Judge: Teresa A. Beaudet, Case: BC632599, Date: 2023-04-25 Tentative Ruling
Case Number: BC632599 Hearing Date: April 25, 2023 Dept: 50
ELIJAH STINY, Plaintiff, vs. NORTHROP GRUMMAN CORPORATION, et al., Defendants. |
Case No.: |
BC632599 |
Hearing Date: |
April 25, 2023 |
|
Hearing Time: |
10:00 a.m. |
|
[TENTATIVE]
ORDER RE: PLAINTIFF’S MOTION TO VACATE ARBITRATION RULING |
Background
Plaintiff Elijah Stiny,
in pro per (“Plaintiff”) filed this action on September 1, 2016 against Defendant
Northrop Grumman Corporation. In the Complaint, Plaintiff alleges one cause of
action for wrongful termination.
On November 15, 2016, Defendant Northrop Grumman Systems Corporation
(“Defendant”), erroneously sued as Northrop Grumman Corporation filed an answer
to the Complaint.
On September 8, 2017, the Court issued a minute order in this matter
providing, inter alia, that “Northrop Grumman Systems Corporation’s
motion to compel arbitration is granted. Matter is stayed pending the
completion of arbitration.”
On September 6, 2022, Defendant filed a notice indicating, inter
alia, that “Defendant Northrop Grumman Systems’…Motion for Summary
Judgment, or in the alternative Motion for Summary Adjudication (‘MSJ’) was
heard by the Hon. Stephen J. Sundvold (Ret.), the arbitrator for this matter
(JAMS Case No. 1200055140).” (September 6, 2022 Notice at p. 1:4-6.) The notice
attaches an August 22, 2022 Order on the motion, which provides, inter alia,
that “[o]n June 3, 2022 and July 1, 2022, Respondent Northrop Grumman Systems
Corporation’s (‘Respondent’) Motion for Summary Judgment (‘Motion’) was heard
in the above-captioned matter. Arbitrator Hon. Stephen J. Sundvold (Ret.),
having read and considered the papers submitted both in support of and in
opposition to the Motion, and based upon the papers and pleadings on file in
this matter as well as oral argument of the parties, and good cause appearing
therefor, the Motion is GRANTED in its entirety and Claimant Elijah Stiny (‘Claimant’)
demand for arbitration (the ‘Demand’) is DISMISSSED WITH PREJUDICE.” (Defendant’s
September 6, 2022 Notice, Ex. B, p. 1:1-7.)
Plaintiff now moves “to
vacate the arbitration ruling on or about August
22, 2022 and requests a new arbitration hearing.” (Mot. at p. 1:23-24.)
Defendant opposes.
Discussion
Plaintiff states that
his motion is based on 9 U.S.C. section
10, which provides, inter alia, that “(a) In any of the following cases the
United States court in and for the district wherein the award was made may make
an order vacating the award upon the application of any party to the
arbitration—(1) where the award was procured by
corruption, fraud, or undue means; (2) where there was evident partiality
or corruption in the arbitrators, or either of them; (3) where the arbitrators were guilty of misconduct in refusing to postpone
the hearing, upon sufficient cause shown, or in refusing to hear evidence
pertinent and material to the controversy; or of any other misbehavior by which
the rights of any party have been prejudiced; or (4) where the arbitrators exceeded their powers, or so imperfectly executed
them that a mutual, final, and definite award upon the subject matter submitted
was not made.” (9 U.S.C. § 10, subd. (a).)
Plaintiff asserts that “[i]n the present case, Arbitrator Judge
Sundvold did not postpone the arbitration hearing to allow for sufficient time
to complete relevant and pertinent Discovery,” and that “[t]he arbitration
hearing for a motion for summary judgment made by defendant Northrop Grumman
never should have occurred so soon and should have been postponed until after
Discovery completed.” (Mot. at p. 2:28-3:1; 3:4-6.)
As
an initial matter, Defendant asserts in the opposition that the Court lacks
jurisdiction to vacate the final award as between Plaintiff and Defendant
because Plaintiff failed to timely file his motion.
Defendant
notes that under the Federal Arbitration Act (“FAA”), “[n]otice of a motion to vacate, modify, or
correct an award must be served upon the adverse party or his attorney within
three months after the award is filed or delivered.” (9 U.S.C. § 12.) Defendant
also notes that under the California
Arbitration Act (“CAA”), “[a] petition to vacate an award or to correct
an award shall be served and filed not later than 100 days after the date of
the service of a signed copy of the award on the petitioner.” (Code Civ. Proc., § 1288.)
Defendant
indicates that “[o]n
August 22, 2022, the third and final MSJ hearing, the
Arbitrator granted the MSJ in full,
holding that Plaintiff’s claims were dismissed with prejudice.” (Zamago
Decl., ¶ 8.) Defendant’s counsel attaches a signed copy of the August 22, 2022
Order. (Zamago Decl., ¶ 8, Ex. B.) Defendant asserts that Plaintiff was
accordingly required
to file a motion to vacate the award by no later than
November 22, 2022 under the FAA, and November 30, 2022 under
the CAA. The instant motion was filed on January 26, 2023.
As
to the deadline provided by the CAA, the Court notes that Defendant does not
appear to provide any evidence as to the date when a signed copy of the award
was served on Plaintiff. However, Plaintiff did not file a reply in support of
the instant motion and does not dispute that the motion is untimely under
either the FAA or the CAA.
Defendant
also asserts that no grounds exist to vacate the arbitrator’s August 22, 2022
ruling. Defendant notes that “an award reached by an arbitrator pursuant to a
contractual agreement to arbitrate is not subject to judicial review except on
the grounds set forth in sections 1286.2 (to
vacate) and 1286.6 (for correction).” (Moncharsh v. Heily & Blase (1992) 3
Cal.4th 1, 33.) Code of Civil Procedure
section 1286.2, subdivision (a) provides as follows:
“(a) Subject to Section 1286.4, the
court shall vacate the award if the court determines any of the following:
(1) The award was procured by corruption, fraud or
other undue means.
(2) There was
corruption in any of the arbitrators.
(3) The rights of
the party were substantially prejudiced by misconduct of a neutral arbitrator.
(4) The
arbitrators exceeded their powers and the award cannot be corrected without
affecting the merits of the decision upon the controversy submitted.
(5) The rights of
the party were substantially prejudiced by the refusal of the arbitrators to
postpone the hearing upon sufficient cause being shown therefor or by the
refusal of the arbitrators to hear evidence material to the controversy or by
other conduct of the arbitrators contrary to the provisions of this title.
(6) An arbitrator
making the award either: (A) failed to disclose within the time required for
disclosure a ground for disqualification of which the arbitrator was then
aware; or (B) was subject to disqualification upon grounds specified in Section
1281.91 but failed upon receipt of timely demand to disqualify himself or
herself as required by that provision. However, this subdivision does not apply
to arbitration proceedings conducted under a collective bargaining agreement
between employers and employees or between their respective representatives.”
As set forth
in Plaintiff’s motion, Plaintiff asserts that “[i]n the present case, Arbitrator Judge Sundvold did not postpone the
arbitration hearing to allow for sufficient time to complete
relevant and pertinent Discovery.” (Mot. at p. 2:28-1.) Thus, the provision of Code of Civil Procedure section 1286.2,
subdivision (a)
apparently at issue in Plaintiff’s motion is that “[t]he rights of the party
were substantially prejudiced by the refusal of the arbitrators to postpone the
hearing upon sufficient cause being shown therefor or by the refusal of the
arbitrators to hear evidence material to the controversy or by other conduct of
the arbitrators contrary to the provisions of this title.” (Code Civ. Proc.,
§ 1286.2, subd. (a)(5); see Mot. at p. 2:22-24.)
However, the Court
does not find that Plaintiff has presented evidence demonstrating that the
arbitrator refused “to postpone the hearing upon
sufficient cause being shown therefor,” or that the arbitrator refused to “hear
evidence material to the controversy.” (Code Civ. Proc., § 1286.2, subd. (a).) As an
initial matter, Plaintiff provides a declaration in support of the motion, but
such declaration is not signed. The Court notes that Code of Civil Procedure section 2015.5¿defines a¿“declaration”¿as a writing that is signed, dated, and certified as true
under penalty of perjury.
Moreover, even if the Court overlooks Plaintiff’s
failure to sign the declaration, the Court does not find that good cause has
been shown to vacate the August 22, 2022 ruling. As discussed, Plaintiff asserts (without providing
competent evidence in support thereof) that “[t]he arbitration hearing was held
before the Discovery window was closed, where in fact all parties acknowledged
that the Discovery window was still open and did not even have a date for
closure. The arbitration hearing for a motion for summary judgment made by
defendant Northrop Grumman never should have occurred so soon and should have
been postponed until after Discovery completed.” (Mot. at p. 3:2-6.)
In the opposition,
Defendant asserts that Plaintiff appears to be conflating the fact that a
motion for summary judgment hearing and an arbitration hearing are two distinct
hearings.
In addition, Defendant indicates that
on September 7, 2018, Plaintiff filed his demand for arbitration, and Defendant
filed its response to the demand on October 17, 2018. (Zamago Decl., ¶¶ 4-5.)
The matter was assigned to Stephen Sundvold Esq., of Judicial Arbitration and
Mediation Services, Inc. (“JAMS”). (Zamago Decl., ¶ 5.) Defendant notes that Rule 18 of Jams Employment Arbitration
Rules & Procedures provides that “[t]he Arbitrator may permit any Party to
file a Motion for Summary Disposition of a particular claim or issue, either by
agreement of all interested Parties or at the request of one Party, provided
other interested Parties have reasonable notice to respond to the motion. The
Request may be granted only if the Arbitrator determines that the requesting
Party has shown that the proposed motion is likely to succeed and dispose of or
narrow the issues in the case.” (Zamago Decl., ¶ 9, Ex. C.)
Defendant
asserts that the arbitrator provided Plaintiff more than sufficient time to
work up his case. Defendant indicates that “Defendant filed a MSJ…on March 28, 2022. Five days
before his Opposition due date, on May 1, 2022, Plaintiff sought to extend the
due date to May 17, 2022, which was granted. On May 20,
2022, JAMS sent an email to the parties to confirm whether Plaintiff
would be submitting an Opposition as he had failed to oppose Defendant’s MSJ on
May 17, 2022. Plaintiff did not respond…At the
June 3, 2022 telephonic hearing regarding the MSJ, Plaintiff confirmed he did
not file an Opposition because he was feeling ill…Thus, Plaintiff asked for a
second extension. The Arbitrator stated he was inclined to grant the MSJ in
full. After allowing for some oral argument, the Arbitrator told Plaintiff he
could brief and oppose his singular Wrongful Discharge in Violation of Public
Policy (‘WDVPP’) claim with the new deadline of June 23, 2022…By the second
rescheduled MSJ hearing, which proceeded on July 8, 2022, Plaintiff had failed
to file any written Opposition. The Arbitrator allowed Plaintiff an additional
extension to file an Opposition (before the August 22 hearing); Plaintiff again
failed to do so. On August 22, 2022, the third and final MSJ hearing, the
Arbitrator granted the MSJ…” (Zamago Decl., ¶ 8.)
Conclusion
Based on the foregoing, Plaintiff’s
motion is denied.
Defendant is ordered to
give notice of this Order.
DATED:
________________________________
Hon. Teresa A.
Beaudet
Judge, Los
Angeles Superior Court