Judge: Stephen I. Goorvitch, Case: 22STCV34399, Date: 2023-05-15 Tentative Ruling
Case Number: 22STCV34399 Hearing Date: May 15, 2023 Dept: 39
AVL Mobility
Technologies, Inc. v. Canoo Technologies, Inc.
Case No.
22STCV34399
Demurrer to
Cross-Complaint
Plaintiff
AVL Mobility Technologies, Inc. (“AVL”) filed this action against Canoo
Technologies, Inc. (“Canoo”) for breach of contract and related claims, as well
as promissory fraud. AVL alleges as
follows: The parties entered into a written contract, dated June 24, 2021,
whereby AVL provided services and deliverables relating to Canoo’s electric
vehicles. (See Complaint, Exh. A, p.
10.) There was a dispute over the
contract. (Ibid.) On September 16, 2022, the parties entered
into a settlement and release agreement to resolve a prior dispute. (Complaint, ¶ 7.) The settlement agreement provided that Canoo
would pay a total of $3,250,000 in four instalments on the following dates: (1)
$500,000 on September 19, 2022; (2) $500,000 on September 30, 2022; (3) $1.125
million on October 7, 2022; and (4) $1.125 million on October 14, 2022. (Complaint, ¶ 8.) AVL alleges that Canoo made the first payment
on September 19, 2022, but has not made any additional payments. (Complaint, ¶ 10.) AVL alleges that Canoo had no intention of honoring
the terms of the settlement agreement when it executed the agreement. (Complaint, ¶¶ 32-37.)
Canoo filed a cross-complaint
asserting causes of action for breach of written contract and breach of
warranty. Canoo does not dispute that
the parties had a written contract, dated June 24, 2021. (First Amended Cross-Complaint, ¶ 6.) Canoo alleges as follows: Canoo paid AVL over
$9 million for work performed under the agreement, but AVL failed to perform
its duties under the agreement. (First
Amended Cross-Complaint, ¶ 7.) Among
other things, many of the deliverables were untimely, incomplete, defective, or
unsuitable for their intended purpose, or did not pass objective performance
criteria. (Ibid.) Despite being notified of the problems, AVL
failed to correct the problems and comply with its requirements under the
agreement. (Id., ¶ 8.) Canoo concedes that it did not pay the
remaining $2.75 million under the settlement agreement in payments based upon
these issues. (Id., ¶ 18.)
AVL demurs to the cross-complaint. “It is black letter law that a demurrer tests
the legal sufficiency of the allegations in a complaint.” (Lewis v.
Safeway, Inc. (2015) 235 Cal.App.4th 385, 388.) In ruling on a
demurrer, the court must “liberally construe[]” the allegations of the
complaint. (Code Civ. Proc., § 452.)
“This rule of liberal construction means that the reviewing court draws
inferences favorable to the Farias, not the Cross-Defendant.” (Perez
v. Golden Empire Transit Dist. (2012) 209 Cal.App.4th 1228, 1238.)
AVL argues that the parties’
settlement agreement bars the cross-claims and requests that the Court take
judicial notice of the parties’ agreement.
Governing contracts are subject to judicial notice as propositions not
reasonably subject to dispute. (Ascherman
v. General Reinsurance Corp. (1986)
183 Cal.App.3d 307, 310-311.) Therefore,
the Court grants the request.
The settlement agreement states
that “the Parties mutually dispute one or more business terms relating to the
Agreement and desire to terminate the services and relationship.” (Request for Judicial Notice, Exh. A, p. 5.) The settlement agreement states that “the Parties
wish to compromise and settle fully and finally all claims, controversies, or
causes of action that they may have arising out of their relationship, or any
work performed by AVL or arising from the cessation of AVL providing services.” (Ibid.)
Therefore, the parties agreed that Canoo would make a “termination
payment” of $3.25 million. (Ibid.) The parties agree that AVL would provide “limited
support services” of: (1) “AVL shall provide MatLab user license integration
support services for five (5) users to Canoo through December 31, 2024;” and
(2) “AVL shall “provide to Canoo a final cost estimate, on a time and materials
basis, for rolling back Canoo’s SIL pipeline to the last stable version (a.k.a.
‘Spring 40’).” (Request for Judicial
Notice, Exh. A, p. 6, ¶¶ 2(b) & 4.)
The settlement agreement includes a mutual release. (Request for Judicial Notice, Exh. A, pp. 5,
¶ 3.)
Canoo argues that the mutual waiver
is effective only upon the satisfaction of the parties’ obligations under the
settlement agreement. Canoo argues that AVL
has not satisfied its obligations under the settlement agreement because it has
not rectified the problems with the untimely, incomplete, defective, or unsuitable
deliverables. Canoo attempts to rewrite
the settlement agreement. The agreement
does not require AVL to do so. AVL was only
required to do provide MatLab user license integration support services for five
users through December 31, 2024, and to provide a final cost estimate, on a
time and materials basis, for rolling back Canoo’s SIL pipeline to the last
stable version. (Request for Judicial Notice,
Exh. A, ¶ 4.) Moreover, AVL was not
required to do anything until on or after the “effective date,” which is the
date on which AVL receives the full termination payment. (Request for Judicial Notice, Exh. A, p. 7, ¶
4.) There is no dispute that Canoo did
not make the full termination payment.
Based upon the foregoing, the Court
orders as follows:
1. The
Court sustains AVL’s demurrer to Canoo’s cross-complaint.
2. The
Court denies leave to amend. It is undisputed
that there is a mutual waiver of all claims relating to the dispute over the underlying
contract, and the settlement agreement does not require AVL to provide the
services claimed by Canoo’s cross-complaint.
Moreover, any obligations by AVL were triggered by Canoo’s full payment
of the settlement amount, and there is no dispute that Canoo has not paid the
entire amount. Therefore, no amendment
would be successful.
3. Counsel
for AVL shall provide notice and file proof of such with the Court.