Judge: Thomas Falls, Case: 22PSCV00720, Date: 2022-12-27 Tentative Ruling
The Court may change tentative rulings at any time. Therefore, attorneys are advised to check this website to determine if any changes or updates have been made to the tentative ruling.
Counsel may submit on the tentative rulings by calling the clerk in Dept. O at 909-802-1126 before 8:30 the morning of the hearing. Submission on the tentative does not bind the court to adopt the tentative ruling at the hearing should the opposing party appear and convince the court of further modification during oral argument.
The Tentative Ruling is not an invitation, nor an opportunity, to file any further documents relative to the hearing in question. No such filing will be considered by the Court in the absence of permission first obtained following ex-parte application therefore.
Case Number: 22PSCV00720 Hearing Date: December 27, 2022 Dept: O
SEAN CALHOUN vs DIANA YARBOI, et al (22PSCV00720)
______________________________________________________________________________
Plaintiff’s
Application for Default Judgment
Tentative Ruling
Plaintiff’s
Application for Default Judgment is DENIED without prejudice.
Background
This case pertains to home improvements. Plaintiff SEAN
CALHOUN dba REOL HELP HOME REPAIR AND REMODEL, a sole proprietorship, alleges
the following against Defendants DIANA YARBOI, an individual; CHRIS YARBOI: the
parties entered into a written and oral contract wherein Plaintiff would
perform construction on Defendants’ property. Defendants, however, have failed
to pay Plaintiff $44,882.00 for unpaid “labor, materials, services and
equipment.”
On July 14, 2022, Plaintiff filed the instant action for:
(1) Breach Of Contract
(2) Quantum Meruit/ Reasonable
Value
(3) Unjust Enrichment
(4) Foreclosure On Mechanics’
Lien
On August 22, 2022, Plaintiff filed a Lis Pendens.
On September 2, 2022, default was entered against both
Defendants.
On September 20, 2022, Plaintiff filed the instant action.
Plaintiff also dismissed the Second Cause of Action for Quantum Meruit.
Discussion
According to Plaintiff, default judgment is appropriate
because “[t]he evidence shows that Plaintiff fully performed its obligations
agreed upon under the parties’ contract and has a right to recover the
outstanding balance it is owed under the contract.” (Application p. 11.) Not so
because Plaintiff has provided insufficient evidence of his labor and
material costs.[1]
For one, while “a contractor's work is complete under C.C.P.
§3116 when the work called for in its contract has reached the point of
"substantial completion," Plaintiff has not provided before and after
photos for the court to determine “substantial completion.” (App.
p. 11.) The requirement of evidence is of particular import in such a case
wherein Defendants seemingly paid for a substantial amount of the agreement
price, leaving questions as to why the remainder was not paid.[2]
(See Ex. A [Contract amount was $192,754 for work to be done for “Plumbing,
Tile, Electrical, Demo Bath #3,4 Possible Plumbing, Electrical, Demo, [and]
Tile Bath #2,3.”].)
Therefore, Plaintiff has not met its evidentiary burden.
Conclusion
Based on the foregoing, the application is DENIED without
prejudice.
[1] Plaintiff is to
provide receipts of materials.
[2]y And on this point, the complaint
alleges that “Plaintiff sums due under said agreement and for change orders and
extra work.” (Complaint ¶13.) However,
according to the parties’ agreement, any such change orders for additional work
must be in writing. (See Exhibit A, Provision 4.1 ‘Changes in the Work’ [“The
Contractor is not required to perform additional work or changes without
written approval in a "Change Order" before any new work is
started.”].) Accordingly, if Plaintiff is attempting to recover for additional
work, he has not provided any such written approval.