Judge: Ronald F. Frank, Case: 22TRCV00244, Date: 2023-06-29 Tentative Ruling

Case Number: 22TRCV00244    Hearing Date: June 29, 2023    Dept: 8

Tentative Ruling¿ 

¿¿ 

HEARING DATE:                    June 29, 2023¿ 

¿¿ 

CASE NUMBER:                      22TRCV00244

¿¿ 

CASE NAME:                           Onni Contracting (California), Inc. v. Solar Alliance Southweast, LLC, et al. 

¿¿ 

MOVING PARTY:                   Defendant, Cross-Complainant, Solar Alliance Southeast, LLC

 

RESPONDING PARTY:        Plaintiff, Cross-Defendant, Onni Contracting (California), Inc.

¿¿ 

TRIAL SETTING DATE:      September 27, 2023

¿¿ 

MOTION:¿                                  (1) Motion for Summary Judgment, or in the alternative, Summary Adjudication

                                               

¿ Tentative Rulings:                   (1)  ARGUE as to the First, Second, and Third Causes of action, in light of the issues noted by the Court as to the duty to conduct a title search and Plaintiff’s actual or constructive notice of the SCE’s easement before Plaintiff contracted with Defendant, and GRANTED as to the Fourth cause of action.

 

                                                 

I. BACKGROUND¿¿ 

¿¿ 

A. Factual¿¿ 

¿¿ 

On March 29, 2022, Plaintiff, Onni Contracting (California), Inc. (“Plaintiff”) filed a Complaint against Defendants, Solar Alliance Southeast, LLC dba Solar Alliance LLC, and DOES 1 through 50. The Complaint alleges causes of action for (1) Breach of Contract; (2) Negligence; (3) Negligent Design; and (4) Express Indemnity.

 

Plaintiff’s Complaint is based on an agreement between the parties, made on November 20, 2018 (“Agreement”) to provide design and construction management services (“DCM”) for the construction fo a rooftop and carport structure mounted solar PV array system. Pursuant to the Agreement, the project was defined as “the construction of a solar PV array consisting of rooftop and carport structure mounted arrays interconnected to respective load centers, in addition to other improvements, grading and landscaping” (“Project”) at the Subject Property. Plaintiff asserts that the tasks Solar was to perform under the Agreement consisted of project management and construction consulting services in connection with the Project and fully outlined in Schedule B of the Agreement. As explicitly stated in the Agreement’s scope of work described in Schedule B of the Agreement, the construction of the carport structure was fully intended to be included in the Project. Defendant Solar’s Project DCM services also included developing the proposals, designs and engineering of the Project to allow Onni to select the construction contractor to perform the actual construction of the Project. Plaintiff contends, as part of its initial design and engineering of the Project, Solar was required to complete an initial site study of the Subject Property. Plaintiff also contends, Solar was further responsible for and liable for any necessary changes to the design as required for permitting and utility acceptance of the Project. Moreover, Plaintiff asserts once the Project started, Solar was tasked with design management, including overseeing construction and installation of the Project to ensure compliance with Solar’s design.

 

Plaintiff also notes that on November 20, 2019, it also entered into a contract with Treepublic, Inc., (“Treepublic”) to construct the PV System and carport structure layout as designed by Solar. Plaintiff notes that Treepublic subcontracted the construction of the carport to Orion Carport Systems & Construction, Inc. (“Orion”). Plaintiff contends that even in spite of this, Solar was tasked with overseeing the work performed by Treepublic and/or its subcontractors. Plaintiff asserts that in addition to Solar’s obligations as DCM, as described above, Solar was also contractually obligated to indemnify Onni pursuant to the Agreement’s Contract General Conditions in Schedule A. Plaintiff argues that solar attempts to abscond with its indemnification obligations by claiming that the indemnification obligation falls only on the construction contractor. However, Plaintiff argues that pursuant to Schedule A of the Agreement, which states in its opening line: “To the extent applicable to the Work required to be performed by the DCM hereunder, and acknowledging that the Construction Contractor identified to construct the project shall be subject to these conditions . . .” the indemnification obligations in the Agreement apply to both the construction contractor and Solar.

 

Plaintiff notes that on May 23, 2019, SoCal Edison (“SCE”) sent a cease-and-desist letter to Onni demanding that the Project be halted because it interfered with an easement in its favor on the Subject Property. Plaintiff does not know whether those Onni employees who communicated with Solar knew about the SCE easement or if so, if they communicated its existence to Solar. However, Plaintiff notes in light of SCE’s cease-and-desist letter, Onni was required to cease work on the carport and carport-mounted PV system and repair the already demolished parking lot on the Subject Property. Plaintiff notes it was unable to obtain a variance to SCE’s easement and was forced to proceed with the Project without installing the carport structure and carport-mounted solar PV array. Plaintiff posits, as it was the responsibility of Solar to design and obtain the requisite utility acceptance of the Project, Solar sent a notice of default to Solar on August 26, 2020. The notice demanded that Solar cure its breach by correcting its defective designs and obtain all necessary permits and secure acceptance of the designs by the relevant utilities.

 

Lastly, Plaintiff contends that upon completion of the scaled down Project, on April 29, 2021, it sent a claim for damages to Solar and its insurance carrier outlining Solar’s alleged responsibilities under the Agreement and its breach thereof. Plaintiff stated that it demanded that Solar compensate it in the amount of $323,817 for the damages it incurred as a result of Solar’s breach of the Agreement. Further, Plaintiff’s  demand letter detailed its damages resulting from Solar’s breach as costs associated with unusable carport materials, repairs to the Subject Property’s parking lot, survey costs, attorney’s fees, and lost energy savings from the scaled down solar PV system. Plaintiff asserts that had Solar identified the SCE utility easement during its initial site study and Project design as required under the Agreement, Onni likely would not have incurred the above detailed damages.

 

Defendant Solar now files a Motion for Summary Judgment.

 

B. Procedural¿¿ 

 

On April 14, 2023, Defendant filed a Motion for Summary Judgment. On June 15, 2023, Plaintiffs filed an opposition. On June 23, 2023, Defendants filed a reply brief.  Each party also filed supporting documents including separate statements, declaration with exhibits, and evidentiary objections and responses thereto.

 

II. EVIDENTIARY OBJECTIONS

 

Defendant’s Objections to Plaintiffs’ Evidence:

 

Overrule: all.

 

Sustain: none.

 

III. ANALYSIS¿ 

 

A. Legal Standard

 

The function of a motion for summary judgment or adjudication is to allow a determination as to whether an opposing party cannot show evidentiary support for a pleading or claim and to enable an order of summary dismissal without the need for trial. (Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 843.) CCP Section 437(c) “requires the trial judge to grant summary judgment if all the evidence submitted, and ‘all inferences reasonably deducible from the evidence’ and uncontradicted by other inferences or evidence, show that there is no triable issue as to any material fact and that the moving party is entitled to judgment as a matter of law.”¿ (Adler v. Manor Healthcare Corp. (1992) 7 Cal.App.4th 1110, 1119.)¿ “The function of the pleadings in a motion for summary judgment is to delimit the scope of the issues; the function of the affidavits or declarations is to disclose whether there is any triable issue of fact within the issues delimited by the pleadings.”¿ (Juge v. County of Sacramento (1993) 12 Cal.App.4th 59, 67, citing FPI Development, Inc. v. Nakashima (1991) 231 Cal. App. 3d 367, 381-382.)¿ 

 

As to each claim as framed by the complaint, the defendant moving for summary judgment must satisfy the initial burden of proof by presenting facts to negate an essential element, or to establish a defense. (CCP § 437c(p)(2); Scalf v. D. B. Log Homes, Inc. (2005) 128 Cal.App.4th 1510, 1520. ) Courts “liberally construe the evidence in support of the party opposing summary judgment and resolve doubts concerning the evidence in favor of that party.”¿ (Dore v. Arnold Worldwide, Inc.¿(2006) 39 Cal.4th 384, 389.)¿ 

 

Once the defendant has met that burden, the burden shifts to the plaintiff to show that a triable issue of one or more material facts exists as to that cause of action or a defense thereto.¿¿¿ 

To establish a triable issue of material fact, the party opposing the motion must produce substantial responsive evidence. (Sangster v. Paetkau (1998) 68 Cal.App.4th 151, 166.) 

 

 

B. Discussion 

 

            Defendant Solar brings this Motion for Summary Judgment on the grounds that it argues Plaintiff’s claims against it are premised on the alleged breach of an obligation that did not exist under the express terms of the parties’ written November 20, 2018 Agreement. Defendant also argues that it has a complete defense of impossibility, predicated on the SCE easement that prohibited the erection of the carport, which it contends was a condition precedent to the installation of a solar array atop the never-built carport. As such, it argues all four (4) of Plaintiff’s causes of action against it have not merit.

 

Breach of Contract

 

Defendant Solar asserts that Plaintiff cannot establish a cause of action against it for Breach of Contract. To state a cause of action for breach of contract, Plaintiff must be able to establish “(1) the existence of the contract, (2) plaintiff’s performance or excuse for nonperformance, (3) defendant’s breach, and (4) the resulting damages to the plaintiff.” (Oasis West Realty, LLC v. Goldman (2011) 51 Cal.4th 811, 821.) Defendant Solar argues that Plaintiff cannot establish that there was a contractual obligation by Solar to construct the carport. Defendant Solar argues that the undisputed evidence demonstrates the absence of the alleged contractual obligation on which Plaintiff’s claims are premised, under the unambiguous, plaint meaning of the terms of the Agreement. Defendant argues the Agreement demonstrates that the construction of the carport was a condition precedent to Solar further performing under the Agreement as to the portion of the Project. Defendant Solar contends that Plaintiff’s failure to ensure the carport was constructed precludes its action against Solar for allegedly failing to perform DCM services related to the installation of the solar PV array on the very carport.

           

In opposition, Plaintiff contends that the express terms of the Agreement required Solar to identify and account for SCE’s utility easement in its design for utility acceptance. As noted by Plaintiff, pursuant to the Agreement, the Project was defined as: the construction of “a solar PV array, consisting of rooftop and carport structure mounted arrays interconnected to respective load centers, plus other improvements, grading and landscaping as outlined in schedule B (the “Project”) at property located at 1230 & 1240 Rosecrans Ave, Manhattan Beach, California 90266 (the “Property”). (Complaint, Exhibit B, ¶ A.) Part of this agreement notes that Defendant Solar, “DCM has been and is responsible for developing the proposals, designs, and engineering of the Project (which shall be consistent with the attached basis of design), leading to the selection of Construction Contractor who will construct the project.” (Schedule B Agreement, p. 13, “Overview,” ¶ 1.) Further, Schedule B further states: “DCM warrants that, to the fullest extent permitted by law, it is responsible for the design and engineering of the Project and is liable for necessary changes to the design as may be required for the permitting or utility acceptance of the Project . . .” (Plaintiff’s UMF No. 18) Additionally, the “Task Breakdown” of Schedule B explicitly allocates responsibility to conduct a site study of the Subject Property onto Solar. (Plaintiff’s UMF No. 16) Plaintiff further points out that Paragraph 8 of the Agreement states: “[Solar] warrants and represents that it has reviewed the conditions at the Project, entered the Property and observed the condition thereof, fully apprised itself of the scope of Work and has satisfied itself as to the condition under which the work will be performed.” (Plaintiff’s UMF No. 11)

 

Plaintiff further notes that in the agreement between it and Treepublic contained no such requirement to conduct a site study in its Schedule B or an allocation of liability to Treepublic for necessary changes to the design as may be required for the permitting or utility acceptance of the Project. Based on this, Plaintiff argues that the express terms of the Agreement show that Defendant Solar was obligated to perform an initial site study of the Subject Property to determine the conditions in which the Project would be carried out.

 

Plaintiff specifies it does not claim that Defendant Solar failed to perform its DCM and project management services that were required after the initial Project design, site study, engineering, and procurement of permits and utility acceptance. Plaintiff instead alleges that Solar breached its obligation to identify the SCE easement in its initial site study and account for it in its Project Design and specifications. Plaintiff further notes that the usual and ordinary meaning of a “site study” naturally includes  review and inquiry of the site/Subject Property. Based on this, Plaintiff argues that based on the definitions of site and study, such a study of the site/Subject Property would include a determination of whether any barriers, such as an easement, are in place which would render Solar’s design of the Project unfeasible. Further, this Court notes that in the Schedule B – Scope of Work “overview” section, it notes that “DCM warrants that, to the fullest extent permitted by law, it is responsible for the design and engineering of the Project and is liable for necessary changes to the design as may be required for the permitting or utility acceptance of the Project…”

 

In its reply brief, Defendant argues that Plaintiff fails to offer evidence demonstrating it performed its obligations, including its failure to meet its obligation under the covenant of good faith and fair dealing, under which Defendant argues Plaintiff had a duty to disclose the material fact that easements on its property prohibited the construction of the carport where Plaintiff contracted to erect it.

 

The key issue for the Court is whether the parties’ contract can reasonably be read as imposing a duty on Defendant Solar to conduct a title search on Plaintiff’s Property to determine whether Plaintiff had the right to enter into the Agreement. There is no mention of the words “title search” in the parties’ contract.  The Schedule B Agreement suggests that Defendant’s duties were to start prior to the a definitive contractor even being hired (e.g., “DCM has been and is responsible for developing the proposals, design and engineering of the Project,…leading to the selection of the Construction Contractor…”.) Such language suggests that construction of the carports were not a condition precedent to Defendant’s contractual obligations being triggered, but instead, Defendant was to begin its duties immediately, alongside the Contractor’s duties in constructing the carport. But can the duty to conduct a “site inspection” be read to also impose a duty to go off-site to Manhattan Beach City Hall or to the County Recorder’s office and conduct a title search?  The Court finds that language is not reasonably susceptible of the interpretation urged by Plaintiff.  But other language of the parties’ agreement requires Defendant Solar to responsible for obtaining permitting and utility acceptance of the Project, which arguably can be read as imposing a duty to pull permits and ascertain any impediments such as pre-existing utility company easements in order to secure “utility acceptance.” The Court will take oral argument on this point.

 

Defendant also argues that unbeknownst to it, at the time Plaintiff entered into the Agreement, there was an express, recorded, public utility easement on Plaintiff’s Property held by SCE. As such, Defendant contends that Plaintiff cannot prove any damages it purportedly sustained were caused by the conduct of anyone but its own. The Court requests oral argument as to Plaintiff’s duty to inform Defendant about an easement known to it, and whether there is evidence before the Court demonstrating that Plaintiff had actual or constructive knowledge of the easement before Defendant signed the parties’ contract.  The Court will also take oral argument as to whether Plaintiff’s knowledge of the existence of the easement would break the chain of causation upon which Plaintiff rests its contract claim against Defendant.

 

Negligence and Negligent Design

Defendant argues that Plaintiff’s negligence and negligent design causes of action require Plaintiff to prove the element of duty to provide DCM services for constriction of the carport. In order to state a claim for negligence, Plaintiff must allege the elements of (1) “the existence of a legal duty of care,” (2) “breach of that duty,” and (3) “proximate cause resulting in an injury.” (McIntyre v. Colonies-Pacific, LLC (2014) 228 Cal.App.4th 664, 671.) Defendant Solar argues it did not assume a duty to perform any services related to the construction of the carport, notwithstanding Plaintiff’s allegations.

In opposition, Plaintiff contends that under the terms of the Agreement, Defendant Solar was under a duty to conduct an initial site study, develop the proposals, design and engineering of the Project. Plaintiff also notes that Defendant Solar was also responsible for obtaining permitting and utility acceptance of the Project. Plaintiff argues that Defendant Solar failed to do so in breach of its duty. Based on this failure, Plaintiff contends Solar’s failure to properly study the site resulted in Solar negligently design the Project in a manner that violated the SCE easement to the detriment of Plaintiff.

 

As discussed above, the fulcrum issue is whether Solar had a duty to conduct a title search.  The Court’s tentative is to ARGUE as to these causes of action as well.

 

Express Indemnity

 

Here, Defendant argues that Plaintiff’s Fourth Cause of Action for Breach of Express Indemnity lacks merit as to Defendant. “An indemnitee seeking to recover on an agreement for indemnification must allege the parties’ contractual relationship, the indemnitee’s performance of that portion of the contract which gives rise to the indemnification claim, the facts showing a loss within the meaning of the parties’ indemnification agreement, and the amount of damages sustained.” (Four Star Electric, Inc. v. F & H Construction (1992) 7 Cal.App.4th 1375, 1380.)

 

Defendant argues that Plaintiff’s Complaint alleges that Defendant Solar breached the express indemnity provision contained in paragraph 9 of the Contract General Conditions (Schedule) incorporated into the Agreement, which Plaintiff alleges obligated Defendant Solar to indemnify and hold Plaintiff harmless from all claims, demands, suites, liabilities, losses and/or property damage that may arise from the performance of the work. However, Defendant argues that these allegations are inconsistent with the actual agreement attached to the Complaint, which makes clear this obligation was not one of Defendant Solar’s, but an obligation expressly assigned to the “Contractor.”

 

In opposition, Plaintiff contends that under the Agreement, Solar agreed to indemnify Onni“[t]o the fullest extent permitted by law, the [Solar] agrees to defend, indemnify and hold harmless the Owner . . . from any and all claims, demands, suits, liabilities, losses (including but not limited to economic losses, expenses and reasonable attorney’s fees), and damage for personal injury, including death or bodily injury, and/or property damage that may arise from the performance of the Work. . .” Plaintiff argues that the plain language of the Agreement states that Defendant Solar has the obligation to indemnify Plaintiff with respect to the work it performed on the Project.

 

In its reply brief, Defendant asserts that the Complaint’s cause of action for express indemnity depends on replacing the term “Contractor” with the term “Solar.” The Court agrees. After review of the exhibits attached to the Complaint, Schedule A and B, the Court does not find one paragraph with indemnity being linked to Defendant Solar. Instead, the paragraph Plaintiff relies on actually states”[t]o the fullest extent permitted by law, the Contractor agrees to defend, indemnify an hold harmless the Owner…from any and all claims demands, suits, liabilities, losses (including but not limited to economic losses, expenses and reasonable attorney’s fees), and damage for personal injury, including death or bodily injury, and/or property damage that may arise from the performance of the Work. . .” As Plaintiff’s only evidence is a miscited quote from their own agreement which clearly replaced “Contractor” with “[Solar]” as seen above, the Court finds that a material disputed fact does not exist as to this issue. As such, Defendant’s Motion for Summary Adjudication is GRANTED as to the fourth cause of action for Express Indemnity.