Judge: Stephen P. Pfahler, Case: 22CHCV00392, Date: 2022-12-28 Tentative Ruling
Case Number: 22CHCV00392 Hearing Date: December 28, 2022 Dept: F49
Dept.
F-49
Date:
12-28-22 c/f 11-15-22 a/f 2-7-23 (10-13-22 ex parte order)
Case
#22CHCV00392
Trial
Date: N/A
ARBITRATION
MOVING
PARTY: Defendant/Cross-Complainant, John Goshorn
RESPONDING
PARTY: Plaintiffs/Cross-Defendants, Aqua Blue Construction, Inc., et al.
RELIEF
REQUESTED
Motion
to Compel Arbitration
SUMMARY
OF ACTION
Plaintiffs
Aqua Blue Construction, Inc., and Britton Julien allege Defendant John Goshorn
failed to pay a remaining balance of $32,305 for construction of a pool and
spa. The balance arises as a result change orders, which Plaintiffs allege
Defendant requested knowing Defendant lacked the ability to pay the changes.
Plaintiffs additionally contend that Defendants submitted a “fraudulent
insurance claim containing” on the construction bond representing the
construction delays were the fault of Plaintiffs. According to Plaintiffs: the
construction was still completed; the claim on the bond was denied.
On
May 31, 2022, Plaintiffs filed a complaint for Breach of Contract, Common
Counts, and Fraud. On August 15, 2022, Goshorn filed a cross-complaint for
Declaratory Relief, Breach of Written Contract, Fraud and Deceit, Negligence,
Contracting without a License, and Recovery on Contractor’s License Bond
against, Aqua Blue, Britton, Hanover Insurance Company, the North River
Insurance Company, and Old Republic Surety. The cross-complaint alleges an
alternative narrative regarding the basis of the construction delays, and
claimed balance due.
On
September 30, 2022, Old Republic Surety Company filed a cross-complaint for
Interpleader. On October 4, 2022, The North River Insurance Company filed a
cross-complaint for Express Indemnity, Implied Indemnity, Statutory
Reimbursement, and Contribution against the Aqua Blue and Britton Julien.
On
November 18, 2022, and December 5, 2022, Goshorm dismissed The North River
Insurance Company from the cross-complaint, and The North River Insurance
Company dismissed its cross-complaint against Aqua Blue and Julien. Meanwhile,
on November 21, 2022, the court entered the stipulation of the parties for Old
Republic Surety Company to interplead all $15,000 of bond funds.
RULING: Granted.
Request
for Judicial Notice of Old Republic Surety Company: Granted.
Defendant/Cross-Complainant, John Goshorn moves to compel
arbitration. Goshorn cites to the arbitration provision in the construction
contract, and maintain all causes of action are subject to arbitration. Plaintiffs
Aqua Blue Construction, Inc., and Britton Julien in opposition challenge the
application of the clause to the subject dispute based on both an issue of
licensure status of the corporate entity, and a third party case against Aqua
Blue Construction, Inc., and Britton Julien. Goshorn in reply challenges any reliance
on the unrelated third party case.
The complaint itself alleges that Plaintiffs sought
arbitration, and Goshorn refused to participate. Goshorn counters the
allegation regarding arbitration was conditioned on the dismissal of four
causes of action within the cross-complaint. Regardless of the allegations and
sought after terms and conditions of the parties, the court considers the
standard.
In a motion to
compel arbitration, the moving party must prove by a preponderance of evidence
the existence of the arbitration agreement and that the dispute is covered by
the agreement. The burden then shifts to the resisting party to prove by a preponderance
of evidence a ground for denial (e.g., fraud, unconscionability, etc.). (Rosenthal
v. Great Western Fin'l Securities Corp. (1996) 14 Cal.4th 394, 413-414; Hotels
Nevada v. L.A. Pacific Ctr., Inc. (2006) 144 Cal.App.4th 754, 758.) Defendants in oral argument cited
recent case law regarding the three step process for moving party to establish
an enforceable arbitration agreement. (Gamboa v. Northeast Community Clinic (2021) 72 Cal.App.5th 158, 164–165.) The first step
requires either presentation of a written agreement to arbitrate, or
presentation of terms without dispute from the opposing party. (Id., at p.
165.)
“Buyers and Aqua Blue
Construction, Inc. agree that any and all disputes regarding any provision
contained in this agreement or any work performed by Aqua Blue Construction…
shall be adjudicated by private arbitration.” [Declaration of John Goshorn, Ex.
A.] The existence and execution of the arbitration agreement itself is not in
dispute. The court therefore considers whether the dispute is covered by the
agreement.
The motion apparently comes under
the presumption that the dispute arises from the construction of the pool and
outdoor hardscape, and is therefore subject to arbitration. The opposition
presents a counter narrative regarding the collateral circumstances raised in
the cross-complaint, thereby leading to argument challenging application of the
arbitration clause.
Aqua Blue begins with a discussion
of pre-construction inquiry by the Contractors State Licensing Board (CSLB)
regarding a lack of workers’ compensation insurance to which Aqua Blue
maintained it was entitled to an exemption. Aqua Blue then follows with a
reference of a third party report during or after the completion of
construction, which led to the initiation of a disciplinary hearing by the CSLB
regarding whether Aqua Blue employed any persons thereby requiring a workers’
compensation policy.
As for the source of the report and
subsequent action by the CSLB, Aqua Blue references a second case entitled
Kriste and Alfredo Galvan v. Aqua Blue Constructions, Inc., et al.
(22CHCV00382), which Aqua Blue represents as containing similar claims and
allegations as the cross-complaint regarding work without a license. The Galvan
complaint was filed before the subject action by different counsel. As
referenced above, the Galvans are also parties to the separate proceeding
brought by the CSLB.
Plaintiffs maintain the totality
of the circumstances ostensibly presents a potential situation for potential
conflicting rulings under Code of Civil Procedure section 1281.2, subdivision
(c) in that the Galvan’s report to the CSLB and pending action, pending separate
complaint of the Galvans, and Goshorn cross-complaint due to the disparate
proceedings. Plaintiffs also contend the licensure arguments pending before the
CSLB and the parties’ actions render enough of the action outside the scope of
the arbitration clause itself. The licensure claims permeate the first, second,
third and fifth causes of action in the operative Goshorn cross-complaint.
In considering the scope of the
arbitration clause itself, the court declines to consider any potential issues arising
from the other action. The court also declines to consider any pending
investigation, hearing or potential conclusions of the CSLB for purposes of
determining the validity of the arbitration clause brought by the unrelated
parties.
The complaint itself remains
subject to the arbitration clause in that payment for completion of the
improvement project remains outstanding. The operative cross-complaint frames
the opposition arguments in that Defendant/Cross-Defendant presents numerous
allegations regarding representation of a contracting business exempt from
workers’ compensation requirements and operated as a licensed contractor in the
introduction, and first, third, and fifth causes of action. [Cross-Comp., ¶¶
25-30, 34-41, 57-60, .] The purpose of the allegations in the Goshorn cross-complaint
present a claim that as an unlicensed contractor, Aqua Blue cannot recover
compensation for work valued at over $500 under California Business and
Professions Code section 7031, and seeks disgorgement. [Cross-Comp., ¶¶ 42-43,
61, 70-73.] The second and fourth causes of action for breach of contract and
negligence challenge the charges in excess of the initial contract price and
workmanship. The sixth cause of action seeking to collect on the contractors
bond lacks any nexus with the alleged licensure claim.
To the extent Aqua Blue and Julien
seek to collect on the balance due, the status of its right to demand payment
depends on licensure status under Business and Professions Code section 7031.
The court therefore finds the argument for disparate treatment of both the
right to collect—an undisputed term subject to arbitration—versus issues
challenging the right to collect due to licensure status, constitutes an inextricable
distinction. In other words, the plain meaning of the arbitration clause includes
claims for outstanding payments, which directly relates to the right to collect said outstanding
claimed balance. The issue of whether Aqua Blue operated properly without
workers’ compensation insurance or not as it relates to the disputed fees subject
to arbitration remains integral. The court finds no basis for a conflicted
ruling. The court therefore finds a basis to compel arbitration between
Goshorn, Aqua Blue, and Julien.
Plaintiffs otherwise present no
request to delay the arbitration pending resolution of the disciplinary
hearing. The court declines to deny arbitration based on an outside proceeding.
In the prior order, the court
noted the lack of address of the contractor bond companies. The court ordered
supplemental briefing regarding these parties.
Following the prior order, on
November 18, 2022, and December 5, 2022, Goshorm dismissed The North River
Insurance Company from the cross-complaint, and The North River Insurance
Company dismissed its cross-complaint against Aqua Blue and Julien. Meanwhile,
on November 21, 2022, the court entered the stipulation of the parties for Old
Republic Insurance Company to interplead all $15,000 of bond funds.
Moving party Goshorn contends nothing in the motion seeks to
compel any bond surety into arbitration. Goshorn represents that Old Republic
Surety, The North River Insurance Company, and Hanover Insurance Company all
appear as bond sureties, and not insurers. Goshorn addresses the stipulation
regarding Old Republic for the interpleader of funds, and the dismissal of
North River. As for Hanover, Goshorn contends it should be compelled to join,
while alternatively stating that Hanover is not a necessary party to
arbitration in its role as a surety.
Old Republic in its supplemental brief maintains that the stipulation to
interplead the $15,000 in bond funds renders any need for participation by Old
Republic moot. Old Republic otherwise denies any basis compelling its
participation in arbitration on grounds that it was never a contracting party,
and it in no way acts as an “insurer” for purposes of the subject action.
[Declaration of Carlos Sosa.]
The court finds no basis compelling Old Republic into
arbitration given the interpleader of funds, and therefore no further necessity
for involvement with the adjudication of the action. The dismissal of both The
North River Insurance Company from the Goshorn cross-complaint, and The North
River Insurance Company dismissal of its cross-complaint against Britton and
Aqua Blue also renders them a non-party to any future proceedings. This only
leaves Hanover Insurance Company, which again is represented by Plaintiffs’
counsel.
Hanover in its supplemental brief acknowledges its
participation only as a surety bond issuer as well. Consistent
with the findings for Old Republic and The North River Insurance Company, the
court orders arbitration without the participation of Hanover as well. The
arbitrator will determine any right to collect on the surety bonds, if
necessary. (See Civ. Code, §§ 2807-2808.)
The court therefore orders the
remaining parties—Britton, Aqua Blue, and Goshorn—into arbitration. The parties may raise any issues regarding any pending
investigation with the CSLB and/or the other pending action with the
arbitrator.
The agreement itself only requires private, neutral
arbitration with no other criteria. In the absence of selection criteria, the
court cites to the applicable code section:
If
the arbitration agreement does not provide a method for appointing an
arbitrator, the parties to the agreement who seek arbitration and against whom
arbitration is sought may agree on a method of appointing an arbitrator and
that method shall be followed. In the absence of an agreed method, or if the
agreed method fails or for any reason cannot be followed, or when an arbitrator
appointed fails to act and his or her successor has not been appointed, the
court, on petition of a party to the arbitration agreement, shall appoint the
arbitrator.
(Code Civ. Proc., § 1281.6.)
The participating parties are to select an arbitration
organization and/or individual arbitrator. If the parties cannot agree on an
organization, or arbitrator, the court orders the parties to submit a list of
one to two organizations and/or arbitrators from each party, where the court
will select the organization or individual. The parties have 30 days from the
date of this order to begin the selection process, with any proposed list due
the day after the lapse of the 30 day period. (Code Civ. Proc., § 1281.6.)
“If a court of competent jurisdiction, whether in this State
or not, has ordered arbitration of a controversy which is an issue involved in
an action or proceeding pending before a court of this State, the court in
which such action or proceeding is pending shall, upon motion of a party to
such action or proceeding, stay the action or proceeding until an arbitration is
had in accordance with the order to arbitrate or until such earlier time as the
court specifies.” (Code Civ. Proc., § 1281.4.) The action is stayed.
The court will set an OSC re: Status of Arbitration at the
time of the hearing. The concurrent demurrer will go off-calendar.
Goshorn to give notice to all parties.