Judge: Mitchell L. Beckloff, Case: 22STCP03463, Date: 2024-02-07 Tentative Ruling
Case Number: 22STCP03463 Hearing Date: February 7, 2024 Dept: 86
ZUSSER COMPANY, INC. v. CALIFORNIA DEPARTMENT OF
INDUSTRIAL RELATIONS
Case Number: 22STCP03463
Hearing Date: February 7, 2024
[Tentative] ORDER
DENYING PETITION FOR WRIT OF MANDATE
Petitioner, Zusser Company, Inc., seeks a writ of
administrative mandate directing Respondent, Katrina S. Hagen, in her official capacity as the Director of the
Department of Industrial Relations (Director) to set aside an administrative
decision affirming a Civil Wage and Penalty Assessment (Assessment) issued by
Real Party in Interest, the Division of Labor Standards Enforcement (DLSE;
collectively with the Director, Respondents). The Assessment arose from a
public works contract between Petitioner and the Metropolitan Water District of
Southern California (MWD) referred to as the Los Angeles Department of Water
and Power (LADWP) Lagoon Refurbishment Project (the Project). Petitioner
challenges the Director’s finding Petitioner misclassified certain workers on
the Project as Sewer and Storm Drain Pipelayers and Drain Pipe Tradesman
instead of Industrial Pipefitters.
DLSE’s
request for judicial notice is denied.
Petitioner’s objections to the request for judicial notice are
sustained.
The Board
Action Report (Report) is part of the administrative record; therefore, the
Report will be considered by the court. (AR 2836-2842.) However, DLSE impliedly
requests to augment the administrative record with additional material related
to the Report, including “video of the Board’s consideration of agenda item 8-3
and all accompanying material.” (RJN 2:15-16.)
In general, “a hearing on a writ of administrative mandamus is
conducted solely on the record of the proceedings before the administrative
agency.” (Toyota of Visalia, Inc. v. New
Motor Vehicle Bd. (1987) 188 Cal.App.3d 872, 881.) Extra-record
evidence may be admitted if, in the exercise of reasonable diligence, the
relevant evidence could not have been produced or was improperly excluded at
the hearing. (Code Civ. Proc., § 1094.5, subd. (e).) A request for judicial notice cannot be
used to circumvent the rules concerning augmentation of the administrative record.
(Ballona Wetlands Land Trust v. City of Los Angeles (2011) 201
Cal.App.4th 455, 475, fn. 10.)
DLSE has
not addressed the requirements of Code of Civil Procedure, section 1094.5, subdivision
(e). DLSE could have, with the exercise of reasonable diligence, submitted
video of the Board meeting (from January 2015) or other materials related to
the Report in the administrative proceedings. Because the reasonable diligence
requirement of Code of Civil Procedure section 1094.5, subdivision (e) is not
satisfied, DLSE’s requests for judicial notice and to augment the record are
denied.
BACKGROUND
Statutory
Framework
“Under
California's prevailing wage law (Lab. Code, § 1720 et
seq.), all public works
contracts involving projects of more than $1,000 require workers be paid no
less than the general prevailing wage rates consisting of cash wages and fringe
benefits.” (Department of Industrial Relations v. Nielsen Construction Co.
(1996) 51 Cal.App.4th 1016, 1020.) “The prevailing wage is determined by the
Director of the Department of Industrial Relations [] according to the craft,
classification or type of worker needed for the project in the particular
locality in which the work is to be performed. (§§ 1770, 1773.)” (Ibid.)
Based on the contract
terms, contractors and subcontractors may be deemed to have constructive notice
of the applicable prevailing wage rates. (See Division of Labor Standards
Enforcement v. Ericsson Information Systems (1990) 221 Cal.App.3d 114,
125.) The contractor also has “the opportunity to request clarification as to
which existing classification applied or to request the director to
specially designate one.” (Ibid.; accord Sheet Metal Workers
Internat. Assn., Local Union No. 104 v. Rea (2007) 153 Cal.App.4th 1071,
1079-1085.)[1]
When DLSE
determines a violation of the prevailing wage laws has occurred following an
investigation, it may issue an Assessment for the wages and penalties due. (Lab.
Code,[2] § 1741, subd. (a).) “An
affected contractor or subcontractor may obtain review of a civil wage and
penalty assessment . . . .” (§ 1742, subd. (a).) “The contractor or
subcontractor shall have the burden of proving that the basis for the civil
wage and penalty assessment is incorrect.”
(§ 1742, subd.
(b).) DLSE “has the burden of coming forward with evidence that . . . provides
prima facie support for the Assessment or Withholding of Contract Payments.” (Cal.
Code Regs., tit. 8, § 17250, subd. (a).) “If the Enforcing Agency meets its
initial burden . . . , the Affected Contractor or Subcontractor has the burden
of proving that the basis for the Civil Wage and Penalty Assessment or for the
Withholding of Contract Payments is incorrect.” (Id. at § 17250, subd. (b).)
“An affected contractor or subcontractor may obtain review of the decision of
the director by filing a petition for a writ of mandate to the appropriate
superior court pursuant to Section 1094.5 of the Code of Civil Procedure.” (§ 1742, subd. (c).)
///
The Project
On October
6, 2014, MWD invited bids for the Project located in Granada Hills. (AR 2835.)
The notice inviting bids provided a description of the Project:
The work
consists of construction of approximately 7,000 feet of 6-inch to 8-inch PVC
pipe, 500 feet of 2-inch PVC pipe, 1,700 feet of utility ductbanks, and three
maintenance holes; modification of two existing maintenance holes; installation
of two standpipes, five submersible pumps and two turbidity meters; on-site
screening of approximately 6,100 cubic yards of underdrain rock; disposal of
approximately 2,000 cubic yards of hazardous material; installation of
approximately 12,500 cubic yards of crushed rock; refurbishment of existing
decant valve structures for four lagoons including asbestos and PCB abatement;
installation of local electrical panels and a utility cabinet; and other
appurtenant work as specified and shown on the drawings. (AR 2782.)
The notice reported
MWD “expects the total cost of construction to range between $2,700,000 and
$3,200,000.” (AR 2782) The notice stated “[a] pre-bid conference will be held
with responsible representatives of prospective bidders at the Joseph Jensen
Water Treatment Plant, 13100 Balboa Blvd., Granada Hills, CA 91344.” (AR 2782.)
The Project
consists of the refurbishment of four lagoons located on property owned by
LADWP. (AR 861, 2836; Opening Brief 6:16.) MWD leased the lagoons from LADWP
for long-term use as part of a “new solids handling system” for MWD’s Joseph
Jensen Water Treatment Plant (the Jensen Plant). (AR 2836-2837 [Report awarding
contract to Petitioner (submitted as DLSE Exhibit No. 12)].)
Petitioner
described the intended use of the lagoons in its closing brief filed in the administrative
proceedings:
The nearby
Jenson Water Treatment Plant . . . exclusively treats water and delivers to MWD
for distribution. Residual solids collected from the [Jensen Plant’s]
sedimentation basins were previously thickened onsite, transported via a
temporary solids transfer system, and then air-dried at two nearby lagoons on
LADWP property. (See Exhs. 10 and 12.)
Solids
produced at the [Jensen Plant] also were discharged in the City of Los Angeles
Sanitary Sewer System. However, sewer disposal is expensive and is limited by
the “discharge permit.” (See Ex. 12.)
To solve
this problem MWD sought to refurbish lagoons owned by LADWP. (AR 861.)
MWD awarded
the contract for the Project to Petitioner with a successful bid of
$3,067,900. The four competing bids
ranged from approximately $3.2 million to $4.3 million. (AR 8 and fn. 8.)
Petitioner
performed work as the general contractor on the Project between July 27, 2015
and August 22, 2017. (AR 8, 3404, 3493.) The Project bid and contract documents
advised Petitioner of and required compliance with the provisions of the Public
Works Law (PWL) related to prevailing wages. (AR 2787, 2833-2835.)[3]
The
Assessment, Administrative Hearing, and Administrative Decision
After an
investigation conducted by Industrial Relations Representative Reisee Salamero,
DLSE determined Petitioner failed to pay workers on the Project the required
prevailing wage rates in several ways, including misclassifying workers as
“Pipelayer” and “Pipe Tradesman” for work which properly falls under the
“Industrial Pipefitter” scope of work. (AR 8-10; 2606-2612.) The relevant scope of work adopted by the
Director for the Industrial Pipefitter classification specifies that it covers:
“All piping in connection with central distributing filtration treatment
stations, boosting stations, waste sewage disposal plants, central chlorination
and chemical treatment work and all underground supply lines to cooling wells,
suction basins, filter basins, settling basins and aeration basins.” (AR 2857,
2606.) Salamero found the Project’s four lagoons were part of the Jensen Plant,
a filtration treatment plant, and therefore the Industrial Pipefitter
classification applied to certain workers—not Pipelayer and Pipe Tradesman. (AR
133-138.)
On March
11, 2019, Salamero issued her Assessment for $547,189.87. The Assessment included
unpaid wages for the misclassifications, unpaid training funds, various
penalties, and apprenticeship violations. (AR 2614-2624.)[4]
Petitioner
timely filed a request for review of the Assessment. The Department of Industrial
Relations conducted a review hearing on November 20, 2019, October 23, 2020,
October 28, 2020, and June 16, 2021. (AR 4.) DLSE presented documentary
evidence and testimony by Salamero to establish prima facie support for
the Assessment. (AR 10-12.) Petitioner presented documentary evidence and
testimony by its Chief Financial Officer and Secretary, Mikhail Fyodorov in
opposition to the Assessment. (AR 17-20.)
The parties
submitted their briefs on August 3, 2021 and August 17, 2021. The matter was thereafter
submitted for decision on August 17, 2021. (AR 5.)
A year
later, in a detailed written decision dated August 18, 2022, the Director
affirmed the Assessment. The Director found “DLSE carried its initial burden of
presenting evidence at the Hearing that provided prima facie support for the
Assessment, and that [Petitioner] failed to carry its burden of proving the
basis for the Assessment was incorrect.” (AR 6.)
This proceeding ensued.
STANDARD OF REVIEW
Petitioners seek relief from the court pursuant
to Code of Civil Procedure section 1094.5.
Under Code of Civil Procedure section
1094.5, subdivision (b), the relevant issues are whether the respondent has
proceeded without jurisdiction, whether there was a fair trial, and whether
there was a prejudicial abuse of discretion. An abuse of discretion is
established if the agency has not proceeded in the manner required by law, the
decision is not supported by the findings, or the findings are not supported by
the evidence. (Code Civ. Proc., § 1094.5, subd. (b).)
Administrative decisions affirming civil
wage and penalty assessments issued by DLSE under the PWL do not affect a
fundamental vested right. (See Northern Inyo
Hosp. v. Fair Emp. Practice Com. (1974) 38 Cal.App.3d 14, 23. [“[T]here is
no vested right to conduct a business free of reasonable governmental rules and
regulations.”]) Accordingly, review of the Director’s findings here is governed
by substantial evidence.
Substantial
evidence is relevant evidence that a reasonable mind might accept as adequate
to support a conclusion (California Youth
Authority v. State Personnel Board (2002) 104 Cal. App. 4th 575, 584-585),
or evidence of ponderable legal significance which is reasonable in nature,
credible and of solid value. (Mohilef v.
Janovici (1996) 51 Cal. App. 4th 267, 305 n. 28.) Under the substantial evidence test,
“[c]ourts may reverse an [administrative] decision only if, based on the
evidence . . ., a reasonable person could not reach the conclusion reached by
the agency.” (Sierra Club v. California
Coastal Com. (1993) 12 Cal.App.4th 602, 610.)
In addition,
an agency is presumed
to have regularly performed its official duties. (Evid. Code,
§ 664.) “[A] trial court must afford a
strong presumption of correctness concerning the administrative findings.” (Fukuda v. City of Angels (1999) 20 Cal.
4th 805, 817.) A petitioner seeking administrative mandamus has the burden of proof and
must cite to the administrative record to support its contentions. (See Alford
v. Pierno (1972) 27 Cal.App.3d 682, 691.) A
court reviewing the administrative decision “will not act as counsel for either
party [] and will not assume the task of initiating and prosecuting a search of
the record for any purpose of discovering errors not pointed out in the
briefs.” (Fox v. Erickson (1950) 99
Cal.App.2d 740, 742 [in context of review by appeal].) When there is a challenge to “the
sufficiency of the evidence, all material evidence on the point must be set
forth and not merely [its] own evidence.” (Toigo v. Town of Ross (1998)
70 Cal.App.4th 309, 317.)
“On questions of law arising in mandate
proceedings, [the court] exercise[s] independent judgment.” (Christensen v. Lightbourne (2017) 15
Cal.App.5th 1239, 1251.) The interpretation of statute or regulation is a
question of law. (See State Farm Mut.
Auto. Ins. Co. v. Quackenbush (1999) 77 Cal.App.4th 65, 77.)
ANALYSIS
The Director Did Not Prejudicially Abuse Her
Discretion By Admitting and Relying Upon the Report
In a lengthy footnote, Petitioner contends the
Director prejudicially abused her discretion in admitting and relying upon the
Report. (Opening Brief 17, fn. 11.)
Specifically, Petitioner contends the Report is “hearsay and cannot
support a finding by itself, without corroborating admissible evidence.” (Opening
Brief 17, fn. 11.) Petitioner also objects that the Report “was not produced to
[it] until the parties exchanged exhibits 3 weeks before the hearing.” (Opening
Brief 17, fn. 11.)
Petitioner relies on applicable regulations to support
its claim. California Code of Regulations, title 8, section 17224, subdivision (d)
provides:
The Enforcing Agency shall make evidence available
for review as specified in subparts (a) through (c) within 20 days of its
receipt of the Request for Review; provided that, this deadline may
be extended by written request or agreement of the Affected Contractor or
Subcontractor. The Enforcing Agency's failure to make evidence available for
review as required by Labor Code section 1742(b) and
this Rule, shall preclude the Enforcing Agency from introducing such evidence
in proceedings before the Hearing Officer or the Director.
The provision is qualified by subdivision (e) of the
same regulation. It states:
This Rule shall not
preclude the Enforcing Agency from relying upon or presenting any evidence
first obtained after the initial disclosure of evidence under subparts (a)
through (d), provided
that, such evidence is promptly disclosed to the Affected
Contractor or Subcontractor. (Cal. Code Regs, tit. 8, § 17224 subd. (e).)
Relatedly, Labor Code section 1742, subdivision
(b) provides in pertinent part:
The contractor or subcontractor
shall be provided an opportunity to review evidence to be utilized by the Labor
Commissioner at the hearing within 20 days of the receipt of the written
request for a hearing. Any evidence obtained by the Labor Commissioner
subsequent to the 20-day cutoff shall be promptly disclosed to the contractor
or subcontractor.
During the administrative hearing,
the parties stipulated “the Request for Review was timely” and “[t]he]
enforcement file was timely made available.” (AR 65.) Accordingly, there is no disputed DLSE
complied with the initial disclosure requirement of sections 1742,
subdivision (b) and California Code of Regulations, title 8, section 17224,
subdivision (b)-(d).
Petitioner suggests DLSE failed to timely disclose
the Report and should have been barred from submitting the Report into
evidence, because “[i]t was not produced to [Petitioner] until the parties
exchanged exhibits 3 weeks before the hearing.” (Opening Brief 17, fn. 11.) The
court is not persuaded.
California Code of Regulations, title 8, section
17224, subdivision (d) expressly authorizes DLSE to “rely[] upon” and “present”
evidence “first obtained after the initial
disclosure of evidence,” provided that such evidence “is promptly disclosed to
the Affected Contractor or Subcontractor.” Here, it is undisputed Salamero
obtained the Report after an internet search about six weeks prior to the administrative
hearing. Salamero conducted the search only after Petitioner asserted the
Jensen Plant is not connected to the lagoons. (AR 11, fn. 16; AR 151-154. See
also Opening Brief 17, fn. 11 [Salamero obtained Report “a week or two before
the exhibits were produced”].) It is also undisputed DLSE produced the Report
to Petitioner about three weeks prior to the hearing. (AR 79-83.)
In its Opening Brief, Petitioner
does not develop any argument DLSE did not “promptly disclose[]” the Report after
Salamero obtained it. In its Reply Brief, Petitioner argues DLSE did not promptly
disclose the Report because it was produced “three weeks prior to the hearing
on the last possible day.” (Reply 12:14-1.) Petitioner
fails to explain, however, why given the circumstances DLSE’s disclosure should
not be considered “prompt.” The evidence shows DLSE disclosed the Report
shortly after Salamero obtained it and when the parties timely exchanged
exhibits for the administrative hearing.
On this record and argument, the
court concludes DLSE satisfied its obligation to promptly disclose the Report. The
court also notes Petitioner has not identified any prejudice from the disclosure
of the Report three weeks prior to the hearing.[5]
In its Opening Brief, Petitioner
cites no authority for his assertion DLSE could not rely on the Report because
it was discovered after the Assessment was issued, and “it was not part of [Salamero’s]
investigation . . . . (See Opening Brief 17, fn. 11.) For the first time in
reply, Petitioner asserts “[t]he admissible evidence that must be utilized [to
support DLSE’s prima facie case] is that which the Deputy relied upon at
the time of the issuance of the [Assessment] on March 11, 2019.” (Reply 9:13-14
[citing Cal. Code Regs., tit. 8, § 17250, subd. (a).)
First, Petitioner does not show good
cause to raise this argument for the first time in its Reply Brief. (Balboa Ins. Co. v. Aguirre (1983) 149 Cal.App.3d 1002, 1010.) The argument is
not new—Petitioner made the claim during the hearing, and there is no reason
Petitioner could not have raised the claim to provide Respondents with a full opportunity
to address the claim. (AR 143.) The court rejects the late reply argument on
that procedural basis.
Second, even assuming the
court did not reject the late argument on procedural grounds, Petitioner’s late
reply argument is unpersuasive on the merits. California Code of Regulations,
title 8, section 17250, subdivision (a)—upon which Petitioner relies—does not
state or suggest DLSE is strictly limited to evidence it relied upon when it
issued an assessment to prove its prima facie case at the hearing.[6]
Petitioner cites no other authority for its position.
The court also notes
Petitioner’s position directly conflicts with section California Code of Regulations,
title 8, section 17224, subdivision (e) and section 1742, subdivision (b). Both
provisions expressly indicate DLSE may rely on evidence “first obtained after
the initial disclosure of evidence” (Cal. Code Regs., tit. 8, § 17224, subd.
(e)) as long as such evidence is promptly disclosed to the affected contractor.
Petitioner’s hearsay argument related
to the Report (see Opening Brief 17, fn., 11) concludes without any real analysis
the Report is “hearsay and lacked foundation.”[7]
California Code of Regulations, title 8, section 17244 provides in part:
(a) The hearing need not be
conducted according to technical rules relating to evidence and witnesses. Any
relevant evidence shall be admitted if it is the sort of evidence on which
responsible persons are accustomed to rely in the conduct of serious affairs,
regardless of the existence of any common law or statutory rule which might
make improper the admission of such evidence over objection in civil actions. .
. .
. . . .
(d) Hearsay evidence is admissible
but shall not be sufficient in itself to support a finding unless it either
would be admissible over objection in a civil action or no Party raises an
objection to such use.
Salamero testified she found the
Report published on MWD’s website. (AR 154.) Given its location on MWD’s website,
MWD has provided the information to inform the public about MWD’s affairs. According
to the Report, it was prepared by MWD staff for a meeting of the MWD’s Board of
Directors held on January 13, 2015. The Report purports to have been signed by
a Chief Engineer and General Manager of MWD in December 2014. (AR 2836-2839.)
The court agrees with Petitioner—the
Report is hearsay.[8] Nonetheless, the Report is
admissible in evidence because the Report “is the sort of evidence on which
responsible persons are accustomed to rely in the conduct of serious affairs, .
. . .” (Cal. Code Regs, tit. 8, § 17244, subd. (a).) The Report’s location and
subject matter provide sufficient indicia of reliability to support use of it
for decision making in matters of serious affairs. Petitioner has not argued
otherwise.[9]
(See Opening Brief 17, fn. 11.)
Given the Report’s admissibility under
California Code of Regulations, title 8, section 17244, subdivision (a) on
these facts, Petitioner does not demonstrate the Director erred by receiving the
Report into evidence or relying upon it.[10]
Substantial Evidence Supports the Director’s Findings
that DLSE Met its Burden to Present Evidence Showing Prima Facie Support
for the Assessment
The
Director made the following findings, among others, when she found DLSE met its
initial burden of proof for the Assessment:
[T]he
scopes of work for the Plumber subclassifications, as well as Salamero's
understanding that the scope of work for the Project was to refurbish the
lagoons connected to the Joseph Jensen Water Treatment Plant. Salamero's
understanding was based on information provided to her by both the Awarding
Body and by the workers she interviewed. . . . MWD's Jensen Plant is a water
treatment plant that delivers water into the water distribution system. (DLSE
Exhibit No. 12 [the Report], p. 238). As part of its water treatment process,
Jensen Plant transfers solids through a pipeline to the lagoons on the LADWP's
Aqueduct Filtration Plant. (Id. at pp. 238-239.) For these reasons, the piping
work underneath the drainage rock in the lagoons constituted piping in
connection with a central distributing filtration treatment station as well as
underground supply lines to filter basins. (AR 23.)
Petitioner contends DLSE did not
meet its burden to present prima facie support for the Assessment
because: (1) “There was no testimony by anyone but Salamero (Opening Brief 17:13);
(2) Salamero “had no understanding of the Project scope of work, and failed to
reach out to anyone within her own agency [or the awarding body, MWD] that
could give her guidance as to the appropriate classification” (Opening Brief 17:14-15);
(3) Salamero had not visited the jobsite; (4) “Salamero’s testimony is not
credible” (Opening Brief 17:17);
(5) Salamero “misled” the Hearing
Officer and her supervisor in her penalty review (Opening Brief 18:3); (6) “The
bid and contract documents did not provide any notice that the lagoons are
connected to the Jensen Plant or any filtration plant” (Opening Brief 19:13-14);
(7) Petitioner’s contracted work was performed “exclusively” in the lagoons
(Opening Brief 7:12); and (8) the Report “relates to future plans with respect
to the lagoons but had nothing to do with the work performed by” Petitioner. (Opening
Brief 19:4-5.)
As discussed, with substantial evidence review “[the
court] do[es] not weigh the evidence, consider the credibility of witnesses, or
resolve conflicts in the evidence or in the reasonable inferences that may be
drawn from it. The administrative agency’s findings come before [the court]
with a strong presumption as to their correctness and regularity. [The court]
do[es] not substitute [its] judgment if the agency’s decision is one which
could have been made by reasonable people. (Doe v. Regents of the University
of California (2016) 5 Cal.App.5th 1055, 1073; accord Valenzuela v.
State Personnel Board (2007) 153 Cal.App.4th 1179, 1184-1185 and California
Youth Authority v. State Personnel Board (2002) 104 Cal. App. 4th 575, 584-585.)
Salamero determined the Industrial Pipefitter classification
applied to the plumbing-related work on the Project pursuant to subsection
A.1.36 of the Plumber scope of work provision, which provides: “All piping
in connection with central distributing filtration treatment stations,
boosting stations, waste sewage disposal plant, central chlorination, and
chemical treatment work, and all underground supply lines to the cooling wells,
suction basins, filter basins, settling basins, and aeration basins.” (AR 125
[emphasis added].)
Salamero testified her “understanding of the scope of work of
this project, the LADWP/Metropolitan lagoons was . . . a filtration plant.” (AR
124-125, 128, 133, 137.) Salamero opined the lagoons and the Jensen Plant were
“attached” and “operate hand in hand.” (AR 133.) Salamero’s understanding of
the scope of work was supported by her review of the Project contract provided
to DLSE by the MWD, the scope of work provision for the Plumber prevailing wage
determination, and her interviews with workers. (AR 112-114, 354-358.) Salamero
further explained she found the Industrial Pipefitter classification applied
because the pipework installed by Petitioner did not involve sewers or storm
drains. (AR 128, 132-133, 2867.)
Significantly, Salamero also explained she determined the
work properly fell under the Industrial Pipefitter scope of work because MWD
awarded the contract for the Project, and MWD owns and operates the water
filtration plan, not LADWP. (AR 132: 10-24.) Salamero questioned: “if in fact the lagoons are owned by LADWP,
why would [LADWP] not have been the awarding body . . . .” Relatedly, the
notice inviting bids stated “[a] pre-bid conference will be held with
responsible representatives of prospective bidders at the Joseph Jensen Water
Treatment Plant, 13100 Balboa Blvd., Granada Hills, CA 91344.” (AR 2782.)[11]
The Report also corroborates Salamero’s
and DLSE’s determination the Industrial Pipefitter classification applied to the Project. The
subject of the Report included the contract with Petitioner “to refurbish
solids lagoons for the Joseph Jensen Water Treatment Plant.” (AR 2836.) The Report summarized the Project:
This action awards a construction
contract to refurbish four existing solids lagoons on property owned by the Los
Angeles Department of Water and Power (LADWP) for long-term use by
Metropolitan's Joseph Jensen Water Treatment Plant. Use of the refurbished
lagoons will support reliable, long-term solids handling at the Jensen plant.
(AR 2836 [emphasis added].)
The Report further provides:
Residual solids collected from the Jensen plant's sedimentation basins
are currently thickened on-site, transported via a temporary solids transfer
system, and then air-dried at two nearby lagoons on LADWP property at the
Aqueduct Filtration Plant. This cooperative arrangement, which was initiated in
2005, provides sufficient solids handling capacity to process only 15 percent
of the solids generated at the Jensen plant's maximum flowrate under design
conditions. Solids produced at the Jensen plant may also be discharged to a
city of Los Angeles sanitary sewer. However, sewer disposal is expensive and is
limited by the discharge permit. [¶] In December 2012, Metropolitan's Board
authorized an agreement with LADWP that enables Metropolitan to utilize four solids
lagoons on LADWP property for a period of 50 years. In conjunction with a
future mechanical dewatering facility at the Jensen plant, this agreement
provides sufficient capacity to meet Metropolitan's anticipated solids handling
needs. [¶] Construction of the first component of the new solids handling
system, which includes a solids transfer pipeline from the Jensen plant, is
currently underway. In November 2013, Metropolitan's Board authorized a
reimbursable agreement with LADWP in an amount not to exceed $5 million to
design and refurbish the four existing LADWP solids lagoons. These
refurbished lagoons comprise the second component of the new solids handling
system. (AR 2836-37 [emphasis added].)
While Petitioner has suggested the Director may not rely on
the Report “in itself to support a finding” (Cal. Code Regs, tit. 8, § 17244,
subd. (d)) necessary to upholding the Assessment, Petitioner is incorrect given
the circumstances here. (See Opening Brief 17, fn. 11.) The Report alone—as admissible
hearsay (Cal. Code Regs, tit. 8, § 17244, subd. (a))—may be relied upon by the Director
to support her findings unless Petitioner objected to the Report’s
admission into evidence during the administrative hearing.[12]
Petitioner expressly stated during the hearing it had no objection to the
Report (hearing Exhibit 12) being admitted into evidence. (AR 514. [“We have no
objections to Exhibits One through 18.”]) Thus, the Director could rely on the Report
to support any finding made.[13]
As DLSE argues, “[i]t is undisputed that
the lagoons are on LADWP’s property, so there would be no plausible reason for
the District to award a contract for their refurbishment unless they were to be
used by the District.” (DLSE Opposition 12, fn. 13.) The court agrees.
It is undisputed LADWP owns the lagoons, and
MWD operates the Jensen Plant located near the lagoons. Petitioner has not
identified any reason MWD would award the contract unless the lagoons were to
be refurbished for use by MWD. The notice inviting bids, the contract,
Salamero’s testimony, and the Report also support, collectively, a conclusion the
lagoons were being refurbished for use by MWD “in connection with” the Jensen
Plant. Specifically, a reasonable person could infer from the record evidence the
lagoons would be used by MWD to support the “solids handling” operations of the
Jensen Plant, which is a water filtration plant. Because the pipework would be used “in
connection” with the Jensen Plant operations, DLSE could reasonably conclude the Industrial
Pipefitter classification applied.
Petitioner’s arguments do not persuade. The Director could
properly rely on the testimony of a single witness, Salamero. (See Michael Distributing Co. v. Tobin (1964) 225 Cal.App.2d 655, 660-661 [“the
testimony of only one witness found worthy of belief is sufficient for the
proof of any fact”].) Petitioner also cites no statute, regulation, or other authority
supporting its contentions Salamero was required to visit the jobsite or
discuss the classification issue with MWD. As discussed, substantial evidence
shows DLSE had prima facie support for the Assessment based on the
investigation Salamero performed. Accordingly, it is irrelevant Salamero did
not take the additional investigative steps proposed by Petitioner.
Petitioner has not demonstrated the classification issue turns
on whether the lagoons are to be used for solids handling, as reflected in the Report,
as opposed to storing “dirty water” that “gets filtered . . . at the treatment
plant,” as suggested by Salamero during her testimony. (See AR 136-137, 356.) In
both circumstances, the lagoons would be used to support the water filtration
operations of the Jensen Plant.[14] Because substantial evidence supports DLSE’s
determination the pipework for the Project would be used “in connection with
[a] central distributing filtration treatment station” (see AR 125), it is
irrelevant Salamero may not have fully understood the mechanics by which the
lagoons would support the Jensen Plant.[15]
Under substantial evidence review, the court cannot conclude
that it was unreasonable for the Director to credit the testimony of Salamero. (See
Opening Brief 17:17-18.) As discussed, Salamero clearly explained the evidence
upon which she relief to determine Petitioner had misclassified its employees. That
Salamero did not discuss the classification issue with MWD—because there was no
legal or factual reason to do so to issue the Assessment—does not detract from
her credibility as a witness. The decision
specifically explains how other evidence supported Salamero’s testimony, and
the basis for labeling Fyorodov’s testimony as unreliable and “self-serving.” (AR
27-28.) On substantial evidence review, the court cannot reweigh the evidence
or make its own credibility determination. Moreover, the Director’s credibility
determinations are supported by substantial evidence.
Finally, as discussed, the notice inviting bids, the
contract, and the Report all corroborate, in some fashion, Salamero’s testimony
and DLSE’s determination Petitioner should have used the Industrial Pipefitter
classification for the pipeworkers on the Project. Petitioner cites no
authority the bid or contract documents needed to specifically state that the “lagoons are connected to the Jensen Plant or any filtration
plant” to uphold the administrative decision. (Opening Brief 19:13-14.)
Based on the foregoing, substantial evidence supports the
Director’s findings “DLSE
carried its initial burden of presenting evidence at the Hearing that provided prima
facie support for the Assessment. . . .” (AR 6, 23.)
Substantial Evidence Supports the Director’s Finding Petitioner
Did Not Meet its Burden to Demonstrate the Basis for the Assessment is
Incorrect
The
Director found Petitioner had not met its burden to show the Assessment was
incorrect. The Director explained:
This
description [of the Project in Petitioner’s closing brief, quoted above, see AR
861] contradicts Fyodorov's testimony that he was unaware of the connection
between Jensen Plant and the lagoons, the purpose of the lagoon refurbishment
project, or the sources of water into the lagoons. [Petitioner] contends that
it "performed no work outside of the lagoons nor was. there any pipeline
connection with any outside facility including the [Jensen Plant]." . . .
. However, Salamero testified that the workers she interviewed during the
course of her investigation advised her that the lagoons were part of the
Jensen Plant. This is further supported by MWD's description of the lagoon
project as the second component of the construction of MWD's new solids
handling system, with the first component of the solids handling system being
the construction of a solids transfer pipeline from the Jensen Plant to the
four LADWP lagoons to be refurbished for MWD use. (DLSE Exhibit No. 12 [Report], pp. 238-239.)
Fyodorov's self-serving testimony that he had no understanding of the
connection between Jensen Plant and the lagoons or of the purpose of the lagoon
refurbishment project must be discounted, particularly in light of his
admission that he would not be surprised to learn that the purpose of the
lagoons was to handle the solids discharge from the Jensen Plant.
The
evidence shows that the four lagoons refurbished by [Petitioner] on the Project
were connected to the Jensen Plant by a solids transfer pipeline, and that the
purpose of connecting the lagoons was to allow Jensen Plant to increase its
capacity to process the solids collected by its sedimentation basins as part of
its treatment of water. Accordingly, the piping work on the Project constituted
piping work in connection with a central distributing filtration treatment
station that falls under the Industrial Pipefitter scope of work. The lagoons
are connected to the Jensen Plant, and constitute an integral part of its water
treatment function. There is no credible evidence that the piping work
performed on the lagoons was related to sewer or storm drain piping work. (AR
27-28.)
Petitioner does not show the Director’s
credibility determination as to Fyodorov is unsupported by substantial
evidence. Although Petitioner summarizes parts of Fyodorov’s testimony at some
length, Petitioner does not squarely address the reasons the Director found
Fyodorov’s testimony to be self-serving and unreliable. In an email communication
to Salamero during the investigation, Fyodorov asserted the lagoons “are not
even connected to the plant.” (AR 4273.)
Fyodorov maintained that position at the hearing. He testified he was not aware when working on the
Project of a connection between the lagoons and the Jensen Plant; of the
purpose of the lagoons to handle solids for the Jensen Plant; or that a
pipeline transferred solids from the Jensen Plan directly to the lagoons. (AR 771,
773, 778.) However, on cross-examination, Fyodorov admitted he would not be
surprised to learn the purpose of the lagoons is to handle the solids
discharged from the Jensen Plant. (AR 773.) He also acknowledged Petitioner did
not discuss the classification of workers on the Project with MWD, and
Petitioner did not request a determination as to the scope of work from the
Director. (AR 768-769.) Fyodorov’s testimony was also undercut by Petitioner’s
closing brief, which acknowledged the lagoons would serve as a solids transfer
system for the Jensen Plant and, therefore, were necessarily connected to the
Jensen Plant. (AR 27, 861.)[16] Given
Fyodorov’s admissions on cross-examination, among other evidence, a reasonable
person could find Fyodorov’s testimony that Petitioner was unaware of a
connection between the Project and the Jensen Plant lacked credibility.
The Director found “[t]here is no credible evidence that the
piping work performed on the lagoons was related to sewer or storm drain piping
work.” (AR 27-28.) Petitioner appears to challenge that finding by citing to Fyodorov’s
testimony regarding the work performed on the Project, as well as Fyodorov’s
opinions as to the differences between the pipelayer/pipe tradesman and
pipefitter classifications. (See Opening Brief 19:12-20.) Petitioner summarizes
Fyodorov’s testimony regarding the drainage system installed by Petitioner at
the lagoons; how some of the pipes installed were “perforated” to allow for
drainage; and why he believed an industrial pipefitter would not install
underdrain pipe. (See e.g., AR 557-581, 746-751.)
However,
Petitioner cites no evidence that Petitioner actually installed pipes to be
used for a sewer or storm drain. Indeed, as Petitioner admitted in its closing
brief, the purpose of the Project was to establish a new solids transfer system
because “sewer disposal is expensive and is limited by the ‘discharge permit.’ ”
(AR 861.) Substantial evidence supports the Director’s findings the piping work
on the lagoons was not related to sewer or storm drain work. Substantial evidence also supports the
Director’s findings “the four lagoons
refurbished by [Petitioner] on the Project were connected to the Jensen Plant
by a solids transfer pipeline, and . . . the piping work on the Project
constituted piping work in connection with a central distributing filtration
treatment station.” (AR 28.)
Significantly, Petitioner has not offered
any persuasive argument the Industrial Pipefitter classification does not apply
to the Project, assuming the pipes installed in the lagoons do have a
“connection” with the Jensen Plant. The
scope of work for Industrial Pipefitter is broadly worded to include: “All piping
in connection with central distributing filtration treatment stations . . .
.” (AR 125 [emphasis added].) Petitioner acknowledges the court should
apply rules of statutory construction to the scope of work. This relevant language
of the Industrial Pipefitter classification appears clear. Petitioner has not
developed any persuasive argument the court not accept the plain meaning of the
Industrial Pipefitter classification.
For the
first time in its Reply Brief, Petitioner argues the Report “actually supports
the use of sewer and storm drain classifications of Pipelayer/Pipe Tradesman.” (Reply
12:19.) According to Petitioner, “[i]t
has no impact on the operation of the Jensen Plant whether the solids are
disposed in city sewers, air dried at the lagoons or placed in the subdrainage
system installed by [Petitioner]. . . . [T]he lagoons have nothing to do with
the water treatment system at the Jensen Plant. The water treatment system at
the Jensen Plant operated in the same fashion before and after [Petitioner’s]
work.” (Reply 13:9-11, 13-15.)
Petitioner’s argument
is late; it does not show good cause to raise these new arguments in Reply. (Balboa Ins.
Co. v. Aguirre, supra, 149 Cal.App.3d at 1010.) The court disregards the
late reply arguments on that basis and need not respond in detail. However, the court notes that, in the reply,
Petitioner does not assert that the solids from the lagoons would be discharged
into the sewer. Petitioner also
acknowledges, in reply, that there is a pipeline connection between the lagoons
and the Jensen Plant.
Based on the foregoing, substantial evidence supports
the Director’s findings that Petitioner “failed to carry its burden of proving the basis for the Assessment was
incorrect.” (AR 6.)
The Time Limits in Section 1742,
Subdivision (b) Are Directory, Not Mandatory
Again, for the first time in its Reply
Brief, Petitioner asserts the Director’s “failure to issue a decision within 45
days of the conclusion of the hearing as required by Section 1742(b)”
invalidates the decision. (Reply 14:20-21.) Petitioner also seems to argue the
Director was required to commence the hearing within 90 days of receipt of
Petitioner’s request for the hearing. (Reply 15:8-9.) Petitioner again waived
the issues by not raising them in the Opening Brief. “The salutary rule is that points raised in a reply brief for the first
time will not be considered unless good cause is shown for the failure to
present them before.” (Balboa Ins. Co. v. Aguirre, supra, 149 Cal.App.3d
at 1010.) Petitioner has not shown good cause to raise the timeliness argument
for the first time in it Reply Brief.
Alternatively,
to the extent Respondents waived the procedural objection through its
opposition on the merits, the court finds persuasive Respondents’ contentions the
time limits in section 1742, subdivision (b) are directory and not
mandatory.
Section 1742, subdivision (b) states:
[u]pon receipt of a timely request, a hearing shall be commenced
within 90 days before the director. . . . Within 45 days of the conclusion of
the hearing, the director shall issue a written decision affirming, modifying,
or dismissing the assessment. (§ 1742, subd. (b).)
The Director issued her decision well
after the 45-day time period specified in section 1742, subdivision (b). Thus,
the issue is whether the 45-day deadline is directory or mandatory.
“The word ‘mandatory’ may be used in a
statute to refer to a duty that a governmental entity is required to perform as
opposed to a power that it may, but need not exercise. As a general rule,
however, a ‘‘directory' or 'mandatory' designation does not refer to whether a
particular statutory requirement is 'permissive' or 'obligatory,' but instead
simply denotes whether the failure to comply with a particular procedural step
will or will not have the effect of invalidating the governmental action to which
the procedural requirement relates.’ [Citation.] If the action is invalidated,
the requirement will be termed ‘mandatory.’ If not, it is ‘directory’
only.” (California Correctional Peace
Officers Assn. v. State Personnel Bd. (1995) 10 Cal.4th 1133, 1145 [CCPOA].)
“Time limits are usually deemed to be
directory unless the Legislature clearly expresses a contrary intent.
[Citation.] ‘In ascertaining probable intent, California courts have expressed
a variety of tests. In some cases focus has been directed at the likely
consequences of holding a particular time limitation mandatory, in an attempt
to ascertain whether those consequences would defeat or promote the purpose of
the enactment. [Citations.] Other cases have suggested that a time limitation
is deemed merely directory 'unless a consequence or
penalty is provided for failure to do the
act within the time commanded.' (Ibid.) As Morris v. County of Marin, supra, 18 Cal.3d 901, 908, held, the consequence or penalty
must have the effect of invalidating the government action in question if the
limit is to be characterized as ‘mandatory.’ ” (CCPOA, supra, 10 Cal.4th
at 1145.)
Section 1742, subdivision (b) does not dictate
any consequence should the Director issue her decision after the 45-day time
limit. As argued by Respondents, section 1742, subdivisions (a) and (c) demonstrates
how the Legislature clearly specifies the consequences for exceeding applicable
time limits.[17]
(See Director’s Opposition 6.) Moreover, “[t]he overall purpose of the prevailing
wage law . . . is to benefit and protect employees on public works projects.” (Lusardi
Construction Co. v. Aubry (1992) 1 Cal.4th 976, 987.) That legislative purpose would be frustrated
with a construction of the time limits in section 1742, subdivision (b) as mandatory
rather than directory.
Based on the foregoing,
the court concludes the time limits in section 1742, subdivision (b) are directory. Accordingly, the
Director’s failure to issue a decision within 45 days after the hearing does
not invalidate her decision.
Because the 45-day time limit is directory, any
alleged prejudice suffered by Petitioner from the delay is not determinative. (Reply
14:23-24.) Petitioner’s “sole remedy for delay is traditional mandamus which
lies ‘to compel the performance of an act which the law specially enjoins, as a
duty resulting from an office, trust, or station. . . .’ ” (CCPOA, supra, 10
Cal.4th at 1146.) In any event, Petitioner has not made a persuasive showing of
prejudice. Notably, Petitioner elected not to raise the Director’s delay in
issuing her decision until its Reply Brief.
Petitioner also seems to argue the
Director must have commenced the hearing within 90 days of receipt of
Petitioner’s request for the hearing. (Reply 15:8-9.) For the same reasons
stated above, the court concludes the 90-day time limit in section 1742, subdivision
(b) is directory, not mandatory. Moreover, as argued by Respondents, the record
demonstrates “Petitioner requested a
hearing date in late November or early December 2019” and thereby invited any
error and waived any objection to commencement of the hearing after 90 days. (See
AR 65.)
Based on the foregoing, Petitioner does
not demonstrate any prejudicial error based on the time requirements of section
1742, subdivision (b).
Petitioner Does Not Demonstrate Laches
In the petition, Petitioner asserted “the
Decision must be vacated on the grounds of laches.” (Pet. ¶ 24.) Petitioner did not pursue or
support that legal theory in the opening brief or reply. Accordingly, Petitioner forfeited the issue. (Nelson
v. Avondale Homeowners Assn., supra, 172 Cal.App.4th at 862-863 [argument
waived if not raised or adequately briefed]; Pfeifer v. Countrywide Home
Loans, Inc. (2012) 211 Cal.App.4th 1250, 1282 [same].)
CONCLUSION
The petition is DENIED.
IT IS SO ORDERED.
February 7, 2024 ________________________________
Hon. Mitchell Beckloff
Judge of the Superior Court
[1]
“The
awarding body must specify the prevailing rate for each craft, classification
or type of worker needed to execute the contract in its call for bids, in the
bid specifications and in the contract itself. (§ 1773.2.)
Alternatively, the awarding body may include in those documents a statement
that copies of the prevailing rates are on file at its principal office, where
they are available for review by any interested party. (§§ 1773, 1773.2 . . . .”
(Sheet Metal Workers Internat.
Assn., Local Union No. 104 v. Rea, supra, 153 Cal.App.4th at
1079.)
[2]
All undesignated statutory references are to this code.
[3] General Condition 46, entitled “Prevailing Rates of
Wages,” states in part:
In accordance with the provisions of the California
Labor Code, the Board of Directors of Metropolitan has obtained from the
Director of Industrial Relations of the State of California his determination
of the general prevailing rates of per diem wages in the locality in which the
work is to be performed. A copy of this determination will be made available to
the Contractor, and he shall post said copy at the jobsite. (AR 2833.)
[4] Petitioner “is challenging only the reclassification
of the pipelayer” in this proceeding. (Opening Brief 10:18-19.)
[5] During the hearing, Petitioner argued its ability to bring
a motion to dismiss at the conclusion of DLSE’s case-in-chief constituted prejudice.
(AR 145.) Petitioner did not argue the disclosure three weeks prior to trial
deprived it of any ability to develop facts in its defense.
[6] California Code of Regulations, title 8, section 17250, subdivision (a) provides:
The Enforcing Agency has the burden of
coming forward with evidence that the Affected Contractor or Subcontractor (1)
was served with an Assessment or Notice of Withholding of Contract Payments in
accordance with Rule 20 [section 17220]; (2) was provided a reasonable
opportunity to review evidence to be utilized at the hearing in accordance with
Rule 24 [section 17224]; and (3) that such evidence provides prima facie
support for the Assessment or Withholding of Contract Payments.
[7] Importantly, as discussed infra, Petitioner expressly
stated it had no objection to the hearing officer admitting the Report into
evidence. (AR 514 [Exhibit 12].) The court acknowledges when Salamero first
testified about the Report, Petitioner raised objections—largely related to the
disclosure issue. (See AR 149-154.)
[8] The court rejects DLSE’s claim the Report is admissible
pursuant to Evidence Code section 1280. Evidence Code section 1280 provides:
Evidence of a writing made as a record of
an act, condition, or event is not made inadmissible by the hearsay rule when
offered in any civil or criminal proceeding to prove the act,
condition, or event if all of the following applies: (a) The writing was
made by and within the scope of duty of a public employee. (b) The writing was
made at or near the time of the act, condition, or event. (c) The sources of
information and method and time of preparation were such as to indicate its
trustworthiness.
Salamero’s
testimony does not establish the foundational facts necessary for admissibility
under Evidence Code section 1280. There is no evidence before the court to support
any finding concerning the preparation of the Report.
[9] In fact, Petitioner relied on information in the Report
in its closing brief for the administrative hearing. (AR 27, 861.)
[10] The court recognizes California Code
of Regulations, title 8, section 17244, subdivision (d) may limit the utility
of the hearsay evidence and to what extent the Director may rely upon it.
[11]
While Petitioner cites evidence the
pre-bid conference ultimately occurred at the lagoons (Opening Brief 7:21-22 [citing
AR 784]), it is undisputed the notice provided the location of the pre-bid
conference as the Jensen Plant.
[12] Petitioner’s Opening Brief omits the phrase “or no Party
raises an objection to such use.” (Cal. Code Regs., tit. 8, §
17244, subd. (d). Opening Brief 17:7-10.)
[13] California Code of Regulations, title 8, section 17244,
subdivision (d) provides:
Hearsay evidence is admissible but shall not be sufficient in
itself to support a finding unless it either would be admissible over objection
in a civil action or no Party raises an objection to such use. (Emphasis
added.)
[14] Salamero admitted she was not an
“expert on filtration.” (AR 137.)
[15] Similarly, Petitioner failed to show Salamero
“misled” the hearing officer or her supervisor who approved the penalty review.
(Opening Brief 18:3-5.) The penalty review stated, correctly, Salamero relied on
the Industrial Pipefitter classification from the Master Labor Agreement
(sub-section A.1.36.) (AR 2606.)
[16]
As noted, the notice inviting bids also stated the pre-bid conference would be
held at the Jensen Plant. (AR 2782.) While Fyodorov testified the pre-bid
conference was ultimately held at the lagoons (AR 784), he presumably would
have been aware, as Petitioner’s Chief Financial Officer and agent, of the
statement on the notice regarding the conference location.
[17]
Section 1742, subdivision (a) states in pertinent part: “If no hearing is
requested within 60 days after service of the assessment, the assessment shall
become final.” (Emphasis added.) Section 1742, subdivision (c) states in
pertinent part: “If no petition for writ of mandate is filed within 45 days after service
of the decision, the order shall become final.” (Emphasis added.)
In both cases, the Legislature clearly specified the consequences for failure
to comply with the stated time limit.