Judge: Stephen I. Goorvitch, Case: 23STCP04397, Date: 2025-01-08 Tentative Ruling
Case Number: 23STCP04397 Hearing Date: January 8, 2025 Dept: 82
Friends
of Kenter, Case No. 23STCP04397
v. Hearing:
January 8, 2025
Location:
Stanley Mosk Courthouse
Department:
82
City of Los Angeles, et al. Judge: Stephen I. Goorvitch
[Tentative]
Order Denying Petition for Writ of Mandate
INTRODUCTION
Kenter Investment Land, LLC and Saeed Kohanoff (the “Real
Parties”) developed a four-story residence located at 824 North Kenter Avenue
in Los Angeles, California (the “Property”).
The City of Los Angeles (“Respondent” or the “City”) approved the
project. Petitioner Friends of Kenter
(“Petitioner”) appealed the issue to the Los Angeles Department of Building and
Safety, the Planning Director, and the West Los Angeles Area Planning
Commission to no avail. Now, Petitioner
seeks a writ of mandate ordering the City to rescind the building permit or
vacate the denial of Petitioner’s appeals and remand the matter for further
consideration. Petitioner raises a
series of issues that were not raised in the underlying appeals, some of which
were raised for the first time in the reply briefs. With respect to the remaining issues,
Petitioner does not demonstrate that the City erred in its interpretation of
the applicable regulations or its approval of the permits. Therefore, the petition for writ of mandate
is denied.
BACKGROUND
A. The Project
The
Real Parties own the Property, which is a 2.5 acre, irregularly shaped, sloping
lot that is zoned RE40-1-H. (AR 478-479,
1466.) The Property is subject to the
Baseline Hillside Ordinance (the “BHO”) and the Hillside Retaining Wall
Ordinance (the “HRWO”). (AR 283, 478, 831-34.)
The adjacent properties are developed with one-story to three-story
single-family dwellings. (AR 478.)
On
June 15, 2018, the Real Parties submitted applications and plans for building
permits for a four-story single-family home (the “Project”). (AR 282, 484,
1729-1747, 2045.) As proposed, the
Project consists of a 28,638 square foot single-family dwelling with an
attached garage, attached accessory dwelling unit (“ADU”), water fountain, new
retaining wall, planter walls, and a new pool and spa. (AR 479, 1729.) The Los Angeles Department of Building and
Safety (the “LADBS”) determined that the proposed Project complies with the Los
Angeles Municipal Code (“LAMC”) and issued ministerial building permits on
December 11, 2019 (the “Building Permits”). (AR 64-83, 478, 493.) On or about October 26, 2020, the Real Parties
submitted plans for supplemental permits to correct an error regarding the
approved building height. (AR 340, 704,
SAR 2463- 2471.) The original permit
stated that the Project height was 30 feet, but the approved height was 36
feet. (AR 340, 704.) The LADBS issued
supplemental permits on January 10, 2021. (Ibid.)
B. Petitioner’s Appeal to the LADBS
On
May 17, 2021, Petitioner submitted a Request for Modification of Building
Ordinances to the LADBS asserting that the Building Permits were improperly
issued. (AR 106-109.) On July 15, 2021, Petitioner filed a
subsequent appeal to the LADBS on the same grounds. (AR 106-109.)
On September 27, 2021, the LADBS issued a written determination that
analyzed and rejected each of Petitioner’s appeal points. (AR 50-55.)
C. Petitioner’s
Appeal to the Director of Planning
On October 12, 2021, Petitioner appealed the LADBS’s
determination to the Director of Planning (the “Director”). (AR 175-190, 273-4.) Petitioner reiterated the arguments made in
the LADBS Appeal, but also raised new issues concerning construction activities
at the Project site. Specifically,
Petitioner asserted that the Project, as constructed, exceeds the height limit
and number of retaining walls approved by the LADBS in the Building
Permits. (See AR 175-190, 558-568.) On June 13, 2022, the Zoning Administrator
(“ZA”), acting on behalf of the Director of Planning, issued a 21-page
determination denying the appeal (the “ZA Determination”). (AR 477- 497.) The ZA stated that the appeal was limited to
“whether LADBS acted within the scope of its authority” in issuing the Building
Permits. (AR 493.) As relevant to this writ petition, the ZA also
stated that the “neighbors and the appellants are well within their right to
register complaints if there is a belief that the current construction of the
single family residence is not consistent with the plans approved by the LADBS
Plan Check Division,” but that these complaints “should be filed with the
Enforcement Division of the Department of Building and Safety.” (AR 494-495.)
D. Petitioner’s
Appeal to the West Los Angeles Area Planning Commission
On June 27, 2022, Petitioner appealed the ZA
Determination to the West
Los Angeles Area Planning Commission (the “APC”). (AR
526-535, 927-935.) On September 23,
2022, after considering the matter at a public meeting, the APC denied Petitioner’s
appeal and adopted the findings made by the ZA. (AR 961-962.)
E. The
City Council’s Review
On
October 4, 2022, the City Council exercised its authority to take jurisdiction
of the appeal under City Charter section 245 and passed a motion instructing the
LADBS, in consultation with the Planning Department:
[T]o prepare a report … that thoroughly
reviews of [sic] the applicability of Los Angeles Municipal Code (LAMC) Section
12.22 C.22 to the subject property, provides an alternate calculation of lot
width pursuant to the methodology outlined in LAMC Sec. 12.22 C.22, and
outlines how this alternate calculation for lot width may impact the proposed
project in relation to the allowable residential floor area bonus (LAMC Sec.
12.21 C.10(b)(3)), particularly via the cumulative side yard setbacks option
(LAMC Sec. 12.21 C.10(b)(3)(iii)).
(AR 1013.)
On November 30, 2022, the LADBS issued the report requested by the City
Council, in which the LADBS opined as follows:
Although, using the lot width calculation in
Section 12.22 C.22 creates a more restrictive circumstance for the applicant,
this option is not mandated by code. The applicant has the discretion to apply
either lot width calculation for the Cumulative Side Yard Setback Option in
Section 12.21C10(b)(3)(iii). Therefore, the applicants use of lot width as
defined in Section 12.03 is both appropriate and code compliant.
(AR 745, 1044.)
F. The
Further Hearing before the West Los Angeles Area Planning Commission
The parties submitted additional correspondence
and evidence in advance of the APC hearing of September 6, 2023. (See, e.g.,
AR 1461-1466, 1502-1506, 1797-1799, 1802-1811, SAR 2202-2234, 2452-2475.)
On November 6, 2023, the APC issued a written determination denying the appeal.
(AR 1832-1833.) This writ petition followed.
STANDARD
OF REVIEW
Under Code of Civil Procedure section 1094.5(b), the
pertinent issues are whether the respondent has proceeded without jurisdiction,
whether there was a fair trial, and whether there was a prejudicial abuse of
discretion. An abuse of discretion is
established if the agency has not proceeded in the manner required by law, the
decision is not supported by the findings, or the findings are not supported by
the evidence. (Code Civ. Proc. §
1094.5(b).)
“Where, as here, a land use decision is
challenged by administrative mandamus, courts are to apply the substantial
evidence standard of review.” (Toigo
v. Town of Ross (1998) 70 Cal.App.4th 309, 317.) Substantial evidence is relevant evidence that a
reasonable mind might accept as adequate to support a conclusion or evidence of
legal significance which is reasonable in nature, credible and of solid value. (California
Youth Authority v. State Personnel Board (2002) 104 Cal. App. 4th 575,
584-85; Mohilef v. Janovici (1996) 51
Cal. App. 4th 267, 305
fn. 28.) Under this standard of review, “[c]ourts may
reverse an [administrative] decision only if, based on the evidence …, a
reasonable person could not reach the conclusion reached by the agency.” (Sierra
Club v. California Coastal Com. (1993) 12 Cal.App.4th 602, 610.)
Petitioner bears the burden of proof
and must demonstrate, by citation to the
administrative record, that the evidence does not support the administrative
findings. (Strumsky v. San Diego County Employees Retirement Assn. (1974) 11
Cal.3d 28, 32; Shenouda v. Veterinary
Medical Bd. (2018) 27 Cal.App.5th 500,
513; Toigo, supra, 70 Cal.App.4th at 317.)
An agency is presumed to have regularly
performed its official duties. (Evid.
Code § 664.)
“[A] trial court must afford a strong presumption of
correctness concerning the administrative findings.” (Fukuda
v. City of Angels (1999) 20 Cal. 4th 805, 817.) When an
appellant challenges “the sufficiency of the evidence, all material evidence on
the point must be set forth and not merely [her] own evidence.” (Toigo, supra, 70 Cal.App.4th at 317.) A reviewing court “will not act as counsel
for either party to an appeal and will not assume the task of initiating and
prosecuting a search of the record for any purpose of discovering errors not
pointed out in the briefs.” (Fox v.
Erickson (1950) 99 Cal.App.2d 740, 742.)
EVIDENTIARY ISSUES
Petitioner has requested that the court take judicial
notice of 13 exhibits. One exhibit is
the City’s Baseline Hillside Ordinance and the remaining 12 exhibits are sections
of the Los Angeles Municipal Code. The
City has requested that the court take judicial notice of eight exhibits, and
the Real Parties have requested that the court take judicial notice of three
exhibits, all of which are sections of the Los Angeles Municipal Code. None of the requests for judicial notice is
opposed. The court grants all requests for
judicial notice.
DISCUSSION
A. The
Scope of Petitioner’s Administrative Appeal
Petitioner argues that the City failed to proceed in the
manner required by law when it narrowly defined the scope of Petitioner’s
appeal and refused to consider whether the Project, as constructed, was built
in compliance with the Building Permits.
(Opening Brief (“OB”) 7.) This
argument implicates two issues: (1) Whether Petitioner raised this issue in its
initial appeal to the LADBS; and (2) Whether the Planning Department and the
APC had the authority to consider this issue.
1. Petitioner
did not raise the issue in its appeal to the LADBS
“Before seeking judicial review a party must
show that he has made a full presentation to the administrative agency upon all
issues of the case and at all
prescribed stages of the administrative proceedings.” (Edgren
v. Regents of University of California (1984) 158 Cal.App.3d 515, 520
[emphasis added].) “[A] corollary
principle to the doctrine that administrative remedies must be exhausted [is
that] a litigant must fully present its arguments and evidence at the
administrative hearing.” (Sustainability,
Parks, Recycling & Wildlife Defense Fund v. Department of Resources
Recycling & Recovery (2019) 34 Cal.App.5th 676, 696 [hereafter, “Sustainability”].) “The requirement that a full presentation be
made before the adjudicating agency applies equally when a second
administrative agency, exercising appellate functions, enters the picture. A
party may not raise new issues on review before such a tribunal if the issues
could have been asserted before the lower administrative body.” (Ibid.)
The LAMC
also required Petitioner to raise all issues in its LADBS appeal. Specifically, “[a]n appeal to the Director of Planning may only
be made after the Department of
Building
and Safety has rendered a decision in writing and provided written
justification and findings on an appeal made pursuant to Section 98.0403.2 (a)
of the Code.” (LAMC
§
12.26.K.1; Pet. RJN Exh. 1 at 18 [emphasis added].) Since LADBS cannot issue a written decision
on matters not presented, the right to appeal to the Director of Planning only
applies to issues raised in the LADBS appeal.
Here, in its appeal filed
with LADBS, Petitioner asserted that: (1) The structure depicted in the Project
plans exceeds the applicable height limit in the LAMC; (2) The retaining walls
depicted in the plans exceeded the amount allowed pursuant to the HRWO; (3) The
grading approved for the Project exceeded the amount allowed under the BHO; and
(4) The Project is ineligible for a residential floor area (“RFA”) bonus. (AR
106-109, 110-120.) Petitioner argued
that “the grant of the ministerial permits was in error” and requested that the
City “revoke all ministerial permits.”
(AR 110, 120.) Petitioner did not
assert that the Project, as constructed, failed to comply with the Building
Permits. Nor did Petitioner file a
supplemental appeal with LADBS to raise such issues. Accordingly, the Planning Department and the APC
properly limited the scope of appellate review to the issues raised in
Petitioner’s LADBS appeal. (See Sustainability, supra, 34
Cal.App.5th at 696-697.)
In its
reply briefs, Petitioner argues, for the first time, that it should be excused
from raising its arguments about construction activities before LADBS because
“due to COVID-19 emergency procedures closing government offices, Petitioner
was unable to access a set of plans to formulate its arguments.” (Reply to City’s Opposition 2.) “The salutary rule is that points raised in a
reply brief for the first time will not be considered unless good cause is
shown for the failure to present them before.”
(Balboa Ins. Co. v. Aguirre (1983) 149 Cal.App.3d 1002,
1010.) Petitioner has not shown good
cause to raise these arguments for the first time in reply, depriving the City
and Real Parties an opportunity to respond in their written oppositions.
Regardless, Petitioner has not shown a valid excuse from
the exhaustion requirement. First,
Petitioner argues: “At the time Petitioner’s appeal was filed on May 17, 2021,
the LADBS offices were closed to the public due to the COVID-19 emergency and
did not permit inspection of plans.”
(Reply To City’s Opposition 3:11-13.)
Petitioner cites to AR 2315, which is a letter to that effect, but it is
dated January 17, 2021, four months before Petitioner filed its appeal. Even assuming that was the case in May 2021, Petitioner
admits that it received “copies of relevant portions of the plans [when] the
Zoning Administrator attached them in response … to the appeal.” (Id. 3:23-24, citing AR 705,
683-696.) Thus, Petitioner admittedly
had access to the plans no later than June 2022, and could have filed an appeal
at that point. (See AR 645, 661-664,
683-696.) Indeed, Petitioner’s new
argument concerns ongoing construction activities, not the issuance of the
building permits, so Petitioner should have filed a new appeal before the
LADBS. Petitioner failed to do so. Therefore, the court finds that the alleged
lack of access to plans due to COVID-19 does not excuse Petitioner’s obligation
to raise the issue before the LADBS.
2.
The Planning Department/APC lack jurisdiction over this issue
Petitioner contends that the Planning Department and the
APC erred in concluding that they lacked jurisdiction to decide whether ongoing
construction activities complied with the Building Permits or the City’s
ordinances. Petitioner raises an issue
of statutory construction. To the extent
“purely legal issues involve the interpretation of a statute an administrative
agency is responsible for enforcing, [the court] exercise[s] [its] independent
judgment, ‘taking into account and respecting the agency’s interpretation of
its meaning.’” (Housing Partners I, Inc. v. Duncan (2012) 206 Cal.App.4th 1335,
1343.)
How much weight to accord an agency's construction is “situational,” and
depends on the circumstances. (See American Coatings Assn. v. South Coast Air
Quality Management Dist. (2012) 54 Cal.4th 446, 461-462.) “Under well-established law, an agency’s view of the meaning
and scope of its own ordinance is entitled to great weight unless it is clearly
erroneous or unauthorized.” (Friends of
Davis v. City of Davis (2000) 83 Cal.App.4th 1004, 1015.)
Here, in
defining the scope of Petitioner’s appeal, the ZA and APC observed that “[a]
review (inspection) of the actual development or construction at the project
site is conducted by the LADBS Enforcement Division (Inspectors), which
generally issues citations when non-compliant matters are discovered during
inspection.” (AR 980, 1856.) The ZA and APC then stated:
The Zoning Administrator acknowledges the
concerns and complaints related to the on-going construction at the project. .
. . The neighbors and the appellants are
well within their right to register complaints if there is a belief that the
current construction of the single-family residence is not consistent with the
plans approved by the LADBS Plan Check Division. Complaints regarding ongoing construction at a
particular site should be filed with the Enforcement Division of the Building
and Safety. The Department of
Building and Safety Inspectors will take
action if it is determined the complaints are valid.
(AR 981-982, 1857-1858.) Thus, the ZA and APC interpreted the
applicable City ordinances to confer initial authority over inspection of
construction activities and related enforcement issues on the LADBS, not the
Planning Department.
Petitioner
has not shown that this interpretation of the applicable City ordinances is
“clearly erroneous.” LADBS, not the
Planning Department, has authority over the inspection of construction work for
which a permit has been issued. “A
permit is merely an application for inspection, the issuance of which entitles
the permittee to inspection of the work which is described therein.” (LAMC § 91.106.4.3.1; City RJN Exh. 6.) “All construction or work for which a permit
is required shall be subject to inspection by authorized employees of [LADBS]….
Prior to the issuance of a Certificate of Occupancy …, a final inspection shall
be made by [LADBS] of all construction or work for which a permit has been
issued.” (LAMC § 91.108.1; City RJN Exh.
7.) LADBS also has broad authority over
enforcement matters related to construction activity:
Whenever any
construction work is being done contrary to the provisions of any law or
ordinance enforced by the Department, the Department shall have the authority
to issue a written notice to the responsible party to stop work on that portion
of the work on which the violation has occurred. The notice shall state the
nature of the violation and no work
shall be done on that
portion until the violation has been rectified and approval obtained from the
Department.
(LAMC § 91.104.2.4; City RJN Exh. 3.) LADBS “is granted the power to enforce all
ordinances and laws relating to the construction … of buildings or structures
in the City.” (LAMC § 98.0403.1(a)1;
Pet. RJN Exh. 2.)
Nonetheless,
Petitioner argues that the Planning Department and the APC have jurisdiction to
review LADBS’s enforcement decisions pursuant to LAMC section 12.26.K.1, which
provides in pertinent part:
K.
Appeals from Building Department Determinations.
1. Right
of Appeal. The Director of Planning shall have the
power and duty to investigate and make a decision upon appeals from
determinations of the Department of Building and Safety where it is alleged
there is error or abuse of discretion in any order, interpretation, requirement,
determination or action made by the Department of Building and Safety in the
enforcement or administration of Chapter I of this Code and other land use
ordinances in site-specific cases. . . . An appeal to the Director of Planning may only
be made after the Department of Building and Safety has rendered a decision in
writing and provided written justification and findings on an appeal made
pursuant to Section 98.0403.2(a) of the Code.
(OB 7-8; Pet. RJN Exh. 1.) LAMC sections 98.0403.1 and 98.0403.2, which
are referenced in section 12.26, provide in pertinent part that LADBS “shall
have the power to hear and act upon requests for slight modifications in
individual cases to the building ordinances of the City” and that appeals of
such decisions shall be made to the Board of Building and Safety Commissioners
(“BBSC”). (See LAMC §§
98.0403.1(a), (b); 98.0403.2(a), (b).)
Section 12.26.K “must be construed in the context of the
entire statutory system of which it is a part, in order to achieve harmony
among the parts.” (People
v. Hull (1991) 1 Cal.4th 266, 272.) As noted,
inspections of ongoing construction are performed by LADBS after a permit is
issued, but before a certificate of occupancy is issued. (LAMC §§ 91.106.4.3.1, 91.108.1.) Then, if construction work is being done in a
manner contrary to the building permits or City’s ordinances, LADBS is the
agency responsible for enforcement. (LAMC
§§ 91.104.2.4, 98.0403.1(a)1.) Harmonizing these ordinances, the City
reasonably interpreted section 12.26.K to authorize the Director of Planning
and the APC to decide appeals related to the LADBS’s enforcement or
administration of the Zoning Code, as reflected in the LADBS’s permitting
decisions. The City also
reasonably concluded that “[a] review (inspection) of the actual development or
construction at the project site is conducted by the LADBS Enforcement Division
(Inspectors),” not by the Planning Department.
(AR 980, 1856.) Petitioner has
not shown that the City’s interpretations of its own ordinances are clearly
erroneous.
The City’s interpretation is also consistent with the well-established
maxim that “an agency’s decision not to prosecute
or enforce, whether through civil or criminal process, is a decision generally
committed to an agency’s absolute discretion.”
(Heckler v. Chaney (1985) 470 U.S. 821, 831.) Here, Petitioner
challenges LADBS’s alleged decision not to issue citations based upon alleged
deviations between the construction and the Building Permits. This is not a challenge to any express or
affirmative “orders, interpretations, requirements, determinations, or actions”
of LADBS. Rather, Petitioner challenges
LADBS’s inaction, which generally falls beyond the scope of review.
3. Conclusion
Petitioner
attempts to raise a new issue, arguing that the construction deviated from the Building
Permits. But Petitioner did not raise
this issue in any appeal to the LADBS and has not demonstrated any good cause
to excuse the exhaustion requirement.
Moreover, Petitioner does not demonstrate that the Planning Department
and the APC clearly erred in finding that they lacked authority to review this
issue. Therefore, the petition for writ
of mandate is denied on this ground.
B. Residential
Floor Area Bonus
Petitioner contends that the City erroneously “granted
Real Party the right to choose how to calculate lot width” in the calculation
of the residential floor area (“RFA”) bonus for the Project, and that the
City’s findings related to the RFA bonus are not supported by substantial
evidence. (OB 10-11.)
1. The “Cumulative Side Yard Setbacks
Option”
The LAMC provides that a 20 percent RFA bonus “shall be
allowed” if one of several listed options is utilized, including, as relevant
here:
Cumulative Side Yard Setbacks Option. The combined width of Side Yards shall be at least 25%
of the total Lot Width, as defined in Section 12.03 of this Code, but in no
event shall a single Side Yard setback be less than 10% of the Lot Width or the
minimum required by Paragraph (a) of this Subdivision, whichever is greater.
One (1) foot shall be added to each required Side Yard for each increment of 10
feet or fraction thereof of height above the first 18 feet of height. The width
of a required Side Yard setback shall be maintained for the entire length of a
Side Yard and cannot alternate from one Side Yard to the other….
(LAMC § 12.21.C.10(b)(3)(iii); Pet. RJN Exh.
4 at 6.) “Lot Width” is defined as
“[t]he horizontal distance between the side lot lines measured at right angles
to the lot depth at a point midway between the front and rear lot lines.” (LAMC § 12.03; Pet. RJN Exh. 9.) “Lot Depth” is defined as “[t]he horizontal distance
between the front and rear lot lines measured in the mean
direction
of the side lot lines.” (Ibid.)
For
“flag lots” located in a Hillside or a Very High Fire Hazard Severity Zone, the
LAMC provides an alternative method of calculating lot width, which states in
pertinent part:
[T]he lot width may be
calculated by measuring the width of the main buildable portion of said flag
lot on a straight line parallel to the general direction of the frontage street
and midway between the rear and front lines of the main buildable portion of
the flag lot….
(LAMC § 12.22.C.22; Pet. RJN Exh. 12 at 4
[emphasis added].) A “flag lot” is
defined as “[a]
lot so shaped and designed that the main building site area is set back from
the street on which it fronts and includes an access strip not less than 20
feet in width at any point connecting the main building site area to the
frontage street.” (LAMC § 12.03; Pet.
RJN Exh. 9.) “A flag lot gets its name
from its resemblance to a flag pole (minimum 20'0" wide access strip)
supporting a flag (main building site area).”
(AR 934.)
2. Substantial evidence supports the
City’s calculation of the lot width
A Lot Width Diagram in the Project plans shows that the
lot width of the Property is 80.3 feet.
(AR 1732.) Twenty-five percent of
80.3 feet is 20.1 feet. (AR 935.) The cumulative sum of the Project’s side
yards is 27 feet, exceeding the 20.1-foot minimum required by LAMC section
12.21.C.10(b)(3)(iii). (Ibid.) Accordingly,
substantial evidence supports the City’s determination that Real Parties are
entitled to a 20 percent RFA bonus.
3. Use of the flag lot measurement is permissive
Petitioner does not challenge the City’s calculations
under section 12.21.C.10(b)(3)(iii).
Rather, Petitioner argues that the APC erred when it did not require the
use of the flag lot measurement to determine lot width when it approved a RFA
bonus for the Project. (OB 9-11.) Petitioner’s arguments are not
persuasive.
LAMC
section 12.22.C.22 plainly states that the width of flag lots “may be
calculated” using its alternative measure of width. The phrase “may be calculated” indicates
that the exception is permissive, not mandatory. (See LAMC § 11.01(a) [“‘Shall’ is mandatory;
‘May’ is permissive.”]; Walt Rankin & Associates, Inc. v. City of
Murrieta (2000) 84 Cal.App.4th 605, 614 [“the usual rule with California
codes is that ‘shall’ is mandatory and ‘may’ is permissive”].)
Petitioner
argues that the LADBS, and not the applicant, “is empowered” to decide which of
the two alternative measurements of lot width to employ. (OB 10.)
The City disagreed and found that
“[t]he applicant has the discretion to apply either lot width calculation for
the Cumulative Side Yard Setback Option in Section 12.21C10(b)(3)(iii).” (AR 745, 1044; see also AR
1832-1833.) The City’s interpretation of
its own ordinance is entitled to deference, is supported by the plain language
of section 12.22.C.22, and is not clearly
erroneous. (See Friends of Davis, supra, 83
Cal.App.4th at 1015.) Regardless, LADBS,
the Planning Director, and the APC all approved the use of the standard
measurement of width lot and denied Petitioner’s administrative appeals. (AR 55, 106, 663, 961-962, 1043-1045,
1832-1833.)
Petitioner’s
reliance on the City Council’s section 245 motion is misplaced. (See OB 10.) The City Council did not purport to offer an
authoritative interpretation of the code’s lot width or flag lot regulations. Rather, the City Council instructed the LADBS,
in consultation with Planning and other relevant departments, to prepare a
report reviewing the applicability of the code’s flag lot regulations to the
proposed Project. (AR 1012-1013.) The LADBS complied with the City Council’s
directive and found that the RFA bonus was properly applied to the Project. (AR
1043-1045.) The City Council did not
assert further jurisdiction over the matter pursuant to section 245 of the City
Charter after the APC denied Petitioner’s appeal on November 6, 2023, after the
flag lot issue was reconsidered by LADBS and the APC. (AR 1832-1833.)[1]
4. Substantial Evidence Supports the
City’s Determination that the Plans Accurately Depict the Property Lot Lines
Petitioner
contends that LADBS “utilized plot plans to calculate the lot width and area
bonus eligibility that had incorrect lot dimensions that deviated significantly
from those dimensions in official recorded maps filed with the County Recorder,
namely Parcel PMEX No. AA-2014–3449.” (OB
11.) Petitioner relies on a 2014 lot
line adjustment, case number PMEX No. AA-2014-3449 (“2014 PMEX”), which
Petitioner claims “was created to divide the lots for 822 and 824 Kenter.” (AR 2227, 2444.)
Real
Parties argue that “[o]n its face, the 2014 PMEX adjusted the lot boundaries
between 822 Kenter Avenue, 774 Kenter Avenue, and 841 Leonard Road, and did not
implicate 824 Kenter.” (Real Parties Oppo.
15.) The Real Parties are correct. (See AR 45, 1804-1807, 2413.)[2] Petitioner did not respond to this argument
in reply. (See Reply to City’s
Opposition 11; see also Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc.
(2003) 111 Cal.App.4th 1328, 1345, fn. 16 [failure to address point is
“equivalent to a concession”].) Thus, Petitioner’s
cited evidence does not support its position that the plot plans used to
calculate the lot width and area bonus had incorrect lot dimensions.
In any
event, with their building plans, the Real Parties included a stamped survey performed
by a licensed surveyor. (AR 1733-1734, 2070-2071.) The dimensions shown on the permits and
approved Project plans align with the survey. (AR 66, 1729-1747; SAR 2465-2466.) Petitioner has not argued, or shown, to the
contrary. At the APC hearing, the LADBS
plan checker testified that LADBS typically accepts a stamped survey from a
licensed surveyor as authoritative evidence of lot lines and dimensions. (AR 2070-2071, 1931.) The plan checker also testified that if a
discrepancy is found during an LADBS inspection, the inspector may request
further information to determine the survey’s accuracy. (AR 2070-2071.) There is no evidence that an inspection
revealed a discrepancy with the survey. Further,
the stamped survey is substantial evidence of the lot’s dimensions, and the
City was entitled to give it more weight than it gave to the 2014 PMEX. (Association of Irritated Residents v.
County of Madera (2003) 107 Cal. App. 4th 1383, 1397 (2003) [“decisionmaker
is ‘permitted to give more weight to some of the evidence and to favor the
opinions and estimates of some of the experts over the others’”].) On substantial evidence review, the court
cannot reweigh the evidence or substitute its own inferences for those of the
City. (McAllister v. California
Coastal Com. (2008)169 Cal. App. 4th 912, 921-22.)
Based on
the foregoing, substantial evidence supports the City’s finding that the
Project is entitled to a 20 percent RFA bonus.
Petitioner has not shown a prejudicial abuse of discretion or other
legal error in that finding. (CCP §
1094.5(b).)
C. Substantial
Evidence Supports the City’s Findings that the Project Complies with the
Baseline Hillside Ordinance’s Height Restrictions
1. The ADU complies with the 36-foot height
limit
Petitioner argues that the APC’s “determination that the
Project was within the maximum height limit of 36 feet set forth in the BHO is
not supported by substantial evidence.”
(OB 11-12.) Petitioner acknowledges
that the “applicable height limit is 36 feet” for ADU part of the Project. (OB 12, fn. 6, citing Table 12.21.C.10-4; AR
85; Pet. RJN Exh. 7 at 2; see also Reply
to Real Parties 8, fn. 4.) Petitioner
does not challenge LADBS’s initial determination that the Project plans for the
ADU comply with this heigh limit. Instead,
Petitioner cites a photograph of the home under construction (SAR 2232) and
estimates from that photograph that the ADU portion of the Project “would be
upwards of 43.5 feet tall upon completion.” (OB 12:1-7.)
As discussed, Petitioner did not argue in the LADBS
appeal that the Project, as constructed, failed to comply with the
applicable height limits. (AR 106-109, 110-120.) Regardless, Petitioner’s arguments are not
persuasive. Height is governed by LAMC
section 12.21.C.10(d)(1), which states that the height limits in Table
12.21.C.10-4 “shall be measured” based on the “Maximum Envelope Height,” defined
as follows:
Envelope
height (otherwise known as vertical height or “plumb line” height) shall be the
vertical distance from the Hillside Area Grade to a projected plane at the roof
Structure or parapet wall located directly above and parallel to the Grade.
Measurement of the envelope height shall originate at the adjacent Hillside
Area Grade at the exterior walls of a Building or Structure.
(Pet.
RJN, Exh. 6 at 5; AR 283.) “Hillside
Area Grade” is defined as “the Elevation, at the perimeter of a Building or
Structure, of the finished or natural surface of the ground, whichever is
lower, or the finished surface of the ground established in conformance with a
grading plan approved pursuant to a recorded tract or parcel map action.” (Pet. RJN Exh. 9.)
In other words, height is
measured at the exterior wall at the grade adjacent to the measured point. Petitioner, in contrast, estimates the height
of the ADU from a point on the opposite end of the structure. (SAR 2232.)
As shown by Petitioner’s picture, the grade adjacent to the ADU is
significantly higher than the measurement point at the opposite end of the
structure. (SAR 2232.) Section
elevations in the record, which Petitioner does not address, show that the
Project will be under the 36-foot height limit on all sides. (SAR 2470-2471; Toigo, supra, 70 Cal.App.4th at 317 [when an
appellant challenges “’the sufficiency of the evidence, all material evidence
on the point must be set forth and not merely [her] own evidence.”].) Substantial evidence supports the City’s
determination that the ADU complies with the 36-foot height limit, which, as
Petitioner admits, applies to that portion of the Project. (See Reply to Real Parties 8, fn.
4.)
2. The height of the main house is not a
basis to grant the petition
Petitioner also asserts that the main house is subject to
a 30-foot height limit for certain parts of the Project structure. (OB 12; Reply
to Real Parties 8-10.) Specifically,
Petitioner contends that a 30-foot height limit applies to the portions of the
Project’s roof that are “flat” and that the “open trellis” is not a “projecting
roof structure” that may be “erected above” the 30-foot limit pursuant to LAMC
Table 12.21.C.10-5. (OB 12.)
Petitioner did not raise these arguments in its LADBS
appeal. (AR 106-109, 110-120.) Contrary to Petitioner’s assertion, the issue
was not raised in any matter and not with “sufficient
specificity for purposes of administrative hearings.” (Reply to Real
Parties 8, citing Mani Brothers Real Estate Group v. City of Los
Angeles (2007) 153 Cal.App.4th 1385, 1395.) Moreover, whether the Project plans justify a
height limit of 30 or 36 feet for the main house presents, at least in part, a
fact question that the LADBS should decide in the first instance. (Reply to Real Parties 8:18-21.) Accordingly, the issue was not properly
before the APC and cannot be raised in the first instance on writ review. (Sustainability,
supra, 34 Cal.App.5th at 696.)
Regardless, Petitioner’s arguments from the opening brief
about a purported “open trellis” are not persuasive. (See OB 12.) In the RE40-1 Zone the height limit is 36
feet “[w]hen the roof of the uppermost story of a building or structure or
portion thereof has a slope of 25% or greater.” (Pet. RJN Exh. 5 at 18; AR 283.) The City’s BHO Comprehensive Guide also
states:
The 25% roof slope is a Southern California
standard which is also commonly referred to as the 3:12 slope. This slope can
be expressed as a ratio of 1 foot of vertical rise for every 4 feet of
horizontal distance…. When a roof is made up of a combination of roof slopes,
the portions of the structure with a roof slope less than 25% will be
considered flat and as a result be required to comply with the lower height.
(Pet. RJN Exh. 5 at 18.)
Here, Petitioner’s slides and the corresponding Project
plan include a sloped roof with the notation “3:12 sloped trellis.” (AR 1743, SAR 2424-2425, 2470.) The plans are substantial evidence that the
main house qualifies for the 36-foot height limit and that the trellis falls
within that height limit. (AR 1743, SAR 2424-2425,
2470.) Accordingly, Petitioner’s
argument that the trellis is not a “projecting roof structure” subject to LAMC Table 12.21.C.10-5 is misplaced. Table
12.21.C.10-5 only applies to structures that are “erected above” the applicable
height limit, and the plans show that the trellis does not extend above the
36-foot height limit. (Pet. RJN Exh. 8
at 2; AR 1743, SAR 2424-2425, 2470.)
In reply, Petitioner argues, for the first time, that “an
open trellis is obviously not a roof” because it “is an ornamental structure
which affords no protection from the elements and is not integral to the
concept of a building.” (Reply to Real
Parties 9:13-14.) Accordingly,
Petitioner argues that the trellis “does not establish a 36-foot height limit
at that portion of the building.” (Id.
9:18-19.) “The salutary rule is that
points raised in a reply brief for the first time will not be considered unless
good cause is shown for the failure to present them before.” (Balboa Ins. Co. v. Aguirre (1983) 149
Cal.App.3d 1002, 1010.) Petitioner does
not show good cause to raise this argument for the first time in reply,
depriving Real Parties an opportunity to respond in their written opposition. Moreover, Petitioner failed to argue in its
LADBS appeal that the “3:12 sloped trellis” is not part of the Project’s
roof. Accordingly, Petitioner did not
preserve the issue for judicial review. (Sustainability, supra, 34
Cal.App.5th at 696.) The court cannot
determine the definition of “roof” for purposes of the BHO—i.e., whether
a “3:12 sloped trellis” is part of the “roof”—without the LADBS first
addressing the issue. Nor can the court
decide this issue without giving the Real Parties and the City an opportunity
to respond.
D. The Retaining
Wall Is Not a Basis to Grant the Petition
Finally, Petitioner argues that a retaining wall intended
for 822 Kenter was incorrectly built on 824 Kenter, which allegedly caused the
Project to exceed the limit of two retaining walls from the City’s Hillside
Retaining Wall Ordinance (“HRWO”). (OB
13-15, citing AR 831-834 and LAMC § 12.21.C.8(a) [HRWO retaining wall limit].) As support, Petitioner relies on “aerial
photography from ZIMAS (AR 1803, SAR 2240), the County of Los Angeles
Assessor’s Portal (AR 1804, SAR 2239), Google Earth (AR 1804) and NavigateLA
(AR 1805),” as well as videos and photos of the two properties taken on
September 2, 2023, by a licensed drone operator hired by Petitioner (AR 1805,
1811). (OB 13.) These arguments were raised in a letter dated
September 4, 2023, just two days before the final September 6, 2023, APC
hearing. (AR 1802.)
These arguments fail for several reasons. With respect to retaining walls, Petitioner only
argued in the LADBS appeal that a planter wall should be considered a retaining
wall; that another retaining wall was, in fact, “more than one wall … because
[it] twists and turns and changes directions”; and that a wall along a storage
building was also a retaining wall. (AR 4-5.) Petitioner did not argue in its LADBS appeal
that a retaining wall intended for 822 Kenter was incorrectly built on 824
Kenter, resulting in the Project’s exceedance of the two-wall limit established
by the HRWO. Further, as Real Parties state,
Petitioner’s argument that a retaining wall was built “in the wrong place” does
not raise a Zoning Code issue to be decided by the APC, but rather a matter for
inspection and enforcement of the applicable building permit by LADBS. (Real Parties Oppo. 17-18.) To illustrate, if a retaining wall was
improperly constructed on 824 Kenter, one possible remedy (among others) could
be to destroy the wall and rebuild it on 822 Kenter. LADBS is the agency responsible for deciding
such issues of enforcement. (LAMC §§
91.104.2.4, 98.0403.1(a)1; Pet. RJN Exh. 1-3.)
Accordingly, that issue was not properly before the APC and Petitioner failed
to preserve the issue for judicial review.
(Sustainability, supra, 34
Cal.App.5th at 696.)
Regardless, there is substantial evidence demonstrating
that the retaining wall at issue was built on 822 Kenter and not 824
Kenter. Specifically, a Topographic
Survey prepared by a licensed surveyor indicates that the retaining wall is
located on 822 Kenter. (AR
1733-1734.) The City was entitled to
rely on this survey over Petitioner’s evidence, including the report from
Petitioner’s aerial drone expert. (Association
of Irritated Residents, supra, 107 Cal. App. 4th at 1397; see AR
1805-1811.)
Petitioner argues that “[t]he LAMC requires the
identification of existing-onsite walls as a ‘condition precedent to issuing a
grading permit,’” and cites LAMC section 91.7006.1.4 as support. (OB 14, citing Pet. RJN Exh. 13.) Relatedly, Petitioner argues that the LADBS
was required by a “Condition 2” of the Project plans “to verify that existing
site conditions conformed with the plans prior to permit issuance.” (OB 14, citing AR 1730.) Neither argument is persuasive. Petitioner’s reliance on section 91.7006.1.4,
a building regulation, and Condition 2, from a soils report, shows that Petitioner’s
arguments do not involve a zoning issue and were not properly before the
APC. Furthermore, section 91.7006.1.4 requires
identification of walls to be constructed and Condition 2 requires verification
of geological data, not the existing walls.
Regardless, LADBS did verify the location of the retaining wall on the
822 Kenter property based on the survey, as noted above. (AR 1733-1734.)
Petitioner argues that permits that are issued based upon
a misrepresentation are void, citing to Stokes v. Board of Permit Appeals
(1997) 52 Cal. App. 4th 1348. (OB
15.) However, Petitioner has not offered
evidence that a misrepresentation was made to LADBS when it issued the permits.
Accordingly, Stokes does not
benefit Petitioner.
In a footnote, Petitioner asserts that “the Court may
shift the burden of proof regarding the location of the existing retaining wall
to Respondent.” (OB 15, fn. 11, citing Lakin
v. Watkins Associated Industries (1993) 6 Cal. 4th 644, 660-661.) Lakin was a personal injury case, and
the Supreme Court did not find that burden shifting was appropriate under the
facts of that case. As discussed above,
Petitioner did not properly raise the issue concerning the retaining wall in
its LADBS appeal. Petitioner also does
not show that it would be impossible for it to prove its case without burden
shifting. (See Sargent Fletcher, Inc.
v. Able Corp. (2003) 110 Cal.App.4th 1658, 1670.) For all these reasons, Lakin does
not support a request for burden shifting in the instant case.
Based on the foregoing, Petitioner failed to raise its
current arguments related to the retaining walls of the Project in an appeal to
LADBS. Accordingly, those issues were
not preserved for judicial review in this writ action. (See Sustainability,
supra, 34 Cal.App.5th at 696-697.) Alternatively, the City’s findings and
decision with respect to the number of retaining walls on the Project site are
supported by substantial evidence.
Petitioner has not shown any prejudicial abuse of discretion or legal
error in the City’s decisions related to retaining walls of the Project. (Code Civ. Proc. § 1094.5(b).)
CONCLUSION
AND ORDER
Based upon the foregoing, the court
orders as follows:
1. The
petition for writ of mandate is denied.
2. The
parties shall meet-and-confer and lodge a proposed judgment forthwith.
3. The
court’s clerk shall provide notice.
IT
IS SO ORDERED
Dated: January 8, 2025 ______________________
Stephen
I. Goorvitch
Superior
Court Judge
[1] Section 245(e) of
the City Charter states: “The Council shall not be limited to veto of actions of the
City Planning Commission or Area Planning Commissions, but, subject to the time
limits and other limitations of this section, after voting to bring the matter
before it, shall have the same authority to act on a matter as that originally
held by the City Planning Commission or Area Planning Commission.”
[2] Although the 2014
PMEX refers to “Parcel 1” in the lot adjustment as “824 Kenter,” the map in the
2014 PMEX identifies Parcel 1 as the real property now designated as 822 Kenter
on various other maps in the record, including those supplied by Petitioner. (See AR 45, 1804-1807, 2413.)