Judge: Stephen P. Pfahler, Case: 24STCV18679, Date: 2025-01-08 Tentative Ruling
Case Number: 24STCV18679 Hearing Date: January 8, 2025 Dept: 68
Dept.-68
Date:
1-8-25
Case:
24STCV18679
Trial
Date: Not Set
PREJUDGMENT POSSESSION
MOVING PARTY: Plaintiff, The People of the State of
California
RESPONDING PARTIES: Defendant, Southern California Edison
RELIEF REQUESTED
Motion for Prejudgment Possession
SUMMARY OF ACTION
On July 26, 2024, The State of California, by and through
its Department of Transportation (DOT) filed a complaint in eminent domain for
property identified as Parcel No. 81664-1 against Defendant Southern California
Edison Company (Edison). On September 13, 2024, DOT filed a Notice of Deposit
and Declaration Regarding Summary Basis for the Appraisal indicating a deposit
of $15,000 with the State Treasurer. On October 14, 2024, Edison answered the
complaint and filed a cross-complaint for Quiet Title and Declaratory Relief.
RULING: Granted.
Plaintiff DOT moves for prejudgment possession of Parcel No.
81664-1. DOT seeks to move an Edison utility pole sitting located on an
easement now secured by a DOT easement over private landowner, third party
Lancantel Investment Co. in order to complete a highway safety improvement. DOT
represents the $15,000 deposit compensates Edison for costs of relocating the
pole within the parcel. Edison in myriad opposition maintains its prescriptive
easement over the parcel for the utility pole, challenges the basis of the
proposed highway improvement as insufficiently supported, failure to comply
with prejudgment eminent domain requirements, and an unfair balance of equities
imposed on Edison. DOT in reply concedes to the prescriptive easement, but
represents full compliance with eminent domain requirements, an appropriate
basis to proceed, and denial of any hardship.
“The power of eminent domain may be exercised to acquire
property for a proposed project only if all of the following are established: (a)
The public interest and necessity require the project. (b) The project is
planned or located in the manner that will be most compatible with the greatest
public good and the least private injury. (c) The property sought to be
acquired is necessary for the project.” (Code Civ. Proc., § 1240.030.) “(a)
Except as otherwise provided by statute, a resolution of necessity adopted by
the governing body of the public entity pursuant to this article conclusively
establishes the matters referred to in Section 1240.030. ...” (Code Civ.
Proc., § 1245.250.) “(a) At any time before entry of judgment, the plaintiff
may deposit with the State Treasury the probable amount of compensation, based
on an appraisal, that will be awarded in the proceeding. The appraisal upon
which the deposit is based shall be one that satisfies the requirements of
subdivision (b). The deposit may be made whether or not the plaintiff applies
for an order for possession or intends to do so. ...” (Code Civ. Proc., §
1255.010.)
“(a) At
the time of filing the complaint or at any time after filing the complaint and
prior to entry of judgment, the plaintiff may move the court for an order for
possession under this article, demonstrating that the plaintiff is entitled to
take the property by eminent domain and has deposited pursuant to Article 1
(commencing with Section 1255.010) an
amount that satisfies the requirements of that article. ... (d)(2) If the
motion is opposed by a defendant or occupant within 30 days of service, the
court may make an order for possession of the property upon consideration of
the relevant facts and any opposition, and upon completion of a hearing on the
motion, if the court finds each of the following: (A) The plaintiff is entitled
to take the property by eminent domain. (B) The plaintiff has deposited
pursuant to Article 1 (commencing with Section
1255.010) an amount that satisfies the requirements of that article. (C)
There is an overriding need for the plaintiff to possess the property prior to
the issuance of final judgment in the case, and the plaintiff will suffer a
substantial hardship if the application for possession is denied or limited. (D)
The hardship that the plaintiff will suffer if possession is denied or limited
outweighs any hardship on the defendant or occupant that would be caused by the
granting of the order of possession. ...” (Code Civ. Proc., § 1255.410.)
DOT represents the necessity of the project for a traffic
public safety improvement. The resolution was adopted during a public hearing.
[Declaration of Gregory Farr, Ex. A.] The deposit was completed pursuant to the
appraisal summary. [Declaration of Katherine Chen, Ex. A.] DOT represents the
overriding need on the basis of public safety concerns and intended traffic
improvement/danger mitigation in the area. The project was approved, and DOT
seeks an expedited time frame to complete the project. [Declaration of Dan
Murdoch.]
DOT also represents Edison is obligated to move the utility
pole under statutory law. “The department and any
utility required to remove a utility facility or to relocate any utility
facility may, by agreement, provide for the respective amounts of the cost to
be borne by each. The department may, without prejudice to its rights under Section 707, advance the cost of removal
or relocation and if the department advances such cost, it is the duty of the
utility to move its facilities as soon as reasonably possible so as not to
delay freeway construction. In the case of any utility which is not financially
able to bear the costs of removal or relocation, the department may by
agreement provide for the work to be done on condition that the utility's
portion of the costs be repaid to the department over a period of time not
exceeding 10 years.
Either
party may maintain an action in a court of competent jurisdiction for an
adjudication as to the obligations and costs to be borne by each party under
such provisions of said contract at any time within four years after the cause
of action first arose thereunder. Such a cause of action shall be deemed to
arise upon and at the time of the completion by the utility of the removal or
relocation in question, or at the time of breach of the agreement by either
party. The filing of a claim with any state agency shall not be deemed a
condition precedent to the maintenance by the utility of any such action.” (Sts.
& Hy. Code, § 706.) “In the event of failure to reach an agreement as
provided in Section 706, the utility or the
department may bring an action in a court of competent jurisdiction for
apportionment of the cost between them in accordance with the provisions of
this article. Such an action may be commenced within three years from the
date of completion by the utility of the removal or relocation in question. The
filing of a claim with any state agency shall not be deemed a condition
precedent to the maintenance by the utility of any such action.” (Sts. &
Hy. Code, § 707.)
Given the
concession to the prescriptive easement position of Edison, the court foregoes
addressing the standard, and instead concentrates on the core dispute—the terms
of the relocation. Edison concedes that a pole relocation cost estimate totals
$11,315.63 for labor and materials without any additional costs, such as real
estate acquisition and potential power outages to customers. The DOT offer to
relocate the poll on the existing parcel already under control of DOT somewhat
undermines the inadequacy of the $15,000 deposit dispute. The court otherwise
finds no articulation regarding the costs of customer disruption. [Declaration
of Eric Park.] Thus, Edison establishes no additional net costs and in fact
concedes to coverage in excess of the required amount from DOT for relocation.
Edison
presents no specific challenge to the necessity of the relocation, and instead
seeks a greater bargaining position with DOT. Edison depends on the lack of a
Joint Use Agreement with DOT, whereby DOT will only provide a license thereby
reserving a right to demand relocation a second time at the cost to Edison. DOT
offers no specific rebuttal or even address to this position in reply, and
instead reiterates the rights to eminent domain and denial of any hardship in
that DOT holds certain statutory rights for this project.
Edison
seeks to elevate the lack of a Joint Use Agreement and only offer for a license
as integral to its position of unequal hardship imposed on Edison. (Code Civ.
Proc., § 1255.410, subd. (d)(2)(D); Los
Angeles County Metropolitan Transportation Authority v. Continental Development
Corp. (1997) 16 Cal.4th 694, 704; People ex rel. Dept. of Transportation v. Southern Pac.
Transportation Co. (1978) 84
Cal.App.3d 315, 324.) The argument relies on a potential scenario of inadequate
payment based on a potential future required second location, and lack of more
secured compensation in case of a potential second relocation. Edison takes
this position based on the lack of a business as usual Joint Use Agreement, and
notwithstanding the concession of proper costs compensation for the instant
project.
The court
appreciates the position of Edison, but finds no basis of legal support under
the statutes or supporting law that a potential contingency imposed due to
changed business practice positions undermines the otherwise conceded adequate
for the immediate required solution to facilitate the project. The court
declines to find a potential undue hardship based on a potential second,
speculative possibility for purposes of determining the validity of the
prejudgment possession motion. Furthermore, DOT specifically concludes that any
and all further compensation rights are subject to determination at trial,
whereby Edison can raise said concerns.
The court
therefore finds the application sufficiently complies with all requirements.
The entitlement to the relocation is well supported, and the compensation for
the single relocation more than adequate. Any resolution of rights as to
potential contingent costs is subject to further adjudication. (Sts. & Hy.
Code, §§ 706, 707.) The court otherwise finds no justification for delaying the
sought after expedited improvement project simply based on a speculative
contingency not currently before the court, and brought on due to
dissatisfaction with new business protocols.
The
motion is GRANTED.
Plaintiff to give notice.