baypost left the project on August 31, 2018 (UMF No. 67.) 

 

The Court sustains Plaintiff’s evidentiary objections to the evidence that M&M, Geoworks, Steven Opdahl, and EGM Construction actually did the respective construction and repair work.  As such, Baypost has not provided admissible evidence that it was not involved in the construction or repair work that occurred on Plaintiff’s property.

 

Therefore, the Court denies summary adjudication as to Issue 3.

 

3.     ISSUE 4: DUTY

 

Baypost contends that the Court should grant summary adjudication as to the second cause of action for negligence, third cause of action for private nuisance, and forth cause of action for public nuisance, on the grounds that Baypost owed Plaintiff no duty of care.

 

The elements of a cause of action for private nuisance are (1) an interference with plaintiff’s use and enjoyment of plaintiff’s property; (2) the invasion of plaintiff’s interest must be substantial, i.e. it caused plaintiff to suffer substantial actual damage; and (3) the interference must also be unreasonable, i.e., of such a nature, duration, or amount as to constitute an unreasonable interference with the use and enjoyment of land.  (Today's IV, Inc. v. Los Angeles County Metropolitan Transportation Authority (2022) 83 Cal.App.5th 1137, 1176.)

 

Similarly, the elements of a cause of action for public nuisance are (1) a proscribed act; (2) interference with the comfortable enjoyment of life or property; and (3) whether the act affects a sufficient number of persons.  (People v. McDonald (2006) 137 Cal.App.4th 521, 535.)

 

Because duty is not an element of the causes of action for private nuisance or public nuisance, resolution of whether Baypost owed Plaintiff a duty of care will not dispose of these causes of action. 

 

With regard to negligence, “To state a cause of action for professional negligence, a party must show (1) the duty of the professional to use such skill, prudence and diligence as other members of the profession commonly possess and exercise; (2) breach of that duty; (3) a causal connection between the negligent conduct and the resulting injury; and (4) actual loss or damage resulting from the professional negligence.”  (Giacometti v. Aulla, LLC (2010) 187 Cal.App.4th 1133, 1137.)

 

Baypost argues there is no duty because (1) Baypost had no written agreement with Plaintiff, did not perform services for Plaintiff, and was not paid by Plaintiff; (2) Baypost was hired by the prior owner of the upslope property and performed no services under a separate oral agreement or understanding with Plaintiff; (3) Baypost was not the general contractor for any work performed on Plaintiff’s property; (4) Baypost did not perform any excavation, construction, grubbing/denuding, or other grading and did not design any aspect of the work performed on Plaintiff’s property; (5) Baypost was not responsible for the means and methods of any of the alleged work performed on Plaintiff’s property; (6) Baypost was not the owner or occupier and did not have control over the real property involved in this action

 

As a threshold matter, as discussed above, Baypost has not provided admissible evidence that it was not involved in the work performed on Plaintiff’s property.

 

Further, “the lack of privity of contract does not preclude imposition of a duty of care.”  (Weseloh Family Ltd. Partnership v. K.L. Wessel Construction Co., Inc. (2004) 125 Cal.App.4th 152, 164 (hereafter Weseloh).)  Thus, the fact that there was no direct contractual relationship between Baypost and Plaintiff does not automatically mean that Baypost owed Plaintiff no duty as a matter of law.

 

Baypost finally argues that because it was not the owner of and did not control the upslope property, there can be no liability.  In support, Baypost cites to Isaacs v. Huntington Memorial Hospital (1985) 38 Cal.3d 112, 113 (hereafter Isaacs) and Donnell v. California Western School of Law (1988) 200 Cal.App.3d 715, 720 (hereafter Donnell).  Both cases are inapposite.

 

In Isaacs, the Court held that the insurer who participated in the decision to dismiss security guards was not liable for plaintiff being assaulted in the hospital parking lot because it did not own, possess, or control the hospital premises.  Similarly, in Donnell, the court held that the defendant owner of land adjacent to city property was not liable for criminal assaults that occurred on the city-owned sidewalk, and the fact that defendant could have placed lights on its own property to illuminate the sidewalk does not create “control” sufficient for liability to attach.

 

By contrast, here, as general contractor, Baypost was responsible for supervising the construction of the retaining wall extension which may have caused Plaintiff’s damage.  As such, Baypost has not met its initial burdens of production and persuasion that there was no duty because there was no privity of contract, because subcontractors actually performed the work, and because Baypost did not own the upslope property.

 

Therefore, Baypost has not met its initial burdens of production and persuasion that Plaintiff will be unable to establish that Baypost owed her a duty.  As such, the Court denies summary adjudication as to Issue 4.

 

4.     ISSUE 5: CAUSATION

 

a.     Baypost’s Evidence

 

Baypost next argues that no acts or omissions by Baypost caused Plaintiff’s harm.  In support, Baypost provides the following evidence:

 

·       During Baypost’s inspection of the project in September 2019, Bayanfar did not observe anything that indicated the retaining wall was failing.  (UMF 70.)

·       During Baypost’s February 12, 2024 site inspection of the Aldave and Engstrom slopes, Bayanfar did not observe anything that indicated the retaining wall extension was not performing as designed.  (UMF No. 74.)

·       At no time was Baypost advised by Linda Flora, the geologist, the soils engineer, the structural engineer, or the City of Los Angeles Department of Building and Safety that the retaining wall extension was not performing and was failing.  (UMF No. 79.)

 

Therefore, Baypost has met its initial burdens of production and persuasion that none of its acts or omissions caused Plaintiff’s harm.

 

b.     Plaintiff’s Evidence

 

In opposition, Plaintiff has provided the expert declaration of Steve Norris, which indicates:

 

It is my opinion that the retaining wall extension did not provide for proper control of stormwater runoff or drainage from the areas behind it, and instead allowed for the collection of water in the area of construction and diversion of runoff and associated loose debris and materials around the edge of the wall and down the slope. The loose soil material was deposited and collected below the portion of the Aldave slope that had been cleared of brush, or “grubbed,” as part of the construction at the Linda Flora property. It is my opinion that, during the rainy season of the winter of 2023-2024, the loose soil material, associated in part with Baypost’s work, cascaded down the slope behind the Aldaves’ home, causing significant damage to both the Aldave property and Ms. Engstrom’s property.

 

(Norris Decl. ¶ 5.)

 

            Therefore, Plaintiff has created a triable issue of material fact as to whether the retaining wall extension caused harm to Plaintiff’s property.

 

            As such, the Court denies summary adjudication as to Issue 5.

 

5.     ISSUE 6: ELDER ABUSE

 

“Financial abuse” of an elder or dependent adult occurs when a person or entity does any of the following:

 

(1)   Takes, secretes, appropriates, obtains, or retains real or personal property of an elder or dependent adult for a wrongful use or with intent to defraud, or both.

 

(2)   Assists in taking, secreting, appropriating, obtaining, or retaining real or personal property of an elder or dependent adult for a wrongful use or with intent to defraud, or both.

 

(3)   Takes, secretes, appropriates, obtains, or retains, or assists in taking, secreting, appropriating, obtaining, or retaining, real or personal property of an elder or dependent adult by undue influence, as defined in Section 15610.70.

 

(Welf. & Inst. Code, § 15610.30, subd. (a).)

 

            The Complaint alleges:

 

13. Plaintiff is informed and believes that Defendants entered Plaintiff’s Property, removed or compacted soil, landscaped the area, and remediated the erosional scar, all without Plaintiff’s consent. Defendants’ excavation for the Project was not proper or usual excavation for the purpose of construction. Plaintiff is informed and believes that Defendants entered Plaintiff’s Property and performed or caused to be performed excavation and other conduct on Plaintiff’s Property, including, without limitation: the entry of workers and equipment onto Plaintiff’s Property; the removal and / or compaction of soil thereon; the removal of native plants therefrom; and the planting of landscaping thereon; all without any prior notice to Plaintiff and without Plaintiff’s consent.

 

[…]

 

76. Plaintiff is older than 65 years of age.

 

77. Defendants have wrongfully taken Plaintiff’ Property as alleged above.

 

[…]

 

79. Here, Defendants knew or should have known that their conduct in taking and retaining Plaintiff's Property, would be harmful to Plaintiff and to Plaintiff's interest in the Property.

 

80. Each Defendant's conduct, individually, and all of the Defendants' conduct, collectively, was a substantial factor in causing Plaintiff's harm.

 

(Complaint ¶¶ 13, 76-77, 79-80.)

 

a.     Baypost’s Evidence

 

Baypost contends that there is no evidence that it took or assisted in taking Plaintiff’s property.  In support, Baypost has provided the following evidence:

 

·       Trees and bushes were removed from a portion of the upper Slope of the Aldave Property and the Engstrom Property prior to August of 2012.  (UMF No. 26.)

·       The Aldave and Engstrom slopes had already been grubbed/denuded when Baypost began acting as Project Manager of the Project.  (UMF No. 30.)

·       The plans Baypost received for the planting of the ground cover specified work in the grubbed/denuded area of what Baypost now knows to be the Aldave and Engstrom property.  (UMF No. 34.)

·       Linda Flora Associates entered into a contract with M&M Landscaping and Gardening Services to plant ground cover and install jute netting and irrigation on a portion of the Aldave and Engstrom Properties that had been grubbed/denuded.  (UMF No. 35.) 

·       The retaining wall extension was constructed entirely on the uphill property.  (UMF No. 58.)

·       The solar tower did not exist when Baypost contends it left the project on or about the 31st of August 2018, and Baypost knew nothing about the solar tower prior to viewing it in 2019. (UMF No. 81.)

·       Prior to leaving the Project, Baypost never observed plans for the solar tower and Baypost was never advised that a solar tower was being considered for any reason. (UMF No. 82.)

·       Baypost was not involved with the design, construction, placement or installation of the solar tower. (UMF No. 83.)

·       At no time did Baypost take, hide, appropriate, obtain or retain the Engstrom slope. (UMF No 87.)

 

Therefore, Baypost has met its initial burdens of production and persuasion that it did not take anything from Plaintiff’s property.

 

b.     Plaintiff’s Evidence

 

In opposition, Plaintiff cites to the evidence demonstrating that Baypost was the general contractor, and the expert opinion of Steve Norris, indicating that the poor drainage for the retaining wall extension caused the mudslide to bring debris onto Plaintiff’s property. 

 

But none of this evidence demonstrates that Baypost or any of its agents took anything from Plaintiff’s property.  The shrubs that had been denuded were taken before Baypost began work on the project, and the rest of Plaintiff’s damages allege trespassing onto Plaintiff’s property, placing items on Plaintiff’s property (including ground cover, part of an irrigation system, and a cell phone tower), remediating the erosion scar, and causing mud and debris to slide onto Plaintiff’s property.

 

Therefore, Plaintiff has not met her burden of demonstrating a triable issue of material fact that Baypost took anything from Plaintiff’s property.  As such, the Court grants summary adjudication as to Issue 6.

 

CONCLUSION AND ORDER

 

Therefore, the Court grants in part and denies in part Baypost’s Motion for Summary Adjudication.  Having found Baypost met its initial burdens of production and persuasion that it did not take anything from Plaintiff’s property, and Plaintiff has not created any triable issue of fact that Baypost did take anything, the Court grants summary adjudication as to Issue 6. 

 

Having found Baypost failed to meet its initial burdens of production and persuasion that the statute of limitations has expired, that it did not intentionally trespass, or that it did not owe a duty of care to Plaintiff, the Court denies summary adjudication as to Issues 1-4.

 

Having found that Baypost met its initial burdens of production and persuasion, but that Plaintiff created triable issues of material fact as to whether Baypost’s actions or omissions caused Plaintiff’s damages, the Court denies summary adjudication as to Issue 5.

 

Because the Court denies summary adjudication as to Issues 1, 2, 3, 4, and 5, the Court similarly denies summary judgment.

 

Baypost shall provide notice of the Court’s ruling and file the notice with a proof of service. 

 

 

 

 

 

DATED:  May 22, 2024                                                         ___________________________

                                                                                          Michael E. Whitaker

                                                                                          Judge of the Superior Court