Judge: Randy Rhodes, Case: 21CHCV00534, Date: 2023-01-18 Tentative Ruling




Case Number: 21CHCV00534    Hearing Date: January 18, 2023    Dept: F51

Dept. F-51¿ 

Date: 1/18/23 

Case #21CHCV00534 

¿ 

MOTION CONTESTING GOOD FAITH SETTLEMENT

 

Motion Filed: 9/6/22 

 

MOVING PARTY: Defendant, Brocca Custom Finish Carpentry (“Moving Defendant”) 

RESPONDING PARTY: Plaintiff/Cross-Defendant, Forza Construction, Inc. (“Plaintiff”); and Defendant/Cross-Complainant, AVE Sheetmetal & Rain Gutters Inc. ("AVE")

NOTICE: OK 

 

RELIEF REQUESTED: An order denying AVE’s application for good faith determination of its settlement with Plaintiff, or, alternatively, 60 days leave to complete further discovery as to Plaintiff’s alleged damages.¿ 

 

TENTATIVE RULING: The motion is denied. Moving Defendant’s evidentiary objections are overruled.

 

BACKGROUND

This indemnity action arises out of underlying claims for construction defects and delays. Nonparty Beach Home Life, LLC filed a demand for arbitration against Plaintiff Forza Construction Inc. seeking damages allegedly arising out of the construction of two single family homes located in Venice, California (the Property). Plaintiff alleges that it entered into subcontracting agreements with Defendants for work performed on the Property. Plaintiff and Beach Life Homes, LLC settled the claims made by Beach Life Homes, LLC in mediation for $340,000 plus attorney fees. As a result, Plaintiff claims that it has been damaged and such damages were caused by the acts and/or omissions of Defendants.

On 7/16/21, Plaintiff filed this action against the four subcontractor Defendants for: (1) Implied Contractual Indemnity; (2) Total Indemnity; (3) Equitable Indemnity; (4) Express Indemnity; (5) Breach of Written Contract; (6) Negligence; (7) Declaratory Relief Re Duty to Defend and (8) Declaratory Relief Re Duty to Indemnify.

On 8/11/22, defendant AVE filed and served a notice of settlement and application for determination of good faith settlement. On 9/6/22, Moving Defendant filed the instant motion challenging the application. On 1/3/23, AVE filed its opposition. On 1/10/23, Moving Defendant filed its reply.

 

ANALYSIS

Legal Standard

“Where there are multiple defendants, each having potential liability for different areas of damage, an allocation of the settlement amount must be made. … Failure to do so may preclude a ‘good faith’ determination because there is no way to determine the appropriate set off pursuant to section 877 against the nonsettling defendant.” (L. C. Rudd & Son, Inc. v. Superior Court (1997) 52 Cal.App.4th 742, 750.)

Once there is a showing made by the settlor of the settlement, the burden of proof on the issue of good faith shifts to the non-settlor who asserts that the settlement was not made in good faith. (Fisher v. Superior Court (1980) 103 Cal.App.3d 47; Code Civ. Proc. § 877.6, subd. (d).) The ultimate determinant of good faith is whether the settlement is grossly disproportionate to what a reasonable person at the time of settlement would estimate the settlor’s liability to be. (City of Grand Terrace v. Superior Court (1987) 192 Cal. App. 3d 1251, 1262.)

In making such a determination, the Court considers several factors: (1) A rough approximation of the plaintiff’s total recovery and the settlor’s proportionate liability; (2) The amount paid in settlement; (3) A recognition that a settlor should pay less in settlement than if found liable at trial; (4) The allocation of the settlement proceeds among the plaintiffs; (5) The settlor’s financial condition and insurance policy limits, if any; and (6) Evidence of any collusion, fraud, tortious conduct between the settlor and the plaintiff aimed at making the non-settling parties pay more than their fair share. (Tech-Bilt, Inc. v. Woodward-Clyde & Associates (1985) 38 Cal.3d 488, 499.)

Here, the relevant terms of ACE’s 8/11/22 application for determination of the good faith nature of its settlement agreement with Plaintiff are as follows:

“A. A.V.E., through its defending insurer, will pay to PLAINTIFF the total sum of $90,000.00 in full and final settlement of all claims by PLAINTIFF against A.V.E. relating in any way to A.V.E. 'S involvement with the two attached single-family homes which are the subject of this litigation. […]

D. The total payment of $90,000.00 toward this settlement is the compromise of disputed claims after extensive negotiations and was agreed to by the settling parties to avoid further litigation. This settlement is “within the ballpark” pursuant to Code of Civil Procedure §877 and Tech-Bilt v. Woodward-Clvde and Associates (1985) 38 Cal.3d 488.

E. PLAINTIFF and A.V.E. agree to execute a Settlement Agreement and Release of All Claims in which PLAINTIFF shall release A.V.E. from all claims, of whatever nature, arising out of A.V.E.’S involvement with the Property which is the subject of this litigation, including a waiver of the rights protected pursuant to California Civil Code § 1542.

F. Each of the settling parties will bear their own costs of litigation, including attorneys’ fees, if any.” (8/11/22 Application for Determination of Good Faith Settlement of A.V.E. Sheetmetal & Rain Gutters, Inc.)

 

Initial Burden to Show Allocation of Settlement Amount

Moving Defendant contests the good faith nature of the settlement between AVE and Plaintiff on the bases that “it is premature to determine the reasonable allocation of Plaintiff’s damages between the defendants in the case at this time, the settlement terms are unclear, as there is no allocation of Plaintiff’s damages, and the settlement is not in the ballpark of AVE Sheetmetal’s potential liability, taking into consideration the potential for indemnity and/or contribution.” (Mot., 2:5–9.)

Moving Defendant argues that AVE is not sufficiently detailed as to how the settlement amount is allocated between the issues and parties. Moving Defendant asserts that based on Plaintiff’s discovery responses, the duration of the alleged construction delays caused by AVE and Moving Defendant appear to overlap, thus requiring a more detailed showing of the allocation calculations. (Mot., 8:25–27.)

In opposition, AVE proffers the settlement agreement between itself and Plaintiff, as well as its attorney’s declaration, stating that Plaintiff allocated to it a total of $183,803.65 in damages and attorney fees. (Decl. of Mona Jeffery, ¶ 4.) AVE further observes that “good faith will not be determined by the proportion [the] settlement bears to the damages of the claimant. For the damages are often speculative, and the probability of legal liability therefor is often uncertain or remote.” (Stambaugh v. Superior Court (1976) 62 Cal.App.3d 231, 239.)

Based on this showing, the Court finds that AVE has met its initial burden as the settling defendant to show the allocation of the settlement amount.

 

Responsive Burden to Show Lack of Good Faith

The burden therefore shifts to Moving Defendant to prove a lack of good faith. (Code Civ. Proc. § 877.6, subd. (d).) Here, Moving Defendant argues that the settlement does not meet the Tech-Bilt factors because the application fails to detail the allocation of the settlement amount between the issues, thereby preventing the Court from determining the amount to offset against the non-settling parties. (Mot. 10:1–7.)

As set forth above, the Court finds that AVE has sufficiently met its initial burden to show the allocation of the settlement amount. Accordingly, without any additional evidence proffered or arguments made to contest the good faith nature of the settlement agreement, Moving Defendant has not demonstrated that the settlement is so far “out of the ballpark” as to be inconsistent with the statutory intent of Code of Civil Procedure section 877.6. (Tech-Bilt, 38 Cal.3d at 499–500.)

Moreover, AVE has shown that the settlement amount of $90,000, which is approximately 49% of the total amount of damages Plaintiff allocated to AVE, is within the “ballpark” of a reasonable settlement. (Opp. 8:14–19.) To the extent that Moving Defendant disputes the allocation amount determined by Plaintiff, Moving Defendant has not sufficiently met its evidentiary burden to challenge the good faith nature of the settlement. Moreover, Moving Defendant appears to concede that it lacks sufficient evidence regarding Plaintiff’s damages allegations against Moving Defendant, by requesting a continuance on this hearing to conduct additional discovery thereto.

 

Additional Discovery

Moving Defendant requests that the court allow 60 days for it to conduct additional discovery before ruling on the good faith nature of the settlement between Plaintiff and AVE. (Mot. 3:13–15.) However, the Court notes that AVE’s application for good faith determination was filed on 8/11/22, and Moving Defendant has since had ample opportunity to conduct its discovery or bring any necessary motions to compel, yet has not done so. As AVE observes, “BROCCA bases its inability to meet its burden of proof on its failure to complete discovery with PLAINTIFF, however BROCCA has not taken any steps to obtain any additional evidence BROCCA deems necessary to evaluate PLAINTIFF’S damages and the respective defendants’ responsibility for such damages.” (Opp. 6:20–23.)

Based on the foregoing, the Court denies Moving Defendant’s request for an additional 60 days to complete its discovery into Plaintiff’s damages, and denies the instant motion in its entirety.

 

CONCLUSION 

The motion is denied.