Judge: Stephen I. Goorvitch, Case: 23STCP02886, Date: 2024-08-19 Tentative Ruling
Case Number: 23STCP02886 Hearing Date: August 19, 2024 Dept: 82
Conjunction Junction LLC
Case No. 23STCP02886
v.
Hearing:
August 16, 2024
Location:
Stanley Mosk Courthouse
Department:
82
The City of Rancho Palos Verdes,
et al. Judge: Stephen I. Goorvitch
[Tentative] Order Sustaining Demurrer and
Denying Motion to Strike
INTRODUCTION
Conjunction
Junction LLC (“Petitioner”) filed this action against the City of Rancho Palos
Verdes (the “City”) and Amy Seeraty, in her official capacity as Senior Planner
for City (“Respondents”). In the
operative first amended petition for writ of mandate and complaint (“FAP”),
Petitioner asserts the following causes of action: (1) Writ of mandate, (2)
Declaratory relief and injunctive relief, (3) Violation of Title 42, United
States Code, section 1983; and (4) “Challenge to Landslide Moratoriums—If
Necessary.” Petitioner alleges that
Respondents failed to comply with the “Builder’s Remedy” of the Housing
Accountability Act with respect to a development application that Petitioner
submitted to City. (See Gov. Code §
65589.5(d)(5).) Respondents demur on
several grounds and move to strike portions of the FAP. The court sustains the demurrer to the first,
third, and fourth causes of action with leave to amend. The court sustains the demurrer to the second
cause of action without leave to amend.
The court denies the motion to strike as moot.
BACKGROUND
The
FAP alleges that Petitioner “submitted a Builder’s Remedy application to the
City of Rancho Palos Verdes” and that the City “began creating roadblocks
immediately to try to block the project,” including:
a. Claiming that Plaintiff cannot build the project due to
the private road used to access their property. The private road is actually a
non-exclusive reciprocal easement between Plaintiff and its neighbors and
provides access to the property.
b. Claiming that Plaintiff is required to comply with its
zoning regulations for a Landslide Moratorium Exclusion Permit….
c. Environmental Review – the project is a 3 unit
development. As such, it falls within Government Code Section 65913.4, which
provides that the project is ministerial and is exempt from environmental
review.
d. Neighborhood Compatibility – Use of a neighborhood
compatibility review is expressly prohibited under the Builder’s Remedy law.
e. Portuguese Bend Community Association – The City informed
Plaintiff that it should comply with all of the design standards for the
Portuguese Bend Community Association (the local HOA.)….
(FAP ¶¶ 46-48.) The FAP alleges that “[t]hese requirements
were imposed in a letter from Defendant Amy Seeraty on July 7, 2023.” (Id. ¶ 49.) Further, “[s]ince the filing of this lawsuit,
… the City has passed a moratorium on new building permits in the region,
including the Petitioner’s property.” (Id.
¶ 51.) Petitioner alleges that “[a]t
the City Council hearing on this matter, the City Attorney represented to the
City that part of the reason to pass the moratorium was to block the pending
Builder’s Remedy applications, including Plaintiff’s application.” (Id. ¶ 52.)
In
the first cause of action for writ of mandate, Petitioner contends that “City
refuses to process Builder’s Remedy applications without Plaintiff being
required to perform actions that fall outside the Builder’s Remedy process.” (Id. ¶ 65.) Petitioner prays for a writ of mandate “ordering
the City to comply with the Builder’s Remedy law.” (Id. ¶ 67.)
In
the second cause of action for declaratory relief, Petitioner “requests a
declaration that the City’s demand that Builder’s Remedy applications require a
Landslide Moratorium Exclusion Permit, Environmental Review, Neighborhood
Compatibility Analysis, and compliance with the Portuguese Bend Community
Association’s rules and regulations violates the Housing Crisis Act of 2019.” (Id. ¶ 77.) Petitioner asserts the third cause of action,
which is a violation of Title 42, United States Code, section 1983. Finally, Petitioner asserts the fourth cause
of action, titled “Challenge to Landslide Moratoriums—If Necessary,” which
seeks seeks a judicial determination that City’s Landslide Moratorium is
invalid.
LEGAL
STANDARD
A demurrer tests the
sufficiency of a pleading, and the grounds for a demurrer must appear on the
face of the pleading or from judicially noticeable matters. (Code Civil Proc. §
430.30, subd. (a); Blank v. Kirwan (1985) 39 Cal.3d 311, 318.) “We
assume the truth of the allegations in the complaint, but do not assume the
truth of contentions, deductions, or conclusions of law.” (California
Logistics, Inc. v. State (2008) 161 Cal.App.4th 242, 247.) The
allegations in the petition must be liberally construed in favor of Petitioner
on demurrer. (See Mobil Oil Corp. v
Exxon Corp. (1986) 177 Cal.App.3d 942, 947.) “A demurrer must dispose of an entire
cause of action to be sustained.” (Poizner v. Fremont General Corp. (2007)
148 Cal.App.4th 97, 119.) “A demurrer
tests the pleadings alone and not the evidence or other extrinsic
matters.” (Hahn v. Mirda (2007) 147 Cal.App.4th 740, 747.)
EVIDENTIARY
ISSUES
Respondents’ request for judicial
notice of exhibits A-H is granted. (See
Evid. Code
§ 452(a), (b), (c), and (h).) However, if the court does not reference an
exhibit in this order, the court did not rely on that exhibit in ruling on the
demurrer.
Petitioner’s
request for judicial notice of exhibits 1-6 is denied. First, Petitioner’s counsel did not comply
with California Rules of Court, rule 8.252, which requires that a request for
judicial notice be filed as a separate pleading. Putting that aside, Respondents’ objections to judicial notice are sustained. Petitioner has not “[f]urnishe[d] the court
with sufficient information to enable it to take judicial notice of” Exhibit 1. (See Evid. Code § 453(b).) Exhibits 2-6 are not relevant to any material
issue in this court’s ruling on the demurrer and motion to strike. (See Ketchum v. Moses (2001) 24
Cal.4th 1122, 1135 fn.1 [“matter to be judicially noticed must be relevant to a
material issue”].)
DISCUSSION
A.
First Cause of Action – Writ of Mandate
1. Applicable
Law
In the first cause of action,
Petitioner seeks a writ of mandate ordering Respondents to comply with the
Builder’s Remedy law. (FAP ¶ 67.) There are two essential requirements to the
issuance of an ordinary writ of mandate: (1) a clear, present, and ministerial
duty on the part of the respondent, and (2) a clear, present, and beneficial
right on the part of the petitioner to the performance of that duty. (California
Ass’n for Health Services at Home v. Department of Health Services (2007)
148 Cal.App.4th 696, 704.) “An action in
ordinary mandamus is proper where … the claim is that an agency has failed to
act as required by law.” (Id. at 705.)
Government
Code section 65589.5(d)(5), known as the “Builder’s Remedy,” is a provision of
the Housing Accountability Act (“HAA”) that prevents jurisdictions without a
substantially compliant housing element from “disapproving” specific types of
housing projects, even if such projects do not comply with the local agency’s
zoning ordinance or general plan. A Builder’s Remedy is only available for a “housing development project,”
which is defined in the HAA as “a use consisting of any of the following: (A) Residential
units only. (B) Mixed-use developments consisting of residential and
nonresidential uses with at least two-thirds of the square footage designated
for residential use. (C) Transitional
housing or supportive housing.” (Gov.
Code § 65589.5(h)(2).)
2. Petitioner
does not allege the project is a “housing development project”
Respondents
argue that Petitioner has not pleaded sufficient facts to state a claim that Petitioner’s application qualifies as a Builder’s
Remedy. (Demurrer (“Dem.”) 11-13.) The court agrees. “[T]he complaint ordinarily is sufficient
if it alleges ultimate rather than evidentiary facts.” (Doe v. City of Los Angeles (2007) 42
Cal.4th 531, 550.) However, “the limited and statutory nature of governmental
liability mandates that claims against public entities be specifically
pleaded.” (Brenner v. City of El
Cajon (2003) 113 Cal.App.4th 434, 439.)
Here, the
FAP includes a single sentence stating that Petitioner submitted a Builder’s
Remedy application to the City. (FAP ¶ 60.) Petitioner does not plead any factual
allegations regarding the application or underlying project, and Petitioner has
not attached the application as an exhibit.
Accordingly, Petitioner has not alleged, with particularity, that its
application pertained to a “housing development project” within the meaning of
the HAA. (Gov. Code §
65589.5(h)(2).) Notably, Petitioner does
not respond to this argument in opposition.
(See Oppo. 2-4; Sehulster
Tunnels/Pre-Con v. Traylor Brothers, Inc. (2003) 111 Cal.App.4th 1328,
1345, fn. 16 [failure to address point is “equivalent to a concession”].)
There
is a genuine question whether Petitioner can satisfy this requirement. Respondents contend that Petitioner’s project
does not qualify as a “housing development project” as a matter of law because
“only 13,032 of the entire 161,193 square foot development plan is meant for
residential use.” (Demurrer 13.) Respondents rely on a preliminary application
submitted by Petitioner to City on April 27, 2023. (Resp. RJN Exh. G.) Petitioner does not address this argument in
its opposition. Nevertheless, the court
will grant leave to amend.
3. Petitioner
does not allege a violation of the Housing Element Law
Respondents
argue that Petitioner has not alleged, with particularity, how the City’s housing
element fails to substantially comply with the Housing Element Law. (Dem. 14.) Under the Builder’s Remedy, a city must
approve a housing development project, as defined in the HAA, if it does not
have a “substantially compliant” housing element. (Govt. Code §65589.5(d)(1).) Petitioner alleges that “HCD maintains a
database of which municipalities within the State of California have been
approved as compliant” and that “[a]s of August 1, 2023, according to the HCD’s
Housing Element Compliant Report, the City of Rancho Palos Verdes is ‘Out of
Compliance.’” (FAP ¶¶ 35-36.) These allegations are insufficient to state a
cause of action. Petitioner does not
include any specific allegations as to how the City’s housing element fails to
substantially comply with state law. The
trial and appellate courts “independently ascertain as a question of law
whether the housing element at issue substantially complies with the requirements
of the Housing Element Law.” (Fonseca
v. City of Gilroy (2007) 148 Cal.App.4th 1174, 1191; accord Martinez v.
City of Clovis (2023) 90 Cal.App.5th 193, 237.) Thus, a determination by HCD that a
municipality is “out of compliance” may not be dispositive. Finally, Petitioner does not allege when it
submitted its application to City. For
all these reasons, it cannot be determined from the FAP whether Petitioner
submitted its application at a time when City’s housing element was out of
compliance with state law.
4. The
first cause of action is not ripe
Finally,
Respondents argue that Petitioner’s first cause of action “is premature because
the City has not issued a final decision on Petitioner’s application as it is
still under administrative review.” (Dem.
14-16.) To state a claim under the HAA
and to invoke the Builder’s Remedy, Petitioner must show that City
“disapprove[d] a housing development project.” (Gov. Code § 65589.5(d).) Section 65589.5(h)(6) of the HAA
states, in relevant part, that “‘disapprove the housing development project’
includes any instance in which a local agency”: (1) “Votes on a proposed
housing development project application and the application is disapproved,
including any required land use approvals or entitlements necessary for the
issuance of a building permit”; (2) fails to comply with the time periods and
limits in the Permit Streamlining Act (“PSA”); or (3) “Fails to make a determination of
whether the project is exempt from the California Environmental Quality Act …, or commits an
abuse of discretion” if certain conditions
are satisfied. (See §
65589.5(h)(6)(A)-(D).)
Relatedly, exhaustion of
administrative remedies is “a jurisdictional prerequisite to judicial
review.” (Cal. Water Impact Network v. Newhall County
Water Dist. (2008) 161 Cal.App.4th 1464, 1489.) “The exhaustion requirement applies
whether relief is sought by traditional (Code Civ. Proc., § 1085) or
administrative (Code Civ. Proc., § 1094.5) mandamus.” (Eight Unnamed Physicians v. Medical
Executive Com. (2007) 150 Cal.App.4th 503, 511.) “Before seeking judicial review a party must
show that he has made a full presentation to the administrative agency upon all
issues of the case and at all
prescribed stages of the administrative proceedings.” (Edgren
v. Regents of University of California (1984) 158 Cal.App.3d 515,
520.) There are exceptions to the
exhaustion requirement, including “when the subject of the controversy lies
outside the administrative agency's jurisdiction, when pursuit of an
administrative remedy would result in irreparable harm, when the administrative
agency cannot grant an adequate remedy, and when the aggrieved party can
positively state what the administrative agency’s decision in his
particular case would be.” (Edgren,
supra, 158 Cal.App.3d at 520 [citations omitted].)
Here, the FAP does not allege that
City failed to comply with time limits in the PSA or that a “disapproval” under
section 65589.5(h)(6)(D) occurred in connection with City’s CEQA review and all
of the stated conditions are satisfied.
Thus, the petition must allege that City “[v]ote[d] on a proposed
housing development project application and the application is disapproved,
including any required land use approvals or entitlements necessary for the
issuance of a building permit.” (§
65589.5(h)(6)(A).) The petition only
alleges that Respondent Amy Seeraty, a Senior Planner for City, issued a letter
on July 7, 2023, specifying that the application was incomplete for various
reasons. (FAP ¶¶ 48-49; see also Resp.
RJN Exh. H.) Petitioner does not allege
that City, through its City Council or other decision-making body, has “voted
on” and made any final determination to disapprove the application on the
grounds it is incomplete or for other reasons.
(See generally Govt Code § 65943(c).) To the contrary, Petitioner admits that “no
final decision has been made on the project itself.” (Oppo. 10:21-22.) Accordingly, Petitioner has not alleged
either a disapproval of the application under the HAA or that it has exhausted
its administrative remedies. Petitioner
also does not allege an excuse from the exhaustion requirement.
Petitioner attempts to circumvent
these requirements, arguing that his writ challenges “what requirements must be
fulfilled to move forward with the project.”
(Oppo. 10:22-23.) But the law on
the Builder’s Remedy is clear: There must be a disapproval. Seeraty’s letter does not constitute a
disapproval. The letter merely requests
additional information in order to deem the application “complete” and begin “processing.” If Petitioner believes so strongly that its
application should be granted without the additional requirements, Petitioner’s
counsel could submit the formal application without the additional materials
and demand that the City process the application. If the City refuses to process the
application and render a decision on the merits, then Petitioner could seek a
writ requiring the City to do so. This
is different than a writ requiring the City to issue a permit, and Petitioner
does not seek this relief in the FAP.
5. Summary
Based upon the foregoing, the court
sustains the demurrer to the first cause of action on these grounds. The court grants leave to amend.
B.
Second Cause of Action – Declaratory and
Injunctive Relief
The second
cause of action for declaratory relief is derivative of the first cause of
action and suffers the same defects
analyzed above. Further, “it is settled
that declaratory relief is not an appropriate method for judicial review of
administrative decisions.” (Selby Realty Co.
v. City of San Buenaventura (1973) 10 Cal.3d 110, 126-127.) In
addition, “[i]njunctive relief is a remedy, not
a cause of action.
A cause of action must exist before a court may
grant a request for injunctive relief.” (Ivanoff v. Bank of America, N.A. (2017)
9 Cal.App.5th 719, 734.) Accordingly, the demurrer to the second cause of action is sustained. The court denies leave to amend.
C.
Third Cause of Action – Violation of 42 U.S.C.
Section 1983
Pursuant to
the local rules, which designate Department 82 as a specialized writs and
receivers department and not a general civil department, only a cause of action
for writ of mandate is properly assigned to this department. (LASC Local Rules 2.8(d) and 2.9.) In the third cause of action, Petitioner
alleges that Respondents deprived Petitioner of rights protected by the
Constitution and laws of the United States.
(FAP ¶¶ 78-84.) Petitioner does
not seek a writ of mandate in connection with the third cause of action. Instead, Petitioner appears to seek
damages. (See FAP Prayer ¶ 4.)
Generally,
when a non-writ cause of action is pleaded in a petition for writ of mandate,
this court will stay the non-writ cause of action pending resolution of the
writ cause of action. Then, after a
decision on the writ, the court may transfer the non-writ cause of action to
Department 1 for assignment to a general civil department.
In this
case, however, the third cause of action appears entirely derivative of the
first cause of action for writ of mandate.
Thus, in the interests of judicial economy, the court exercises its
discretion to rule on the demurrer to the third cause of action. Petitioner alleges that “Defendants acted
pursuant to a policy or custom of Defendant City of Rancho Palos Verdes of
refusing to accept or process Builder’s Remedy applications in violation of
State and Federal law.” (FAP ¶ 82.) To allege a section 1983 claim, Petitioner
must allege that it was “deprived of a constitutionally protected property
interest.” (Gerhart v. Lake County,
Mont. (9th Cir. 2011) 637 F.3d 1013, 1019.)
For the reasons discussed above as to the first cause of action,
Petitioner does not allege that City has rendered a final decision on the
development application and that Petitioner has been deprived of any property
interests. Accordingly, the demurrer to
the third cause of action is sustained with leave to amend.
D.
Fourth Cause of Action – Challenge to Landslide
Moratoriums – If Necessary
In the
fourth cause of action, Petitioner alleges: “Plaintiff believes that a
Builder’s Remedy project does not need to comply with the Landslide Moratorium
municipal code sections as they are Zoning Codes, and thus are overruled by the
Builder’s Remedy…. However, if Plaintiff is forced to comply with the Landslide
Moratorium, Plaintiff also asserts that the Moratorium itself is invalid.” (FAP ¶¶ 86-87.) Petitioner alleges that the Moratorium is
“invalid” because of the following:
After [a
slow-moving] landslide occurred, the City enacted a “one size fits all”
solution on the region. They passed a
series of development moratoriums on the region, including the subject
property….. [On remand from Monks v.
City of Rancho Palos Verdes (2008) 167 Cal.App.4th 263], City therefore
carved out a small portion of Portuguese Bend now known as the “Monks Parcels”
where development is allowed, but retained the moratorium for all of the other
owners in the region. These parcels are not wholly contiguous, but instead are
scattered throughout the area. This
places the other owners in the moratorium, including Plaintiff, in the same
position that the Monks plaintiffs were at the beginning of their process. The City has now engaged in “spot zoning” to
allow development amongst a small group of parcels, with the only appreciable
difference between the Monks parcels and the non-Monks parcels being that the
owners of the Monks parcels sued to be allowed to develop and won.
(FAP
¶¶ 90, 98-103 [internal paragraph numbers omitted].) Petitioner further alleges: “City has not
submitted the moratorium to the HCD for approval, nor has the moratorium been
approved. Therefore, under Government Code Section 66300 the moratorium is
void.” (Id. ¶ 104.)
The first amended petition cites no
legal predicate or authority for the fourth cause of action. The court cannot determine whether the fourth
cause of action seeks a writ of mandate under Code of Civil Procedure section
1085 and/or 1094.5; whether the fourth cause of action raises a constitutional
challenge; or whether the fourth cause of action asserts a right under some
other law. Based upon the allegations,
it appears that Petitioner is attempting to circumvent the ripeness issue that
precludes him for proceeding on the first cause of action. Petitioner’s counsel articulates a variety of
theories in his opposition. The legal
and factual basis for this claim must be clear in the operative petition
itself. Therefore, the court sustains
the demurrer to the fourth cause of action with leave to amend.
CONCLUSION AND ORDER
Based upon the foregoing, the court
orders as follows:
1. The
court sustains the demurrer to the first, third, and fourth causes of action
with leave to amend.
2. The
court sustains the demurrer to the second cause of action without leave to
amend.
3. Petitioner’s
counsel may file a second amended petition within 30 days.
4. The
court continues the trial setting conference to November 20, 2024, at 9:30
a.m.
5. Respondents’
counsel shall provide notice and file proof of service with the court.
IT IS SO
ORDERED.
Dated:
August 19, 2024
Stephen
I. Goorvitch
Superior
Court Judge