Judge: Theresa M. Traber, Case: 22STCV09799, Date: 2022-08-11 Tentative Ruling
Case Number: 22STCV09799 Hearing Date: August 11, 2022 Dept: 47
Tentative Ruling
Judge Theresa M. Traber, Department 47
HEARING DATE: August 11, 2022 TRIAL
DATE: NOT SET
CASE: LGP Equipment Rentals, Inc. v. Joshua
Road, LLC, et al.
CASE NO.: 22STCV09799 ![]()
MOTION
TO REDUCE OR ELIMINATE MECHANICS LIEN
![]()
MOVING PARTY: Defendant Joshua Road, LLC
RESPONDING PARTY(S): Plaintiff LGP
Equipment Rentals, Inc.
STATEMENT
OF MATERIAL FACTS AND/OR PROCEEDINGS:
This is an action, filed on March 21, 2022, asserting claims for breach
of contract, foreclosure of a mechanic’s lien, and for common counts. Plaintiff
alleges that Defendants breached a contract for rental of construction
equipment by allowing the equipment rented to be stolen and refusing to
reimburse Plaintiff for the lost equipment.
Defendant
Joshua Road, LLC moves to eliminate the mechanic’s lien on the property owned
by Defendant or to reduce the lien from $80,000 to $1,500.
TENTATIVE RULING:
Defendant’s
Motion to Eliminate Plaintiff’s Mechanic’s Lien is GRANTED.
DISCUSSION:
Defendant
Joshua Road, LLC moves to eliminate the mechanic’s lien on the property owned
by Defendant or to reduce the lien from $80,000 to $1,500.
Legal Standard
“Under
California's mechanic's lien law, a mechanic's lien attaches to any interest in
a work of improvement and the real property on which it is situated. The
lien is a direct lien, similar to a mortgage, and is imposed as security for
payment of sums due the mechanic.” (Wachovia Bank v. Lifetime Industries,
Inc. (2006) 145 Cal.App.4th 1039, 1050; see also Cal. Const., art. XIV, §
3.) The California mechanic’s lien statutes are intended “to prevent unjust
enrichment of a property owner at the expense of a laborer or material
supplier.” (Burton v. Sosinsky (1988) 203 Cal.App.3d 562, 568.) The relevant
statute, California Civil Code section 8430, governs amounts permissibly
included in mechanic’s liens, and provides for “a direct lien for the lesser of
the following amounts: [¶] (1) the reasonable value of the work provided by the
claimant. [¶] (2) The price agreed to by the claimant and the person that
contracted for the work.”
“When
a claimant has recorded a mechanic’s lien and then secured a stay of an action
to foreclose the lien, an owner must have a speedy court remedy for showing
that the lien is invalid.” (Lambert v. Superior Court (1991) 228
Cal.App.3d 383, 389.) Accordingly, a Lambert motion examines the
“probable validity of the lien” under Civil Code section 8430. (Id. at
p. 388.) The question is “not the ultimate merit of the contractor’s claim but
whether the contractor should be entitled to retain the security of the
mechanic’s lien . . . pending a resolution of the matter.” (Cal Sierra
Construction, Inc. v. Comerica Bank (2012) 206 Cal.App.4th 841, 850.) The
court is empowered to reduce or remove the lien to the extent that it does not
comply with Civil Code § 8430.
In
a Lambert motion, the burden is on the claimant-plaintiff to establish
the probable validity of the lien. (See Cal Sierra Construction, Inc. v.
Comerica Bank (2012) 206 Cal.App.4th 841, 845; Lambert, supra, 228
Cal.App.3d at p. 387.)
Validity of Lien
Plaintiff
contends that the lien recorded for $80,000 plus interest is valid because this
amount represents the reasonable value of the contract between Plaintiff and
the subcontractor, Southern Cali, that leased the equipment from Plaintiff
which was stolen. Plaintiff contends that the reasonable value of the contract
is not only the rent due, but the replacement value of the equipment and loss
of initial revenue, and that these amounts are properly encompassed within §
8430(a)(1).
Plaintiff
is mistaken: the statute provides not for a lien for the reasonable value of
the contract but the reasonable value of the work done. Plaintiff cites
no law standing for the proposition that the reasonable value of the work
done includes the price or replacement of stolen equipment, or the loss of
rental revenue from the theft of that equipment. That proposition would be
contrary to the purpose of the statute to prevent a property owner from being unjustly
enriched at the expense of the laborer. Plaintiff contends that Defendant
is being unjustly enriched because it “could have stolen the Skidsteer for its
own use.” This accusation, unsupported by facts or evidence, is not only
flagrantly improper but insufficient to support Plaintiff’s position. The Court
fails to see how Defendant was unjustly enriched by a piece of expensive
construction equipment being stolen while it was on Defendant’s property.
Plaintiff
has also failed to show that the claimed breach of contract damages included
within the lien are proper. Civil Code § 8430(c) expressly authorizes the
inclusion of breach of contract damages in a lien, but nevertheless limits the
amount of the lien to the reasonable value of the work provided by the
claimant. Further, breach of contract damages are not available against a
property owner unless the complaint shows the existence of a contract between
the owner and the claimant. (Golden Gate Bldg. Materials Co. v. Fireman (1928)
205 Cal. 174, 177-78.) Plaintiff does not allege, either in the Complaint or in
its opposition, that Defendant had entered into a contract with Plaintiff for
the use of the equipment, but rather that Defendant entered into a contract
with an unlicensed subcontractor. (Declaration of Lanai Gomez ISO Opp. Exh. A.)
The
Court finds that Plaintiff has failed to show the probable validity of the lien
beyond the rental value of the Skidsteer for the five days it was on
Defendant’s property. The Court now turns to the issue of service of the
preliminary notice.
Preliminary Notice
To
record a valid lien, the claimant must serve a preliminary notice that complies
with all statutory requirements. (Civ. Code § 8200(b).) Civil Code § 8102
requires that the notice include certain information to the extent known to the
person giving the notice, including the contact information of the reputed
owner, the direct contractor, and any construction lender, as well as, if the
person giving the notice is a claimant, a general statement of the work
provided, the name of the person to or for whom the work is provided, and a
statement or estimate of the claimant’s demand, less all just credits and
offsets. (Civ. Code § 8102(a).) Variance from the requirements of subdivision
(a) of section 8102 does not invalidate a notice so long as it substantially
informs the owner of the information required in the notice. (Civ. Code §
8102(b).)
Defendant
contends that the notice is invalid because the preliminary notice stated that
the direct contractor was “Cherry Development,” which allegedly contracted for
the equipment. (See Complaint Exh. A.) Defendant contends that this error
rendered the notice inadequate to provide it with the information required in
the notice, since no contractor by that name was ever involved in this matter
and is not identified in the Complaint. Plaintiff, in opposition, concedes that
the notice was erroneous, arguing that it mistakenly believed that Cherry
Development was the general contractor for the work at Defendant’s property,
based on information provided by Southern Cali. (Gomez Decl. ¶¶ 8-10.)
It
cannot be said as a matter of law that a notice of mechanic’s lien that names a
completely unrelated entity as a general contractor and only states that the
lien is for “equipment rental” is sufficient to substantially inform an owner
of the basis for a lien on its property. As stated by Defendant in reply,
Plaintiff’s primary case in support, Indus. Aslphalt v. Garrett Corp. (1986)
180 Cal.App.3d 1001, is inapplicable. In that case, the Court of Appeal held
that a notice of lien was not invalid where the owner received proper
notice, but an original contractor did not. (Indus. Asphalt v. Garrett Corp.,
supra, at p. 1006.) Here, it is the
owner itself that is contesting the lack of adequate notice of the lien or its
basis. The Court agrees. Even considering the leeway afforded a claimant under
the statutory scheme, the Court cannot conclude that a notice which names an utterly
unrelated party as the direct contractor and as the person who contracted for
the equipment rental is sufficient to put an owner on notice of the basis for a
mechanic’s lien. The Court therefore finds that the lien is not compliant with §
8102 of the Code of Civil Procedure and is therefore invalid.
Accordingly, Defendant’s Motion to
Eliminate Plaintiff’s Mechanic’s Lien is GRANTED.
CONCLUSION:
Accordingly,
Defendant’s Motion to Eliminate Plaintiff’s Mechanic’s Lien is GRANTED.
Moving
party to give notice.
IT IS SO ORDERED.
Dated: August 11, 2022 ___________________________________
Theresa
M. Traber
Judge
of the Superior Court
Any party may submit on the
tentative ruling by contacting the courtroom via email at Smcdept47@lacourt.org by no later than 4:00 p.m. the day
before the hearing. All interested parties must be copied on the email. It
should be noted that if you submit on a tentative ruling the court will still
conduct a hearing if any party appears. By submitting on the tentative you
have, in essence, waived your right to be present at the hearing, and you
should be aware that the court may not adopt the tentative, and may issue an
order which modifies the tentative ruling in whole or in part.