Judge: Teresa A. Beaudet, Case: 21STCV21382, Date: 2023-02-23 Tentative Ruling
Case Number: 21STCV21382 Hearing Date: February 23, 2023 Dept: 50
|
R&R MASONRY, Plaintiff, vs. H.A. LEWIS, INC., et
al., Defendants. |
Case No.: |
21STCV21382 |
|
Hearing Date: |
February 23, 2023 |
|
|
Hearing Time: |
10:00 a.m. |
|
|
[TENTATIVE]
ORDER RE: LOS ANGELES UNIFIED SCHOOL DISTRICT’S DEMURRER TO H.A. LEWIS, INC.’S
SECOND AMENDED CROSS-COMPLAINT; LOS ANGELES UNIFIED SCHOOL DISTRICT’S MOTION TO STRIKE PORTIONS OF H.A.
LEWIS, INC.’S SECOND AMENDED CROSS-COMPLAINT |
||
|
AND RELATED CROSS-ACTION |
|
|
Background
On June 7, 2021,
Plaintiff R&R Masonry (“R&R”) filed this action against Defendants H.A.
Lewis, Inc. (“H.A. Lewis”), Los Angeles Unified School District (the “District”),
and U.S. Specialty Insurance Company. The Complaint alleges causes of action
for (1) breach of contract, (2) quantum meruit, (3) account stated, (4) open
book account, (5) enforcement of stop payment notice, (6) enforcement of stop
payment notice release bond, and (7) recovery on payment bond.
In the Complaint, R&R
alleges that prior to September 10, 2018, H.A. Lewis entered into a prime
contract to provide labor, services, equipment, and materials for a work of
improvement known and described as Marshall High School Towe Repair, Contract
No. 1810063, Project No. 23A10590. (Compl., ¶ 11.) On or about September 10,
2018, R&R and H.A. Lewis entered into a subcontract for R&R to provide
labor, services, equipment, and materials necessary to do a portion of the
subject project, identified in the subcontract as “Historical Restoration,
Façade Renovation and Masonry.” (Compl., ¶ 12.) H.A. Lewis ordered extra work
from R&R, which increased the total compensation under the subcontract to
the sum of $1,008,741.80. (Compl., ¶ 13.) R&R alleges that on or about
September 30, 2020, H.A. Lewis breached the subcontract by failing to pay the
sum then due and owing in the amount of $388,059.94. (Compl., ¶ 15.)
On July 28, 2021, H.A.
Lewis filed a Cross-Complaint against R&R, the District, and Fidelity
and Deposit Company of Maryland. On
January 18, 2022, H.A. Lewis filed a First Amended Cross-Complaint (“FACC”),
asserting causes of action for (1) breach of contract, (2) breach of warranty,
(3) breach of subcontract, (4) breach of warranty, (5) recovery on performance
bond, (6) equitable indemnity, and (7) declaratory relief.
The District demurred to
the sixth and seventh causes of action of the FACC, and moved to strike portions
of the FACC. On August 31, 2022, the Court issued an Order sustaining the
District’s demurrer in its entirety, with leave to amend. The District’s motion
to strike was denied as moot.
On
September 21, 2022, H.A. Lewis field the operative Second Amended
Cross-Complaint (“SACC”), asserting causes of action for (1) breach of
contract, (2) breach of warranty, (3) breach of subcontract, (4) breach of
warranty, (5) recovery on performance bond, (6) implied contractual indemnity,
(7) declaratory relief, and (8) declaratory relief.
The
District now demurs to the sixth and seventh causes of action of the SACC. The
District also moves to strike portions of the SACC. H.A. Lewis opposes the demurrer.[1]
Request for Judicial
Notice
The Court grants the District’s request for
judicial notice.
Demurrer
A. Legal Standard
A demurrer can be used
only to challenge defects that appear on the face of the pleading under attack
or from matters outside the pleading that are judicially noticeable. (Blank
v. Kirwan (1985) 39 Cal.3d 311, 318.) “To survive a demurrer, the
complaint need only allege facts sufficient to state a cause of action; each
evidentiary fact that might eventually form part of the plaintiff’s proof need
not be alleged.” (C.A. v. William S. Hart
Union High School Dist. (2012) 53 Cal.4th 861, 872.) For the purpose of testing the sufficiency of the cause of action,
the demurrer admits the truth of all material
facts properly pleaded. (Aubry v.
Tri-City Hospital Dist. (1992) 2 Cal.4th 962, 966-967.) A demurrer “does not admit contentions, deductions or conclusions
of fact or law.” (Daar v. Yellow Cab Co.
(1967) 67 Cal.2d 695, 713.)
B. Allegations
of the SACC
In the SACC, H.A. Lewis alleges
that in or about August 2018, H.A. Lewis and the District entered into a
contract wherein the District agreed to pay H.A. Lewis for performing the work
on a historical renovation of John Marshall High School, Contract No. 1810063
(the “Contract”), Project No. 23A10590 (the “Project”). (SACC, ¶ 9.) Among
other things, the Contract required H.A. Lewis to construct and install Glass Fiber
Reinforced Concrete (“GFRC”) crenellations on the Project. (SACC, ¶ 9.)
On or about September
10, 2018, R&R and H.A. Lewis entered into a subcontract for R&R to
provide labor, services, equipment, and materials to complete a portion of the Project
(the “Subcontract”). (SACC, ¶ 10.) In March 2019, the District made a submittal
to the Division of the State Architect (“DSA”) for its approval of the GFRC crenellations.
(SACC, ¶ 12.) DSA rejected the submittal in May 2019 because the submittal was incomplete
and, among other things, did not properly provide for the specifications for
the GFRC, including without limitation the GFRC testing and inspection
requirements. (SACC, ¶ 12.)
In December 2019, the District first advised H.A. Lewis of its
position that H.A. Lewis, and specifically, R&R’s manufacturer’s engineer,
was responsible for developing the GFRC testing requirements. (SACC, ¶ 14.)
H.A. Lewis, R&R, and R&R’s subcontractors immediately disputed the
District’s position, and explained how the contract expressly allocated the
responsibility for developing the GFRC testing requirements and testing and
inspection program to the District. (SACC, ¶ 14.)
To mitigate further delays and corresponding losses, and without
prejudice to its position, H.A. Lewis directed R&R to perform the subject
work. (SACC, ¶ 16.) Under protest, H.A. Lewis, R&R, and R&R’s
subcontractors developed the GFRC testing requirements and testing and
inspection program for the District’s review and submittal to the DSA. (SACC, ¶
17.) All the while, H.A. Lewis and R&R continued to assert that all such
work was outside the scope of their contractual obligations. (SACC, ¶ 17.)
On February 14, 2020,
H.A. Lewis presented a notice of claim on performance bond to R&R and its
bonding company Fidelity. (SACC, ¶ 18.) The notice detailed R&R’s failure
to perform and complete its work pursuant to the Subcontract. (SACC, ¶ 18.) Fidelity
refused to pay H.A. Lewis for R&R’s alleged default. (SACC, ¶ 18.)
On May 21, 2020, in
compliance with the Contract’s requirements for presentation of claims, H.A.
Lewis formally presented to the District its claims and a change order proposal
for adjustments to contract time and contract amount. (SACC, ¶ 19.) By way of
this claim, H.A. Lewis, in part, sought to pass through, to the District,
R&R’s alleged losses on the Project, including but not limited to,
R&R’s losses related to the GFRC testing and inspection. (SACC, ¶ 19.) The District disputed all aspects of
the claim and rejected the claim in its entirety. (SACC, ¶ 19.) On or about
February 19, 2021, R&R served a stop payment notice and statement of claim
for a sum of $388,059.94. (SACC, ¶ 21.)
H.A. Lewis alleges that the
District breached the parties’ Contract by various acts and omissions, and that
as a result of such breaches, work on the Project was delayed and disrupted,
the work was made more difficult and expensive, and H.A. Lewis was required to
perform extra work without compensation. (SACC, ¶¶ 27, 29.)
C. Sixth
Cause of Action for Implied Contractual Indemnity
The
District asserts that H.A. Lewis’s sixth cause of action for implied
contractual indemnity is improper for several reasons.
First,
the District asserts that there are no allegations that H.A. Lewis and the
District have a joint obligation to R&R. The District notes that “[t]raditional
equitable indemnity and implied contractual indemnity share a key feature that
distinguishes them from express indemnity: unlike express indemnity, neither
traditional equitable indemnity nor implied contractual indemnity is available
in the absence of a joint legal obligation to the injured party. Under this
principle, there can be no indemnity without liability, that is, the indemnitee
and the indemnitor must share liability for the injury.” (Jocer
Enterprises, Inc. v. Price (2010) 183 Cal.App.4th 559, 573 [internal
quotations and citation omitted].)
The District asserts that it does not have any contractual relationship
with R&R. In the SACC, H.A. Lewis alleges that in or about August 2018, H.A. Lewis and the
District entered into a contract, and that on or about September 10, 2018,
R&R and H.A. Lewis entered into a subcontract. (SACC, ¶¶ 9-10.) The
District also asserts that the
only claims alleged against
the District by R&R in R&R’s Complaint concern enforcement of
its stop payment notice, which does not involve allegations of District fault or liability on a
contract. (Citing to Crosno
Construction, Inc. v. Travelers Casualty & Surety Co. of America (2020) 47 Cal.App.5th 940, 950, “[a] stop payment notice notifies a project
owner…to withhold funds due to the direct contractor sufficient to satisfy the
amount of the stop notice claim, plus reasonable litigation costs.”) In
R&R’s Complaint in the instant action, only the fifth cause of action for enforcement
of stop payment notice and the sixth cause of action for enforcement against
stop payment notice release bond are alleged against the District. The District
asserts that because it is not a
party to H.A. Lewis’s subcontract with R&R, the District cannot have a
joint and several legal
obligation with H.A. Lewis to R&R.
H.A. Lewis counters that
its implied contractual indemnity cause of action does not require R&R to
have contractual privity with the District. In its opposition, H.A. Lewis relies primarily on Sehulster Tunnels/Pre-Con v. Traylor Brothers,
Inc./Obayashi Corp. (2003) 111 Cal.App.4th 1328, 1331, which concerns a contract to build the “South
Bay Ocean Outfall Project,” a tunnel under the Pacific Ocean to discharge
treated sewage at sea. “The City of San Diego (City) was the Project
owner, Traylor Brothers, Inc./Obayashi Corporation, a joint venture (TBO), was
the general contractor and Sehulster Tunnels/Pre-Con, a joint venture
(Sehulster), was the subcontractor that supplied to TBO the precast concrete
ring segments lining the tunnel.” (Ibid.) “[D]isputes
arose between City, TBO and Sehulster for cost overruns incurred by Sehulster
in manufacturing the tunnel ring segments as a result of certain design changes
in the Project.” (Ibid.) The Sehulster Court concluded, inter alia, that
“because City did not breach its contract with TBO, as a matter of law City
cannot be held liable to TBO under the equitable theory of implied contractual
indemnity on a public works contract for cost overruns incurred by a
subcontractor under a purchase order agreement with the general contractor.” (Id. at pp. 1332-1333.)
However, the Court noted
that “[i]mplied contractual
indemnity is applied to contract parties and is designed to apportion loss
among contract parties based on the concept that one who enters a contract
agrees to perform the work carefully and to discharge foreseeable damages resulting
from that breach. As a form of equitable indemnity, the doctrine rests on
the equities apparent from the surrounding circumstances, because contracting
parties should share loss in proportion to their breach. An implied
contractual indemnity action does not amount to a claim for contribution from a
joint tortfeasor because it is founded neither in tort nor on any duty that the
indemnitor owes to the injured party. Rather, it is predicated on the
indemnitor’s breach of duty owing to the indemnitee to properly perform its
contractual responsibilities.” (Sehulster Tunnels/Pre-Con v. Traylor
Brothers, Inc./Obayashi Corp., supra, 111 Cal.App.4th at pp.
1350-1351 [internal quotations and citations omitted].)
H.A.
Lewis asserts that “[c]ontrary
to LAUSD’s contentions, the fact that R&R does not pursue these contract claims by itself is irrelevant because R&R – like the
subcontractor in Sehulster – does not have privity with owner
and thus, requires Lewis – the party with such contractual privity-to pass
through contract claims on R&R’s behalf to LAUSD.” (Opp’n at p. 12:7-11.) In Sehulster, the Court of Appeal found that “California law protects the interests of the subcontractor by
providing that a subcontractor’s claim passes through the general
contractor to the owner. Consequently, by contract or settlement agreement, a general
contractor and a subcontractor can agree that the contractor will pass through
the subcontractor’s claims against the contractor to the owner…When a public agency breaches a construction contract with a
contractor, damage often ensues to a subcontractor. In such a situation, the
subcontractor may not have legal standing to assert a claim directly
against the public agency due to a lack of privity of contract, but may assert
a claim against the general contractor. In such a case, a general
contractor is permitted to present a pass-through claim on behalf of the
subcontractor against the public agency. The pass-through process
and such agreements are designed to shorten the legal process by not requiring
the subcontractor to first sue the general contractor and the latter to
actually pay damages to the former before suing the owner.” (Sehulster Tunnels/Pre-Con v. Traylor
Brothers, Inc./Obayashi Corp., supra, 111 Cal.App.4th at pp.
1348-1349 [internal quotations and citations omitted].)
The
District notes that in Sehulster, the Court of
Appeal also found that “[b]ecause of our conclusion that TBO is not entitled to implied
contractual indemnity from City, it is unnecessary to address whether
permitting TBO to recover under the theory of implied contractual indemnity
implicates the public policy considerations recognized in Amelco Electric v. City of Thousand Oaks, supra, 27 Cal.4th 228, that preclude a contractor from recovering additional
compensation from a governmental entity on a public works contract if it would
defeat the policies to protect the public underlying the
competitive bidding statutes. Further,
we note that the parties proffered no authority specifically addressing whether
a public entity in this context can be held liable under an implied contractual
indemnity claim to a general contractor on a public works contract.” (Sehulster
Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp., supra, 111
Cal.App.4th at p. 1352, fn. 22.)
The District contends that Sehulster thus cannot
provide authority for maintaining a claim for
implied contractual indemnity against the District. But as set forth above, the
Sehulster Court also found that “[a]n implied contractual indemnity action
does not amount to a claim for contribution from a joint tortfeasor because it
is founded neither in tort nor on any duty that the indemnitor owes to the
injured party. Rather, it is predicated on the indemnitor’s breach of duty
owing to the indemnitee to properly perform its contractual responsibilities.” (Sehulster Tunnels/Pre-Con v. Traylor Brothers,
Inc./Obayashi Corp., supra, 111 Cal.App.4th at p. 1351.) The District’s first argument in the
demurrer that “[t]here are
no allegations that H.A. Lewis and the District have a joint obligation to R&R Masonry”[2] is
thus refuted by the foregoing authority in Sehulster.
The District also asserts that H.A.
Lewis cannot maintain an implied contractual indemnity claim under the
circumstances of this case. The District notes that the Sehulster Court found as follows:
“Additionally, Public Contract Code section 7105, subdivision (d)(2) provides that a public works
contract that must be awarded by competitive bid may be amended or modified
only if it is so provided in the contract or authorized by law. The section
expressly states: ‘The compensation payable, if any, for amendments and
modifications shall be determined as provided in the contract.’ TBO
requested City to implement the design changes and later agreed they would have
no impact on the Prime Contract price. On its own behalf under the provisions
of the Prime Contract, TBO never requested the originally negotiated price be
modified as a result of the redesign. The Prime Contract is without any
indemnity provision that would require City to indemnify TBO for its liability
for Sehulster’s cost overruns occasioned by the redesign. To permit TBO to
recover here under the theory of implied contractual indemnity would be
inconsistent with the cited public policy reflected in Public Contract Code section 7105.” (Sehulster
Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp., supra, 111
Cal.App.4th at p. 1352.)
The
District asserts that here too, an implied contractual indemnity claim would
violate law prohibiting a contractor from recovering additional compensation or
adding/modifying terms on a competitively-bid public works contract. The
District notes that “public
works contracts are the subject of intensive statutory regulation and lack the
freedom of modification present in private party contracts.” (Amelco Electric v. City of Thousand Oaks (2002) 27
Cal.4th 228, 242.)
To the extent the District is asserting
that H.A. Lewis’s implied contractual indemnity cause of action is barred by Public Contract Code section 7105, H.A. Lewis asserts
that this is not the case. As set forth above, in Sehulster, “TBO
requested City to implement the design changes and later agreed they would have
no impact on the Prime Contract price…The Prime Contract is without any
indemnity provision that would require City to indemnify TBO for its liability
for Sehulster’s cost overruns occasioned by the redesign.” (Sehulster Tunnels/Pre-Con v. Traylor Brothers,
Inc./Obayashi Corp., supra, 111 Cal.App.4th at p. 1352.) H.A. Lewis asserts that to the
contrary, in this case, the SAC alleges that “[o]n May 21, 2020, in compliance with the Contract’s requirements for
presentation of claims, H.A. Lewis formally
presented to the District its claims and a change order proposal for adjustments to contract time and contract amount. Although H.A. Lewis
did not know the full extent of its or R&R’s losses at the time of this
presentation, H.A. Lewis intended to recover, among other things, all losses
from the District’s breaches and repudiations of the Contract, including but
not limited to, the unwarranted and untimely hoisting of the District’s own
responsibility to develop the GFRC testing requirements and testing and
inspection program onto H.A. Lewis, and in turn, R&R.” (SACC, ¶ 19,
emphasis added.) H.A. Lewis asserts that it thus does not seek a “termination,
amendment, or modification” of the prime contract as described in Public Contract Code section 7105, subdivision (d)(2),
but rather for the District to approve H.A. Lewis’s change orders and claims
after the District allegedly breached the prime contract.
Next,
the District asserts that H.A. Lewis still has not alleged a pass-through claim
on behalf of R&R. The
District notes that in the SACC, H.A. Lewis alleges as follows:
“On May
21, 2020, in compliance with the Contract’s requirements for presentation of
claims, H.A. Lewis formally presented to the District its claims and a change
order proposal for adjustments to contract time and contract amount. Although
H.A. Lewis did not know the full extent of its or R&R’s losses at the time
of this presentation, H.A. Lewis intended to recover, among other things, all
losses from the District’s breaches and repudiations of the Contract, including
but not limited to, the unwarranted and untimely hoisting of the District’s own
responsibility to develop the GFRC testing requirements and testing and
inspection program onto H.A. Lewis, and in turn, R&R. By way of this claim,
H.A. Lewis, in part, sought to pass through, to the District, R&R’s alleged
losses on the Project, including but not limited to, R&R’s losses related
to the GFRC testing and inspection. Presentation of this claim was timely.
Nevertheless, the District disputed all aspects of the claim and rejected the
claim in its entirety.” (SACC, ¶ 19.)
The
District contends that these allegations are insufficient because they are
“limited to what H.A. Lewis – with no mention of R&R – ‘intended’ to
recover by the pre-litigation claim it submitted to the District…H.A. Lewis
does not allege that R&R actually presented a pass-through claim,
requested that H.A. Lewis make a pass-through claim on its behalf, or
that R&R believed that it had, or intended to assert, a claim against the District
for breach of contract.” (Demurrer at p. 15:7-11, emphasis omitted.) But the
District does not cite to any legal authority demonstrating that those specific
allegations must be pled for purposes of stating a cause of action for implied
contractual indemnity.
In addition, H.A. Lewis
now alleges in support of the sixth cause of action that “[t]he District’s breaches of Contract,
breaches of warranty, acts, omissions, and wrongful conduct have caused or contributed as a substantial
factor in causing R&R to make
certain claims against H.A. Lewis, and thus, caused or contributed as a
substantial factor in causing
H.A. Lewis to incur or sustain costs, fees, liability, or damages in defending
against these claims by
R&R.” (SACC, ¶ 51.) H.A. Lewis further alleges that “[t]o the extent [it]
has incurred and will incur fees, costs, and expenses, in defending against
R&R’s claims that are caused by the District’s breaches of Contract,
breaches of warranty, acts, omissions, and wrongful conduct, the District is
responsible and liable to H.A. Lewis.” (SACC, ¶ 52.) As set forth above, H.A.
Lewis also now alleges that “[o]n May 21, 2020, in compliance with the
Contract’s requirements for presentation of claims, H.A. Lewis formally
presented to the District its claims and a change order proposal for
adjustments to contract time and contract amount…By way of this claim, H.A.
Lewis, in part, sought to pass through, to the District, R&R’s alleged
losses on the Project, including but not limited to, R&R’s losses related
to the GFRC testing and inspection.” (SACC, ¶ 19.) The Court does not find that
the District has demonstrated that the foregoing allegations are insufficient
for purposes of pleading a cause of action for implied contractual indemnity.
The District also asserts that the
allegations of the sixth cause of action are impermissibly uncertain,
ambiguous, and unintelligible. A pleading is uncertain if it is ambiguous
or unintelligible. (Code Civ. Proc., § 430.10(f).)
A demurrer for uncertainty may lie if the failure to label the parties and
claims renders the complaint so confusing defendant cannot tell what he or she
is supposed to respond to.¿ (Williams v. Beechnut
Nutrition Corp. (1986) 185 Cal.App.3d 135, 139, fn. 2.) However, “[a]
demurrer for uncertainty is strictly construed, even where a complaint is in
some respects uncertain, because ambiguities can be clarified under modern
discovery procedures.” (Khoury v. Maly’s of
California, Inc. (1993) 14 Cal.App.4th 612, 616.)¿
The District asserts that “R&R Masonry does not allege any
breach of warranty or other ‘breaches of Contract, breaches of warranty, acts,
omissions, and wrongful conduct’ by the District in its complaint – only a
breach of the subcontract by H.A. Lewis…Given the lack of clarity in the
allegations of the SACC in light of the allegations of R&R’s Complaint, it
is impossible for the District to ascertain which claims H.A. Lewis is passing
through to the District on behalf of R&R.” (Demurrer at p. 15:24-16:1.) But
H.A. Lewis’s first cause of action in the SACC is for breach of contract
against the District, and paragraph 51 of the SACC alleges that “[t]he
District’s breaches of Contract, breaches of warranty, acts, omissions, and
wrongful conduct have caused or contributed as a substantial factor in causing
R&R to make certain claims against H.A. Lewis, and thus, caused or
contributed as a substantial factor in causing H.A. Lewis to incur or sustain
costs, fees, liability, or damages in defending against these claims by
R&R.” (SACC, ¶ 51.) The Court does not find that the sixth
cause of action is ambiguous or unintelligible. Therefore, the special demurrer
on the basis of uncertainty is overruled.¿
The District also asserts in the reply that R&R does not allege a
cause of action for breach of contract against the District in the Complaint,
such that “there can be no indemnity.” (Reply at p. 5:15-16.) But as the
District acknowledges in the demurrer, “[a]s a matter of
law, a general contractor can present a subcontractor’s claim on a pass-through
basis. When a public agency breaches a construction contract with a contractor, damage often
ensues to a subcontractor. In such a situation, the subcontractor may not have
legal standing to assert a claim directly against the public agency due to a
lack of privity of contract, but may assert a claim against the
general contractor. In such a case, a general contractor is permitted to
present a pass-through claim on behalf of the subcontractor against the public
agency.” (Howard Contracting, Inc. v. G. A. MacDonald Construction Co . (1998) 71 Cal.App.4th 38, 60 [internal citation omitted].)
Next,
the District asserts that the implied contractual indemnity cause of action is
barred by the express indemnity provision of the District’s contract with H.A.
Lewis. The District notes that “[w]ithin the limitations of the language used,
however, an express indemnity clause is accorded a certain preemptive
effect, displacing any implied rights which might otherwise arise within
the scope of its operation.” (E. L. White, Inc. v. Huntington
Beach (1978) 21 Cal.3d 497, 507-508.)
The
District requests that the Court take judicial notice of “[t]he General
Conditions of the contract between H.A. Lewis and the District for the work on
a historical renovation of John Marshall High School, Contract No. 1810063.”
(District’s RJN, ¶ 3, Ex. C.) The District notes that pursuant to Evidence Code section 452, subdivision (c), “[j]udicial notice may be taken of…Official acts of the
legislative, executive, and judicial departments of the United States and of
any state of the United States.”
The District also cites to Ingram v. Flippo (1999) 74 Cal.App.4th 1280, 1285,
footnote 3, where the Court of
Appeal noted that “[s]ince the contents of the letter and media release form
the basis of the allegations in the complaint, it is essential that we evaluate
the complaint by reference to these documents. Respondents have requested that
we take judicial notice of the letter and media release under Evidence Code section 452, subdivision (h), and
appellant has not opposed this. We therefore take judicial notice of the
District Attorney’s March 28, 1997, letter and press release and we attach them
as appendices A and B to this opinion.” In the SACC, H.A. Lewis alleges that in or about August 2018, H.A. Lewis and
the District entered into a contract wherein the
District agreed to pay H.A. Lewis for performing the work on a historical
renovation of John Marshall High School, Contract
No. 1810063. (SACC, ¶ 9.) Portions of the contract are attached to the SACC as
Exhibit 1. (SACC, ¶ 9, Ex. 1.) The District asserts that “H.A. Lewis failed to
attach to its Complaint a relevant portion of the Prime Contract known as the
General Conditions, which sets forth detailed terms and conditions of the
Contract, including indemnity provisions. Because of this and as the General
Conditions are official documents of a public agency, it is appropriate for the
Court to take judicial notice of Exhibit C.” (District’s RJN at p. 3:26-5:2.) In light of the foregoing and
H.A. Lewis’s lack of opposition to the request, the Court grants the District’s
request for judicial notice of Exhibit “C.”
The District asserts
that the provisions of the parties’ contract do not require the District to
indemnify H.A. Lewis for R&R’s claims, and that rather, H.A. Lewis is obligated
to indemnify the District for third-party claims. The District notes that Section 6.53 of the contract provides in pertinent
part:
“6.53 Indemnification:
. . . CONTRACTOR shall defend, indemnify, and hold harmless
OWNER . . .
from and against claims, actions, damages, losses, penalties, costs and
expenses
(including, but not limited to attorneys’ fees and costs including fees of
consultants)
arising out of or resulting from, whether in whole or in part, breach of or
noncompliance
with this Contract . . . negligence, gross negligence or willful
misconduct,
or the acts, omissions, or other conduct of CONTRACTOR, any
Subcontractor
or any person or entity engaged by them for the Work.
CONTRACTOR’s
obligations under this Article 6.53 include without limitation . . .
(v) other
losses, liabilities, damages or costs resulting from, in whole or in part, any
acts, omissions or other conduct of CONTRACTOR . . . arising out of or related
to the
Contract,
Work and/or Project, including without limitation, performance of the Work;
payment of
Subcontractors and/or others; use of the Project site; . . . . The obligations
provided in
this Article 6.53 shall be binding on CONTRACTOR regardless of whether
the
allegations underlying such claims, action, damage, loss, penalty, cost or
expense
are with or
without merit, true or false and whether or not caused in part by any of the
Indemnified
Parties. . . . Nothing set forth in this Article 6.53 is intended to provide
indemnification
for those situations precluded by law, including without limitation, the
circumstances described in Civil Code §§ 2782(a) and
2782(b).” (District’s RJN, ¶ 3, Ex. C.)
The District asserts
that “any claim by R&R falls squarely within the scope of the indemnity
provisions of the Contract because it arises out of or results from H.A. Lewis’
“breach of or noncompliance with this Contract” and/or “performance of the
Work; payment of Subcontractors.” The District asserts that H.A. Lewis is accordingly
“obligated to defend and indemnify the District for any claims, actions,
damages, losses, penalties, costs and expenses (including, but not limited to
attorneys’ fees and costs including fees of consultants) regarding the same,
not the other way around.” (Demurrer at p. 18:5-8.)
H.A. Lewis counters
that the subject indemnity provision covers H.A. Lewis’s indemnity obligations
to the District in the event that the conduct of H.A. Lewis, its
subcontractors, or their agents caused losses, damages, or costs to the
District and its agents. H.A. Lewis notes that the provision does not cover the
District’s indemnity obligations to H.A. Lewis in the event that the District
and its agents are the cause of certain losses, damages, or costs to H.A. Lewis
or its subcontractors.
Both parties cite to E.L. White, Inc. v. Huntington Beach, supra,
21 Cal.3d at page 502, where
“Plaintiff E. L. White, Inc. (White) and its insurance carrier appeal from a
judgment of dismissal entered following an order sustaining, without leave to
amend, the demurrer of defendant City of Huntington Beach (City) to its first
amended complaint in an action for indemnity and equitable contribution.”
(Internal quotations omitted.) The California Supreme Court reversed the
judgment. (Ibid.) In E. L. White, the City demurred on the
grounds that “the complaint failed to state a cause of action because
the contract of the parties -- providing that White would indemnify and save
City harmless from ‘any suits, claims, or actions brought by any person or
persons for or on account of any injuries or damages sustained’ because of or
arising out of the work -- effectively operated to preclude any claim for
implied indemnity or ‘equitable contribution’ in favor of White and its carrier
against City.” (Id. at p. 506.) “In short it
[was] argued that the parties, by agreeing to the quoted indemnification
provision, thereby memorialized the entire agreement between them regarding
indemnity inter se, and
by excluding from their agreement any language indicating a right of indemnity
in White against City, they indicated their intention that no such right should
exist or be implied under any circumstances in favor of White.” (Ibid.) The California Supreme Court found that
“[t]his contention finds no support in our law. The obligation of
indemnity, which we have defined as the obligation resting on one party to make
good a loss or damage another has incurred may arise under the law of this
state from either of two general sources. First, it may arise by virtue of
express contractual language establishing a duty in one party to save another
harmless upon the occurrence of specified circumstances. Second, it may find
its source in equitable considerations brought into play either by contractual
language not specifically dealing with indemnification or by the equities of
the particular case.” (Id. at pp. 506-507
[internal quotations and citations omitted].)
In
light of the foregoing, the Court overrules the District’s demurrer to the
sixth cause of action for implied contractual indemnity.
D. Seventh
Cause of Action for Declaratory Relief
In support of the seventh cause
of action for declaratory relief, H.A. Lewis alleges that it “seeks a judicial declaration, decree,
or order determining the District’s duties and obligations to indemnify H.A.
Lewis for such costs, fees, liability or damages incurred or sustained by H.A.
Lewis in defending against R&R’s claims that are caused by the District’s breaches
of Contract, breaches of warranty, acts, omissions, and wrongful conduct.”
(SACC, ¶ 56.)
The District asserts that the declaratory relief cause of action is “wholly
derivative” of H.A. Lewis’s implied contractual indemnity cause of action, and
is therefore improper. Thus, because the Court overrules the District’s
demurrer to H.A. Lewis’s implied contractual indemnity cause of action, the
Court also overrules the demurrer to the seventh cause of action for
declaratory relief.
Motion to Strike
A court may strike any “irrelevant, false, or improper matter
inserted in any pleading” or any part of a pleading “not drawn or filed
in conformity with the laws of this state, a court rule, or an order of the
court.” (Code Civ. Proc., § 436.)
The District moves to
strike paragraph 30 from the SACC, which alleges that “[p]ursuant to California
law, H.A. Lewis is entitled to recover its reasonable attorney’s fees incurred
in the prosecution of this action and/or penalties against the District as a
result of their violation of the Prompt Payment Act as alleged herein. H.A.
Lewis has retained the law firm of Rutan & Tucker, LLP to protect its
interests pursuant to the Contract. As a result, H.A. Lewis has incurred and
will continue to incur attorney’s fees in connection herewith.” (SACC, ¶ 30.)
The District asserts that the applicable
prompt payment statute does not authorize an award of attorney’s fees or
penalty interests against the District based on H.A. Lewis’s allegations. The
District notes that the “California
Prompt Payment Act” is contained at Government Code section 927,
et seq. Government Code section 927, subdivision (c) provides
that “[n]otwithstanding any other
provision of law, this chapter shall apply to all state agencies, including,
but not limited to, the Public Employees’ Retirement System, the State
Teachers’ Retirement System, the Treasurer, and the Department of General
Services.” The District
indicates that it is not a state agency. In the SACC, H.A. Lewis does not
allege that the District is a state agency, rather, it generally alleges that
the District “is, and at
all times alleged herein was, a public entity organized and existing under
the laws of California.” (SACC, ¶ 2.)
H.A. Lewis indicates
that it does not oppose the granting of the District’s motion to strike.
However, it requests leave to amend and asserts that the alleged defects in
paragraph 30 are correctible. H.A. Lewis states in its opposition that “the
LAUSD correctly points out that the Prompt Payment Act does not apply to LAUSD
as a non-State agency… The LAUSD also concedes that to the extent the LAUSD
wrongfully withheld or delayed payment of retention, penalties pursuant to
P.C.C. section 7107 might apply.” (Opp’n at p. 3:15-20.)
In the motion to strike, the District states that “H.A. Lewis has not alleged
any other basis to recover attorneys’ fees, such as section
7107 of the Public Contract Code,” but also argues that “H.A. Lewis may not
seek penalty interest from the District under section
20104.50 or section 7107 of the Public Contract
Code.” (Mot. at p. 4:7-9; 4:15-16.)
Based on the foregoing,
the Court grants the District’s motion to strike, with leave to amend.
Conclusion
Based
on the foregoing, the District’s demurrer is overruled in its entirety. The
District’s motion to strike is granted, with leave to amend.
The Court orders H.A. Lewis to file and serve an amended cross-complaint,
if any, within 20 days of this Order. If no amended cross-complaint is filed
within 20 days of this Order, the District is ordered to file and serve its
answer within 30 days of this Order.
The District is ordered to give notice of this Order.
DATED: February 23, 2023 ________________________________
Hon. Teresa A.
Beaudet
Judge, Los
Angeles Superior Court