Judge: Timothy Patrick Dillon, Case: 21STCV29644, Date: 2022-10-14 Tentative Ruling
Case Number: 21STCV29644 Hearing Date: October 14, 2022 Dept: 73
THE MACHINE GROUP, INC. v. NC
DYNAMICS, LLC
Counsel for Plaintiff/Cross-Defendant
(Movant): Stephen P. Semos, Baker Burton & Lundy, P.C.
Counsel for Defendant/Cross-Complainant
(Opposition): Jeffrey S. Goodfried, Freeman, Freeman & Smiley, LLP
DEMURRER To
FIRST AMENDED cross-COMPLAINT With motion to strike
(filed
09/02/2022)
TENTATIVE RULING
Plaintiff/Cross-Defendant’s (TMG)
Demurrer to Defendant/Cross-Complainant’s (NC Dynamics) First Amended
Cross-Complaint is OVERRULED.
TMG’s Motion to Strike NC Dynamics
claims is DENIED
Factual Background
This case concerns a contract dispute
for the sale and alleged underperformance of specialized machinery. NC Dynamics, the Defendant/Cross-Complainant,
is a full-service manufacturing facility that manufactures products for
aerospace companies. (FACC ¶ 5.) According to NC Dynamics, NC Dynamics took
steps to upgrade the manufacturing process in regard to an existing contract it
had with Bombardier Aerostructures (“Bombardier”). (FACC ¶ 8.)
As part of that process, NC Dynamics requested bids from three companies
to sell manufacturing equipment to NC Dynamics.
(FACC ¶ 9.) NC Dynamics also
requested the companies to conduct time studies to establish the running time
for the construction of specific titanium parts for the Bombardier
contract. (FACC ¶ 10.)
The Machine Group (“TMG”), the
Plaintiff/Cross-Defendant in this case, was one of the three companies to
submit a bid, but the only company that offered to sell an upcoming machine
from another company called OKK. (FACC ¶
9.) OKK conducted the time study. (FACC ¶
11, 14.) NC Dynamics contend that TMG
ultimately won the bid based on a guarantee made by TMG President Richard
Wackeen (“Wackeen”) that the parts would be manufactured in ten hours with the
OKK machine (FACC ¶ 11) and also upon the misrepresentation that OKK was aware
that Wackeen was guaranteeing a ten hour running time (FACC ¶¶ 12, 16).
NC Dynamics and TMG entered into two
contracts for the purchase of two OKK machines.
(FACC ¶¶ 17, 18.) The machines
failed to construct the parts in the contracted ten-hour running time, and
multiple attempts were made to reduce the running time. (FACC ¶¶ 20-23.) Because of the slow running time, NC Dynamics
contend that they were forced to purchase a third machine from TMG to meet its
production needs for the Bombardier contract.
(FACC ¶ 26.) NC Dynamics further allege
that TMG continued to guarantee that the OKK machines would achieve the
ten-hour running time despite knowing the OKK machine could not do so. (FACC ¶¶ 29-30.) NC Dynamics later learned that six weeks
before the parties entered into the third contract, a TMG manager named Jim
McCulloch (“McCulloch”) admitted in an email that the OKK machines would never
achieve a running time. (FACC ¶ 29.) McCulloch was present to witness the final
run of the OKK machines, which at the lowest point exceeded 24 hours. (FACC ¶ 32.)
As a result of the running time, NC Dynamics contend that they lost
Bombardier, and others, as a current and future customer. (FACC ¶ 31.)
NC Dynamics now brings seven causes of action: (1) breach of contract;
(2) fraud in the inducement; (3) negligence; (4) intentional interference with
contractual relations; (5) intentional interference with prospective economic
relations; (6) negligent interference with prospective economic relations; and
(7) breach of warranty of fitness for particular purpose.
Procedural Background
On August 11, 2021, TMG filed a
Complaint against NC Dynamics for breach of contract and recission. NC Dynamics demurred and moved to strike TMG’s
complaint, which this Court overruled on February 16, 2022.
On March 18, 2022, NC Dynamics filed a
cross-complaint against TMG. On May 31,
2022, TMG demurred to the cross-complaint.
This Court sustained the TMG’s demurrer on July 22, 2022 to the
challenged causes of action. (07/22/22
Minute Order.)
On August 1, 2022, NC Dynamics filed a
First Amended Cross-Complaint (“FACC”).
On September 2, 2022, TMG filed the instant Demurrer with Motion to
Strike. On September 26, 2022, NC
Dynamics filed its Opposition. TMG
replied on September 30, 2022.
Meet and Confer
Upon review of the
declaration submitted along with the instant demurrer, the Court finds that TMG
has satisfied the meet and confer requirement set forth in Code of Civil
Procedure § 430.41. (Semos Decl. ¶ 2.) Accordingly, the Court considers the Demurrer
on the merits.
Analysis
TMG demurs to the FACC on the
following grounds: (1) the Second Cause of Action does not state facts
sufficient to constitute a cause of action for fraud; (2) the Second Cause of
Action is vague and uncertain; (3)The Third Cause of Action does not state facts
sufficient to constitute a cause of action for negligence; (4) the Fourth Cause
of Action does not state facts sufficient to constitute a cause of action for
intentional interference with contractual relations; (5) the Fifth Cause of
Action fails to state facts sufficient to constitute a cause of action for
intentional interference with prospective economic relations; (6), the Fourth
and Fifth Causes of Action are barred by the applicable Statute of Limitations;
and (7) the Sixth Cause of Action fails to state facts sufficient to constitute
a cause of action for negligent interference with prospective economic
relations.
A.
Legal Standard for Demurrer
A demurrer tests the sufficiency of
whether the complaint states a cause of action.¿¿(Hahn v. Mirda¿(2007)
147 Cal.App.4th 740, 747.)¿¿When considering demurrers, courts read the
allegations liberally and in contest--any defects must be apparent on the face
of the pleading or via proper judicial notice.¿¿ (Donabedian v. Mercury Ins.
Co.¿(2004) 116 Cal.App.4th 968, 994.)¿¿A demurrer tests the pleadings alone
and not the evidence or other extrinsic matters. (SKF Farms v. Superior
Court¿(1984) 153 Cal. App. 3d 902, 905.)¿ Therefore, it lies only where the
defects appear on the face of the pleading or are judicially noticed.¿¿(Code
Civ. Proc., §§ 430.30, 430.70.)¿ The only issue a demurrer is concerned with is
whether the complaint, as it stands, states a cause of action.¿¿(Hahn, supra,¿147
Cal.App.4th¿at¿747.)
1. Fraudulent
Inducement
“The elements of fraud,” including a cause of action for
fraudulent inducement, “are (a) a misrepresentation (false representation,
concealment, or nondisclosure); (b) scienter or knowledge of its falsity; (c)
intent to induce reliance; (d) justifiable reliance; and (e) resulting damage.” (Hinesley v. Oakshade Town Ctr. (2005)
135 Cal.App.4th 289, 294.) The facts
constituting the alleged fraud must be alleged factually and specifically as to
every element of fraud, as the policy of “liberal construction” of the pleadings will not ordinarily
be invoked. (Lazar v. Superior
Court (1996) 12 Cal.4th 631, 645.)
To properly allege fraud against a corporation, the plaintiffs must
plead the names of the persons allegedly making the false representations,
their authority to speak, to whom they spoke, what they said or wrote, and when
it was said or written. (Tarmann v.
State Farm Mut. Auto. Ins. Co. (1991) 2 Cal.App.4th 153, 157.)
TMG contends that the intent and scienter elements of a
fraudulent inducement claim can not be satisfied by aggregating statements from
multiple individuals. The applicable
statements are Wackeen’s time guarantee and McCulloch’s email stating to the
effect that it was known company-wide that the OKK machines would never achieve
a running time of ten hours. (FACC ¶ 29.) NC Dynamics argues in opposition that TMG
fails to cite any authority for that proposition yet itself relies on case law[1]
inapplicable to this case. Thus, the
issue is whether Wackeen knew that the OKK machines would never reach the
ten-hour running time, as McCulloch indicated in the email, and when so
representing to NC Dynamics.
Accepting as true all reasonable inferences of a
well-pleaded complaint, the Court finds that NC Dynamics states a claim for
fraud in the inducement as to the third contract. McCulloch’s statement—“we all know [the running time of the
OKK machine] will never be 10 hours” (FACC ¶ 29)—can be reasonably construed to include Wackeen and his
knowledge that the OKK machines will never perform to the terms of the
contract. This satisfies these elements.
TMG further contends that NC Dynamics does not state facts
sufficient to show a material misrepresentation occurred. To show a material misrepresentation, TMG
argues that NC Dynamics must establish a causal connection between Wackeen’s
representation that OKK knew of TMG’s running time guarantee and the
underperformance of the OKK machines. NC
Dynamics argue that the FACC contains detailed allegations to state a claim for
fraud in the inducement, including the allegation that TMG represented that OKK
was aware of the guaranteed running time despite OKK’s lack of awareness of the
same and the representation s that a
10-hour run time would be achieved.(FACC ¶¶ 12-13.) OKK’s full support of the
10-hour guarantee is a material representation.
In reality, NC Dynamics alleges that there was no such support. (Ibid.)
TMG misstates the issue.
The issue is whether Wackeen’s allegedly false representation—that OKK
knew of TMG’s time guarantee in forming sales contracts of the OKK machine—is
material. At this early stage, the Court
so finds. NC Dynamics has set forth
allegations of the materiality of the ten-hour running time in agreeing to all
three contracts. (See FACC ¶¶ 11-13.) Further, NC Dynamics alleges that TMG “offered
to do all the programming on the machines” because NC Dynamics “would not have
the programming capacity to bring the machines into proper production.” (FACC ¶
16.) Read in context, the assurances of
a ten-hour running time and OKK’s full support of the guarantee contributed to
TMG winning the bid. (FACC ¶¶ 16,
34.) Thus, Wackeen’s representation that
OKK was aware of and supported TMG’s timing guarantee is a material
misrepresentation. At this point, on
demurrer, NC Dynamics has set forth facts sufficient to state a fraud in the
inducement claim.
Accordingly, the Court OVERRULES the Demurrer as to the
Second Cause of Action.
2. Uncertainty
of Fraudulent Inducement Claim
TMG contends, confusingly so, that the
Second Cause of Action is uncertain. A special demurrer for uncertainty
pursuant to Code of Civil Procedure § 430.10(f) is disfavored and will only be
sustained where the pleading is so bad that one cannot reasonably respond—i.e.,
cannot reasonably determine what issues must be admitted or denied, or what
counts or claims are directed against the party. (Khoury v. Maly’s of California, Inc.
(1993) 14 Cal.App.4th 612 at 616.)
Moreover, even if the pleading is somewhat vague, “ambiguities can be
clarified under modern discovery procedures.”
(Id.) A review of the
pleadings reveals that the FACC is not so bad that TMG cannot reasonably
respond. Additionally, TMG identifies
the Second Cause of Action in its Demurrer and argues a lack of sufficient
facts, which show TMG could reasonably respond to the claims directed at it in
the FACC.
Accordingly, the Court OVERRULES the
Demurrer as to the Second Cause of Action based on uncertainty.
3. Negligence
To state a claim for negligence, a plaintiff must allege (1)
the existence of a legal duty of care, (2) breach of that duty, and (3)
proximate cause resulting in an injury.
(McIntyre v. Colonies-Pacific, LLC (2014) 228 Cal.App.4th 664,
671.)
TMG argues that the conduct NC Dynamic complains of amounts
to an alleged breach of contract rather than a cause of action for negligence
because TMG’s alleged running time misrepresentation does not violate an
independent duty of the contract. NC
Dynamics opposes on the ground that the same conduct may support a breach of
contract and a tort claim, as has been alleged here.
The Court agrees with NC Dynamics. Both parties cite Erlich v. Menezes to support their
positions, but critically, TMG overlooks the language in Erlich that expressly supports NC Dynamic’s position. (See Erlich v. Menezes (1999) 21 Cal.4th
543, 551 (approving of the observation that “the same wrongful act
may constitute both a breach of contract and an invasion of an interest
protected by the law of torts.” (Citation omitted.).) The court in Erlich also observed that “[t]ort damages have
been permitted in contract cases . . . where the contract was fraudulently
induced.” (Id. at p. 551-52
citing Las Palmas
Associates v. Las Palmas Center Associates (1991) 235
Cal.App.3d 1220, 1238-1239.) NC Dynamics
has so alleged. Furthermore, it can be
reasonably inferred from the allegations that TMG had a duty of care to make
truthful representations in negotiating the three contracts with NC Dynamics. TMG’s alleged failure to do so constituted a
breach of that duty resulting in lost business contracts. (See FACC ¶¶
31, 50-53.) Accordingly, the Court
OVERRULES the Demurrer as to the Third Cause of Action.
4. The
Fourth and Fifth Causes of Action
TMG argues that NC Dynamics fails to allege facts to support
the intentional act element of the fourth and fifth causes of action because no
“wrongful act” is alleged. Nor does a
foreseeable relationship exist between the alleged behavior and NC Dynamics’ contract
with Bombardier.
a.
Intentional Interference with
Contractual Relations
The fourth cause of action is intentional Interference with
contractual relations, the elements of which are “(1) a valid contract between
plaintiff and a third party; (2) defendant’s knowledge of this contract; (3)
defendant's intentional acts designed to induce a breach or disruption of the
contractual relationship; (4) actual breach or disruption of the contractual
relationship; and (5) resulting damage.” (I-CA Enterprises, Inc. v. Palram Americas,
Inc. (2015) 235 Cal.App.4th 257, 289.)
Citing Quelimane Co. v.
Stewart Title Guar. Co. (1998) 19 Cal.4th 26, 56, NC Dynamics
contends that it is sufficient to allege that an actor knew or was
substantially certain that interference would occur as a result of the actor’s
conduct. TMG argues that NC Dynamics
must also show a wrongful act independent of the interference itself. For this proposition, TMG cites Korea
Supply Co. v. Lockheed Martin Corp. (2003) 29 Cal.4th 1134, 1154, and Della Penna v. Toyota Motor Sales, U.S.A., Inc. (1995)
11 Cal.4th 376, 378.
NC Dynamics correctly contends that it is not required to
allege the existence of an independent wrongful act because Della Penna concerned the tort of intentional
interference with prospective economic relations. NC Dynamics alleges that TMG was substantially certain that its
misrepresentations and actions would interfere with the Bombardier
contract. (See FACC ¶ 56-58.) This is
sufficient. Under the controlling case case law, at this point, NC Dynamics states a claim for
intentional interference with contractual relations.
Accordingly, the Court OVERRULES the
Demurrer as to the Fourth Cause of Action.
b.
Intentional Interference with
Prospective Economic Relations
The Fifth Cause of Action is intentional interference with
prospective economic relations. The
elements of intentional interference with prospective economic advantage are “(1)
an economic relationship between the plaintiff and some third party, with the
probability of future economic benefit to the plaintiff; (2) the defendant’s
knowledge of the relationship; (3) intentional or negligent acts on the part of
the defendant designed to disrupt the relationship; (4) actual disruption of
the relationship; and (5) economic harm to the plaintiff proximately caused by
the acts of the defendant.” (Crown
Imports, LLC v. Superior Court (2014) 223 Cal.App.4th 1395, 1404,
citations, brackets, and quotation marks omitted.) “[T]he third element also requires a plaintiff
to plead intentional wrongful acts on the part of the
defendant designed to disrupt the relationship.” (Korea Supply Co., 29
Cal.4th at p. 1154 citing Della Penna,
11 Cal.4th at p. 390.) “[T]he facts pleaded by a plaintiff must show an intent to do
something which takes the defendant’s acts beyond those of a mere competitor
securing business for himself.” (A.F. Arnold & Co. v. Pacific
Professional Ins., Inc. (1972) 27 Cal.App.3d
710, 716.)
Here, NC Dynamics
states a claim. NC Dynamics has
alleged sufficient wrongful acts on the part of TMG that were “designed to disrupt the
relationship” between NC Dynamics and Bombardier. Under Korea Supply, at this
early stage, NC Dynamics alleges that TMG
knew its alleged wrongful acts were substantially certain to injure NC
Dynamics’ business expectancy with Bombardier. NC Dynamics alleges that TMG was
substantially certain that their running time misrepresentations would
interfere with prospective Bombardier business.
(See FACC ¶ 64.) NC Dynamics has alleged an independent
wrong acts. NC Dynamics alleges sufficient
facts to state an intentional
interference with prospective economic relations claim based on the substantial
certainty prong.
Accordingly, the Court OVERRULES the
Demurrer as to the Fifth Cause of Action.
5. Negligent
Interference with Prospective Economic Relations
TMG quickly argues that the alleged conduct undergirding the
sixth cause of action “amounts to little more than an alleged breach of
contract.” NC Dynamics, again citing Erlich, supra, contends that overlap in the
underlying supporting facts does not render deficient the negligent
interference claim.
“The elements of negligent interference with prospective
economic [relations] are (1) the existence of an economic relationship between
the plaintiff and a third party containing the probability of future economic
benefit to the plaintiff; (2) the defendant’s knowledge of the relationship;
(3) the defendant’s knowledge (actual or construed) that the relationship would
be disrupted if the defendant failed to act with reasonable care; (4) the defendant’s
failure to act with reasonable care; (5) actual disruption of the relationship;
and (6) economic harm proximately caused by the defendant’s negligence.” (Redfearn v. Trader Joe’s Co. (2018) 20 Cal.App.5th 989, 1005.)
The Court agrees with NC Dynamics. Moreover, the Court finds that NC Dynamics
alleges facts sufficient to state a claim for negligent interference with
prospective economic advantage. NC
Dynamics has alleged the existence of an economic relationship with Bombardier
(FACC ¶ 8); that TMG knew of the relationship (FACC ¶ 71); that TMG was aware
or should have known that a failure to act with due care would interfere with
the relationship (FACC ¶ 71); that TMG failed to act with reasonable care by
representing that OKK guaranteed the required running time and continuing to so
represent despite knowing the machines could not achieve the running time (FACC
¶¶ 11-13, 29, 72); and that NC Dynamics lost Bombardier altogether as a current
and future customer because NC Dynamics could no longer fulfill its obligation
to Bombardier or offer a contract with a lower price (FACC ¶ 72). Each element
is met.
Accordingly, the Court OVERRULES the
Demurrer as to the Sixth Cause of Action.
B.
Leave to
Amend
When a demurrer is sustained, the
court may choose to grant or deny leave to amend. (Cal. Code Civ. Proc. § 430.41(e)(1)). Leave to amend following a demurrer must be allowed
where there is a reasonable possibility plaintiff can amend the complaint to
cure the defect. (Schulz v.¿Neovi¿Data
Corp.¿(2007) 152 Cal.App.4th 86, 92.)¿ Although the Court has sustained
once before a demurrer to the original cross-complaint with respect to the
intentional interference claims, the Court grants leave to amend.
C.
Motion to
Strike
A motion to strike lies only where the pleading has
irrelevant, false or improper matter, or has not been drawn or filed in
conformity with laws.¿ (Code Civ. Proc. § 436.)¿ The grounds for moving to
strike must appear on the face of the pleading or by way of judicial notice.¿ (Id.
§ 437.)¿¿¿
TMG requests the Court to strike the following portions of
the FACC without leave to amend:
·
The FACC’s Third Prayer for Relief in
the form of punitive damages;
·
The FACC’s Sixth Prayer for Relief in
the form of punitive damages;
·
The FACC’s Eighth Prayer for Relief in
the form of punitive damages.
The Prayers for Relief are for the Second, Fourth and Fifth
Causes of Action. Because the Court
overrules the Demurrer as to the Second,
Fourth and Fifth Causes of Action, the court rules on the Motion to Strike as to those claims.
Citing Miller v. Nat’l Am. Life Ins. Co. (1976) 54
Cal.App.3d 331, 336, TMG moves to strike the Third Prayer because punitive
damages are not available in an action based solely upon breach of a
contractual obligation. But, as stated
above, “tort damages have been permitted in contract cases . . . where the
contract was fraudulently induced.” (Las Palmas Associates, supra, 235
Cal.App.3d at p. 1238-1239.)
Furthermore, Civ. Code § 3294 (a) permits a plaintiff to recover
punitive damages “where it is proven by clear and convincing evidence that the
defendant has been guilty of oppression, fraud or malice . . . .” For the purposes of a punitive damages award,
“fraud” means “an
intentional misrepresentation, deceit, or concealment of a material fact known
to the defendant with the intention on the part of the defendant of thereby
depriving a person of property or legal rights or otherwise causing injury.” (See Cal. Civ. Code § 3294(c)(3).) Here, NC Dynamics has alleged facts
sufficient to show that TMG’s running time misrepresentations caused the loss
of the Bombardier contract. Accordingly,
the Motion to Strike is DENIED.
D.
Conclusion
The Demurrer is OVERRULED.
The motion to strike is DENIED.
THIS IS A TENTATIVE RULING
[1] NC Dynamics cites N. Nat. Gas
Co. v. Superior Ct. (1976) 62 Cal.App.3d 983 for the proposition that
because a company acts through its employees, its employees’ knowledge may be
imputed to the company. However, that
case concerns agency law and, as set forth within, confuses the issue.